MICE Project Report Alan Bross (for Paul Drumm)

Upload: winifred-clark

Post on 19-Jan-2016

227 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

MICE Project Report

Alan Bross(for Paul Drumm)

Page 2: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Project Issues● Key dates:

– ISIS Synchrotron start-up scheduled for 1st August● Shielded area around decay solenoid (DSA) must be

completed; significant risk (high impact)● concentrates the mind!

– ISIS user runs - start up for production running 2nd October

– These dates are subject to last minutechanges

Page 3: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Strategy● Schedule of work in the synchrotron in parallel

with that in the MICE hall● Work on the shielding, cryoplant and beam line

within DSA broken into steps● Parallel work in mice hall once solenoid is

installed

Page 4: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Current events● Shielding is being delivered from DL● Next heavy-gang job is to pull out the existing

shielding blocks - not under our control● Preparations for final drilling in concrete roof● Preparations for cutting solenoid trolley

Page 5: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Urgent needs● many urgent items in time order:

– Shielding design plan (steel plates);– Plinth;– Rails & extension frames;– Solenoid trolley mods;– Linde equipment installation;– Decay solenoid repair;– D2;– Q4-6;

Page 6: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Synchrotron components● Dipole & Quadrupole stand parts now out for

manufacture - delivery expected to drive schedule (for installation in May)

● Installation - people - may suffer clash

Page 7: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

D2 is a copy of D1 stand

Rebuild of Q in progress

D2, Q-stands● Engineering being finished off● Rebuild of 1st Q35 is in progress

– issue with coils - still being investigated– may need to remake some coils

Page 8: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Target● Progress

– Successful test in October– Didn’t manage a second go (for more statistics)

● Power supply operating at DL at higher amps– Power supply into a load > into target so far– One conclusion has been that the target controls

are not fast enough– A plan has been evaluated & will be reviewed at

beginning of March (TB + local review team) documents being prepared

● Risk: we need to “prove” reliability with time running out...

Page 9: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Milestones

~

~

not critical

Beam line - Synchrotron Review controls & EE

(9th March)

Orange: prove mechanism at low amps~3 mo

Red: prove at high amps ~3 mo

On probation? To be discussed

Page 10: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Muon Solenoid

few days late

risk!

Labour intensive!Have a plan with RAL+Ox+Lv+Imp

Page 11: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Beam line component Stands

}

Work in parallel to gain time!

Just in time

Page 12: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Overall MICE BL Project Plan Schedule

Our RiskZero slack in asequential work plangain ~ 1 mo with|| working

Page 13: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

progressing● Iron shields

– control room side - engineering ~complete– linac side - simple wall – needs detailing

● MICE Plinth - concrete base under MICE– leave access clear for shielding installation– floor fixings need to be determined

● False floor - between linac wall and MICE plinth

Page 14: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Schedule Summary● parallel work (plus a proportion of weekends)● delays arise too easily

– task review - anticipation● dependent on delivery of items

– north and south● installation of items

– more control– team of 2+2+1+2 established– crane operators

● Can we do it!– yes we can!

Page 15: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Instrumentation & TOF0 & CKOV● Still need to work out mounting scheme

– follow from shielding design● Need TOF for beam diagnostic● installation in July?● FNAL beam monitors

– not yet clear how many needed– not yet clear on cost

Page 16: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

RF Activities● Important for Phase 2 - MICE-CERN-UK● Tight schedule

– 300kW power mid year● waiting on final rebuild of amplifier

– 4MW end of 2007● build HT rack● control rack● 4MW load?

● Conflicts of other activities– management issue in Daresbury

Page 17: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

LH2 & Absorber● Specification close to completion

– sign off with MICE– sign off with RAL– tender - delivery in X months?– Overlap of MICE running & LH2 work

● LHe work will be important to learn safety implications● Advise a mid point review before starting with LH2

Page 18: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

ISIS Running in August

[4] MICE beam can basically run any time synchrotron is running, provided beam losses in Straight 7 acceptable. But machine programme determined by ISIS operations, not MICE.

Provisional – subject to change

Page 19: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

ISIS user running● Provisional dates s2c

– Cycle starts Tuesday 2nd October– ~60 days of user beam in 2007

Cycle 2007/01 10/02/07Machine physics 11/02/07

Minor maintenance 11/05/07Run-up + machine physics 11/09/07

Beam line permits 11/12/07Cycle 2007/02 — The odd squirt of beam to TS-2 11/13/07

16-Dec-07 / ISIS anniversary / Few protons on to TS-2 12/14/07Moderator change 12/17/07

Run-up + machine physics 01/21/08Beam line permits 02/04/08

Cycle 2007/03 — Routine squirts of beam to TS-2 02/05/08

Provisional – subject to change

Page 20: MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around

Organisational & Safety Issues● October collaboration meeting:

– MICE management needs to re-organise itself into “an operational structure”, e.g.

● Physicist in charge (for weeks running)● Engineer in charge (for weeks running)● Shift teams (call up and rostering)● weekly run planning meetings● monthly safety review meetings

– MICE Spoke/MICE EB should set up a team to deliver this structure, operating procedures, local rules need to be developed (raised at (see) CM16 October '06)