metropolitan washington airports authority washington

51
METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON DULLES INTERNATIONAL AIRPORT SPECIFICATION AND STATEMENT OF WORK FOR TWO (2) 180kVA DUAL OUTPUT 400HZ AIRCRAFT GROUND POWER UNITS GATES B37 AND B47 September 2011

Upload: others

Post on 26-Jan-2022

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

METROPOLITAN WASHINGTON AIRPORTS AUTHORITY

WASHINGTON DULLES INTERNATIONAL AIRPORT

SPECIFICATION AND STATEMENT OF WORK FOR TWO (2) 180kVA DUAL OUTPUT 400HZ

AIRCRAFT GROUND POWER UNITS

GATES B37 AND B47 September 2011

Page 2: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 2 of 51 September 2011

TABLE OF CONTENTS

1.0 GENERAL .................................................................................................................................................... 4 

1.1 PROJECT SCOPE ................................................................................................................................. 4 1.2 DEFINITIONS ...................................................................................................................................... 5 1.3 INTENT OF CERTAIN TERMS OR ADJECTIVES ........................................................................... 6 1.4 PROGRESS SCHEDULE ..................................................................................................................... 6 1.5 SHIPPING AND DELIVERY ............................................................................................................... 7 1.6 TRAINING ............................................................................................................................................ 8 1.7 SPARE PARTS ..................................................................................................................................... 8 1.8 WARRANTY ........................................................................................................................................ 8 1.9 MANUALS ............................................................................................................................................ 8 1.10 MATERIALS ........................................................................................................................................ 9 

2.0 GROUND POWER UNIT EQUIPMENT SPECIFICATIONS ............................................................ 10 2.1 GENERAL REQUIREMENTS ........................................................................................................... 10 2.2 APPLICABLE CODES AND STANDARDS .................................................................................... 11 2.3 NOMINAL RATING .......................................................................................................................... 11 2.4 INPUT POWER ................................................................................................................................... 11 2.5 OUTPUT POWER – 400Hz AC ......................................................................................................... 12 2.6 OVERLOAD ....................................................................................................................................... 13 2.7 FAULT SYSTEMS ............................................................................................................................. 13 2.8 INDICATORS ..................................................................................................................................... 13 2.9 SWITCHES AND CONTROLS .......................................................................................................... 14 2.10 EXTERNAL INTERFACE ................................................................................................................. 14 2.11 PHYSICAL CHARACTERISTICS .................................................................................................... 14 2.12 OTHER DESIGN REQUIREMENTS ................................................................................................. 15 2.13 CABLES AND CABLE HOISTS ....................................................................................................... 16 2.14 INPUT POWER, CIRCUIT BREAKER, SO CORD AND DOGLEG ............................................... 16 2.15 CERTIFICATIONS ............................................................................................................................. 18 

3.0 INSTALLATION SPECIFICATIONS .................................................................................................... 19 3.1 GENERAL REQUIREMENTS ........................................................................................................... 19 3.2 APPLICABLE CODES AND STANDARDS .................................................................................... 20 3.3 INSTALLATION REQUIREMENTS ................................................................................................ 20 3.4 SUBSTANTIAL COMPLETION, PUNCH LISTS, FINAL ACCEPTANCE ................................... 21 

4.0 QUALITY ASSURANCE ......................................................................................................................... 22 4.1 GENERAL REQUIREMENTS ........................................................................................................... 22 4.2 CONTRACTOR’S QUALITY PLAN ................................................................................................. 22 4.3 NON-CONFORMING GOODS .......................................................................................................... 23 4.4 INSPECTIONS .................................................................................................................................... 24 

4.4.1 INSPECTION PRIOR TO SHIPMENT ................................................................................................. 24 4.4.2 INSPECTION UPON DELIVERY ........................................................................................................ 24 4.4.3 INSPECTION DURING INSTALLATION PROCESS ........................................................................ 24 4.4.4 INSPECTION AT SUBSTANTIAL COMPLETION ........................................................................... 24 4.4.5 FINAL ACCEPTANCE ......................................................................................................................... 25 

4.5 FACTORY ACCEPTANCE TESTING ............................................................................................. 25 

Page 3: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 3 of 51 September 2011

4.6 ON-SITE FUNCTIONAL TESTING ................................................................................................. 26 5.0 CONTRACTOR SUBMITTALS .............................................................................................................. 27 

5.1 PROPOSAL ......................................................................................................................................... 27 5.2 INSTALLATION ................................................................................................................................ 27 5.3 QUALITY ASSURANCE / TESTING ............................................................................................... 27 5.4 OTHER ................................................................................................................................................ 27 5.5 FINAL PAYMENT ............................................................................................................................. 28 5.6 DESIGN ............................................................................................................................................... 28 

5.6.1 SHOP DRAWINGS AND SAMPLES .................................................................................................... 28 5.6.2 OWNER’S REVIEW OF SHOP DRAWINGS ...................................................................................... 29 5.6.3 RE-SUBMITTAL PROCEDURES FOR SHOP DRAWINGS .............................................................. 29 

EXHIBIT I ........................................................................................................................................................... 30 EXHIBIT II ......................................................................................................................................................... 32 EXHIBIT III ........................................................................................................................................................ 34 EXHIBIT IV ........................................................................................................................................................ 43 EXHIBIT V .......................................................................................................................................................... 50 

Page 4: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 4 of 51 September 2011

1.0 GENERAL 1.1 PROJECT SCOPE

1. The scope of this project will consist of a) Removing two (2) existing Jetway 120kVA dual output 400Hz Ground Power Units (GPU), which are

currently mounted on the Passenger Boarding Bridges (PBB) at Gates B37 and B47 (see EXHIBIT I) b) Supply and installation of two (2) new 180kVA dual output 400Hz GPU’s; one each on the PBB’s at

Gates B37 and B47. 2. The existing 120kVA GPU’s shall be turned over to the Authority. 3. The existing cable hoists will be reused. 4. The Authority will supply its own GPU output cables. 5. The existing GPU Pendant Controls and wiring and PBB interlock wiring shall reused. 6. For Gate B37 –

a) The existing 1/0 AWG power cable used for the PBB and the 120kVA dual output GPU will be re-used for the PBB only.

b) A new 3/0 AWG, 3C-W/G, 600V SO cord power cable, aluminum dogleg and conduit will be supplied for the new 180kVA dual output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements.

c) The existing adjustable PBB / GPU circuit breaker in the SST disconnect cabinet mounted on the PBB rotunda shall be reused for the PBB only. It will be “dialed down” to its lowest setting.

d) A new adjustable, 250 amp maximum circuit breaker, identical to the other two existing circuit breakers, will be added to the SST disconnect cabinet mounted on the PBB rotunda for the new 180kVA dual output GPU. The existing 2-breaker shut off linkage shall be reused for the PBB and Pre-Conditioned Air (PCAir) disconnects only. A handle shut off mechanism will be supplied for the new adjustable 250 amp GPU circuit breaker. This new circuit breaker shall also be capable of being Locked or Tagged out.

e) Input power to the new GPU only circuit breaker shall be taken from the existing PBB / GPU circuit breaker.

7. For Gate B47 – a) The existing 2 AWG power cable used for the 120kVA dual output GPU will be abandoned in place.

Each end shall be shrink wrapped, coiled and secured to the PBB rotunda rigid frame and the PBB C tunnel floor.

b) A new 3/0 AWG, 3C-W/G, 600V SO cord power cable, aluminum dogleg and conduit will be supplied for the new 180kVA dual output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements.

c) The existing adjustable circuit breaker in the SST disconnect cabinet mounted on the PBB rotunda shall be reused and it shall be “dialed up” to 200 amps.

8. The new 180kVA GPU shall be required to operate on a MAXIMUM of 200 amps input power. 9. The Contractor shall modify the existing circuit breakers in the terminal building as follows:

a) For Gate 37, the thermostatic trip module in the building circuit breaker must be replaced with a module that will trip at 250 amps. The current trip module is only 225 amps.

b) For Gate B47, the building circuit breaker is an adjustable and must be adjusted to 400 amps. c) See EXHIBIT V for more information on the building circuit breakers.

10. The Contractor shall employee a local testing company, which must be NETA Certified, to verify that:

Page 5: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 5 of 51 September 2011

a) At Gate B37, the new GPU circuit breaker, the now PBB only circuit breaker in the PBB SST disconnect and the modified building circuit breaker for the 250 amp circuit supplying power to the PBB SST Disconnect, are all correctly set and do trip at the correct loads.

b) At Gate B47, the existing GPU dial circuit breaker in the PBB SST disconnect and the modified building circuit breaker supplying power to the breakers in the PBB SST Disconnect, are all correctly set and do trip at the correct loads.

c) The local testing company must adjust, test and certify the new breaker settings and provide written documentation that the breakers have been tested and are functioning properly.

11. Listed below are three (3) companies that are capable of performing this testing. a) Reuter Hanney

4270-I Henninger Court Chantilly, VA 20151 703-2637163

b) Substation Testing 4390 Parliament Place Suite Q Lanham, MD 20706 301-967-3500

c) Potomac Testing 4831 Telsa Drive Bowie, MD 20715 301-352-1930

12. The Authority requires that Gate B37 and B47 be taken out of service for only a very short period of time while the installation scope of work is completed. The gates shall not be taken out of service simultaneously. The Contractor should plan only one (1) mobilization as the work should be able to progress without interruption. The Contractor shall coordinate taking the Gates out of service with the Authority’s COTR.

1.2 DEFINITIONS

1) “Authority” or “Airport” or “Owner” or “MWAA” may be used interchangeably throughout this Specification and shall mean The Metropolitan Washington Airports Authority, which operates the Dulles International Airport, a large hub international airport.

2) Technical Specifications Representative: Don Mesecher, DK Consultants, LLC is the person designated by the Authority to prepare and present these Specifications for this Project. Questions, comments, or concerns about these Specifications shall be sent in writing using the link provided via the Airports Authority’s website as stated in Block 5, on page I-1 of the solicitation. The submit-a-question link is accessed through the Project Overview tab on the webpage.

3) “Bidder” or “Contractor” or “Supplier” may be used interchangeably throughout this Specification and shall mean the individual, partnership, corporation, or other business entity that submits a Proposal to the Authority and may be awarded a Contract by the Authority. The term "Bidder" in no way defines the Proposal as a "BID".

4) “Proposal” or “Bid” may be used interchangeably throughout this Specification and shall mean the Proposal submitted to the Authority for the 180kVA Dual Output GPU described herein. The term “Bid” in no way defines the Requested for Proposal as a “Bid”.

Page 6: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 6 of 51 September 2011

5) Addenda - Those written or graphic instruments issued by the Authority prior to the receipt of Proposals in accordance with the RFP requirements that clarify or change the RFP Requirements, Contract Documents or Specifications.

6) Drawings - That part of the Contract Documents prepared or approved by the Authority that graphically shows the scope, intent, and character of the Goods and Services to be furnished by Contractor.

7) Goods - The tangible and movable equipment that is described in the Specifications, regardless of whether the property is to be later attached to realty.

8) IAD – Shall mean Washington Dulles International Airport. 9) Project - The total undertaking of which the Goods and Services to be provided under the Contract are a

part. 10) Samples - Physical examples of materials, equipment, or workmanship that are representative of some

portion or all of the Goods and which establish the standards by which certain portions of the Goods or Special Services will be judged.

11) Shop Drawings - All drawings, diagrams, illustrations, schedules, test reports, certifications, cut sheets, calculations and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to demonstrate that the Contractor will provide Goods and Services which meet the requirements of the RFP and Specifications.

12) Services - Services associated with the Goods to be furnished by Contractor as required by the Contract Documents.

13) Specifications - That part of the Request for Proposal consisting of written technical descriptions of materials, equipment, systems, standards and workmanship as applied to the furnishing of the Goods and Services, and certain administrative details applicable thereto.

1.3 INTENT OF CERTAIN TERMS OR ADJECTIVES

1) The Specifications may include the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by the Authority. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Authority as to the Goods or Services. It is intended that such exercise of professional judgment, action or determination will be solely to evaluate, in general, the Goods or Services for compliance with the requirements of and information in the Specification and conformance with the design concept of the completed Project as a functioning whole as shown or indicated in the Specification (unless there is a specific statement indicating otherwise). The use of any such term or adjective shall not be effective to assign to Authority any duty or authority to supervise or direct the furnishing of Goods or Services or any duty or authority to undertake responsibility contrary to any other provision of the Specification.

2) Unless stated otherwise in the Specification, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.

3) The word “non-conforming”, when modifying the words “Goods” or “Services”, refers to Goods or Services that fail to conform to the requirements of the Specification, written Amendments, Change Orders and written clarifications or interpretations issued by the Authority,

1.4 PROGRESS SCHEDULE

1) The work under this Contract shall be complete as specified below. These completion dates may be used to determine the assessment of Liquidated Damages, at the sole discretion of the Authority. NTP shall mean the date of the Authority’s Notice to Proceed issued to the Contractor.

Page 7: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 7 of 51 September 2011

a) Delivery of Goods to IAD - Per the Contractor’s Delivery Quotation in the RFP. The Contractor’s Quoted Delivery shall be a factor in the Authority’s Proposal Evaluation Criteria.

b) Substantial Completion – Gate B37 - Within 2 days from the Authority’s Authorization to begin work at Gate B37.

c) Final Acceptance – Gate B37 - Within 5 days from the Authority’s Authorization to begin work at Gate B37.

d) Substantial Completion – Gate B47 - Within 2 days from the Authority’s Authorization to begin work at Gate B47

e) Final Acceptance – Gate B47 - Within 5 days from the Authority’s Authorization to begin work at Gate B47

2) Within fifteen (15) days after the NTP issued to the Contractor, the Contractor shall submit to Owner an acceptable Progress Schedule of Project activities; including at a minimum: a) Design, Engineering, Preparation and Submittal of all Shop Drawings. Note – Shop Drawings are

inclusive of ALL submittal requirements, as set forth in these Specifications. b) Authority’s review and approval of Shop Drawings c) Material Procurement d) Fabrication and Assembly e) Contractor’s Factory Tests f) Factory Tests to be witnessed by Owner, at Owner’s discretion. g) Shipping and Delivery h) Installation activities at Gate B37, which shall be completed first. i) Installation activities at Gate B47 j) Final inspections by Owner

3) The Progress Schedule shall be in Gantt chart format. 4) The Progress Schedule will be acceptable to Owner if it provides an orderly progression of the submittals,

tests, and deliveries to completion within the specified Milestones and the Contract Times. Such acceptance will not impose on Owner responsibility for the progress schedule, for sequencing, scheduling, or progress of the work nor interfere with or relieve Contractor from Contractor’s full responsibility therefore. Such acceptance shall not be deemed to acknowledge the reasonableness and attainability of the schedule.

1.5 SHIPPING AND DELIVERY

1) Contractor shall select the carrier and bear all costs of packaging, transportation, insurance, special handling and any other costs associated with shipment and delivery.

2) Contractor shall deliver the Goods, F.O.B. Point of Destination, in accordance with the Contract Times set forth in the Contract Documents, or other date agreed to by Owner and Contractor.

3) Contractor shall provide written notice to Owner at least fifteen (15) days before shipment of the manner of shipment and the anticipated delivery date. Contractor shall also require the carrier to give Owner at least twenty-four (24) hours’ notice by telephone prior to the anticipated hour of delivery.

4) The Contractor shall assure that adequate facilities and other special equipment or services required at the Point of Destination are available to unload and care for the Goods.

5) All such delivery coordination activities shall be the responsibility of the Contractor. 6) The Owner shall provide the Contractor with a point of contact at IAD for such coordination activities. 7) The Contractor shall be responsible for acceptance of the Goods at the Point of Destination. The Contractor

shall inspect the Goods upon arrival and immediately replace missing or damaged items and will be responsible for making any and all claims against carriers.

Page 8: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 8 of 51 September 2011

8) Delivery shall be made to: Washington Dulles International Airport

Main Warehouse 44701 Propeller Court

Dulles, VA 20164 1.6 TRAINING

1) Contractor shall provide the Manufacturer’s standard Operations and Maintenance class for the GPU and any ancillary equipment. These classes will be conducted on-site at IAD and shall occur prior to Substantial Completion of the work at Gate B37.

2) Contractor shall submit a Training Syllabus for all training classes to be conducted at IAD within thirty (30) days of the Notice to Proceed. Format and content of Contractor’s proposed Training classes shall be subject to approval of the Authority.

1.7 SPARE PARTS

1) Contractor shall provide a recommended spare parts list for spare parts that may be required during first two years of normal operation of the GPU. This recommended Spare Parts List shall be provided prior to the Substantial Completion of work at Gate B37

2) The Manufacturer of the Goods shall maintain an inventory, production capability or source of supply of any required Spare Parts for the Goods for a period of ten (10) years after Final Acceptance of the Goods.

1.8 WARRANTY

1) The Contractor shall provide 2-year material and labor warranty all Goods and Services provided under this Contract.

2) If the Contractor is NOT the GPU Manufacturer, the Contractor shall supply the Manufacturer’s 2-year Warranty Certificate, in favor of the Authority, for all Goods supplied under this Contract. Such Warranty Certificates shall be supplied with the Final Payment Application.

3) All Warranty times will commence upon Final Acceptance of the Goods by the Authority. 1.9 MANUALS

1) O&M manuals for each type of equipment shall be shipped with the Goods. 2) Contractor shall submit a proposed Format and Content of the O&M manuals within thirty (30) days of the

Notice to Proceed. Format and Content of O&M manuals shall be subject to approval of the Authority. 3) O&M manuals MUST be specific to the design, features, functions and characteristics of the Goods

delivered to the Authority. 4) O&M Manuals shall contain complete equipment and component drawings, electrical schematics,

equipment and component descriptions. 5) O&M Manuals shall contain exploded parts drawings and complete parts listings indexed to the exploded

parts drawings. 6) O&M Manuals shall contain comprehensive trouble shooting and repair procedures for every major

component or subsystem. 7) O&M manuals shall contain comprehensive operator instructions, including descriptions of all controls,

indicators and displays; and all error messages, meaning and action. 8) Number of Manuals to be supplied shall be:

a) Six (6) hard copies

Page 9: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 9 of 51 September 2011

b) One (1) soft copy on CD in .PDF format 1.10 MATERIALS

1) Unless otherwise indicated, it is understood and agreed that any materials purchased or otherwise incorporated into the supplied Goods by the Contractor shall be NEW and UNUSED. If required by the Authority, the Contractor will furnish satisfactory evidence as to the kind and quality of materials and equipment.

2) Whenever an item of material or equipment to be incorporated into the Goods is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Contractor or manufacturer, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or equal” item is permitted, other items of material or equipment or material or equipment of other suppliers or manufacturers may be submitted to Owner for review and approval. a) If in Owner’s sole discretion, such an item of material or equipment proposed by Contractor is

functionally equal to that named and sufficiently similar so that no change in related work will be required, it may be considered by Owner as an “or equal” item.

b) For the purposes of this clause, a proposed item of material or equipment may be considered functionally equal to an item so named if: i) in the exercise of reasonable judgment, Owner determines that:

(1) it is at least equal in quality, durability, appearance, strength, and design characteristics; and (2) it will reliably perform at least equally well the function imposed by the design concept of the

completed Project as a functioning whole; and ii) Contractor certifies that:

(1) there is no increase in any cost including capital, installation or operating to Owner; and (2) the proposed item will conform substantially, even with deviations, to the detailed requirements

of the item named in the Contract Documents. 3) The Owner will be allowed a reasonable time within which to evaluate each proposal or submittal made

pursuant to Paragraph 2 of MATERIALS. Owner will be the sole judge of acceptability. No “or equal” will be ordered, manufactured or utilized until Owner’s review is complete, which will be evidenced by an approved Shop Drawing. Owner will advise Contractor in writing of any negative determination. Notwithstanding Owner’s approval of an “or equal” item, Contractor shall remain obligated to comply with the requirements of the Contract Documents.

4) The Owner may require Contractor to furnish at Contractor’s expense a special performance guarantee or other surety with respect to any such proposed “or-equal.”

5) Contractor shall provide all data in support of any such proposed “or equal” at Contractor’s expense.

Page 10: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 10 of 51 September 2011

2.0 GROUND POWER UNIT EQUIPMENT SPECIFICATIONS 2.1 GENERAL REQUIREMENTS

1) The Ground Power Unit (GPU) shall be capable of providing dual output power to an aircraft docked to the PBB at voltages of 90kVA 400Hz Vac simultaneously on both output cables. The unit shall be mounted under the cab of the PBB; utilizing the mounting holes of the existing Jetway JP2 120kVA dual output 400Hz GPU.

2) The unit design shall be based on a Pulse Width Modulated (PWM) design for maximum efficiency. 3) The PBB at Gate B37 has a 250 amp adjustable circuit breaker mounted in the PBB disconnect cabinet

located at the PBB Rotunda (See EXHIBIT II). This circuit breaker is currently utilized for the main power to the PBB and to the existing 120kVA dual output GPU. The existing 1/0 AWG power cable in the PBB cable carrier used for the PBB and GPU is insufficient for the service load requirements of the PBB and the new 180kVA 400Hz Dual Output GPU. Therefore, the Contractor will be required to supply an additional adjustable 250 amp circuit breaker for the 180kVA 400Hz Dual Output GPU power. Input power for this new breaker shall be tapped off the existing PBB/GPU breaker. This new breaker shall be capable of being Locked or Tagged out. a) The existing PBB/GPU breaker will then be dialed down and this electrical circuit will only be used for

PBB power. a) The existing 2-breaker shut off linkage shall be reused for the PBB only and PCAir disconnects. A new

handle shut off mechanism will be supplied for the new adjustable 250 amp GPU circuit breaker. The shut off handle shall be mounted on the exterior of the SST disconnect cabinet door and shall engage the circuit breaker’s shut off mechanism when the SST disconnect cabinet door is closed.

b) The existing 1/0 AWG power cable in the PBB cable carrier will be reused for PBB power only. The Contractor shall supply a new 3/0 AWG, 3C-W/G, 600V SO cord input power cable and aluminum dogleg, to provide input power for the new 180kVA 400Hz Dual Output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements.

b) The contractor shall remove the old GPU input power cable from the C2 junction box and plug the hole in the C2 junction box (See EXHIBIT IV).

4) The PBB at Gate B47 has separate circuit breakers mounted in the PBB disconnect cabinet located at the PBB Rotunda for the PCAir, GPU and PBB (See EXHIBIT II). The GPU circuit breaker is currently set to 125 amps. It can be dialed up to the 200 amps required for the new 180kVA 400Hz Dual Output GPU. The existing 2 AWG flat pack power cable in the PBB cable carrier used for the 120 kVA 400Hz GPU is insufficient for the service load requirements of the new 180kVA 400Hz Dual Output GPU. Therefore, the Contractor will be required to supply a new input power cable from the existing GPU circuit breaker in the PBB disconnect cabinet to the new 180kVA 400Hz Dual Output GPU. a) The existing GPU breaker will be dialed up to 200 amps. c) The Contractor shall supply a new 3/0 AWG, 3C-W/G, 600V SO cord input power cable and aluminum

dogleg, to provide input power for the new 180kVA 400Hz Dual Output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements.

b) The Contractor shall disconnect the existing 2 AWG flat pack cable from the GPU breaker in the PBB Disconnect Cabinet and from the existing 120kVA 400Hz GPU. The ends of the cable shall be shrink wrapped, coiled and secured to the PBB Rotunda Rigid Frame and the PBB C Tunnel (See EXHIBIT IV).

5) The new 180kVA GPU shall utilize the existing Pendant Control (s) and PBB interlock.

Page 11: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 11 of 51 September 2011

6) The GPU design proposed by the Contractor shall have been IN USE for a minimum of five (5) years. Specific prior projects documenting compliance to this requirement shall be supplied with the Contractor’s Proposal. Contact information shall also be supplied for these projects.

2.2 APPLICABLE CODES AND STANDARDS

The following codes and standards shall apply to the supplied Ground Power Unit and any / all mounting brackets and hardware. 1) Material: Structural Plate/Steel/Shapes: ASTM-A36; Structural Tube: ASTM-A500; Steel Plate: ASTM-

A514; Bolts: High Strength SAE-J429 Grades 5 & 8 or ASTM-A325 & A440. 2) Electrical: All equipment and methods of installation shall conform, where applicable, to the requirements

and recommendations of the Institute of Electrical and Electronic Engineers (IEEE), National Electrical Manufacturers Association (NEMA AB1 and NEMA 250), the National Electrical Code (NEC), American National Standards Institute (ANSI C2), National Fire Protection Agency (NFPA 70); all latest issue; and State, County and Local construction and electrical codes.

3) Paint: Surface preparation and painting shall conform to the guidelines and standards of the Structural Steel Painting Council (SSPC).

4) Certification: The Ground Power Unit shall be certified for Compliance to the following US and International Standards by the 3rd party Nationally Recognized Testing Laboratory (NRTL), such as ETL. Evidence of such certification MUST be supplied with the Contractor’s Proposal. Failure to provide the required Certification will cause the Proposal to be non-compliant and it shall be rejected. a) ANSI/UL 1012, latest edition (Standard for Power Units Other Than Class 2) b) CSA C22.2 No. 107.1-01, latest edition (General Use Power Supplies)

5) Other Applicable Codes and Standards, latest edition a) DFS-400 (Euro-standard, 400 Hz) b) MIL-STD-704E (Aircraft Electrical Power Characteristics) c) MIL-STD-461B (Electromagnetic Interference Characteristics) d) ARP-5015 (SAE, Aerospace Recommended Practices) e) ARP-1940 (SAE, Aerospace Recommended Practices for Solid State Frequency Converters. f) ARP-1247 (SAE, Aerospace Recommended Practices for 400 Hz Ground Power Performance

Requirements)

2.3 NOMINAL RATING 1) For AC Voltage – 180kVA at .8 power factor load on the output

2.4 INPUT POWER 1) Input Voltage: The GPU shall operate with input voltages not varying more than plus 10% or minus 15% of

nominal voltage rating. 2) Input Frequency: The GPU shall operate on 50/60 Hz input power frequencies. 3) Input Current Requirements at Rated Load: The nominal input current at rated load shall be 480 Vac and a

MAXIMUM of 200 amps at full rated load. 4) Input Inrush Current: On start up the GPU shall withstand inrush current of up to 100% of that input current

required when the GPU is operating at rated load output. 5) Input Power Factor: The GPU shall operate with an input power factor to .95 or greater at loads of 25% to

100% of the nominal rated load for the unit. 6) Input Phase Rotation: The GPU shall be input phase rotation independent, allowing the GPU to be

connected to the incoming power without regard for phase rotation.

Page 12: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 12 of 51 September 2011

7) Input Harmonic Distortion: shall be a maximum of 10%. 8) Efficiency: The overall efficiency of the GPU shall not be less than 91% at 50% or greater load. 9) Input Power Break: The GPU shall be capable of supplying uninterrupted power to the aircraft during a

micro break on the input power. 10) Input Circuit Breaker: The GPU will contain an internally mounted circuit breaker on the input power line(s)

to allow the input power to be removed in the case of a fault or for maintenance. 11) Input Power Disconnect: A new adjustable, 250 amp maximum, lockable circuit breaker shall be added to

the main PBB disconnect at the Rotunda. The circuit breaker supplied shall be the same as the existing circuit breakers in the Disconnect Cabinet; or an Authority approved equal. In addition, a new handle shut off mechanism will be supplied for this circuit breaker. The shut off handle shall be mounted on the exterior of the SST disconnect cabinet door and shall engage the circuit breaker’s shut off mechanism when the SST disconnect cabinet door is closed.

12) Unit Disconnect Breaker: The GPU shall be equipped with either a) a fixed mounted shunt trip breaker or b) a switch that shuts off power to the output cables, shuts down the SCR’s and discharges lethal power from the DC Bus. This breaker or switch shall also serve as a door or panel interlock which will activate when the main panel door is opened. A bypass door interlock switch shall be provided to allow testing and repair of the unit with the doors opened.

2.5 OUTPUT POWER – 400Hz AC

1) Output Voltage: Shall be adjustable by plus or minus 10% of 115 Volts. 2) Output Voltage Drift: The output voltage shall not change by more than 1% of its originally set value with

the unit operating at a constant load, a change in ambient temperature up to 55 degrees C in an eight hour period or as the unit stabilized from a cold condition at any load.

3) Output Voltage Regulation: Voltage regulation shall not exceed ± 1% from no load to full load and from rated load to no load with ± 10% input voltage. Output voltage shall recover to the steady state condition less than 50 ms after any load change up to 100%. The voltage shall not exceed the limits of MIL-STD-704E during transient recovery.

4) Output Voltage Distortion (Total Harmonic Distortion): Total harmonic distortion on the output voltage waveform shall not exceed 3% (line to line/line to neutral) with any rated load up to 100% load. Any single harmonic will not exceed 2%.

5) Output Voltage DC Content: The DC voltage at the output terminals will not exceed 0.1 volts under any rated load conditions.

6) Output Voltage Modulation: The modulation of the voltage waveform shall not exceed 0.5% as measured from the peak of one waveform to the peak of another adjacent waveform under steady state, rated load conditions.

7) Output Voltage Balance: The maximum output voltage deviation of any of the three output phases will not exceed 1% from the average of the three output phase voltages under balanced load conditions. Voltage unbalance shall not exceed 3 volts, with 10% unbalanced load on 1 phase and shall meet MIL-STD-704E, figure 1 and ARP1940, 3.1.5.10.

8) Output Frequency Regulation: Shall be 400 Hz plus or minus 0.1% at any rated load condition. 9) Output Frequency Modulation: Shall be less than ± 0.25% of the period of output voltage wave. 10) Output Phase Displacement: The phase angle between each of the three output phases will be 120 degrees

plus or minus 1.5 degrees under all rated, balanced load conditions. The phase angle displacement with an unbalanced load of 15% the unit’s rated current shall be 120 degrees plus or minus 4 degrees.

11) Output Current: 90kVA (260 amps) at .8 power factor load continuous, simultaneously on both outputs. 12) Bus Capacitors: Bus capacitors shall be the polypropylene type and not electrolytic capacitors.

Page 13: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 13 of 51 September 2011

13) No Break Power Transfer: The GPU must be capable of continuous operation during a switch from the Aircraft APU to the GPU.

14) Line Drop Compensation: The GPU shall have a built-in automatic line drop compensation, which shall be adjustable from 1% to 8% of rated voltage at rated load.

15) Power Factor: The GPU will be capable of operating with an output power factor of 0.0 to 1.0. 2.6 OVERLOAD

1) Overload Capacity: The GPU shall be capable of supplying overloads of up to 125% for 10 minutes, 150% for 30 seconds, and 200% for 10 seconds.

2) Short Circuit Capability: The GPU shall withstand an output short and the short shall be cleared by internal solid-state circuitry.

2.7 FAULT SYSTEMS 1) The GPU will be capable of monitoring the following items and shutting down in the event they are out of

tolerance. The faults listed below will be displayed. a) Input voltage 10% higher than nominal rating b) Input voltage 15% less than nominal rating c) Output voltage less than 100 Vac per MIL-STD-704E d) Output voltage greater than 125 Vac per MIL-STD-704E e) Output overload f) No 28vdc returned on EF wires g) EF wire voltage greater than 60v h) DC bus faults i) Over temperature of heat sink j) Output frequency fault

2) The GPU shall be capable of performing a “self-check” of the output power quality before allowing power to be supplied to the aircraft.

2.8 INDICATORS

1) The GPU shall display the following information using an LCD or LED or via downloading to the Owner’s laptop PC via an RS232 port. If the use of an RS232 port interface is required, the Contractor shall supply the necessary cables and software to connect to the Owner’s laptop to the GPU, retrieve and display the required data. a) Input voltage – each phase and average b) Input current – 3 phase average c) Output voltage – each phase and average d) Output current – each phase and average e) Output kVA (total) or Vdc (total) f) Output frequency g) Event History. h) Unit Settings

3) Front panel lights will indicate the following: a) Fault occurred b) Input voltage applied to unit c) 28Vdc bypass switch in bypass position d) Output voltage present, unit is connected to aircraft and operating

Page 14: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 14 of 51 September 2011

e) 28Vdc EF voltage missing

2.9 SWITCHES AND CONTROLS 1) The new GPU and the existing Cable Hoists shall be controlled by the existing Pendant Controls mounted

near the wheel bogie of the PBB. These existing Pendant Controls and existing cabling to the GPU shall be reused.

2) The following controls and indicators shall be located on the outside of the GPU unit: a) Start / Stop / Reset for 400Hz and 28 Vdc outputs b) 400Hz operate light – green LED lamp with clear lens c) 28Vdc Bypass switch d) Fault displays and error messages e) LCD contrast, if LCD screen is supplied

3) The following controls and indicators shall be located on the outside or inside of the GPU unit: a) Line drop compensation adjustment b) Voltage adjustment ( ± 10%) c) Hour meter (99,999 hours)

2.10 EXTERNAL INTERFACE 1) The GPU shall contain either a) externally pluggable connectors or b) internally mounted terminal blocks for

the GPU Pendant Control and PBB Interlock. 2) Internally mounted terminal blocks shall be used for connecting the GPU output cable and any control

functions from the GPU output cable, pendant control or PBB interlock. All connection points shall be clearly labeled as to the function that will connect to them from the GPU output cable, pendant control and PBB interlock. The terminal blocks for the GPU output cables shall be “stud” type.

3) The Contractor shall utilize the existing GPU’s mounting bracket holes under the cab of the PBB and shall supply new mounting brackets and hardware to install the new GPU under the PBB cab.

4) The GPU shall have yellow and black safety tape applied to the bottom circumference of the GPU. 2.11 PHYSICAL CHARACTERISTICS

1) Weight: The GPU shall weigh no more than 2,000 pounds. 2) Cabinet Dimensions: The GPU shall be mountable under the Cab of the PBB and shall utilize the existing

GPU’s mounting bracket holes. 3) Cabinet Material: The cabinet will be constructed from painted anodized aluminum. The Authority will

choose from the Manufacturer’s standard colors. The Authority would prefer the exterior color of the new GPU’s closely match the “Dulles” gray color of the PBB’s.

4) Weather Rating: The GPU’s cabinet / enclosure shall be rated as NEMA 3R or IEC IP54. 5) Wiring: All internal and external wires or cables shall be numbered or labeled. 6) Connectors: All connectors shall be unique to the point of connections on the boards 7) Terminal Blocks: All wire splicing and connections shall be accomplished on terminal blocks. Wire

splicing, twist connectors, etc. shall not be permitted. 8) Acoustical Noise: The GPU shall not emit more than 70 dBA at 1.5 meter height and 1.0 meter distant. 9) Temperature Rating: The GPU shall be capable of operating temperature of -40 to +55°C.

Page 15: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 15 of 51 September 2011

2.12 OTHER DESIGN REQUIREMENTS 1) The GPU shall be sectional in design. Transformer section shall be isolated and separate from the front and

back sections of the unit. 2) Wires used inside the GPU shall be rated for the maximum voltage and amperage being applied to the wires

during normal operation and overload conditions prior to the unit shutting down. 3) Vertical cooling towers or heat sink shall be utilized to cool sensitive internal electronic components. 4) Cooling Fans shall cool the cooling tower or heat sinks. Any fans that circulate air into the interior of the

GPU must utilize input air that is filtered. The filters shall be easily accessible and removable for cleaning. The filters shall be a washable mesh type.

5) Interior of the unit shall be sealed so that contaminates brought into the unit by cooling fans will not enter the control sections of the unit.

6) All control boards must be mounted in a card rack OR a board specific location. 7) All connection to the boards shall be accomplished by plug in connectors 8) Each connector must be unique to its point of connection to eliminate misconnections 9) Each connector shall be labeled along with all its wire connections 10) All wires, including spares, within GPU shall be neatly secured and routed. Wire routing trays shall be used

when interior space permits. 11) Grommets and suitable anti-chafe material shall be used where wires are required to pass through structure

or similar relief or opening which exposes the wire to possible chafing. 12) Wire ties SHALL NOT be used to securing any wiring. NEC / UL approved clamps and methods must be

used to secure wiring. Wire clamps shall NOT utilize a self-adhesive method of mounting. 13) Wires shall not be pulled tight in the GPU or subjected to chafing or damage vibration of the GPU or by the

operation of the PBB. Wires shall not droop or sag in their routing. 14) The front and rear door of GPU shall be hinged to allow for maintenance and equipped with a door interlock

switch that trips the unit’s main shunt trip breaker when opened. The door interlock must be able to be by-passed for maintenance access to the unit.

15) The front and rear door of GPU shall be lockable to prevent unauthorized access into the unit. There shall be two lockable latches on each door, on either side of the door.

16) The GPU shall be able to provide the required signal to the PBB and provide a suitable connection for the interlock wiring.

17) Attached to the interior of the GPU’s front door shall be a laminated component drawing with a list of components identified with a description and manufacture’s part number. Also attached shall be a wiring schematic showing the exact wiring of the GPU’s front compartment section.

18) Attached to the interior of the GPU’s rear door shall be a laminated component drawing with a list of components identified with a description and manufacture’s part number. Also attached shall be a wiring schematic showing the exact wiring of the GPU’s rear compartment section.

19) Attached to the interior of the GPU’s rear door shall be a laminated component drawing, for the interior compartment of the GPU, with a list of components Also attached shall be a wiring schematic showing the exact wiring of the GPU’s interior compartment section.

20) If the GPU’s front and / or rear doors are equipped with electrical controls or components, the doors shall be equipped with grounding straps.

21) Grounding straps used on the GPU shall be braided. Wire type straps shall not be allowed. 22) The GPU shall be equipped with a desiccant filter or other means of removing moisture from the sections of

the GPU containing the circuit boards. 23) An unused holes or penetrations in the exterior of the GPU shall be plugged. If the holes are threaded, SST

bolts shall be used to plug the hole.

Page 16: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 16 of 51 September 2011

2.13 CABLES AND CABLE HOISTS

1) The existing Cable Hoists and Output Cables shall be reused. 2.14 INPUT POWER, CIRCUIT BREAKER, SO CORD AND DOGLEG

1) In addition to the requirements listed below, EXHIBIT III and EXHIBIT IV contain additional information and requirements for the input power circuit from the PBB Disconnect Cabinet to the new 180kVA 400hz Dual Output GPU’s.

2) The Contractor shall supply and install a 3-tunnel PBB aluminum dogleg, which will be required to route the SO cord for the input power supply for the new 180kVA 400Hz Dual Output GPU’s. The PBB’s at Gate B37 and B47 are Jetway A3-68/141’s. The dogleg shall be JBT Jetway Systems P/N 2102461-506 or an Authority approved equal. Installation shall conform to the requirements of JBT Jetway Systems drawings 2102461, Rev 2, Sheet 1 & 2 and 2931001 Rev -, or Authority approved equal. See EXHIBIT III.

3) The Contractor shall install the dogleg mounting brackets onto left side rear lower corner of B and C tunnels and on the left side forward corner of the rotunda rigid frame. The brackets shall be welded onto the PBB and kept parallel to each other. The weld shall be a full penetration weld, clean of all burrs, spatter and carbon. The weld area shall be primed and painted to match the PBB

4) The Contractor shall install the proper length 3/0 AWG, 3C-W/G, 600V SO cord FROM the GPU circuit breaker in the SST Disconnect Cabinet on the PBB rotunda TO the new 180kVA 400Hz Dual Output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements.

5) The SO cord shall be a single run from the SST disconnect cabinet at the PBB rotunda, through the dogleg and then through conduit / cable tray on the C Tunnel, to the new 180kVA 400Hz Dual Output GPU unit. No intermediate junction boxes will be allowed.

6) The Contractor shall use strain relief to secure the SO cord to the side panel of the SST disconnect cabinet mounted on the PBB rotunda. The SO cord shall be routed along the rear of the disconnect cabinet and up the left side of the PBB rotunda column. The SO cord shall be secured using a strain relief at the bottom rotunda rigid frame so that the SO cord forms a loop prior to the double dogleg.

7) SO cord bushing/grommets shall be used to seal the penetration where the SO cord enters the SST disconnect cabinet.

8) SO cord bushings/grommets shall be installed at the top or bottom hinge points of each section of conduit in the dogleg, depending on location of “Kellum” grips.

9) “Kellum-grip” type stainless steel mesh strain relief grips shall be used on the SO cord on the top or bottom hinge points of the dogleg. Kellum-grips shall be attached using a threaded collar and shall have a bushing to protect the SO Cord from damage. Threaded collar and bushing shall be installed at the opposite end of the dog leg pipe from the Kellum-grip to protect the SO Cord from damage.

10) Ground straps shall be installed at the points of intersection between the hinge points of the dogleg. 11) Conduit on C Tunnel shall be threaded on both ends and SO cord grommets/bushings shall be used at

both ends of the conduit. If cable tray is used on the conduit, SO Cord grommets / bushings shall be used at all cable entry and exit points.

12) Conduit bridge clamps and self-tapping screws shall be used to fasten the conduit to the low corrugated pan sections of the floor of the PBB.

13) Rubber insulated “Adel” type cable clamps and self-tapping screws shall be used to fasten SO cord to PBB.

14) A threaded SO cord bushing/grommet shall be used in the hole of the GPU for the input power cord.

Page 17: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 17 of 51 September 2011

15) A “drip-loop” must be built-into the SO cord where it enters the GPU’s interior Power Panel. To accomplish this, SO cord must enter the side of the unit’s main Power Panel, approximately ½ of the distance from the top of the Power Panel.

16) Sufficient SO cord loops shall be left at all dogleg hinge points to prevent cord damage. 17) At Gate B37, the Contractor shall supply and install a new 250 amp, adjustable circuit breaker for the

new 180kVA 400Hz Dual Output GPU to the left of the existing PBB / 400hz 250 amp adjustable circuit breaker. The circuit breaker shall match the existing 2 circuit breakers, or be an Authority approved equal. a) Input power for the new GPU circuit breaker shall be “tapped” off the existing input power to the

PBB / 400Hz circuit breaker. b) One 110V circuit breaker will have to be relocated. c) The existing PBB / 400Hz circuit breaker, dialed down to the lowest setting, will be reused for the

PBB only. d) The existing input power 1/0 AWG cable, which is in the PBB cable carrier, will be reused for the

PBB only. e) The existing 2-breaker shut off linkage shall be reused for the PBB only and PCAir disconnects. A new

handle shut off mechanism will be supplied for the new adjustable 250 amp GPU lockable circuit breaker. The shut off handle shall be mounted on the exterior of the SST disconnect cabinet door and shall engage the circuit breaker’s shut off mechanism when the SST disconnect cabinet door is closed. The new shut off handle shall match the existing shut off handle.

f) The Contractor shall remove the existing input power cable from the C2 junction box to the existing 120kVA dual output GPU and plug the hole in the C2 junction box (See EXHIBIT IV).

18) At Gate B47, the Contractor shall dial up the existing adjustable circuit breaker to 200 amps for the new 180kVA 400Hz Dual Output GPU. a) The existing input power 2 AWG cable, which is in the PBB cable carrier, is insufficient for the new 180

kVA 400Hz Dual Output GPU. b) The Contractor shall disconnect the existing 2 AWG flat pack cable from the GPU breaker in the PBB

Disconnect Cabinet and from the existing 120kVA 400Hz GPU. The ends of the cable shall be shrink wrapped, coiled and secured to the PBB Rotunda Rigid Frame and the PBB C Tunnel (See EXHIBIT IV).

19) All exterior electrical components, including terminal blocks / terminal strips, shall be housed in weather tight, stainless steel (SST) enclosures of NEMA 3R or 4 rating. The enclosures cover shall be hinged and have SST latches or self-retaining screws. The enclosure covers shall also have a weather gasket.

20) All pass through junction boxes shall be housed in weather tight, stainless steel (SST) enclosures of NEMA 3R or 4 rating. The enclosures cover shall be hinged and have SST latches or self-retaining screws. The enclosure covers shall also have a weather gasket.

21) Strain relief shall be provided for all unsupported cables. 22) No standard electrical and/or communication service conduit or SO Cord shall be permitted on the exterior

sides of the PBB Tunnels. 23) Spare wires shall be numbered and also labeled as “SPARE”. Spare wires shall be indicated on the

electrical schematics. Spare wires shall be neatly secured in the relevant junction box. 24) All wiring shall be brought to terminal blocks. The wiring shall be formed and restrained to give a neat

appearance. Wire splices of any type shall NOT be used. Terminals must meet the applicable requirements of SAE J561, J858 and J928.

25) Wiring terminals must be protected by insulating boots or heat-shrinkable tubing.

Page 18: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 18 of 51 September 2011

26) Grommets and suitable anti-chafe material shall be used where wires are required to pass through structure or similar relief or opening which exposes the wire to possible chafing.

27) Quick Disconnect fittings must be MS standard receptacles and plugs and shall be UL or ETL approved. 28) Wire ties SHALL NOT be used to securing any wiring. NEC / UL approved clamps and methods must be

used to secure wiring.

2.15 CERTIFICATIONS 1) The GPU shall be certified by a NRTL for compliance to UL-1012 and CSA-C22.2 No. 107.1-01. Evidence

of such certification must be supplied with the Contractor’s Proposal. 2) The GPU shall be UL Certified and a UL Certification name plate must be affixed to the GPU.

Page 19: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 19 of 51 September 2011

3.0 INSTALLATION SPECIFICATIONS 3.1 GENERAL REQUIREMENTS

1) The installation activities for this project shall be planned and executed in a manner so as to minimize the impact on existing operations at Gate B37 and B47. Within thirty (30) days from the Notice to Proceed, the Contractor shall submit their Installation Methods Statement, which shall include, but not be limited to: a) Site Safety Plan and Program b) How Contractor / Subcontractor will ensure compliance to all relevant codes and regulations during

installation activities. These shall include, but are not limited to i) FAA Regulations ii) OSHA Regulations iii) IAD Safety and Security Procedures iv) MWAA Construction Safety Manual v) State, County and Local Construction and Electrical Codes vi) NEC vii) NEMA

c) Description of equipment delivery and off-loading process to be used. d) Description of GPU installation procedures. This should be based on the Manufacturer’s Installation

Manual, modified for the requirements of this specific project. e) Description of equipment acceptance testing. f) Description of how punch list items are identified, fixed, tracked and verified as complete. g) Use of barriers to segregate installation activities from other AOA activities. h) Proposed Site Manager and his / her qualifications.

2) The purpose of this Methods Statement is to ensure the Contractor and their Subcontractor(s) completely understand and have planned for ALL of the Installation requirements for this Project.

3) The Authority reserves the right to approve the Subcontractor selected by the Contractor to perform the Installation Scope of Work.

4) A full time Site Manager shall be utilized by the Contractor and he/she shall be present at IAD for ALL project Installation Activities and shall directly supervise and control all work activities, employees, and other Subcontractors and their employees. This Site Manager shall have a minimum of 5-years’ experience as a Site Manager directly supervising GPU installations on PBB’s. This Site Manager shall be an employee of the Contractor or the selected Subcontractor. The Resume’ or CV of the Site Manager shall be submitted to the Authority for review and approval 30 days after the NTP is issued.

5) The Contractor’s Site Manager shall coordinate all installation activities with the Authority’s representative. The Authority’s representative will provide subsequent coordination with any affected airlines. The Contractor’s Site Manager shall keep the Authority informed on a daily basis of the projects progress.

6) The Contractor’s Site Manager shall also function as the Contractor’s Site Safety Manager and coordinate all safety related issues and activities with the Authority’s and airline’s Safety Managers. The Contractor’s Site Manager shall have the necessary training, background and experience to perform the function of Safety Manager. Documentation of qualifications to perform the function of the Site Safety Manager MUST be in the Site Manager’s Resume which is submitted to the Authority for approval.

7) The Authority reserves the right to approve the Site Manager proposed by the Contractor and /or Subcontractor.

8) The Contractor shall be responsible to obtain any required licenses and permits required to carry out the Installation activities and Scope of Work.

Page 20: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 20 of 51 September 2011

9) The Contractor’s Site Manager and other representatives from the Contractor and/or Subcontractor shall be required to obtain badging at IAD. THE AUTHORITY WILL PROVIDE NO ESCORTS.

10) The Air Operations Area (AOA) and facilities at Dulles International Airport are smoke-free. The Contractor is required to ensure that all of its personnel and subcontractors adhere to and abide with the smoking policy and designated smoking areas at IAD.

11) Contractor and/or Subcontractor shall provide all tools, equipment, vehicles, consumables, supplies required to complete the Installation Scope of Work.

12) The Contractor will shall obtain a Burn Permit from the MWAA Fire Marshal at IAD PRIOR to any welding or torch cutting.

3.2 APPLICABLE CODES AND STANDARDS

1) IAD Security, Badging, AOA Access, Safety and Construction Policies and Procedures 2) State, County and Local Construction and Electrical Codes 3) DOT 14 CFR Part 107 - Airport Security 4) DOT 14 CFR Part 157 - Notice of Construction, Alteration, Activation and Deactivation of Airports 5) NEC (National Electric Code) 6) NEMA (National Electrical Manufacturers Association

3.3 INSTALLATION REQUIREMENTS

1) For the installation of the new 180kVA Dual Output 400Hz GPU’s, the Contractor shall be responsible to: a) Remove the existing Jetway JP2 120kVA Dual Output 400Hz GPU and turn it over to the Authority. b) Utilize the existing Pendant Control(s), Cable Hoists, Output Cables, PBB interlock. c) Install the new 180kVA 400Hz Dual Output GPU’s and reinstall the connections to the Pendant

Controls, Output Cables and PBB Interlock. Mounting brackets shall utilize existing mounting holes in the PBB cab structural members.

d) Secure all control wiring using black-colored wire “Tie-Wraps” and correctly mark and label all power and control wires

e) Install / modify the input power circuit for the new 180kVA 400Hz Dual Output GPU’s. f) Modify the building circuit breakers per the requirements of the Specifications (see EXHIBIT V). All

modifications must be coordinated with the Authority’s COTR. g) Employee a local testing company, which must be NETA Certified:

i) At B37, verify that the new GPU circuit breaker, the now PBB only circuit breaker, and the circuit breaker for the 250 amp circuit supplying power to the SST Disconnect are correctly set and do trip at the correct loads. Verify that the building circuit breaker thermal trip has been correctly modified and does trip at the required load.

ii) At B47, verify that the GPU circuit breaker and the building circuit breaker have been adjusted to the correct amp settings and do trip at the required load.

iii) The testing company must adjust, test and certify the new breaker settings and provide written documentation that the breakers have been tested and are functioning properly.

h) Conduct resistive AND reactive load testing of both outputs from the new GPU’s. Prepare and submit document test results of load testing.

i) Verify that the PBB interlocks for the GPU’s and the Cable Hoists are active and functioning correctly. 2) Contractor shall be responsible to collect and dispose of any waste materials, including any hazardous

wastes associated with paint touch up, lubricants, etc. 3) Contractor shall maintain the apron area in a clean and orderly manner during installation activities. At the

close of each shift, all tools and equipment shall be appropriately stored. All waste materials shall be

Page 21: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 21 of 51 September 2011

collected and disposed of. All parts shall be collected and organized in an orderly fashion near the terminal building.

4) Contractor shall utilize Authority approved barriers to segregate the work area around the PBB at Gates B37 and B47.

3.4 SUBSTANTIAL COMPLETION, PUNCH LISTS, FINAL ACCEPTANCE

1) Upon completion of Installation Scope of Work, including any required testing, the Authority will accept the equipment as Substantially Complete.

2) In order to be Substantially Complete, the Equipment must be fully installed and operational and be able to use by the Authority and airlines as intended.

3) The Authority’s representative and the Contractor’s Site Manager shall jointly develop a Punch List of any outstanding work, defects or non-compliances. At this time a Completion Date for the Punch List works shall be agreed to by the Authority’s representative and Contractor’s Site Manager.

4) The Contractor shall complete this Punch List work within the agreed upon completion date. Upon the completion of the Punch List work, the Authority will issue a Final Acceptance of the equipment.

Page 22: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 22 of 51 September 2011

4.0 QUALITY ASSURANCE 4.1 GENERAL REQUIREMENTS

1) The quality assurance requirements for this project shall focus on ensuring Contractor designs, manufactures, delivers and installs the required equipment that fully complies with the requirements of this Specification.

2) The quality assurance requirements shall consist of: a) The Contractor’s and Manufacturer’s Quality System – Consisting of the Contractor’s Quality Manual

and Quality Procedures b) The Contractor’s Quality Plan – The Quality Plan developed by the Contractor to ensure all

requirements of this RFP and Specification are met. c) Contract Review and Design - The Specification Compliance Document, drawings, cut sheets,

calculations, third party certifications, test results, etc. submitted by the Contractor for review and approval of the Authority.

d) GPU Manufacturer’s Material Receipt, In-Process Manufacturing and Final Inspections – All receiving, in-process and final inspection documents and reports shall be submitted for review and approval of the Authority.

e) Factory Acceptance Testing – GPU Manufacturer shall conduct Factory Acceptance Testing to ensure all equipment meets the design requirements of this Specification. The Contractor shall submit reports of such acceptance testing for review and approval of the Authority.

f) Authority Inspection prior to Shipment – The Authority reserves the right to perform an in-factory inspection of all equipment PRIOR to shipment. This inspection shall review compliance to the Specifications and to ensure all equipment has passed Factory Acceptance Testing. Witness of certain Factory Acceptance Testing shall also be part of this in-factory inspection. Travel, lodging, per diem and other costs for the Authority’s representatives to conduct any subsequent inspections required, should the equipment fail the initial inspection, shall be the responsibility of the Contractor.

g) Contractor’s Installation In-Process and Punch List Completion Inspection – All Installation In-Process and Punch List Completion inspection documents and reports shall be submitted for review and approval of the Authority.

h) Authority In Process Installation Inspection – The Authority’s representative will perform an in process inspection during the Installation process.

i) Functional Testing – As part of the installation process, the Contractor shall conduct Functional Testing to verify the equipment meets certain functional requirements of the Specification. This shall include both resistive and reactive load testing of the GPU’s. All test reports from such Functional Testing shall be submitted to the Authority for review and approval.

j) Authority Final Inspection – The Authority’s representative will perform a final inspection after Substantial Completion is achieved on all equipment. At this time, a Final Punch List will be generated, identifying all non-conformances with the Goods and Services and the agreed upon date between the Authority and the Contractor for the Contractor to remedy all non-conformances.

4.2 CONTRACTOR’S QUALITY PLAN

1) The Contractor shall develop a Quality Plan that identifies the relevant inspection points and acceptance criteria that will be utilized by the Contractor to ensure all of the requirements of the Specification are met.

Page 23: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 23 of 51 September 2011

2) The Quality Plan shall identify the inspection and review points during the contract review, design, manufacturing and installation where the Contractor will perform inspections or tests to ensure compliance to the Specifications.

3) The Quality Plan shall identify the scope of the inspections and tests and the specific acceptance criteria that will be utilized by the Contractor for each inspection and test.

4) The Quality Plan shall also identify the test plan, procedures, methods, techniques, etc. that will be utilized by the Contractor to conduct the required FACTORY ACCEPTANCE TESTING AND ON-SITE FUNCTIONAL TESTING

5) The Contractor shall submit their Quality Plan to the Owner for approval within thirty (30) days of the issuance of the Notice to Proceed.

4.3 NON-CONFORMING GOODS

1) The Owner has the right to disapprove or reject Goods or Services that the Owner believes to be non-conforming.

2) If the Owner elects to reject the Goods or Services in whole or in part, Owner’s notice to the Contractor will describe in sufficient detail the non-conforming aspect of the Goods or Services. If Goods or Services have been delivered to Owner, Contractor shall promptly, and within the Contract Times, remove and replace or modify the rejected Goods or Services.

3) Contractor shall bear all costs, losses and damages attributable to the removal and replacement or modification of the non-conforming Goods or Services.

4) Upon rejection of the Goods, Owner retains a security interest in the Goods and Services or to the extent of any payments made and expenses incurred in their testing and inspection.

5) If the Owner elects to permit the Contractor to modify the Goods or Services to remove the non-conformance, Contractor shall promptly provide a schedule for such modifications and shall make the Goods or Services conforming within a reasonable time.

6) Instead of requiring modification or removal and replacement of non-conforming Goods or Services discovered either before or after final payment, Owner may accept the non-conforming Goods or Services. Contractor shall bear all costs, losses, and damages attributable to Owner’s evaluation of and determination to accept such non-conforming Goods or Services.

7) Contractor shall pay all claims, costs, losses, and damages, including but not limited to all fees and charges for re-inspection, retesting and for any engineers, architects, attorneys and other professionals, and all court or arbitration or other dispute resolution costs arising out of or relating to the non-conforming Goods or Services, including the modification or removal and replacement of the non-conforming Goods or Services and the replacement of property of Owner and others destroyed by the modification or removal and replacement of the non-conforming Goods or Services, or the obtaining of conforming Goods or Services from others.

8) Contractor’s responsibility for correcting all non-conformities in the Goods and Services will extend for the Warranty Period as specified in the Contract Documents after the date of Final Acceptance of the Goods and Services, or for such longer period of time as may be prescribed by Laws or Regulations or by the terms of any specific provisions of the Contract Documents.

9) Neither payments made by Owner to Contractor prior to any tests or inspections, nor any tests or inspections shall constitute acceptance of non-conforming Goods, or prejudice Owner’s rights under the Contract.

Page 24: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 24 of 51 September 2011

4.4 INSPECTIONS 4.4.1 INSPECTION PRIOR TO SHIPMENT

1) The Authority reserves the right to conduct a pre-delivery inspection at the GPU manufacturing location and to perform any of the inspections and tests as set forth in the specifications where such inspections are deemed necessary to assure conformity to the specifications and Contract. The Contractor shall supply the Authority’s inspection representative with instruments and all such assistance as they may find necessary. By signing the Agreement, the Contractor gives permission to the Authority to perform such inspections and tests and to do so at the GPU manufacturer’s premises.

2) Contractor shall provide Owner 15-days written notice, prior to shipment, of the readiness of the Goods for the Authority’s inspection.

3) If, on the basis of any inspections or testing, the Goods appear to be conforming, Owner will give Contractor prompt notice thereof. If on the basis of said inspections or testing, the Goods appear to be non-conforming, Owner will give Contractor prompt notice thereof and will advise Contractor of the required remedies and if such remedies must be accomplished prior to shipment and if a subsequent inspection by the Authority’s representative will be required prior to shipment.

4.4.2 INSPECTION UPON DELIVERY

1) Contractor shall inspect the Goods upon delivery at IAD solely for purposes of identifying the Goods and general verification of quantities and observation of apparent condition in order to ensure Goods are acceptable and suitable for installation at IAD. Such inspection will not be construed as final or as receipt of any Goods and Services that, as a result of subsequent inspections and tests, are determined to be non-conforming.

2) Within one (1) day of such receiving inspections, Contractor shall provide Owner with written notice of Contractor’s determination regarding conformity of the Goods. In the event Contractor does not provide such notice, it will be presumed that the Goods are suitable for Installation.

4.4.3 INSPECTION DURING INSTALLATION PROCESS

1) The Authority’s representative will conduct one or more inspections during the Installation process to review the Contractor’s compliance with the Installation Specification and the rectification of any previously identified non-conformities. The Contractor shall supply the Authority’s inspection representative with instruments and all such assistance as they may find necessary.

2) The Authority reserves the right to conduct these Installation inspections, unannounced and at any time during the Installation process.

3) If, on the basis of any inspections or testing, the Goods or Services appear to be non-conforming, Owner will give Contractor prompt notice thereof will advise Contractor of the required remedies and the required completion date of such remedies.

4.4.4 INSPECTION AT SUBSTANTIAL COMPLETION

1) The Authority’s representative will conduct a Substantial Completion Inspections, on a gate by gate basis, when the Contractor has completed the Installation of the Goods at a gate.

2) The Authority’s representative shall review all of the Goods to ensure they are installed properly, that the Services have been completely carried out and that all previously identified non-conformities have been remedied. During this Substantial Completion Inspection, the Contractor shall conduct, with the Authority’s representative as a witness, the specified on-site functional testing of the Goods. The Authority’s

Page 25: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 25 of 51 September 2011

representative will identify any Punch List items that must be remedied by the Contractor during the Substantial Completion Inspection.

3) The Contractor shall provide (2) days written notice to the Authority of the proposed date of Substantial Completion and on-site functional testing.

4) If the Goods are considered by the Owner to be Substantially Complete and useable for the intended purpose, the Contractor shall issue a Substantial Completion Certificate to the Owner. This Substantial Completion Certificate must list all identified Punch List items, must indicate a due date for the completion of the Punch List items and must be approved by the Owner.

4.4.5 FINAL ACCEPTANCE

1) Once the Contractor has remedied all of the Punch List items, the Owner shall be notified to re-inspect the Goods and Services. Upon such notification, the Authority’s representative shall re-inspect the Goods and Services to verify the Punch List items have been remedied.

2) If any of the Punch List items have not been remedied to the Owner’s satisfaction and subsequent inspections are required by the Authority’s representative, the Contractor shall bear any and all costs, including labor, material, travel and per diem, incurred by the Authority to conduct such repeat FINAL ACCEPTANCE inspections.

3) Once all Punch List items are remedied and accepted by the Owner, the Contractor shall issue a Final Acceptance Certificate, indicating the date the Goods and Services have been accepted by the Owner. This date will also be the start date of the Contractor’s Warranty Period.

4.5 FACTORY ACCEPTANCE TESTING

1) The Contractor shall develop a Factory Testing Plan, as part of its overall Quality Plan, which identifies the specific testing to be done at the Contractor’s factory. The Factory Tests, which must be conducted in the GPU manufacturer’s factor, must confirm, to the extent possible, that all features, functions and capabilities of the Goods, as defined in the Specification and Contract Documents, are performing as intended. The Factory Test Plan shall be submitted with the Contractor’s Quality Plan and approved by the Owner fifteen (15) days prior to any Factory Tests being conducted.

2) It is the intent of the Owner that the Contractor shall develop a comprehensive Factory Test Plan, identifying the specifics of the tests to be carried out, and the acceptance criteria of such test, to ensure the Goods comply with the requirements of the Specification and Contract Documents.

3) The Factory Test Plan, shall at a minimum, address the following requirements. In addition, these tests shall be the required Factor Tests to be witnessed by the Owner’s representative(s) if the Owner decides to conduct an inspection prior to shipment, per 4.4.1. a) Input Power

i. Amperage draw at start up ii. Amperage draw, through start up to full load, both outputs.

b) Output Power – 400Hz Vac i. Output voltage and adjustment

ii. Output Voltage Drift iii. Output Voltage Regulation iv. Output Voltage Distortion v. Output Voltage DC Content

vi. Output Voltage Modulation vii. Output Voltage Balance

viii. Output Frequency Drift

Page 26: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 26 of 51 September 2011

ix. Output Frequency Regulation x. Output Current

xi. Output Phase Displacement c) Harmonic Distortion d) All Indictors, lights, displays e) Noise Level

4) The results of the Factory Testing shall be supplied to the Owner prior to shipment. The Owner will NOT approve shipment of the GPU’s without its review and approval of the Factory Test Results.

4.6 ON-SITE FUNCTIONAL TESTING

1) The Contractor shall develop an On-Site Testing Plan, as part of its overall Quality Plan, which identifies the specific testing to be done by the Contractor after the Goods are installed at IAD. The On-Site Testing must confirm that all of the Goods function as intended, alone and in conjunction with each other and provide the required features, functions and capabilities as defined in the Specification and Contract Documents. The On-Site Test Plan shall be submitted with the Contractor’s Quality Plan and approved by the Owner thirty (30) days prior to any On-Site Tests being conducted.

2) It is the intent of the Owner that the Contractor shall develop a comprehensive On-Site Test Plan, identifying the specifics of the tests to be carried out, and the acceptance criteria of such test, to ensure the Goods comply with the requirements of the Specification and Contract Documents.

3) The items listed below shall be considered as “suggested” tests and in no way shall be interpreted as a complete and comprehensive On-Site Test Plan. The Contractor has the responsibility to identify such tests and develop the On-Site Test Plan to ensure the Goods comply with the requirements of the Specification and Contract Documents. The Owner reserves the right to witness any or all On-Site Tests. a) GPU functions properly when operated with Pendant Control – 400Hz Vac output for each output,

verified via load testing, both resistive and reactive. b) Cable hoists operate properly with Pendant Control c) PBB does not operate when GPU is running or either cable hoist is deployed.

4) In addition to the “suggested” tests listed above, the Contractor shall conduct both resistive AND reactive load bank testing of both GPU outputs, simultaneously. These load tests hall be carried out at various load levels, beginning at minimum loads and increasing in several steps to maximum load. A written test procedure for this load test shall be submitted and approved thirty (30) days prior to the tests being conducted.

5) The results of the On-Site functional testing shall be provided to the Owner with the Final Acceptance Certificate and Final Payment Application.

Page 27: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 27 of 51 September 2011

5.0 CONTRACTOR SUBMITTALS 5.1 PROPOSAL

Description Due Date All Required Proposal Forms, including any Exceptions to the requirements of this Specification.

With Proposal

Proposed Project Schedule With Proposal Certification by a Third Party Agency or NRTL that the GPU design complies with UL-1012 and CSA-C22.2 No. 107.1-01.

With Proposal

5.2 INSTALLATION

Description Due Date Written Notice to Owner of scheduled delivery date and time 15 Days prior to shipment Phone notification to Owner of scheduled delivery date and time 24 hours prior to delivery Installation Methods Statement 30 Days from NTP Proposed Installation Subcontractor 30 Days from NTP Resume or CV of Proposed Installation Site Manager 30 Days from NTP Written Notice of Proposed Date of Substantial Completion on On-Site Testing.

2 Days Prior to Proposed Date of Substantial Completion

Substantial Completion Certificate and Punch List Items Upon Substantial Completion Final Acceptance Certificate Upon completion of Punch List

Items 5.3 QUALITY ASSURANCE / TESTING

Description Due Date Quality Plan, including Factory Acceptance Testing Plan and On-Site Functional Testing Plan

30 Days from NTP

Certificate of Compliance to the Requirements of Section 2.0 With Design Submittals Notice of Goods for Inspection 15 Days prior to Shipment Notice of Receiving Inspection of Goods delivered to Site 1 Day from receipt of GoodsContractor’s Factory Test results and records 2 Days after shipment Contractor’s On-Site Functional Test Results and Records With Final Acceptance 5.4 OTHER

Description Due Date Project Progress Schedule 15 Days from NTP Proposed content and format of O&M Manuals 30 Days from NTP Training Syllabus 30 Days from NTP Recommended Spare Parts List Substantial Completion O&M Manual With shipment of GPU

Page 28: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 28 of 51 September 2011

5.5 FINAL PAYMENT

Description Due Date Final Acceptance Certificate With Final Payment ApplicationAs Built Drawings With Final Payment ApplicationContractor’s and GPU Manufacturer’s Certificate of Warranty With Final Payment ApplicationRelease of Lien from Contractor With Final Payment ApplicationRelease of Lien from all subcontractors of Contractor With Final Payment Application 5.6 DESIGN 5.6.1 SHOP DRAWINGS AND SAMPLES

1) Shop Drawings - All drawings, diagrams, illustrations, schedules, test reports, certifications, cut sheets, calculations and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to demonstrate that the Contractor will provide Goods and Services which meet the requirements of the Specifications.

2) Samples - Physical examples of materials, equipment, or workmanship that are representative of some portion or all of the Goods and which establish the standards by which certain portions of the Goods or Special Services will be judged.

3) Contractor shall submit Shop Drawings and Samples for Owner’s review and approval in accordance with the schedule required in approved Progress Schedule. All submittals will be identified as required and furnished in the number of copies specified in the Contract Documents. The data shown on the Shop Drawings will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show Owner the services, materials, and equipment Contractor proposes to provide.

4) Where a Shop Drawing or Sample is required by the Contract Documents, any related work performed prior to Owner’s approval of the pertinent submittal will be at the sole expense and responsibility of Contractor

5) Shop Drawing submittals shall be the GPU Manufacturer’s standard submittal package and shall contain sufficient information for the Authority to confirm that the Goods being supplied meet the requirements of this Specification.

6) Shop Drawings shall provide sufficient detail and be organized in a manor so that compliance to specifications can be easily determined by the Authority.

7) Submittal Packages shall be prepared and submitted by the Contractor for the Specifications in Section 2.0. To the extent possible, the Contractor shall organize the Submittals in the same groupings as the requirements of Section 2.0.

8) Recognizing that the GPU Manufacturer’s standard submittal package may not provide the Authority with enough detail to verify each and every requirement of Section 2.0, the Authority shall require a Certificate of Compliance, signed by the GPU Manufacturer’s General Manager, Engineering Manager and Quality Manager, that the GPU being supplied fully complies with the requirements of Section 2 of this Specification.

9) Manufacturing drawings shall not be considered acceptable as submittal documents. 10) Submittals will also include proof of compliance with codes, regulations and testing requirements. 11) Before submitting each Shop Drawing or Sample, Contractor shall have determined and verified:

Page 29: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 29 of 51 September 2011

a) all field measurements (if required), quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto; and

b) that all materials are suitable with respect to intended use, fabrication, shipping, handling, storage, assembly, and installation pertaining to the furnishing of Goods and Services.

5.6.2 OWNER’S REVIEW OF SHOP DRAWINGS

1) Owner will provide timely review of Shop Drawings and Samples. 2) Owner’s approval will not relieve Contractor from responsibility for any variation from the requirements of

the Contract Documents unless the Owner has given written approval of each such variation by specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample approval.

5.6.3 RE-SUBMITTAL PROCEDURES FOR SHOP DRAWINGS

1) Contractor shall make corrections required by Owner and shall return the required number of corrected copies of Shop Drawings and submit as required new Samples for review and approval. Contractor shall direct specific attention in writing to any revisions other than the corrections called for by Owner on previous submittals.

Page 30: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 30 of 51 September 2011

EXHIBIT I Gate B37 – Existing 120 kVA Dual Output 400Hz GPU

Page 31: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 31 of 51 September 2011

Gate B47 – Existing 120 kVA Dual Output 400Hz GPU

Page 32: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 32 of 51 September 2011

EXHIBIT II Disconnect Cabinet at B37 Existing PBB / GPU Circuit Breaker

Page 33: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 33 of 51 September 2011

Disconnect Cabinet at B47 Existing GPU circuit breaker that will be “Dialed Up” to 200 amps

Page 34: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 34 of 51 September 2011

EXHIBIT III The Contractor shall supply and install a 3-tunnel PBB aluminum dogleg, which will be required to route the SO cord for the input power supply for the new 180kVA dual output GPU. The PBB at Gate B37 is a Jetway A3-68/141’s. The aluminum dogleg shall be supplied and installed per JBT Jetway Systems’ drawings 2202461, Rev D, Sheets 1&2 and 2931001 Rev -; or Authority approved equal.

Page 35: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 35 of 51 September 2011

Page 36: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 36 of 51 September 2011

The Contractor shall install the dogleg mounting brackets onto • left side rear lower corner of C Tunnel • left side rear lower corner of B Tunnel • left side forward corner of the rotunda rigid frame.

The brackets shall be welded onto the PBB and kept parallel to each other. The weld shall be a full penetration weld, clean of all burrs, spatter and carbon. The weld area shall be primed and painted to match the PBB

Page 37: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 37 of 51 September 2011

The Contractor shall use a “Kellum Grip” threaded strain relief with bushing, to secure the SO cord to the side panel of the SST disconnect cabinet mounted on the PBB rotunda. The SO cord shall be routed along the rear of the disconnect cabinet and up the left side of the PBB rotunda column. The SO cord shall be secured using a strain relief at the bottom rotunda rigid frame so that the SO cord forms a loop prior to the double dogleg.

Page 38: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 38 of 51 September 2011

The Contractor shall install the proper length 3/0 AWG, 3C-W/G, 600V SO cord FROM the new GPU circuit breaker in the SST disconnect cabinet on the PBB rotunda TO the new 180kVA dual output GPU. SO cord must be Class M Stranding, UL listed, sunlight resistant and marked every meter with UL requirements. The SO cord shall be a single run from the SST disconnect cabinet at the PBB rotunda, through the dogleg and then trough conduit / cable tray on the C Tunnel, to the new GPU unit. No intermediate junction boxes will be allowed. Sufficient SO cord loops shall be left at all dogleg hinge points, top and bottom, to prevent cord damage.

Page 39: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 39 of 51 September 2011

When installing the SO cord, the Contractor shall use “Kellum-grip” type stainless steel mesh strain reliefs, with threaded busing, on the SO cord on the bottom or top hinge points of the dogleg . SO cord bushings/grommets shall be installed in the dogleg conduit at the bottom or top hinge points, depending on where the “Kellum” grips are installed.

Page 40: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 40 of 51 September 2011

Unacceptable uses of bushings or other methods of securing SO Cord in Dog Leg.

Page 41: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 41 of 51 September 2011

Ground straps shall be installed at the points of intersection between the hinge points of the dogleg, top and bottom.

Page 42: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 42 of 51 September 2011

Conduit on C Tunnel shall be threaded on both ends and SO cord grommets/bushings shall be used at both ends of the conduit. If cable tray is used on the C Tunnel, SO cord grommets/bushings shall be used on all SO cord entry and exit points. Rubber insulated “Adel” type cable clamps and self-tapping screws shall be used to fasten SO Cord to PBB. Conduit bridge clamps and self-tapping screws shall be used to fasten the conduit to the low corrugated pan sections of the floor of the PBB or other PBB tunnel structure members.

Page 43: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 43 of 51 September 2011

EXHIBIT IV Gate B37 The Contractor shall remove the existing input power cable from the C2 junction box to the existing 120kVA dual output GPU and plug the hole in the C2 junction box.

Page 44: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 44 of 51 September 2011

The Contractor shall replace the control cable from the C2 Junction box to the new GPU unit. The location of the entry point of the control cable is different on the old unit vs. the new unit. New Dual Output 180kVA GPU Existing Dual Output 120 kVA GPU

Page 45: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 45 of 51 September 2011

Current PBB Rotunda and SST Disconnect at Gate B37

Page 46: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 46 of 51 September 2011

The Contractor shall supply and install a new 250 amp, adjustable, lockable circuit breaker for the new 180kVA dual output GPU to the left of the existing PBB / 400hz circuit breaker. The circuit breaker shall match the existing 2 circuit breakers, or be an Authority approved equal. Current B37 Disconnect The Contractor shall reuse the existing 2-handle breaker shut off linkage for the now PBB only and PCAir circuit breakers.

Input power for the new GPU circuit breaker shall be “tapped” off the existing input power to the PBB / 400Hz circuit breaker. One 110V circuit breaker will have to be relocated. The existing PBB / 400Hz circuit breaker, dialed down to the lowest setting, will be reused for the PBB only. The existing input power 1/0 AWG cable, which is in the PBB cable carrier, will be reused for the PBB only.

Page 47: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 47 of 51 September 2011

Similar MWAA project at Gate A14. The Contractor shall supply and install a new 250 amp, adjustable, lockable circuit breaker for the new 180kVA dual output GPU to the left of the existing PBB / 400hz circuit breaker. The circuit breaker shall match the existing 2 circuit breakers, or be an Authority approved equal A new handle shut off mechanism will be supplied for the new adjustable 250 amp GPU lockable circuit breaker. The shut off handle shall be mounted on the exterior of the SST disconnect cabinet door and shall engage the circuit breaker’s shut off mechanism when the SST disconnect cabinet door is closed. The new shut off handle shall match the existing shut off handle.

Input power for the new GPU circuit breaker shall be “tapped” off the existing input power to the PBB / 400Hz circuit breaker.

Page 48: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 48 of 51 September 2011

Gate B47 The Contractor shall disconnect the existing 2 AWG flat pack power cable from the GPU breaker in the disconnect, shrink wrap the end, coil and attach the cable to the Rotunda Rigid Frame. The Contractor shall disconnect the input power cable from the existing GPU, shrink wrap the ends, coil and attach the cable to the PBB C Tunnel

Page 49: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 49 of 51 September 2011

Current PBB Rotunda and SST Disconnect at B47

Page 50: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 50 of 51 September 2011

EXHIBIT V

The thermostatic trip unit in the building circuit breaker for Gate B37 must be replaced and upgraded to 250 amps. Cutler Hammer Westinghouse Series C 400 amp 600 vac Cat # HKD3400F Style # 1492D82G03

Page 51: METROPOLITAN WASHINGTON AIRPORTS AUTHORITY WASHINGTON

Specification and Statement of Work - 180kVA Dual Output 400Hz GPU IAD Gates B37 and B47

Page 51 of 51 September 2011

The adjustable building circuit breaker for B47 must be adjusted to trip at 400 amps. Siemens HLD63F600 Trip Unit Info---------400a Magnetic Adj. 2000-4000

END OF DOCUMENT