Dredging and Embankment of River
DETAIL CONSTRUCTION OF WORKS ITEMS
METHOD STATEMENT Project Name : Dredging and Embankment of Ciliwung-Gunung Sahari Drain & Waduk Melati
Sub-Project Province : DKI Jakarta Bidder Name : PT. BRANTAS ABIPRAYA (Persero)
Dredging and Embankment of River
1. Location;
Construction on 2 Site , Waduk Melati, Cideng Drain, Gresik Drain and Gunung Sahari Drain
Dredging Works - Dredging and Disposal
- Excavated garbage
Assumption:
Works
- Preparation of Shop Drawing till get approval from Engineer
- Preparation of Equipments work and man power / Labors
2. Measurement
3. Excavation
Excavation must be done according to height line, grade, slope and elevation which is shown in
Drawing.
CONSTRUCTION METHOD FOR DREDGING WORK - Construction;
Sequences : 1. Preparation Work, include :
Equipments : 1. Excavator
2. Pontoon
3. Floating Barge
4. Dump truck
5. Tools
Before excavation started, must be done work of Measurement to know elevation and boundary plan of excavation.
1. Work by heavy equipment ( mechanically), Labors and Tools
2. Work location :Gunung Sahari Drain and Waduk Melati as according to the Drawing and BQ
Description This work have to include all excavation in the line, grade, slope and elevation shown on the Drawing,
boundary, removal, transportation, dumping and Spreading and grading in disposal area.
At construction process, if Any damage to existing structure or facilities that is caused by Contractor’s
operational, contractor will be repaired to the pre-project condition at the contractor’s expense
All Construction will be execute as according to determined Technical specification in tender document
Dredging and Embankment of River
FLOW CHART of DREDGING WORK
START
Determined Access Road into Work Site
Determined & Measurement of work site
Mobilization of Equipments & Personal
Excavation of river’s sediment / waduk’s sediment by Excavator
on Pontoon & Temporary Disposal
Cek
Ok
No
Handling The material by Dump truck
Delivery and transport into Determined Disposal Area
Dumping in disposal area
FINISH
“If determined”
Spreading & Grading by Buldozer
Cek
Ok
No
FINISH
Separation the Garbage
Handling The material by Dump truck
Delivery and transport into Determined Disposal Area
Dumping in disposal area
FINISH
Dredging and Embankment of River
Dredging, Sheet Pile & Capping Beam FOR waduk melati
- Work Location
Construction;
- All Construction Will be constructed from Up Stream up to Down stream
- At first, Common excavation will construction - Continue by Sheet Pile Construction
Dredging
Sheet Pile Construction
Work Direction
Dredging and Embankment of River
Dredging
1. Temporary Disposal
Work Direction
Temporary Disposal for Red Area
Using Drain Existing
Temporary Disposal for Yellow Area using Container
Dredging and Embankment of River
Dredging for Red Area
Separation Garbage - Use separator /screen to separate large size solid waste
- Use Labor, floating pontoon ship and Tool or - Use Labor and tools in temporary disposal. For some location, Work by Excavator Usually for this
method for floating Garbage
Handling Excavated material into Temporary Disposal
Excavated Material
Temporary Disposal
Handling Location
Traffic Handling to disposal area
Garbage
Excavated Material
Dredging and Embankment of River
- Movable Floating barges by Tug boart
Access Road;
- Problem 1. Existing Access Road already Owner by Third party.
- Solution 1. Contractor will coordination to using that road from the owner.
2. Mediator by Project owner if needed
3. Any damage to existing structure & existing road or facilities that is caused by Contractor’s operational, contractor will be repaired to the pre-project condition at the contractor’s expense
(even more better) 4. Handling and hauling of material excavated and garbage at mind night from 22.00 wib up to
05.00 wib
Routes for Dredged Material ;
- Jl. Kebon Kacang
- Jl. MH. Thamrin - Jl. Merdeka Barat
- Jl. Majapahit - Jl. Juanda
- Jl. Ciliwung Gunung Sahari
Existing Road Owner by third party
Dredging and Embankment of River
Handling and Hauling into disposal area
- Excavated Material will be transported into disposal, Spreader and grading. Handling Material, Truck’s
Dump must be equipped by Water Seal during transportation process, so that no debris of Excavated
material on access road.
- Traffic management with traffic lights that have been there (intersection lights) and will be assisted with traffic management by contractor
- Contractor will request and permissions using Ancol’s land to using access road for disposal of
excavated material determined to the tender document
- For Garbage, Disposal as determined to the tender document or otherwise determined by Director Bantar Gebang
Illustration
Spreading excavated material on disposal area
Dredging and Embankment of River
Dredging for Yelow Area
- Excavated material will be used Container
- Temporary Placed Container on Left Side ( West Side) of Melati basin - Separated Garbage by man and tool on temporary Disposal (Container)
- Use separator /screen to separate large size solid waste - Use Labor and tools in temporary disposal. For some location, Work by Excavator Usually for this
method for floating Garbage
- Container is Steel Plate and Profil L - Work is 24 hour
- Movable Floating barges by tug boat
1.2 m
1.2 m
2.4 m
Dredging and Embankment of River
Handling
- Separated Garbage by man and tool on
temporary Disposal (Container)
Hauling to disposal area
- Work is 22.00 wib up to 05.00 wib
- Access Road; Problem
1. Some of Existing Access Road already Owner by Third party. There is Border by Fence
Solution
1. Contractor will coordination to using that road from
the owner. 2. Mediator by Project owner if needed
3. Any damage to existing structure & existing road or facilities that is caused by Contractor’s operational,
contractor will be repaired to the pre-project condition
at the contractor’s expense (even more better) 4. Handling and hauling of material excavated and
garbage at mind night from 22.00 wib up to 05.00 wib
Existing Road Owner by third party
Dredging and Embankment of River
Design Container Unit that open in Side system based from Drag Line Method.
Spreading excavated material on disposal area
Type, capacity, Labor and Material
Description : Dredging and disposal Item no 301
1) Labour 3) Production / m3 8 hour /day 4) Equipments
- Foreman = 1 = 21.00 m3 /hour - Excavator Long Arm = 3 Unit
- Skill Labor = = 168 m3 /day - Pontoon = 3 Unit
- Labor = 3 - Floating Barge = 10 Unit
- Steel Container = 50 Unit
2) Material - Tug Boat = 3 Unit
- Non - Service Crane 15-25 ton = 3 Unit
- Dump Truck 16t = 7 Unit
Schedule = As according to " Construction Schedule" that one of attacments in Tender Bid Document
Dredging and Embankment of River
Dredging, Sheet Pile & Capping Beam FOR GUNUNG SAHARI DRAIN
Construction Plan
Stage 1
- All construction will be start from Up stream (Hulu) up to down stream (Hilir) - Construction for Dredging Will be constructed Form End Project (STA. 5+100)
- Construction for Sheet Pile Will be constructed Form Jl. Mangga Besar (STA. 2+450) up to STA. 0+000)
- Construction Will be Fontal (at same time)
Sheet Pile 4.832 m
Dredging 5.100m
Dredging and Embankment of River
EXISTING
WEST SIDE EAST SIDE
Site Visit on West Side River; - At many place, Existing link Road for parking vehicle - Almost for Business Area and residents - Many Building - Difficult for hauling - Many Electric Cable - On same place, that side of river, there is Existing
Building as semi permanent and permanent - High Social cost - Possible for Contractor’s Office
Site Visit on East Side River; - Existing structure are 2 kind of them, there are 3 m
and 5 m - Existing is Pedestrian road (Trotoar) and Planting - Some building as Gazebo - For Hauling can be reach from Existing Road - There are re-condition for temporary disposal after
construction
Dredging and Embankment of River
Routes for Dredged Material ;
- Jl. Pos / Dr Sutomo
- Jl. Ciliwung Gunung Sahari - Jl. RE. Martadinata
- Jl. Pelabuhan Ratu 1 - Jl. Raya Ancol Baru
Dredging
Type 1 1. Excavation & Hauling
- Work at 22 – 05.wib
- Movable Floating barges by winch Separation Garbage
- Use separator /screen to separate large size solid waste - Use Labor, floating pontoon ship and Tool or - Use Labor and tools in temporary disposal. For some location, Work by Excavator Usually for
this method for floating Garbage
Type From Floating barge min 20 m³ directly into Dump Truck by Mobile Excavator
- Work can be happen, if Dredged material in temporary disposal has been finished loaded, and Construction of Dredging still continue.
1. Excavation
2. Hauling and Handling
Excavation Lumpur
Temporary Place Loading Into Disposal Area Dumping
Side of River
Dredging and Embankment of River
Side View
Top View
Side View
Top View
Type 2
Loading to temporary placed
- Excavator on Pontoon for
excavation
- Excavated material disposed on temporary
disposed on Temporary
Disposal by Floating Barge (Oil drum and
Woo)
- Other Excavator loading excavated material into
dump truck
- Dump truck delivery of
excavated material into determined disposal area
Dredging and Embankment of River
1. Excavation
this method for floating Garbage
Labor and tools
- 24 work Hour
- Movable Floating barges and Temporary Floating Barges from Oil Drum by winch
Separation Garbage
- Use separator /screen to separate large size of solid waste
- Use Labor, floating pontoon ship and Tool or
- Use Labor and tools in temporary disposal. For other location, Work by use Excavator Usually for
2. Hauling and Handling - Work hour at 22.00 – 05.00 wib - Garbage separation will be executed on Temporary Disposal and put on temporary garbage box by
Dredging and Embankment of River
- Temporary Floating Disposal by Oil Drum, Wood, Board wood and Plastic to cover of Wood - Movable Floating barges and Temporary Floating Disposal from Oil Drum by winch
Type, capacity, Labor and Material
Description : Dredging and disposal Item no 201
1) Labour 3) Production / m3 8 hour /day 4) Equipments
- Foreman = 1 = 29.00 m3 /hour - Excavator, 0.8m3 = 2 Unit
- Skill Labor = = 232 m3 /day - Pontoon = 2 Unit
- Labor = 3 - Floating Barge = 18 Unit
- Excavator, 0.8m3 = 1 Unit
2) Material - Dump Truck 16t = 5 Unit
- Non - tools = 1 Ls
Schedule = As according to " Construction Schedule" that one of attacments in Tender Bid Document
Max 50 m
3 m
1.5 m
Dredging and Embankment of River
DREDGING UNDER THE BRIDGES
- Construction From Up stream up to down stream
- Construction in this location will be 2 Stage 1. Blow of Sediment /dredged material under Bridge Using Water Injection. Water Injection take
water from river via Pipe intake and will blow on work site via Pipe Out Put
Water Injection
Up Stream Down Stream
Work Direction
Direction of Moving Sediment Excavator take / excavation of sediment removal (have been blew by Water Injection)
2. The material that moved will be dredged by excavator in other side
3. Movable Floating barges and Temporary Floating Disposal from Oil Drum by
winch
Dredging and Embankment of River
FLOW CHART of DREDGING WORK UNDER BRIDGE
START
Determined Access Road into Work Site
Determined & Measurement of work site
Mobilization of Equipments & Personal
Handling The material by Dump truck
Delivery and transport into Determined Disposal Area
Dumping in disposal area
FINISH
“If determined”
Spreading & Grading by Buldozer
Cek
Ok
No
FINISH
Cek
Ok
No
Blow sediment by Water Jet
Excavation by Excavator in other side of bridge
Cek
Ok
No
Separation the Garbage
Delivery and transport into Determined Disposal Area
Dumping in disposal area
FINISH
Handling The material by Dump truck
Dredging and Embankment of River
DREDGING ON
- Gresik Drain
- Cideng hulu drain
Assumption - Construction by labor and Tools
- Temporary Disposal by Container
Equipment;
@ Location - Container = 5 Unit
- Dump Truck = 2 Unit for Cideng drain and 1 Unit for Gresik - Mobile Crane = 1 Unit
- Labor
1.2 m
1.2 m
2.4 m
= 20 Person
Container
Dredging and Embankment of River
Illustration
- Garbage separation will be executed on Temporary Disposal and put on temporary garbage box by Labor
and tools
Spreading excavated material on disposal area
- Labor and Tools
- Placed Dredged material on temporary disposal (river bank)
To loading / bring of dredged material into temporary
disposal
Dredged Material Lansir & Loading
Dredging and Embankment of River
On Location where Loading and estafet by wagon can be executed, Dredeg can be assiten by Temporary
floating (made by bambo and wood)
Hauling at 22.00 up to 05.00 wib
Dumping and spreading on CDF
Dredging and Embankment of River
FLOW CHART OF MANUAL DREDGING WORK
START
Penentuan & Pengukuran Lokasi Pekerjaan
Penentuan Akses ke lokasi Pekerjaan
Pek. Pengerukan Lumpur oleh Pekerja & Alat bantu
Mobilisasi Peralatan & Personil
Temporary placed Ex. Material kerukan di atas Bantara kali
Cek
Ok
No
Loading oleh Pekerja + alat bantu ke gerobak (langsir) & Dari
gerobak ke dalam bak dump truck
Transportasi material ex. Kerukan ke lok. pembuangan / disposal area
Dumping di lokasi pembuangan / disposal area
FINISH
Perapian di damping Area oleh Buldozer & Excavator
FINISH
Cek
Ok
No
“Item ini di bayar tersendiri”
Dredging and Embankment of River
CONSTRUCTION PLAN FOR DAILY STORAGE OF SOLID WASTE (Bigger than 30 x 30 cm) -
method for floating Garbage - Time for Construction are 2 kind of work
1. Construction that can be done for 24 hour Waduk Melati
1.1. Using existing Drain for temporary disposal
1.2. Using Container
Gunung Sahari Drain 1.3. Temporary Disposal
Excavated Material
Handling Excavated material into Temporary Disposal
Use separator /screen to separate large size solid waste
- Use Labor, floating pontoon ship and Tool or
- Use Labor and tools in temporary disposal. For other location, Work by Excavator Usually for this
Dredging and Embankment of River
2. Construction that can be done only on 22.00 up to 05.00 local time
Waduk Melati
2.1. Using existing Drain for temporary disposal
Hauling and dumping into Disposal
2.2. Using Container
Hauling and dumping into Disposal
Gunung Sahari Drain 2.3. Temporary Disposal
Hauling and dumping into Disposal
2.4. Directly from Pontoon Barge (assumption top of sediment that contain of garbage already
excavated on day time and separation on temporary disposal)
Hauling and dumping into Disposal
Dredging and Embankment of River
wib.
- The Contractor will use the existing road for the works. Design Route for Hauling and Handling into CDF
Routes for Dredged Material ; Jl. Kebon Kacang
Jl. MH. Thamrin Jl. Merdeka Barat
Jl. Majapahit
Jl. Juanda Jl. Ciliwung Gunung Sahari
Ancol without retribution cost.
- The garbage to Bantargebang, the bidder must include the retribution cost and follow the cost
regulation of Bantargebang. They can find out the cost per ton or per truck by themselves to
Bantargebang.
- During Handling and Hauling dredged Material into Confined Disposal Facility (CDF) at Ancol Area,
contractor will be prepare of Water tank truck for
cleaning of existing road routes from fall dredged material during transported
- For Garbage, Disposal as determined to the tender document or otherwise determined by Director Bantar Gebang
- All truck / vehicles transporting the dredged material will be equipped with Global Positioning
System as instructed, for monitoring purpose. All Truck will be Recording.
- Daily report that mention ;
Type of truck License plate number
Time of truck depature from the loading location Time arrival at the deposit area in CDF Ancol
CONTRUCTION PLAN FOR FINAL DISPOSAL - Handling and hauling of material excavated and garbage at midnight from 22.00 wib up to 05.00
- Access to the Site can generally be achieved by the network of public roads and streets in the vicinity of Site.
- The dredged materials shall be properly disposed in the designated Confined Disposal Facility (CDF) at
- The Contractor will be fully inform himself of the conditions of roads, traffic conditions and
traffic regulations with respect to gaining access to the Site for the purposes of performing the
Works and shall take all necessary actions to ensure availability of access to the Site as required.
Dredging and Embankment of River
wib.
- Access to the Site can generally be achieved via the network of public roads and streets in the vicinity of Site.
- The Contractor will use the existing road for the works.
- The Contractor shall fully inform himself of the conditions of roads, traffic conditions and traffic regulations with respect to gaining access to the Site for the purposes of performing the Works and
shall take all necessary actions to ensure availability of access to the Site as required.
- Dredged Material will be transported into disposal, Spreader and grading. Handling Material, Truck’s
Dump must be equipped by Water Seal during transportation process, so that no debris of Excavated
material on access road.
- Traffic management with traffic lights that have been there (intersection lights) and will be assisted
with traffic management by contractor
- Contractor will request and permissions using Ancol’s land to using access road for disposal of excavated material determined to the tender document Confined Disposal Facility (CDF) at
Ancol Area
- Measurement and Payment
Payment for dredging and disposal (garbage excluded)
will be made at the negotiated and approved Contract unit price per m3 defined in the Bill of Quantities,
multiplied by the total m3 of verified and weighted volume (say 35% of the dumped volume plus 65% of the
dredged volume, ratio subject to change). No payment
shall become due to the Contractor for over dredging or excess dredging which exceeds the allowable over depth.
- For Garbage, Disposal as determined to the tender document or otherwise determined by Director Bantar Gebang
- All truck / vehicles transporting the dredged material will be equipped with Global Positioning
System as instructed, for monitoring purpose. All Truck will be Recording.
- Daily report that mention ;
Type of truck License plate number
Time of truck depature from the loading location
Time arrival at the deposit area in CDF Ancol
HAULING OF DREDGED SEDIMENT TO CDF - Handling and hauling of material excavated and garbage at midnight from 22.00 wib up to 05.00
Dredging and Embankment of River
GARBAGE SEPARATION / REMOVAL/DISPOSAL
Separation; - Use separator /screen to separate large size solid waste
- Use Labor, floating pontoon ship and Tool or - Use Labor and tools in temporary disposal. For some location, Work by Excavator Usually for this
method for floating Garbage
Disposal - The garbage to Bantargebang, the bidder must include the retribution cost and follow the cost
regulation of Bantargebang. They can find out the cost per ton or per truck by themselves to
Bantargebang.
- Garbage Material will be transported into disposal (bantargebang). Handling Material, Truck’s Dump
must be equipped by Water Seal during transportation process, so that no debris of Garbage on access road.
Temporary Disposal for Garbage Temporary Disposal for
Dredge Material
Dredging and Embankment of River
EMBANKMENT WORKS / CONSTRUCTION METHOD FOR CCSP
On Waduk Melati
@ 15 m
On Gunung Sahari
@ 14 m
Description; - Structure Type W 450 B1000 (@ 15m and 14 m) - Work of CCSP is conecction with Revetment work Finished of CCSP will continue with Revetment
Work - Construction;
1. Location;
Construction on 2 Site , Waduk Melati and Gunung Sahari
Waduk melati = @ 15 m
Gunung Sahari = @ 14 m
2. Other
Based of The drawing on Gunung Sahari Site, Work site divide to 2 side of River. West River (left side) and East River (Right side).
Contractor will construction this work by some Group of Works Frontal on Waduk Melati and Gunung Sahari
Dredging and Embankment of River
CONSTRUCTION OF SHEET PILE (ALL LOCATION ON WADUK MELATI / MELATI BASIN)
Refer to Tender Document, Work Stage / Construction Plan will be Constructed as bellowing Drawing
1. Temporary Stock Pile for Sheet Pile
- Based the Work Location, Stock Pile Possible Placed on Side of East of Waduk Melati
- Start Point for Handling Material and Equipment From Upper location as describe at Image bellowed.
From Starting Point, The material will be to site by Pontoon and service Crane - Any damage to existing structure or facilities that is caused by Contractor’s operational, contractor will
be repaired to th pre-project contition at the contractor’s expense (even more better) - Handling the material at mind night from 22.00 wib up to 05.00 wib
Temporary Stock Pile
Plan of Stock Pile
Point for Mob. & Handling Material etc
Plan of Stock Pile
Dredging and Embankment of River
Delivery and handling The Material
Temporary Stock Pile
Dredging and Embankment of River
2. Stage Construction
Pilling
CUT TOP PILE ( with leveling as according to the drawing)
LEAN CONCRETE
Temporary Stock Pile
Dredging and Embankment of River
REINFORCING STEEL
FORM WORK (BY MULTIPLEX AND WOOD)
Concreting
- Concreting by Ready mix - Compaction by Concrete
Vibratory - Concreting by Truck mixer on
Ponton
Dredging and Embankment of River
CONCRETING
Concreting of West
Side of Waduk
melati
Directly from Truck Mixer via Gutter
Concreting of East
Side of Waduk melati
Dredging and Embankment of River
FINISH
- Removal Form work
- Installation on next location (side of existing capping beam)
Detail of Capping Beam
Capping Beam - Reinforcing Steel
- Form Work
- Concreting as
according to the drawing and
technical
specification
Dredging and Embankment of River
Finish
Detail Construction Of CCSP Work Assumption:
1. Work by Heavy Equipment (Machinery)
2. Location : As according to the drawing 3. Material CCSP (type as according to the drawing)
Description
1. Site Work Preparation
- Work site made with good level that a Crane can stand up goodly - Crane stand up above plate of form which in the form of steel plate 1,5 x 6 meter or On pontoon in
position that Piling should be on water
2. Stake point of Pilling
- Stake point of pilling of Concrete Corrugated Sheet Pile is executed by surveyor which is approved / agreed by Consultant Supervisor
3. Fabrication of Material sheet pile
- Fabrication / manufacturing of Concrete sheet pile is formed after the drawing has been approved by Consultant supervisor.
- Delivery to work site
4. Pilling
- Excavation by labor to get form of pilling
- Made of guide beam on pilling position using steel material WF type with elevation distance from
sub grade 1 to 2 meter, before pilling is executed
- Guide beam is made with strength enough that can supporting of moment when pilling is executed and stabile
- Piling founded by vertical and monitored with measuring instrument ( Theodolite) and yarn in 2
direction which each other vertical
- Before pilling, pile with Vibro hammer have to in position of sentries
- Concrete Sheet pile is vibrated by Vibro hammer is and the Sheet pile will be pilled into ground
cause of gravitation moment and weight of Sheet pile it selfand also helped by Water Jet Pump
that spraying water, that mean this construction to easyly andalso helped byWaterJetPump thatspraying waterwhichis intendedtosoften of soileasierPilling proccess
- Vibratory is executed as sequence.
- At pilling time, between one of Steel Sheet pile and each other of side (has been pilled) if there is gap, can be near by trek beam.
Dredging and Embankment of River
- Pilling is executed until a Sheet pile reach deepness elevation plan as according to the drawing.
Pengadaan dan Transportasi Material
Sheet Pile
Dredging and Embankment of River
Type, capacity, Labor and Material
Description : Driving of Corrugated Pre-stressed concrete pile W 450 Item no 342
1) Labour 3) Production / m 8 hour /day 4) Equipments
- Foreman = 1 = 7.00 m /hour - Crane On track 25 ton = 2 Unit
- Skill Labor = = 56 m /day - Vibro Hammer = 2 Unit
- Labor = 3 - Generator Set 50-70 KVA = 2 Unit
- Pontoon = 2 Unit
2) Material - tools = 1 Ls
- Concrete Corrugated Sheet Pile
Schedule = As according to " Construction Schedule" that one of attacments in Tender Bid Document
Dredging and Embankment of River
FLOW CHART OF CCSP
Pilling Process pemancangan
Transportation of Sheet Pile
setting out Of location Pilling
Guide Beam Installation
Placed Sheet Pile on Work Site / stock area
Installation of Sheet Pile on Vibro Hammer (Pilling equipment)
Pilling
Finished Pillingi / Piled Sheet Pile
Check
No
Yes
Delivery of Sheet Material on Trailer
Check
No
Yes
Order & Manufacture By Supplier / Sub Contractor
Equipment Mobilization (Crane with Vibro Hammer)
START
Finished Earth Work
Ok
No
FINISH
Capping Beam
Dredging and Embankment of River
WADUK MELATI PUMP
- Special Construction;
This Waduk melati Pump, for outlet of pump should be cross of Train Rail existing
- Construction Plan Contruction Method for this Point will be used JACKING SLURRY (FULL JACK) method
Umumnya pemasangan pipa jacking diaplikasikan pada kondisi-kondisi lapangan seperti : - Melintang dibawah jalan raya yang padat (jalan tol, jalan kolektor, dll)
- Melintang dibawah jalan rel K.A.
- Saluran dibawah sungai (Syphon) - Pipa dengan installasi yang sangat dalam (lebih dari 5m)
Pelaksanaan Pekerjaan Jacking Pipa 1. Pembuatan Driving / Receiving Pit /
SISTIM PENURAPAN UNTUK TANAH LABIL
TANPA SKALA
DETAIL KONSTRUSI PENDUKUNG GALIANDENGAN TEROWONGAN
TANPA SKALA
UNTUK SEMUA PENYOKONG
TANPA SKALA
SKALA : TANPA SKALA
I
Adalah pekerjaan galian tempat untuk peralatan dan mesin jacking guna mendorong pipa secara
horizontal, konstruksi starting/driving pit berukuran;
Perkuatan dinding pit menggunakan Material sesuai dengan gambar diatas
Disamping itu di dalam driving pit juga dilengkapi dengan block beton untuk dead man, pondasi
mesin, lantai kerja.
2. Pekerjaan Boring & Jacking
Pekerjaan pengeboran tanah dapat dilakukan dengan mesin, akan tetapi memungkinkan juga dilakukan secara manual apabila diameter pipa cukup besar untuk akses pekerja galian dan kondisi
tanah cukup stabil.
Dredging and Embankment of River
Urutan pelaksanaan pekerjaan jacking
2.1. Persiapan Starting Pit & Ariving Pit
Starting/Driving Pit adalah titik dimana Peralatan Mesin dipasang guna mendorong pipa selama pekerjaan jacking dilakukan. Sedangkan titik tujuan dinamakan Arriving Pit/Receiving Pit, yang
digunakan untuk mengangkat kembali mata bor & pilot tube. Secara berturutan dan bila dimungkinkan Arriving Pit akan menjadi Starting pit untuk pekerjaan
jacking section berikutnya.
Pekerjaan persiapan ini antara lain adalah : pembuatan perkuatan dinding galian, pembuatan
deadman untuk menahan thrusting block, pembuatan lantai pondasi untuk guide-rail
Pondasi
Struktu Perkuatan Dinding Tanah
Deadman/ Concrete Trust Wall
STARTING PIT
DRIVING PIT
ARRIVING PIT
RECEIVING PIT
7.0
0
6.00
1.4
0
2.40Dudukan/Pengarah
Jacking Pipe
Concrete Thrust
Wall
Pressure plate
Steel Sleeper
Main Jack Cutter Edge
Arah Jacking
Concrete Pipe
Thrust Ring
Dredging and Embankment of River
2.2. Installasi Mesin Jacking
Setelah pekerjaan Starting Pit & Arriving selesai, mesin jackin mulai dipasang, Tipe Mesin
Jacking yang dipilih perlu disesuaikan dengan ukuran diameter pipa, dan kapasitasnya disesuaikan dengan gaya dorong yang diperlukan.
Pada umumnya peralatan mesin jacking terdiri dari: trusting block / hydraulick jack, guide rails,
steel pressure plate, power pack, steel trusting ring, jacking shield / pilot tube, conveyor belt /
slurry hose, dan control panel untuk operator mesin.
2.3. Pemasangan Pilot Tube / Jacking Shield
Pilot Tube / Jacking Shield adalah berupa silinder baja yang dipasang pada ujung pipa jacking
dimana Mata bor terpasang.
**) untuk ekskavasi tanah dengan cara manual biasanya mata bor diganti dengan
driving collar (steel collar yang didesain khusus untuk menembus tanah).
Guide Rails
STARTING PIT
Steel Thrust Ring
Hydraulic Jack
Steel Pressure Plate
Power Pack
Control Panel
Laser
Pilot Tube
STARTING PIT
ARRIVING PIT
Mata Bor **)
Dredging and Embankment of River
2.4. Pekerjaan pemboran dan jacking awal
Setelah pilot tube dan mata bor terpasang, maka pekerjaan pemboran tanah dimulai dan
setelah pilot tube masuk kedalam tanah, maka pipa pertama dipasang, kemudian pemboran dilakukan secara menerus sementara pipa didorong perlahan
2.5. Pekerjaan pengangkutan tanah
Selanjutnya untuk pipa ke-2, ke-3 dan selanjutnya sampai menuju ke arriving pit. Pekerjaan
pengeboran dan pekerjaan mendorong pipa dilakukan secara berturutan / bersamaan. Pembuangan tanah hasil dari pemboran dibuang melalui conveyor, untuk type mesin lainnya
biasanya untuk diameter kecil, tanah hasil pengeboran dicampur dengan air sehingga berbentuk slurry dan dibuang melalui pipa pembuangan.
Pembuangan tanah untuk cara manual dapat digunakan trolley. Kecepatan pemasangan pipa jacking tergantung pada diameter pipa dan kondisi tanahnya,
umumnya 1 s/d 6 pipa per hari (8 jam kerja).
Pipa -1
ARRIVING PIT STARTING PIT
Steel Collar
STARTING PIT
ARRIVING PIT
Dredging and Embankment of River
2.6. Pekerjaan Jacking tahap akhir
Setelah pipa jacking pertama sampai ke arriving pit, maka pilot tube dan mata bor di angkat,
dan mesin jacking dipindahkan ke section berikutnya.
Stage Construction
STARTING PIT ARRIVING PIT
1 2
1 2
3
4