METODE PELAKSANAAN PEMASANGAN GEOTUBE
PADA TANGGUL BARAT
PT. PEMBANGUNAN JAYA ANCOL
PT. BRANTAS ABIPRAYA (PERSERO)
![Page 2: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/2.jpg)
DAFTAR ISI:1. Layout Dufan
2. Metode Kerja
3. Schedule Pelaksanaan
4. Foto-Foto Pelaksanaan Lapangan
![Page 3: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/3.jpg)
LAYOUT DUFAN(PEMASANGAN TANGGUL BARAT)
STOCK PILE PASIR(Di Atas Tongkang)
Awal Pemasangan Geotube
![Page 4: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/4.jpg)
METODE KERJAI. PEKERJAAN PERSIAPAN
1.Pengukuran oleh Surveyor, dalam hal ini pengukuran berpedoman pada Patok BM6 dan BM 7 yang merupakan koordinat lokal yang telah ada di Duvansi, dan mengacu pada patok DMG 1 dan 2 yang telah ada sebelumnya yang dibuat perencana.
2.Penentuan titik – titik koordinat tanggul yang telah ada pada gambar rencana pekerjaan tanggul Duvansi, dimulai dari koordinat titik A, B, C, D, E, F, G, dan H.
3.Pembuatan patok stake out dan positioning tanggul oleh surveyor mengacu kepada koordinat gambar desain. Bahan yang digunakan untuk patok AS adalah dari bambu, yang panjang setiap patoknya 50 m. Untuk keamanan dari patok-patok as tanggul diberikan rambu-rambu di laut.
4.Pemancangan patok guidance dari pipa besi 2,5”, dengan jarak patok geiden sekitar 7 m pada posisi kiri dan kanan dari rencana tanggul.
![Page 5: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/5.jpg)
5.Setting pompa hisap dan pembuang, baik yang ada di atas ponton maupun diatas stok pile, serta pekerjaan menyambung instalasi pipa – pipa pengisian untuk matras/geutube.
II. PEKERJAAN PENGISIAN MATRAS DAN GEOTUBEa.Lansir material matras/geutube ke lokasi tanggul yang direncanakan
menggunakan perahu.b. Penghamparan matras ke dasar laut, dimana matras tersebut sebelumnya di
ikat pada tiang – tiang patok pipa yang telah di pancang sebelumnya, dengan menggunakan tali pada posisi ujung bagian depan dan belakang serta kiri kanan matras/tube.
a. .
![Page 6: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/6.jpg)
c. Pada saat matras berada di dasar laut, baru di laksanakan pengisian matras tersebut dengan menggunakan pompa 4” yang telah disiapkan diatas stok pile yang ada di atas tongkang.
d. Pompa – pompa pengisian di tempatkan di atas tongkang yang berjumlah 6 buah yang pompa tersebut terdiri dari pompa hisap dan pembuang.
e.Pengisian matras dilaksanakan tahap demi tahap dari sisi kiri atau kanan matras/tube tersebut pada lobang inlet yang berjumlah tiga lobang, satu lubang inlet telah ditutup sebelumnya dengan tali. Adapun jumlah alur matras yang ada berjumlah 12 buah.
f. Saat pengisian matras dengan pasir, harus diperhatikan apakah matras tersebut sudah terisi penuh atau belum, dengan melaksanakan pengecekan dengan tim penyelam. Untuk mendapatkan hasil pengisian matras/tube secara maksimal tekanan dan pengaturan pompa pengisian pasir harus selalu diperhatikan.
g. Jika pengisian matras dan geutube dirasa cukup, baru di laksanakan pengukuran ketinggian, lebar dan panjang geutube yang di isi, dengan melakukan pengukuran dengan meteran ukur yang dilaksanakan oleh tim penyelam dan tim survey, yang disaksikan oleh konsultan pengawas, pelaksana kerja dan subkontraktor, kemudian baru dibuatkan berita acara lapangan.
![Page 7: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/7.jpg)
h.Untuk pengisian matras/geutube yang direncanakan ( sesuai gambar ) adalah ketinggian, 2,3 m, lebar 5,3m dan panjang 20 m. Selama pengisian yang harus diperhatikan adalah konsolidasi pasir yang telah di isi, apabila konsolidasi pasir terjadi, maka dilaksanakan pengisian selanjutnya, sampai matras/getube dianggap padat dan penuh.
i. Selama pengisian geutube, pekerjaan penghamparan matras, pematokan patok pipa dengan lego-lego ( pancang ) dan pengisian pasir berjalan terus menerus, supaya tetap terjaga tahapan pengisian selanjutnya ( kontinue ) sampai selesai semua pekerjaan pembuatan tanggul duvansi.
![Page 8: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/8.jpg)
ALAT-ALAT YG DIGUNAKAN:
1. Barge (Tongkang) pasir 2 unit Kapasitas 2000 m3 dan 5000m32. Tug Boat untuk mendorong tongkang3. Pompa-pompa pasir (sand pump) 6 unit Kapasitas 75 m3/jam4. Pompa- pompa air 4 unit.5. Pipa-pipa spiral untuk air maupun pipa pasir6. Ponton kecil untuk tempat pompa ( 3 unit)7. Pancang (Lego-Lego)8. Pipa Besi Diameter 2,5”9. Perahu Kayu10. Tali11. Bambu12. Selang Pipa Diameter 4”13. Drum
![Page 9: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/9.jpg)
MATERIAL:1. Geotube Strength 200 KN2. Matras3. Pasir
TENAGA:1. Pekerja2. Penyelam
![Page 10: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/10.jpg)
ILUSTRASI URUTAN PEMASANGAN GEOTUBE
1. Pemasangan Dan Pengisian Pasir Geotube Lapis Bawah
START PEKERJAAN TANGGUL
TANGGUL LAPIS - 1
![Page 11: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/11.jpg)
2. Pemasangan Dan Pengisian Pasir Geotube Lapis Kedua
START PEKERJAAN TANGGUL
TANGGUL LAPIS - 2
![Page 12: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/12.jpg)
3. Pemasangan Dan Pengisian Pasir Geotube Lapis ketiga (Atas)
START PEKERJAAN TANGGUL
TANGGUL LAPIS - 3
![Page 13: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/13.jpg)
Concrete pump
Dasar laut
15,9 m
PASIR
STOCK PILE
PATOK GUIDANCE
MATRAS
INSTALASI PIPA UNTUK MENGISI MATRAS/TUBE
![Page 14: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/14.jpg)
Concrete pump
Dasar laut
15,9 m
PASIR
STOCK PILE
PATOK GUIDANCE
MATRAS
GEOTUBE
![Page 15: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/15.jpg)
SCHEDULE PELAKSANAAN
![Page 16: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/16.jpg)
FOTO-FOTO PELAKSANAAN LAPANGAN
![Page 17: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/17.jpg)
1. PENGUKURAN
![Page 18: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/18.jpg)
2. STAKE OUT DAN POSITIONING
![Page 19: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/19.jpg)
3. PEMANCANGAN PATOK GAIDEN DENGAN ALAT PANCANG LEGO-LEGO (UNTUK PEMASANGAN GEOTUBE DAN MATRAS)
![Page 20: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/20.jpg)
4. PATOK CENTER LINE DAN GAIDEN YANG TERPASANG UNTUK PANDUAN PEMASANGAN GEOTUBE DAN MATRAS
![Page 21: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/21.jpg)
5. GELAR MATRAS DAN GEOTUBE DARI ATAS PONTON
![Page 22: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/22.jpg)
6. MATRAS DAN GEOTUBE YANG TELAH DITURUNKAN/GELAR DI LAUT
![Page 23: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/23.jpg)
7. PENGISIAN PASIR UNTUK MATRAS DENGAN POMPA DI ATAS PONTON
![Page 24: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/24.jpg)
8. PENGISIAN PASIR UNTUK MATRAS DENGAN POMPA DI ATAS PONTON
![Page 25: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/25.jpg)
9. INSTALASI PIPA PENGISIAN MATRAS/TUBE
![Page 26: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/26.jpg)
10. INSTALASI PIPA UNTUK PENGISIAN GEOTUBE DAN MATRAS
![Page 27: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/27.jpg)
11. PEKERJAAN PENGISIAN PASIR DARI ATAS PONTON (STOK PILE )
![Page 28: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/28.jpg)
12. POMPA YANG DIGUNAKAN UNTUK PENGISIAN GEOTUBE
![Page 29: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/29.jpg)
13. STOCK PILE PASIR DI TONGKANG
![Page 30: Metode Geotube Karly](https://reader031.vdocuments.mx/reader031/viewer/2022012307/5695d11e1a28ab9b02953a38/html5/thumbnails/30.jpg)