mice pid detectors & shielding

29
MICE CM17, CERN, 24 Feb V. Palladino PID Detectors & MICE PID detectors & Shielding MICE CM17, CERN Feb 25, 2007 V. Palladino, Univ & INFN Napoli for the small PID team Bonesini, Chimenti, Cremaldi, Giannini, Graulich, Gregoire, Karazdov, Orestano, Sandstrom, Summers, Torun, Tortora, Tsenov, and more

Upload: fallon-pittman

Post on 03-Jan-2016

43 views

Category:

Documents


4 download

DESCRIPTION

MICE PID detectors & Shielding. MICE CM17, CERN Feb 25, 2007 V. Palladino, Univ & INFN Napoli for the small PID team Bonesini, Chimenti, Cremaldi , Giannini , Graulich , Gregoire, Karazdov , Orestano, Sandstrom, Summers, Torun, Tortora, Tsenov, and more. picture & contributors - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

MICE PID detectors

& Shielding

MICE CM17, CERN Feb 25, 2007V. Palladino, Univ & INFN Napoli

for the small PID team Bonesini, Chimenti, Cremaldi, Giannini, Graulich,

Gregoire, Karazdov, Orestano, Sandstrom, Summers, Torun, Tortora, Tsenov, and more

Page 2: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

picture & contributorsUpstream PID Review requirements (almost) fulfilled (AB dixit) TOF0-I being rescued from INFN funding crisis (with CalSys, KL and TOF II) Building & making installation plans (Aug-Sep 07) CKOV (LC) TOF0/I and Cal Sys (MB, YK)

Completing design of TOF I global PMT shield cage (GG) ….. to be funded ! quite effective, mitigating local PMT shielding requirements

Downstream A) EMCal/KL can be completed, if funding really OK, for installation with TOF0 & I in Aug-Sep 07 (DO for LT) a (simple) review procedure should/could endorse that B) TOF II : funding being solved, for installation Mar 2008 being driven to final design from PID (MB) & Analysis (RS/MA) teams as is global PMT shield cage (GG) (RS/MA) local PMT shielding issues, more severe, being finalized measurements in mag field in progress in Milano (MB) For all above, front end (RT) and read out (JSG) electronics well defined performance requirement being properly formulated (CR) complete G4MICE performance re-evaluation being taken up seriously (YK)

Then C) EMCal/SW further away, in 2008, funding not tackled yet conceptual G4MICE design well advanced, proven to be necessary AND sufficient (RS) practical design started (GG, PC, AB)

 

Page 3: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

to Alan for preview while few last answers still being added, MICE Note soon

Page 4: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

• to AB for preview

Lucien

Page 5: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

TOF0 & I , Maurizio

OK

Page 6: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

OK, if funds confirmed to be available

Page 7: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

OK, if funds there

Page 8: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

TOF I global shield (Ghislain) …………… NB to be funded and farmed !!

After tech drawings

finalized by Ghislain

in consultation with Steve

Page 9: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Cage shield vs Plate shield (Maurizio)

GG cage

GG plate

Choice soon

+ more local iron

Page 10: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Frascati test beam, YK

So “TOFI-TOF0” < 70 ps

Page 11: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

For real “TOFI-TOF0”, useful statistics only with (worse) active splitter

useful to establish that time walk correction is needed (FADC)

Page 12: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

KL … 3/7 exist …. can be finished for phase I , if funds

NB … L. managed to make them larger than anticipated

Domizia (and Ludovico)

Page 13: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Page 14: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Page 15: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Page 16: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

TOF II, Maurizio …. aiming at Mar 08

fixed

Page 17: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

funds required, to be confirmed to be available

Page 18: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

TOF II global shield, Ghislain

600 now

700 now

being redoneto be funded and farmed !!after tech drawingsfinalized by Ghislain in consultation with Steve

Page 19: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

More local PMT shield needed

Final word from Milano’s mag test stand

Page 20: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Radii of downstream holes and aperture (Rikard)

Page 21: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Radii of downstream holes and aperture (Marco)

to be all checked throughto be reduced AMAP!

Page 22: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Page 23: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Downstream apertures yesterday’s decisions

• Front plate of TOF II shield 600 mm

• Lateral size of TOF II 600 mm

• Back plate of TOF II shield 700 mm

• Lateral size of KL 900 mm

• Lateral size of SW ≥ 1000 mm

}

Page 24: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

front end (Roumen)

and read out (J. Sebastien) electronics well defined

have (or can have) it all available for TOF0, I, KL

of splitter & stretcherfor FADC digitizationof all detectors

PID electronics OK

Page 25: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

ps

70 ps OK for longitudinal emittance, Chris

Page 26: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Rikard :KL + SW do the e/µ separation with 99.9 efficiency 99,8 purity

See MICE Note 164

Page 27: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

SW detailed design being tackled (Pietro, Gianrossano, Alan)

TO BE FUNDED !

On the floor in 2008?

Page 28: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

Mechanics in Trieste

Scibars from Fermilab prototype planepossibly soon

Page 29: MICE  PID detectors & Shielding

MICE CM17, CERN, 24 Feb 2007 V. Palladino PID Detectors & shields

picture & contributorsUpstream PID Review requirements (almost) fulfilled (AB dixit) TOF0-I being rescued from INFN funding crisis (with CalSys, KL and TOF II) Building & making installation plans (Aug-Sep 07) CKOV (LC) TOF0/I and Cal Sys (MB, YK)

Completing design of TOF I global PMT shield cage (GG) ….. to be funded ! quite effective, mitigating local PMT shielding requirements

Downstream A) EMCal/KL can be completed, if funding really OK, for installation with TOF0 & I in Aug-Sep 07 (DO for LT) a (simple) review procedure should/could endorse that B) TOF II : funding being solved, for installation Mar 2008 being driven to final design from PID (MB) & Analysis (RS/MA) teams as is global PMT shield cage (GG) (RS/MA) local PMT shielding issues, more severe, being finalized measurements in mag field in progress in Milano (MB) For all above, front end (RT) and read out (JSG) electronics well defined performance requirement being properly formulated (CR) complete G4MICE performance re-evaluation being taken up seriously (YK)

Then C) EMCal/SW further away, in 2008, funding not tackled yet conceptual G4MICE design well advanced, proven to be necessary AND sufficient (RS) practical design started (GG, PC, AB)