  • MECHANICAL-ELECTRICAL & PLUMBING

    A HANDBOOK FOR MEP

    ENGINEERS

    Photograph-Dubai sports city : Source www.dubaisportscity.com

    By: Dr. S.L.Sharma, B.E (E), M.Phil, Ph.D.

  • 2

    Author

    Dr. Sanwar Lal Sharma B.E (Ele.), D.E (Ele), D.M&M

    B.A (Economics), M.A (Criminology), M.Phil (I.R) &Ph.D (H.R) A. Resident Engineer (MEP)

    DIAR Consult Victory height Project- Dubai International sports city

    DUBAI-UAE

  • 3

    PREFACE

    This tiny effort has been made in the direction to appreciate the importance of electro-mechanical and plumbing work in the construction industry. This will serve as a hand book with ready reckoned to all professionals engaged in the MEP work. It will also provide a ready made guidance to all contractors and sub contractors at site. This book clearly defines the roll and responsibility of each one involved in the execution of the project. It is observed in my long years of experience in the field that there is always a dispute within the agencies regarding administrative procedures to be followed. Keeping that thing in mind we tried to segregate all administrative obligations to be adhered by each agency. It is hoped that this small effort will bring a big change in the professionals approach engaged in the construction industry. Sincerely, Dr. S.L.Sharma Date: 10-09-2007

  • 4

    Contents

    Pages Preface 3

    Reference Standards/documents 5-6

    Project Co-ordination 7-11

    MEP Organization 12-25

    MEP staff Responsibilities 26-32

    Inspection Methodology 33-56

    (Electrical) Inspection Methodology 57-74

    (Mechanical) Standards of submittals 75-85

    Annexure (Templates) 86-105

    Abbreviation 106-107

    About Author 108

  • 5

    REFERENCE STANDARD& DOCUMENTS

  • 6

    3- Source of Documents

    The philosophy of the electro mechanical project management is drawn from ISO

    9001 (2000) and British standards.

    However, every particular project is guided by its own project contract and

    supervised by quality manual.

    Main documents referred for smooth operation and implementation of quality

    standards of the project are :

    1.ISO 9001( 2000)

    2. BS standards

    3.ASTM standards

    4. ASHRE standards

    5.IEE regulation 16 th edition (Electrical)

    6. IP Standards.

    7. Local authorities rules and regulations.

    8. MEP Guide

    9. Contractual documents(applicable to specific project) such as :

    (a) Specification manual

    (b) BOQ

    (c) Tender drawings

    (d) Fidic-2005

  • 7

    PROJECT COORDINATION

  • 8

    4- Co-ordination

    4.1 The project co-ordination is the main operational and management tool to

    Execute the project smoothly and timely.

    Co-ordination among all agencies such as client, consultant, main contractor

    and other subcontractor are most essential to have proper reporting system to

    Over look and supervise all activities in progress at site.

    Generally the following chain is maintained:

    Client(Management)

    Consultant

    Main Contractor

    All sub contractor

  • 9

    4.2 Co-ordination between client and consultant

    4.2.1 It is the main obligation of the consultant to appraise the progress of the

    Project to the client periodically.

    4.2.2 Where Specified with in the tender documents or in contract documents,

    specific client reporting templates (formats) and coordination procedures will

    Be implemented. In other cases the formats published/distributed by

    Consultant will be utilized and followed.

    4.2.3 Should client need any direct reporting on specific formats the same will be

    Distributed to all concern by consultant.

    4.2.4 Generally all reporting to the client or his representative will be followed or

    routed through consultant. However client as the owner of the project can

    direct any agency involved in the project to submit specific reports. All

    agencies are requiring submitting the desired report to client under intimation

    to consultant if not directed to do so by the client.

  • 10

    4.3 Coordination between consultant and main contractor

    4.3.1 It is the main obligation and sole responsibility of the contractor to convert

    designed project in to a reality.

    4.3.2 To fulfill this task the consultant becomes the main controller of the all

    project.

    4.3.3 It is the sole responsibility of the consultant that all local and international

    norms including safety and environment protection are adhered and

    followed.

    4.3.4 The quality standards are maintained as per designed specification laid down

    in the construction documents.

    4.3.5 The consultant or his representative will act as main controller of the project.

    4.3.6 The main contractor will keep a close association with the consultant. All

    drawing/material will be approved by engineer before putting them in use.

    4.3.7 The contractor will invite engineer for all technical activities prior decided.

    4.3.8 It is the duty of consultant to remove all project bottlenecks.

    4.3.8 The contractor is obliged to bring a clear picture of all activities going on at

    the site by submitting periodic reports.

    4.3.9 The contractor will use all specific reporting formats advised by consultant

    for all project activities.

    4.3.10It is the sole responsibility of contractor to provide all infrastructure facilities

    for his and engineers staff.

    4.3.11The contractor is to provide all method statement as per enclosed template.

  • 11

    4.4 Co ordination between main contractor and sub contractor

    4.4.1 All sub contractors will work under the supervision of main contractor.

    4.4.2 All sub contractors are compulsorily registered with local government.

    4.4.3 All submittals submitted by sub contractor should be routed through main

    contractor.

    4.4.4 Main contractor should act as intermediate agency between consultant and

    sub contractor.

    4.4.5 All the periodic report submitted by sub contractor should be forwarded to

    engineer by main contractor.

    4.4.6 It is mandatory for main contractor to take the approval of all sub contractors

    engaged for project activities.

    4.4.7 Main contractor is required to pass on all standard formats of engineer to sub

    contractor.

    4.4.8 It is the sole authority of engineer to deal directly with any of the sub

    contractor wherever required or desired so by engineer.

  • 12

    MEP ORGANIZATION

  • 13

    Index Page no. 5. 01 Introduction 14-14 5.02 Management and reporting scheme 14-15 5.03 MEP orgonogram 16-16 5.04 Key personnels Job descriptions 17-25 5.05 Departments responsibilities and functions 26-26

  • 14

    5.01 - INTRODUCTION

    Comply with local Government guide lines with clear defined responsibilities especially in the area of quality assurance, site management, testing &commissioning and finally handing over the completed project to the client. 5.02 - Management reporting scheme

    MANAGING DIRECTOR

    Director

    Design manager

    Architecture

    Design manager-Inte. HeadMEP

    General Affairs

    Project REs

  • 15

    It is desired that the final goal of organization will be reached together with companys growth and development of all functions. The function of general affairs include: Human Resources, Computer systems, Legal affairs, Public relations etc. However, targeted structure of Operational organization is outlined separately and not in the scope of this manual.

  • 16

    5.03- (MEP) ORAGONOGRAM The MEP organization structure, which is a good transitional solution adequate to the current companys size, needs and resources. In this document organization of MEP Operations is outlined in details. It is based on the planned scope of activities with the expectation that desired goals will be reached.

    Assistant Resident Engineers MEP

    Senior Mechanical Engineers

    Senior Electrical Engineers

    Mechanical Inspectors

    Electrical Inspectors

    HEAD OF MEP

    Department

    Resident Engineer

    Consultant Managing Director

  • 17

    5.04 Key personnels Job descriptions

    5.04.01- Head MEP Division Jobtitle:

    HEAD MEP DEVISION

    Jobcode:

    Jobholder:

    Reportsto:Managing Director /RE

    First reports:

    All MEP project heads from various projects

    Job description:

    This is key position for ensuring Proper design with quality & safety. Development and control of quality program, technologies, products and system evaluation and highest adherence of all local and international standards.

    Responsibility: SEE IN STAFF RESPONSIBILTIES Authority: Can hire or fire staff with the approval of MD

    Can suspend staff notifying MD Approves revenue items within budget Approves capital expenditure against budget Agrees and approves product changes. Recruitment and training of MEP staff. Re location and realignment of MEP staff as per project

    requirements. Communication

    internal

    All Project heads All senior management All other personnel deem fit.

    Regulatory authorities Professional bodies Customers Suppliers

    external

    Requirements: Graduated in Mechanical / Electrical engineering. Minimum 15 years experience out of which 10 years in

    Middle East. UAE experience preferred. Leadership & Management abilities Excellent oral and written English

  • 18

    In depth understanding of local government rules and requirement.

    Familiar with computers A postgraduate qualification would be an advantage

    Managing Directors Review

    HumanResourcesReview

    Employees review

  • 19

    5.04.01 Assist. Resident Engineer

    Jobtitle: Assist. Resident Engineer

    Jobcode:(ifany)

    Jobholder:

    Reportsto: Head MEP /RE

    First reports:

    From mechanical engineer and electrical engineer of respective project.

    Job description:

    This is key position for ensuring Proper design with quality & safety. Development and control of quality system, technologies, products and system evaluation. Design of specification and product selection .Highest adherence of all local regulation and international standards.

    Responsibility: SEE IN STAFF RESPONSIBILITIES Authority: Can hire or fire staff with the approval of Head MEP

    Can suspend staff notifying Head MEP Agrees, recommend and approves product changes. Recruitment and training of MEP staff under intimation to

    MEP Head. Re location and realignment of MEP staff as per project

    requirements with in own responsibilities.

    internal

    Respective Project heads All senior management All other personnel deem fit.

  • 20

    Communication external

    Regulatory authorities Professional bodies Customers Suppliers

    Requirements: Graduated in Mechanical / Electrical engineering. Minimum 10 years experience out of which 05 years in

    Middle East. UAE experience preferred. Leadership & Management abilities Excellent oral and written English In depth understanding of local government rules and

    requirement. Familiar with computers A postgraduate qualification would be an advantage

    Head of MEP s review Human resource review Employees Review

  • 21

    5.04.03 Sr. Engineers/Engineers

    Jobtitle: Sr. Engineers

    Jobcode:(ifany)

    Jobholder:

    Reportsto: ARE(MEP)/RE

    First reports:

    From engineer/inspectors (electrical/Mechanical) of respective project.

    Job description:

    This is key position for ensuring implementation of design with quality & safety. Follow of quality program and system. Highest adherence of all local regulation and international standards.

    Responsibility: SEE IN STAFF RESPONCIBILTIES Authority:

    Agrees, recommend and approves product changes. Recruitment /interview recommendations. Training of MEP

    staff under intimation to MEP Head. Re location and realignment of MEP staff as per project

    requirements with in own responsibilities. Communication

    internal

    Respective MEP head /Project heads Technical co-ordination with other departs. All other personnel deem fit under intimation to ARE MEP

    Regulatory authorities Professional bodies Customers Suppliers

    external

    Requirements: Graduated in Mechanical / Electrical engineering.

  • 22

    Minimum 7 years experience out of which 03 years in Middle East. UAE experience preferred.

    Leadership & Management abilities Excellent oral and written English In depth understanding of local government rules and

    requirement. Familiar with computers A postgraduate qualification would be an advantage.

    Head of MEP s review

    Human resource review

    Employees Review

  • 23

    5.04.04 - MEP Inspectors

    Jobtitle: MEP Inspectors

    Jobcode:(ifany)

    Jobholder:

    Reportsto: Sr. Engineer/ Engineer

    First reports:

    Nil.

    Job description:

    This is key position for ensuring Implementation design with quality. Follow quality program. Highest adherence of all local regulation.

    Responsibility: SEE IN STAFF RESPONCIBILTIES Authority: Can recommend approval/suspension /rejection of inspection

    notifying sr. engineer/engineer. Recommend product changes. Training of MEP staff under guidance of MEP Head.

    internal

    Respective sr. engineers/MEP heads All other personnel deem fit guided by superiors.

  • 24

    Communication external

    Regulatory authorities &Professional bodies notifying MEP

    head in the project.

    Requirements: Graduated in Mechanical / Electrical engineering.

    Minimum 3 years experience out of which 02 years in Middle East. UAE experience preferred.

    Or Technical diploma with 10 years relevant experience.

    Excellent oral and written English In depth understanding of local government rules and

    requirement. Familiar with computers desirable

    Head of MEP s review Human resource review Employees Review

  • 25

    5.05 Departments responsibilities and functions

    5.5.01 MEP department will work with civil engineering in a close coordination. 5.5.02 it is the main responsibility of the department to approve all drawings/material related to HVAC, Plumbing and electrical. 5.5.03 the department will carryout all schedule inspections requested by MEP contractor. 5.5.4 It is the obligation of the department to verify and approve the sub contractor For MEP work at site. 5.5.5 All services coordination under ground and other floors above ground is to be checked and approved by department. 5.5.6 MEP department (Electrical) will assist sub contractor in solving DEWA bottle necks. 5.5.7 MEP department (Mechanical) will assist sub contractor in solving the DM problems related to water and drainage. 5.5.8 MEP department will also support civil and main contractor to solve civil defense and fire fighting problems. 5.5.9 MEP department will scrutinize all the CVs of sub contractor and approve them as per listed specification. 5.5.10 MEP department will participate in all weekly progress meetings. 5.5.11 MEP department will also participate in all other meetings called by client and or his representative. 5.5.12 MEP department will coordinate with other infrastructure contractor working with the specified area. 5.5.12 MEP department will submit periodic reports to MEP head at head office. 5.5.13 MEP department will keep all the records of inspection, material submittal and drawing submittals. 5.5.14 Any other obligations not listed here but falls under the jurisdiction of the MEP Department.

  • 26

    STAFF RESPONSIBILITIES

  • 27

    Index Page no.

    6.1 Head of Department ( MEP) 29-29

    6.2 Assistant Residence Engineer (MEP) 30-30

    6.3 Senior Engineer(Electrical/ Mechanical) 31-32

    6.4 Electrical/Mechanical Inspector 33-33

  • 28

    6.1- Head of Department (H.O.D)-MEP Technical /Administrative Responsibilities:

    6.1.1 Electro Mechanical (MEP) project management as per Dubai Govt.

    /International norms. 6.1.2 To review and approve material submittals reviewed & recommended by ARE/ Sr. engineer / Engineer.

    6.1.3 To review and approve drawing submittals reviewed & recommended by ARE/ Sr.engineer / Engineer.

    6.1.4 Participating in weekly project review meetings for tracking project progress & de-bottlenecking & implementation of procedures as per norms and Standards.

    6.1.5 To authenticate monthly payment bill after reviewed and recommended by ARE/ Senior engineers. 6.1.6 Involve in strategic technical planning for achieving targeted schedules and Their implementation 6.1.7 Departmental reporting to management on periodic basis. 6.1.8 Final authorization & counter signing for all MEP activity. 6.1.8 To provide management guidance and leadership to MEP team members. 6.1.9 To review and forward all MEP variations applicable to all on going projects. 6.1.10 To review and counter sign all the MEP correspondences made with the

    Client, main Contractor or Sub-Contractors. 6.1.11 to review and approve all contractor claim & variation (related to MEP).

    6.1.12 Institute change-management practices in the department, including restructuring & manpower rationalization initiatives, and facilitate acceptance by the staff across hierarchical levels. Formulate and benchmark functional best practices to focus on core MEP function.

    6.1.13 Evolution of performance of contractors and other associated agencies 6.1.14 Oversee smooth implementation of manpower planning, recruitment, selection, induction, orientation and development of new employee, promotion in the department through Career and Succession Planning.

  • 29

    6.2- Assistant Resident Engineers (ARE) MEP Technical and Administrative responsibilities 6.2.1 To provide leadership and technical guidance to site MEP department at site.

    To handle all incoming and out going correspondence related to MEP. 6.2.2 To review the Design of all MEP services and bring any concern to the

    attention of H.O.D. 6.2.3 To ensure that DIAR Consult concept / procedures are strictly followed by all

    the MEP staff. 6.2.4 Electro Mechanical (MEP) project management at site as per Dubai

    Govt. /International norms 6.2.5 To review and approve the material submittals reviewed & recommended by

    Sr. engineer / Engineer. 6.2.6 To review and approve the Drawing submittals reviewed & recommended by Sr.engineer / Engineer.

    6.2.7 Participating in weekly project review meetings for tracking site progress & de-bottlenecking & implementation of procedures as per norms and standards. 6.2.8 To ensure that the contractors / subcontractors are registered and obtained

    license from local authorities before commencement of the work at site. 6.2.9 To obtain approval of H.O.D on all material submittal. (if they are not

    specified) 6.2.10 To coordinate the MEP services with Civil / Architectural works. 6.2.11 To review the program of work submitted by the contractor and approve comments 6.2.12 To ensure that all testing and commissioning procedure are strictly followed

    by concerned all MEP staff. 6.2.13 To review, write and forward the performance appraisals to head of the department for all the staff working under him. 6.2.13 To prepare periodic reports for the Head of the department related to site

    progress and execution.

  • 30

    6.3- Senior Engineers (Electrical/Mechanical) (SEE/SEM)

    Responsibilities

    6.3.1 To check and review all the related material submittals documents and verify

    their conformity with the specification and Contract documents and forward to the MEP head.

    6.3.2 To ensure that all the material submittals must be submitted as per standards listed in specification book. Such as:

    a. Submittal to have Main index list b.Submittal to have Specified material list c. Submittal to have Specification copy. d.Submittal to have Catalogue copy e. Submittal to have Data sheet i.e. to describe about the proposed Technical characteristics of the material and also to show the catalogue number of the proposed material. f. Submittal to have Compliance statement showing the exact comparison between specified and proposed material submittal and to be properly stamped and signed by the main Contractor and Supplier. g.Manufacturer/supplier address to be clearly shown on submittal form.

    6.3.3 To advise sample approval of all related material before any installation in the site for MEP Head.

    6.3.4 To check and review all the related shop drawing as per the contract, tender drawing and all addenda. To ensure that shop drawings are accurate and detailed and are fully coordinated with all other services.

    6.3.5 To note and review all the changes or variations coming in drawings or BOQ (i.e. Quantity) during execution of the project.

    6.3.6 To approve request for inspection for any Electrical/mechanical activity done at site.

    6.3.7 To check the quality of work at site and insure that site execution is as per project specification and authorities regulations.

    6.3.8 To check as per actual installation and forward the As Built Drawings received from contractor to head MEP. To attend weekly site coordination meetings.

  • 31

    6.3.9 To guide and liaise with contractor/sub contractor for obtaining all approvals related to MEP from authorities.

    6.3.10 To make correspondence with the Client, Main Contractor Sub-Contractor under guidance of head MEP/ project RE.

    6.3.11 To provide guidance and supervision to related inspectors for site inspection work.

    6.3.12 To counter sign on all the inspection reports performed at site by inspectors. 6.3.13 To report to immediate superiors all matters of non conformity and

    irregularities of executed works and to record such matters consistently and systematically in proper filing system.

    6.3.14 To accept full responsibilities of site supervision of electrical / mechanical works on project as assigned by management in a professional and competent manner.

    6.3.15 To work in full coordination with all members of staff at site / head office and subscribe to the over all procedures.

  • 32

    6.4- Inspectors (Electrical/ Mechanical) (EI / MI)

    Responsibilities 6.4.1 To accept full responsibilities of site supervision of Electrical/mechanical

    Works executed at site. 6.4.2 To conduct inspections for all Electrical /mechanical works done at site as per inspection request submitted by contractor. 6.4.3 To supervise & improve the quality and quantity of Electrical / Mechanical installation at site 6.4.4 To check and be ensured at site that only approve material/drawing is

    (being) used. 6.4.5 To conduct and witness all types of electrical/mechanical site testing and commissioning and make written report to superiors at sites. 6.4.6 To conduct / check all the insulation resistance test, continuity test of LV cable

    Polarity test, earth resistance test, air balancing test, chilled water balancing test, pressure test, hydraulic test, units & equipment test etc.

    6.4.7 To review the location and the installation levels for all Electrical/Mechanical equipments, panels, accessories etc at site.

  • 33

    INSPECTION METHODOLOGY

    (ELECTRICAL)

  • 34

    INSPECTION METHODOLOGY-(ELECTRICAL) INDEX Page No.

    7.1 L.V Panel Main Distribution Board (MDB) 35-36 7.2 SUB Main Distribution Board (SMDB) 36-37 7.3 Final Distribution Board (DB) 38-38 7.4 Capacitor Bank 39-40 7.5 Equipment Control Panel 40-41 7.6 Isolators 41-41 7.7 Electrical Manholes (EMH) 42-42 7.8 Telephone Manholes (TMH) 42-43 7.9 Light Fittings (Indoor Fittings, Wall Lights, & Emergency

    Lights) 43-44

    7.10 Light Switches & Power Switches 45-45 7.11 Switched Sockets 46-46 7.12 Standby Generator Set 47-48 7.13 Transformer & Ring Main Unit (RMU) 48-48 7.14 Equipment Earth Pits Neutral Earth Pits (EP) 49-49 7.15 Fire Alarm System 49-50 7.16 Voice Data Structured Cabling System 51-51 7.17 Intruder Alarm System 52-52 7.18 CCTV System 52-53 7.19 Building Management & Control System 53-54 7.20 Public Address & Music System 54-55 7.21 MATV System 56-56 7.22 Lightning Protection System 56-56

  • 35

    7.1- (L.V). Main Distribution Boards MDB M.D.B should be checked & inspected as per approved material submittal and Listed specification. The below mentioned checks should be done by electrical inspector and verified by sr. engineer/engineer electrical. 7.1.1 MDB Should be from approved vendor as per approved material submittals IP grade , color and form of the panel to be confirmed as per approval. 7.1.2 Check and verify Factory Test Certificate from panel manufacturer. 7.1.3 MDB should be as per approved component and drawings. 7.1.4 Make and rating of the Circuit Breakers, meters (A&V), ELCBs etc. should be as per approved submittal. 7.1.5 Rating & Quantity of future space / spare feeders should be as per approvals. 7.1.6 Fault rating of the bus bar & circuit breaker should be as per approved drawings 7.1.7 Circuit Breaker settings verified / adjusted should be as per approved drawings 7.1.8 Bus Bar compartment should be fully shrouded and proper warning labels to be provided 7.1.9 MDB door gaskets, protective covers / shrouds should be fitted 7.1.10 MDB installation should be done properly & sufficient supports provided 7.1.11 Cable glanding, termination, cables supports & tagging should be proper and satisfactory. 7.1.12 MDB power cables, Cable glands and all components should be easily accessible 7.1.13 Cable tray and trunking in side the panel should be in installed properly with cove on. Earthing to the panel to be provided. 7.1.14 Earthing and equiv. potential bonding of MDB is done properly & size of earth cable should be as per drawing 7.1.15 MDB internal & external surfaces should be clean & all unused holes plugged 7.1.16 Insulation (Megering) resistance for MDB should be carried out at site and to be recorded 7.1.17 Insulation resistance for main & all feeder cables should be carried out and to be recorded 7.1.18 ATS operation (auto / manual) functional check should be carried out (if applicable) 7.1.19 Earth Leakage / fault teat should be carried out & should be satisfactory where ever applicable.

  • 36

    7.1.20 KWh installation, type, C.T ratio and locations should be as per local govt. authoritys approval. 7.1.21 MDB main label with feeder description & Component identification labels should be provided 7.1.22 Laminated approved load schedules should be provided inside the MDB. 7.1.23 As-Built drawing from panel builder should be provided in drawing pocket in MDB. 7.2- SUB Main Distribution Board (SMDB) Should be checked & inspected as per specification & material submittal approval by the inspector & is to be cross checked by Engineer stated as follow.

    7.2.1 SMDB Supplied From approved vendor should be as per approved material submittal.

    7.2.2 Factory test certificate from panel builder should be verified and values to be accepted.

    7.2.3 SMDB should be as per approved drawings, single line diagram and to be requirements.

    7.2.4 Rating & Quantity of the Circuit Breakers, meter etc. should be as per approved drawing.

    7.2.5 Rating & Quantity of future space / spare feeders should be as per approvals7.2.6 Fault rating of the bus bar & circuit breaker should be as per approved

    drawings. 7.2.7 Circuit Breaker settings verified / adjusted should be as per approved

    drawings. 7.2.8 Bus Bar Compartment should be fully shrouded and to be proper warning

    label provided. 7.2.9 SMAB door gaskets, protective covers / shrouds should be fitted 7.2.10 SMAD installation to be done properly & sufficient supports should be

    provided.

  • 37

    7.2.11 Cable glanding, termination, cables supports & tagging should be satisfactory.

    7.2.12 SMDB power cables, Cable glands and all components should be easily accessible.

    7.2.13 Cable tray and trunking should be installed properly, covers and earthing are to be provided.

    7.2.14 Earth bonding of SMDB to be done properly & size of earth cable should be as per drawing.

    7.2.15 SMDB internal & external surfaces should be clean & all unused holes to be plugged.

    7.2.16 Installation resistance for SMDB should be carried out at site and to be recorded.

    7.2.17 Installation resistance for main & all feeder cables should be carried out and to be recorded.

    7.2.18 Functional Test for SMDB should be carried out and to be found satisfactory.

    7.2.19 Earth Leakage / fault teat should be carried out &to be found satisfactory (if applicable).

    7.2.2O Main Label, feeder description & Component identification labels should be provided.

    7.2.21 Laminated approved load schedules should be provided inside the SMDB 7.2.22 As-Built drawing from panel builder should be provided in drawing pocket

    in SMDB. 7.2.23

    As-Built drawing from panel builder should be provided in drawing pocket in SMDB.

  • 38

    7.3- Final Distribution Board (DB) D.B should be checked & inspected as per approved material submittal and listed specification. The below mentioned checks should be done by electrical inspector and verified by sr. engineer/engineer electrical. 7.3.1 DB Should be from approved vendor as per approved material submittals IP grade, color and form of the panel to be confirmed as per approval. 7.3.2 Check and verify Factory Test Certificate from panel manufacturer. 7.3.3 DB should be as per approved component and drawings. 7.3.4 Make and rating of the Circuit Breakers, meters (A&V), ELCBs etc. should be as per approved submittal. 7.3.5 Rating & Quantity of future space / spare feeders should be as per approvals. 7.3.6 Fault rating of the bus bar & circuit breaker should be as per approved drawings 7.3.7 Circuit Breaker settings verified / adjusted should be as per approved drawings 7.3.8 Bus Bar compartment should be fully shrouded and proper warning labels to be provided 7.3.9 DB door gaskets, protective covers / shrouds should be fitted 7.3.10 DB installation should be done properly & sufficient supports provided 7.3.11 Cable glanding, termination, cables supports & tagging should be proper and satisfactory. 7.3.12 DB power cables, Cable glands and all components should be easily accessible 7.3.13 Cable tray and trunking in side the panel should be in installed properly with cove on. Earthing to the panel to be provided. 7.3.14 Earthing and equiv. potential bonding of DB is done properly & size of earth cable should be as per drawing. 7.3.15 DB internal & external surfaces should be clean & all unused holes plugged. 7.3.16 Insulation (Megering) resistance for DB should be carried out at site and to be recorded 7.3.17 Insulation resistance for main & all feeder cables should be carried out and to be recorded 7.3.18 ATS operation (auto / manual) functional check should be carried out (if applicable) 7.3.19 Earth Leakage / fault teat should be carried out & should be satisfactory where ever applicable 7.3.20 DB main label with feeder description & Component identification labels should be provided 7.3.21 Laminated approved load schedules should be provided inside the DB. 7.3.22 As-Built drawing from panel builder should be provided in drawing pocket in MDB.

  • 39

    7.4- Capacitor Bank Should be checked & inspected as per specification & material submittal approval by the inspector & is to be cross checked by Engineer stated as follow.

    7.4.1 Panel supplied from approved vendor should be as per approved material submittal.

    7.4.2 Factory Test Certificate from panel builder should be verified and values to be accepted.

    7.4.3 Panel should be as per approved drawings, load schedules and requirement. 7.4.4 Rating of circuit breakers, fuses, capacitor should be as per approved

    drawing. 7.4.5 Switching step of capacitor banks should be as per approved drawing. 7.4.6 Fault rating of the bus bar & circuit breaker should be as per approved

    drawing.

    7.4.7 Circuit breaker settings should be verified / adjusted should be as per approved drawing.

    7.4.8 Bus bar should be fully shrouded and proper warning label should be provided.

    7.4.9 Panel door gaskets, protective cover/ shrouds should be fitted. 7.4.1O Air inlet filter, ventilation with thermostat should be provided. 7.4.11 Panel installation should be done properly& sufficient support should be

    provided. 7.4.12 Cable glanding, termination cable support & tagging should be satisfactory 7.4.13 Panel power cables, cables glands and all components should be easily

    accessible. 7.4.14 Cable tray and trunking installed properly, cover and earthing should be

    provided. 7.4.15 Earth bonding of panel should be done properly & size of earth cable

    should be as per drawing. 7.4.16 Panel external and internal surface should be clean and all unused holes

    should be plugged. 7.4.17 Installation resistance of panel should be carried out at site & to be record. 7.4.18 Installation resistance of main cable should be carried out and to be record.

  • 40

    7.4.19 Functional test for the capacitor panel carried out & should be found satisfactory

    7.4.2O Panel main tag and components identification should be by permanent labels

    7.4.21 As-built drawing from panel builder should be provided in a drawing pocket in panel.

    7.5- Equipment Control Panel Equipment control panel should be checked & inspected as per approved material submittal and listed specification. The below mentioned checks should be done by electrical inspector and verified by sr. engineer /engineer electrical.

    7.5.1 Panel supplied should be from approved vendor and as per approved material submittal.

    7.5.2 Factory test certificate should be from panel builder to be verified and result to be accepted

    7.5.3 Control panel dimensions & arrangements should be as per the approved drawings

    7.5.4 Ratings and quantity of MCB / MCCB / ELCB should be as per approved drawings.

    7.5.5 Panel power and control wiring should be as per standard drawings and requirements.

    7.5.6 Rating of contactors / over load relays should be as per approved drawings.

    7.5.7 Permanent identification of all components inside the control panel should be marked.

    7.5.8 Wire sizes, color coding, terminations should be properly executed inside the panel.

    7.5.9 Panel gaskets, bus bar shrouding, protective cover & warning label should be provided.

    7.5.1O Installation of the panel should be done properly.

    7.5.11 Cable size type, glanding, terminations, support & tagging should be satisfactory.

    7.5.12 Panel cables, glands and all components should be accessible easily. 7.5.13 Control wiring type & size, dressing, terminations and marking should be

    done properly. 7.5.14 Panel internal & external surfaces should be clean & all unused holes

    should be plugged.

  • 41

    7.5.15 Earthing of the equipment and panel should be done satisfactorily. 7.5.16 Insulation resistance for power and control cables should be carried out and

    to be recorded. 7.5.17 Test / commissioning of system in coordination with supplier should be

    done & to be certified. 7.5.18 All functional checks and testing for circuits should be carried out & to be

    found satisfactory. 7.5.19 Panel builder As-built drawing should provided inside the panel in

    drawing pocket 7.6- Isolators Equipment control panel should be checked & inspected as per approved material Submittal and listed specification. The below mentioned checks should be done by electrical inspector and verified by sr. engineer /engineer electrical.

    7.6.1 Isolators should be from approved vendor as per approved material submittal

    7.6.2 Mounting arrangement of isolator unit should be satisfactory (Recess / Surface).

    7.6.3 Isolator should be suitable for the location (check IP rating). 7.6.4 Isolator duty ampere rating should be as per approved drawing and

    requirements. 7.6.5 7.6.6 Isolator unit location should be satisfactory & easily accessible for

    operation 7.6.7 Gasket (if any), protective cover / shrouds (if applicable) should be fitted. 7.6.8 Isolator unit installation should be done properly & sufficient support to be

    provided. 7.6.9 Power cable glanding, termination, cables support & tagging should be

    satisfactory. 7.6.1O Installation of the concealed ducts for isolator cables should be satisfactory

    ( If applicable). 7.6.11 Cable tray and trunking should be installed properly, covers should be

    provided. 7.6.12 Earthing of the isolator should be done properly & and size of earth cable to

    be as per approved drawing. 7.6.13 Isolator unit internal & external surface should be clean and unused holes

    plugged. 7.6.14 Earth leakage teat should be carried out and to be found satisfactory ( If

    applicable) 7.6.15 Isolator unit main tag provided should be as per equipment & drawings.

  • 42

    7.7- Electrical Manholes (EMH) Should be checked by inspector as per shop drawing. Location, specification & size are to be checked. A co-ordination between electrical and civil is to be done as per following steps.

    7.7.1 Manhole construction should be as per specification. 7.7.2 Manhole size and location should be as per approved drawing and

    requirement 7.7.3 Manhole inner finish should be smooth and coated with water proofing

    material 7.7.4 Ducts should be as per approved vendor and material submittal 7.7.5 Duct location, arrangement should be in the manholes are to be satisfactory. 7.7.6 Duct size should be such that it remains with 60% empty space after

    installing the cable/wire in it. 7.7.7 Spare ducts with pull wires should be installed for future use. 7.7.8 Duct ends should not be damaged and to be provided with end bell. 7.7.9 Ducts should be utilized evenly and spare space should be available in each

    ducts. 7.7.1O Cable installations and neatness inside the manholes should be satisfactory. 7.7.11 Sufficient cable loops should be provided in side the Manhole (where

    applicable). 7.7.12 All cable should be in the Manholes are to be identified by aluminum /

    stainless steel tags. 7.7.13 All ducts ends should be sealed with gasoline resistance compound. 7.7.14 Cover size should be same as manhole size & is water tight. 7.7.15 Cover should be oil-gasoline resistance gasket, greased, painted and to be

    tagged. 7.7.16 Cover should fit to the frame properly and no rattle cover after installation. 7.7.17 Manhole to have Arabic and English tagging, clarifying the manhole is for

    Electrical. 7.8- Telephone Man Holes (TMH) Should be checked by inspector as per shop drawing. Location, specification & size are to be checked. A co-ordination between electrical engineer and civil engineer is to be done as per following

    7.8.1 Manhole construction should be as per specification. 7.8.2 Manhole size and location should be as per approved drawing and

    requirement. 7.8.3 Manhole inner finish should be smooth and to be coated with water

    proofing material

  • 43

    7.8.4 Ducts should be as per approved material submittal.

    7.8.5 Duct location, arrangement in the manholes should be satisfactory. Electrical wiring and telephone wiring should not be mixed.

    7.8.6 Duct size should be as per approved drawing and to be sufficient to install cables.

    7.8.7 Spare ducts with pull wires should be installed for future use. 7.8.8 Duct ends should be not damaged and to be provided with end bell. 7.8.9 Ducts should be utilized evenly and spare space to be available in each

    ducts 7.8.10 Cable installations and neatness inside the manholes should be satisfactory.

    7.8.11 Signal / Data cables inside Manhole should be installed in flexible conduits. 7.8.12 Sufficient cable loops should be provided in side the Manhole (where

    applicable). 7.8.13 All cable in the Manholes should be identified by aluminum / stainless steel

    tags. 7.8.14 All ducts ends should be sealed with gasoline resistance compound. 7.8.15 Cover size should be same as manhole size & is water tight. 7.8.16 Cover should be oil-gasoline resistance gasket, greased, painted and to be

    tagged. 7.8.17 Cover fit to the frame should be properly and should not rattle cover after

    installation.0. 7.9- Light Fittings (indoor fitting, Wall light & Emergency Lights) Installation is to be checked & inspected as per specification, approved drawings & Approved submittal by the inspector. Engineer has to ensured that the following procedure is strictly followed.

    7.9.1 Light fitting should be as per material submittal 7.9.2 Light fitting should be as per specification, approved drawing approved

    sample & requirement 7.9.3 Lamp wattage & type (day light, etc) should be as per the drawing and

    specification. 7.9.4 Light fitting should be suitable for location (IP rating, Mounting etc.) 7.9.5 Light layout / location should be as per approved drawings. 7.9.6 Installation of light fitting should be done properly.

  • 44

    7.9.7 Fitting and Ceiling rose / light point should be easily accessible and to be replaceable.

    7.9.8 Control Transformer (if any) should be install properly and to be easily accessible.

    7.9.9 wiring should be as per drawing (Plug in Ceiling rose, heat resistance cable, etc).

    7.9.1O Earth connection to the fittings should be done properly. 7.9.11 Conduit sizes are adequate & should be as per the specification. 7.9.12 Conduit installation to the ceiling roses / light points should be satisfactory. 7.9.13 Conduits above false ceiling should be clamped adequately (others

    concealed).

    7.9.14 Switch / Automatic controls, circuit wiring and wire sizes should be as per the drawing.

    7.9.15 Light fitting surface, trims and diffusers should be clean. They are to be free from dust and stains.

    7.9.16 Light fitting should be complete in all respects (annular glass/ emergency kit etc.).

    7.9.17 Light fitting and circuit wiring should be tested for functionality. 7.9.18 Emergency light / kit should be tested for functionality.

  • 45

    7.10- Light Switches & Power Switches Installation is to be checked & inspected as per specification, approved drawings & approved submittal by the inspector. Engineer should ensure that the following procedure is strictly followed.

    7.10.1 Switches should be as per specification and approved make and should be strictly as per approved material submittal.

    7.10.2 Switch rating, type, poles rocker design and gang should be as per the drawing & approved specification.

    7.10.3 Location & mounting height of switch should be as per local authority rules and regulation as well as per approved drawings and IP rating should be as applicable.

    7.10.4 Wiring and wire type, size, color coding etc. should be as per drawing and specification.

    7.10.5 Installation and finishing around the switch should be aesthetically satisfactory

    7.10.6 Phase barrier and warning labels should be provided (If applicable). 7.10.7 Power switches should be with light indicator. 7.10.8 Brushed / stainless steel front plate accessory should be provided (where

    specified). 7.10.9 Power switches should be with approved flex outlet / connection unit to be

    as per drawing. 7.10.1O Location, Installation & finishing around flex outlet / connect unit should

    be satisfactory. 7.10.11 Functional test should be carried out and should be satisfactory.

  • 46

    7.11- Switched Sockets Installation is to be checked & inspected as per specification, approved drawings & approved submittal by the inspector. Engineer should ensure that the following procedure is strictly followed.

    7.11.1 Sockets should be as per specification, make and as per approved material submittal & sample provided.

    7.11.2 Sockets rating, type & gang should be as per the drawing & specification. 7.11.3 Location & mounting height of sockets should be as per local authoritys

    rule and regulation and as per specification / requirement reflected in approved drawings.

    7.11.4 Back box installation and conduit arrangement / termination should be satisfactory.

    7.11.5 Socket suitable for location (IP Ratings) and should be as per drawing. 7.11.6 Wiring(ring/ radial), wire type, size, color coding etc. should be as per

    drawing and standard. 7.11.7 Earth connection to the socket & earth loop to back box should be done

    properly and satisfactorily. 7.11.8 Sockets should be switched type with Sutter and to be red light indicator (If

    applicable). 7.11.9 Installation and finishing around the socket should be aesthetically

    satisfactory. 7.11.1O Installation and wiring should be skirting & trucnking / floor box should be

    satisfactory (if applicable). 7.11.11 Brushed / stainless steel front plate accessory should be provided (where

    specified). 7.11.12 Installation / Location of socket above false ceiling (if applicable) should be

    satisfactory. 7.11.13 Functional test should be carried out and should be mandatory satisfactory.

  • 47

    7.12- Generator (As stand by power source) Installation is to be checked & inspected as per IEE rules, approved drawings & Engineer has to ensure that the following procedure is strictly followed.

    7.12.1 Generator supplied should be from approved vendor /make and capacity is as per approved material submittal.

    7.12.2 Factory test certificate from manufacturer should be verified and values to be accepted

    7.12.3 Generator set should be as per approved, specification and capacity.

    7.12.4 Technical characteristics of generator should be as per drawing / specification.

    7.12.5 Installation of generator should be done as per local authoritys /IEE rules regulation & should be certified by generator dealer/supplier.

    7.12.6 Linear vibration isolator & anti vibration pad should be provided and leveling of the machine should be checked by calibrated level indicator and expert engineer only.

    7.12.7 Silencer and muffler should be provided. 7.12.8 Flame/ spark arrestor and rain cap at end of exhaust pipe should be

    provided. 7.12.9 Type, rating of batteries and battery charger & controls should be verified.

    7.12.1O Fuel level gauge, Fuel low level alarm and shut down should be verified. 7.12.11 Double earthing of Engine-generator frame and single earthing for fuel tank

    should be done satisfactorily. Earthing should be with flat copper plate /copper wire and should be as per IEE rules.

    7.12.12 Generator neutral earthing should be done and tested. Earthing (Resistance) value to be recorded periodically and during commissioning. The earthing value should be less then 01 OHM when measure between two earthing points separated six meters from each other. Body earthing point and neutral earthing should not be mixed together.

    7.12.13 Generator panel metering, control & alarms should be as per the specification and to be verified. A mechanical and electrical isolation should be provided as safety between DEWA power and generator.

    7.12.14 Power cable glanding, termination, cable support & tagging should be provided.

    7.12.15 Cable tray & trunking should be installed properly; covers and earthing should be provided.

  • 48

    7.12.16 Installation resistance for alternator (with - outgoing cable disconnected), and out going cables (in open end status) should be carried out and to be recorded.

    7.12.17 Startup and commissioning should be carried out by authorized person from dealer/supplier and all parameters are to be recorded such as frequency, voltage, RPM, engine oil pressure and fuel governor function.

    7.13- Transformer & Ring Main Unit (RMU) The Responsible Engineer must Ensure that the installation of Transformer & Ring Main Unit is done as per the rule & regulations of electricity authority & should be checked as follows

    7.13.1 Transformer & RMU supplied should be as per approval by Electricity authority.

    7.13.2 Transformer & RMU rating should be as per approved drawings and specification.

    7.13.3 Installation should be done satisfactory & approved by authority (if done by contractor)

    7.13.4 Power cable glanding, termination, cable support & tagging should be satisfactory.

    7.13.5 Covered cable tray and trucking should be installed properly. Proper /satisfactory Earthing should be provided.

    7.13.6 Installation resistance for transformer LV cables should be carried out (In open end status) and to be recorded.

    7.13.7 Transformer & RMU body earthing should be satisfactory and as per authority / IEE regulation.

    7.13.8 Transformer neutral earthing should be satisfactory and as per authority regulation. Neutral and body earthing should not be mixed. The earthing resistance value when measured should be less 01 OHM.

  • 49

    7.14- Equipment Earth pits / Neutral Earth pits (EP) Inspection is to be conducted as per the following procedure & should be cross checked by the responsible Engineer as follows

    7.14.1 Earth pit construction should be as per specification. 7.14.2 Earthing materials should be from approved make and to be as per

    approved submittal. 7.14.3 Earth pit location should be as per approved drawing / requirement and

    should be satisfactory. 7.14.4 Copper earth rod (size), cable clamps (material) and accessories (make)

    should be as per approved material submittal. 7.14.5 Earth cable size should be as per approved drawing & standards. Earthing

    cable installation should be duct/conduit as applicable and to be satisfactory.

    7.14.6 Spacing between parallel rods should be as per specified in the drawing & should be more then length of rods.

    7.14.7 Earth termination in pit should be visible, accessible, greased, tape and to be shrouded. White grease (white jelly) to be used.

    7.14.8 Back filling of earth pit should be done properly. 7.14.9 Pit should be cover fit flush with finish floor / tile level without any rattle. 7.14.10 Earth pit cover (for transformer / generator - neutral earth) should be

    marked by paint. Other earthing points should be given number if more then one earthing point exits and to be recorded for future reference.

    7.14.11 Earth resistance test should be carried out, to be recorded and should be found with in limits ( 01 OHM).

    7.15- Fire Alarm System The responsible Engineer must ensure that the following procedure is strictly followed and checked

    7.15.1 Fire Alarm system supplied should be as per approved make and as per material submittal.

    7.15.2 Factory QC test certificate from supplier should be verified. 7.15.3 Fire Alarm panel zone, alarm and indications should be as drawing /

    specification.

  • 50

    7.15.4 Mounting arrangements and installation of fire alarm panel should be satisfactory.

    7.15.5 Cable glanding, terminations, & tagging in the fire alarm panel should be satisfactory.

    7.15.6 Fire alarm panel internal and external surface should be clean. 7.15.7 Cable for out door (XLPE armored) / in door (FP200) and correct size should be

    used. 7.15.8 Fire sensor terminal box / Cover (From approved manufacture) should be in

    white color. 7.15.9 Junction box location and ducts location should be as per drawing.

    7.15.1O Cable glanding, terminations & tagging inside junction box should be satisfactory.

    7.15.11 Fire alarm detectors, Break glass, and bell their numbers and location should be as per approved drawing / specifications.

    7.15.12 Location of fire alarm devices should be as per drawing and requirement. 7.15.13 Bell and Break glass installed out door should be W/P type (where

    applicable). 7.15.14 Installation and wiring of fire alarm devices should be as per drawing /

    satisfactory. 7.15.15 Wires for devices installed should be in conduit and concealed (except above

    false ceiling).

    7.15.16 Installation resistance for cables should be carried out and to be recorded. 7.15.17 Test / Commissioning of system in co-ordination with supplier should be done

    & to be certified. The system should be connected through telephone line to local fire station where necessary and mandatory as per local rules.

    7.15.18 Functional test should be carried out, should be recorded and to be found satisfactory

    7.15.19 Engraved zone chart should be provided adjacent to fire alarm panel. Emergency telephone numbers of fire station should be written with bold letters on or near to fire alarm system/panel.

  • 51

    7.16- Voice Data / Structured Cabling System The responsible Engineer must ensure that the following procedure is strictly followed and checked 7.16.1 Structured cabling system installation should be done by approved

    contractor by Etisalate or DU. 7.16.2 Location, size and installation of Etisalat & intermediate DP should be

    satisfactory. 7.16.3 Recessed cabinet for Etisalat & intermediate DP should be satisfactory 7.16.4 Patch panel size, location and installation should be satisfactory.

    7.16.5 Cable glanding, terminations & tagging to / in patch panel should be satisfactory.

    7.16.6 Patch panel internal & external surface should be clean. 7.16.7 Cables for outdoor / indoor used should be correct and as per approved

    submittal. 7.16.8 Telephone junction box / cover (from approved manufacturer) should be in

    white color. 7.16.9 Junction box locations and ducts should be as per approved drawing. 7.16.10 Cable glanding / terminations & tagging inside junction box should be

    satisfactory. 7.16.11 Voice / Data socket & locations should be as per drawings / specification.

    Identification tags should be provided. 7.16.12 Front plate accessories and voice data sockets to be as per approved

    submittal. 7.16.13 Installation & wiring of voice data device should be as per drawings and

    satisfactory. 7.16.14 Wires for devices should install in conduit and concealed (except above

    false ceiling). 7.16.15 DOMS unit location, installation and wiring should be satisfactory. 7.16.17 Cables & other elements installed should be as per automation drawing /

    requirements. 7.16.18 Test / commissioning of system in co-ordination with supplier should be

    done & to be certified. 7.16.19 Functional tests should be carried out and recorded and to be found

    mandatory satisfactory. 7.16.2O Tank gauging cabling, JB and power / data socket provided should be as per

    drawings.

  • 52

    7.17- Intruder Alarm System The responsible Engineer must ensure that the following procedure is strictly followed and checked 7.17.1 System should be supplied from approved vender and should be as per

    approved material submittal. 7.17.2 Panel, keypad, sensor, LIM & motion detector location should be as per

    drawings. 7.17.3 Panel and LIM above false ceiling should be easily accessible / replaceable. 7.17.4 Ceiling mounted glass break sensors should cover the entire glass area. 7.17.5 Cabling, terminations & tagging of intruder elements should be satisfactory. 7.17.6 Cable installed should be in conduits and concealed (except above false

    ceiling). 7.17.7 Intruder alarm buzzer location should be as per drawing & outdoor use (If

    applicable). 7.17.8 Intruder alarm programmed should be as per user requirement. 7.17.9 Test / Commissioning of system in co-ordination with supplier should be

    done & to be certified and recorded. 7.17.10 Functional test should be carried out and recorded and to be found

    mandatory satisfactory. 7.17.1 Engraved zone chart for intruder system should provide adjacent to key

    pad.

    7.18- CCTV System The responsible Engineer must ensure that the following procedure is strictly followed and checked

    7.18.1 System should be supplied from approved vendor & should be as per approved material submittal

    7.18.2 Cameras, monitors, switching & recording, modem locations should be as per drawings.

    7.18.3 Poles specification & installation should be as per approved drawings / user requirement.

    7.18.4 Cameras should be PTZ type and monitor is 17 size minimum (color monitor).

    7.18.5 Camera installation should be per approved drawing and to be easily accessible.

  • 53

    7.18.6 Ceiling mounted and pole mounted cameras should installed properly. 7.18.7 System cable installation, termination & tagging should be satisfactory. 7.18.8 Power cable installation, termination and tagging for cameras should be

    satisfactory.

    7.18.09 Installation of monitors and switching devices should be satisfactory and as per user requirement.

    7.18.10 CCTV system should be programmed as per requirement & specification.

    7.18.11 Software integration should be satisfactory.

    7.18.12 Camera resolutions and picture quality on the monitor should Be satisfactory.

    7.18.13 Test / Commissioning of system should be coordination with supplier done & to be certified.

    7.18.13 Functional tests should be carried out, should be recorded and to be found satisfactory. 7.19- Building Management and Control System Installation is to be done in co-ordination with the supplier. The installation is to be Inspected & checked using the following procedure which is to be confirmed by the responsible Engineer 7.19.01 All wiring and tubing should be properly supported and run in a neat and workmanship manner. 7.19.02 All wiring and tubing exposed and in equipment rooms should run parallel to or

    at right angles to the building structure. 7.19.03 All piping and wiring with in enclosures should be neatly bundled and to be enclosed to prevent obstruction to devices and terminals. 7.19.03 Soft copy of Master computer programs and data files is to be preserved.

    (Including all control programs, initial approved parameters, settings, English descriptors, and color graphics complete with dynamic dispersed data)

    7.19.04 Diskette should be copied and preserved and to be used/reloaded in cash of system crash and memory failure.

    7.19.05 Should be completely checked for calibration test of all connected hardware and software to be insure that the system performs in accordance with the approved specification and sequences of operation submitted.

  • 54

    7.19.06 All instruments, switches, sensors, transmitters etc. should be suitably wired and mounted. They are to be protect them from vibration, moisture, mechanical damages and temperature variations. 7.19.07 All equipment and panels should be identified, with permanently mounted tags.

    7.19.08 Auxiliary pilot duty relays on all starters is require for control function. 7.19.09 All wiring should be as recommended by system supplier and manufacturer. All communication cables/wire should be of low impedance type and should be screened type. 7.20.10 All blower motors for AHUs connected to BMS system should be speed controlled with frequency control device. 7.21.11 if system is monitored and controlled type then it should be connected to PC as specified and directed by user. 7.19.12 Functional test should be carried out and to be found satisfactory. 7.20- Public Address and Music System The responsible Engineer must ensure that the following procedure is strictly followed and checked. 7.20.1 System supplied should be from approved vendor and make and as per

    approved material submittal. 7.20.2 Speakers for public address and music system location should be as per

    approved drawing. 7.20.3 Public address system cabinet and control installation should be as per

    approved drawing / requirement.

    7.20.4 Radio Channel, VCD Channel, Tape channel, provided should be as per approved drawing / requirement.

    7.20.5 Zoning of each area to be required by the detail design as indicated in the single line diagram.

    7.20.6 PA system interlinked with the fire alarm system and provision for automatic broad cost of emergency evacuation message should be satisfactory and requirement.

  • 55

    7.20.7 Sound pressure level (SPL) and distribution for the various area should be satisfactory.

    7.20.8 Paging microphone mounted on a table desk with illuminated push buttons for selective paging of different zone should be satisfactory.

    7.20.9 Test / Commissioning of system in co-ordination with supplier should be done and to be certified

    7.20.1O Functional test to be carried out, should be recorded and to be found satisfactory.

    7.21- MATV System The responsible Engineer must ensure that the following procedure is strictly followed and checked. 7.21.1 System should be supplied from approved vendor/make and as per

    approved material submittal 7.21.2 MATV system (head end station, Disheartens, Amplifier, Junction Boxes)

    etc. location should be as per drawing. 7.21.3 Numbers of satellite dishes complete with their feed horn and LNB

    selection of channels should be as per approved drawing / requirement. 7.21.4 Number of Antennas with their mast for AM/FM reception channels should

    be as per approved drawing / requirement. 7.21.5 Head end station which houses all amplifier, receiver, modulator, invertors,

    , power supply units character generators etc. for a minimum of 40 numbers digital channels and in house audio, video and information channels should be as per requirement and to be satisfactory.

    7.21.6 All necessary splitter boxes, line amplifies, cabling, conduits, cable trays, TV, FM outlets etc. location should be as per drawing.

    7.21.7 Provision to connect the MATV system at the head end station to a minimum 10 more channel in future should be provided.

  • 56

    7.21.8 Splitters and tap-off boxes used with in system for distributing the signal to the outlet sockets have a minimum frequency range of 0.15 MHZ up to 2050 MHZ should be as per requirement and to be satisfactory.

    7.21.9 Test / Commissioning of system in co-ordination with supplier should be done satisfactorily and to be certified.

    7.21.1O Functional test should be carried out , to be recorded and should found satisfactory

    7.22- Lightning Protection System The responsible Engineer must ensure that the following procedure is strictly followed and checked 7.22.1 System supplied should be from approved vendor/make and as per

    approved material submittal. 7.22.2 Lightning system location should be as per drawing.( at the highest point of

    the building) 7.22.3 Air terminal networks, down conductors, earthing network, equiv. potential

    bonding of all metal works, all related accessories, thermo weld joints and terminations and connections should be satisfactory 7.22.5 Protection of all electronic equipment with in the building against the

    transient over voltage caused by lightning should be provided. 7.22.6 Sufficient number of rods, resistance to earth not exceeding 10 ohm is

    satisfactory. 7.22.7 Direct paths from air terminals to ground earth connections should be done.

    Avoid sharp bends & narrow loops. 7.22.8 Testing / Commissioning of system in co-ordination with supplier should be

    done and certified.

  • 57

    INSPECTION METHODOLOGY (MECHANICAL)

  • 58

    8- INSPECTION METHODOLOGY-(MECHANICAL) INDEX Page No.

    8.1 Piping Installations 59 8.2 Sleeves & Escutcheon 60 8.3 Access Panels & Accessibility 60 8.4 Protection 60 8.5 Identification 60 8.6 Vibration Control 61 8.7 Mechanical Insulation 61 8.8 Valves 61 8.9 Drainage Specialties 62 8.10 Fire Fighting System 62 8.11 Fire Pumps 63 8.12 Plumbing Pumps 63 8.13 Chilled Water Pumps 64 8.14 Chilled Water Piping 64-65 8.15 Chillers 65-66 8.16 Air Handling Unit. 66 8.17 Fan Coil Units 67 8.18 Duct Work 67 8.19 Air Outlets 68 8.20 Air Filtration 68 8.21 Coordination / Roof Works 69-70 8.22 External Services 70 8.23 Testing & Commissioning 71-74

  • 59

    8.1- Piping Installation

    8.1.1 Where possible, store pipe and tube inside and protected from weather 8.1.2 All piping under buildings and roads shall be encased in concrete with 150 mm cover on all sides 8.1.3 Provide thrust blocks for buried water mains, at every change in direction of the pipe 8.1.4 Provide expansion joints for all piping at building expansion joints 8.1.5 All horizontal drainage piping for sizes 100mm and above shall be installed with 1 % minimum slope unless otherwise indicated and 2% for sizes less than 100mm

    8.1.6 All pipe work shall be tested hydraulically to a pressure equal to twice the working pressure. If the working pressure is greater than 600 kPa the test pressure may be one and a half times the working pressure 8.1.7 Install air vents at all high points where air may collect and not be carried by

    The system 8.1.8 Arrange and install piping to obtain maximum head room, avoiding structural interference 8.1.9 Install piping parallel to building walls 8.1.10 Pipes transporting hot fluids shall be installed at least 6" (150 mm) away from pipes transporting cold fluids 8.1.11 Electrical conduits shall not touch or be supported on pipe 8.1.12 Protect the open ends by using temporary plugs or caps.

    8.1.13 All reductions in pipe size shall be made by using reducing fittings 8.1.14 Provide flanged or union connections for ready disconnection of piping at equipment 8.1.15 Provide drip pans below all water, or drain piping, if any, located in electrical rooms and transformer rooms 8.1.16 All piping work in finished areas shall be concealed in ceiling spaces and shafts or chased into walls. 8.1.17 Cover all temporary openings n ducts and pipes with polyethylene sheets or caps until final connection is made.

  • 60

    8.2- Sleeves and Escutcheon 8.2.1 Escutcheons shall be provided at all penetrations of piping into finished areas. 8.2.2 Pipes, ducts and conduits shall have sleeves where they pass through walls, floors, ceilings and partitions, with minimum 12 mm clearance

    8.3- Access Panels & Accessibility 8.3.1 All parts of the installation requiring periodic maintenance shall be accessible and provided with access panel

    8.4- Protection 8.4.1 Fixtures and equipment shall be properly protected from damage during the construction period 8.4.2 All equipment shall be thoroughly cleaned before start-up and again before handover.

    8.5- Identification 8.5.1 All piping and ductwork shall be marked in English to show the service and direction of flow. 8.5.2 Marking shall be placed at 10 m intervals on all exposed piping and ductwork

    and at each access panel or door. 8.5.3 All the equipments shall have a manufacturers name plate which shall show

    full details as manufacturer's name, unit and unit motors serial numbers, model numbers, date of manufacture and BS or other number.

    8.5.4 All the equipments should be identified by name. 8.5.5 The schedules and schematic diagrams of all the systems shall be framed and

    glazed and hung in the relevant plant rooms.

  • 61

    8.6- Vibration Control 8.6.1 All equipments to be adequately isolated to maintain acceptable noise levels in the occupied areas of the building 8.6.2 Vibration isolators to be selected in accordance with the type of construction and the vibration/ noise generated by the selected equipment. 8.6.3 If required, approved Acoustic Consultant to ensure and implement

    Appropriate noise and vibration control systems and elements 8.6.4 Vibration isolation hangers should be installed with the spring as close to the ceiling as possible 8.6.5 Where ductwork passes through a wall or floor, other than when a fire damper is required, pack around the duct using a fire resistant material to ensure a sound and air-tight joint

    8.7- Mechanical Insulation 8.7.1 All the insulations stored at site should be protected from dirt and moisture by

    Adopting proper storing procedure. 8.7.2 Fungicidal protective coatings shall be applied over external surfaces of chilled

    water pipes and interior and exterior surfaces of ductwork. 8.7.3 All the pipe and ductwork exposed externally to the building, installed on roof

    is to be insulated and clad with aluminum. 8.7.4 Diesel engine exhaust pipe and muffler shall be insulated.

    8.8- Valves 8.8.1 Provide valves at inlet and outlet of equipment to isolate from the system for

    ease of maintenance. 8.8.2 Do not support weight of piping system on valve ends. 8.8.3 Install all valves with the stem in the upright position keeping aero marking

    towards direction of liquid flow. 8.8.4 Prior to flushing of piping systems, place all valves in the full-open position. 8.8.5 Provide drain valves at low points of piping systems. 8.8.6 Install shut-off (NRV) valves at all equipment and at each branch take-off

    from mains. 8.8.7 All equipment inlet piping should be connected through V mess filter

    installation.

  • 62

    8.9- Drainage Specialties 8.9.1 All roof and floor drains shall be installed with water proof membrane

    extended up to and within the drain and flashed to prevent any water penetration through the drain.

    8.9.2 Make sure that only approved drains as per material submittal is only used. 8.9.3 Co- ordinate with civil engineer for roof floor sloop. The sloop should lead to

    drain point from all direction. 8.9.4 Floor drains should be located at the center of the floor tiles. 8.9.5 Position roof drains and floor drains for easy access and maintenance. 8.9.6 Co- ordinate with civil and make sure that sloop of the floor is such that it

    gives easy flow of water to drain. Grates of drains are to flush with finish floor level.

    8.9.7 Clean outs shall be installed at change of direction of drainage pipes. 8.10- Fire Fighting System 8.10.1 Run all piping as straight as possible There should be minimum possible bend to avoid dropping of water pressure/head. 8.10.2 Where piping is embedded in masonry or concrete, provide protective sleeve Covering. 8.10.3 System drain point to be provided at the lowest level of piping.8.10.4 Ensure that all the fire protection piping system shall be tested hydrostatically 8.10.5 Motorized /manual (as applicable) fire dampers should be installed in all ductwork crossing fire walls. 8.10.6 Fire dampers will be included in return and extract ductwork at each fire zone crossing. 8.10.7 While approving the sprinkler system shop drawings, ensure that it is well

    Co-ordinate with reflected ceiling plan. 8.10.8 All fire hydrant piping should be painted with florescent red paint. 8.10.9 All fire hydrant piping should be aero marked for the flow of water. 8.10.10 No valves are allowed to be installed in the piping. 8.10.11 Insure for batterys make capacity and battery recharger in the system. 8.10.12 Functional test of the jet and spray at the end of hose to be done and ensure no

    leakage. 8.10.13 Hose real box is to be marked with FIRE HOSE REAL. The hose real box

    should not be locked. 8.10.14 Water level indicator should be installed in fire tank. 8.10.15 System should be commissioned by authorized person from supplier before

    presenting the system to civil defense and to be recorded.

  • 63

    8.11- Fire Pumps 8.11.1 Contractor to submit full hydraulic calculations based on shop drawings to verify actual flow and head operating conditions.

    8.11.2 Examine areas, equipment foundations, and conditions with installer present for

    compliance with requirements for installation and other conditions affecting pump performance

    8.11.3 Check the alignment of pump and driver shafts after complete unit has been leveled on foundation.

    8.11.4 All systems shall be field tested and run on load, with all automatic controls in operation and all circuits balanced to produce design conditions.

    8.11.5 Contractor shall arrange the system manufacturer or factory trained representative to conduct on-site training for Clients personnel.

    8.11.6 Maintenance manual and operational manual to submitted by supplier. 8.11.7 Check for battery make, capacity and in built charger in the control panel. 8.11.8 Testing and commission procedure to be recorded.

    8.12- Plumbing Pumps

    8.12.1 Contractor to submit full hydraulic calculations based on shop drawings to verify actual flow and head operating conditions.

    8.12.2 Contractor to submit the Civil Defense approval copy for proposed make of pumps and its supplier, together with the material submittal. 8.12.3 Examine areas, equipment foundations, and conditions with installer present for compliance with requirements for installation and other conditions affecting pump performance. 8.12.4 Check the alignment of pump and driver shafts ( If applicable)after complete 8.12.5 unit has been leveled on foundation. In cash of mono block check for pump level only. 8.12.6 All systems shall be field tested and run on load, with all automatic controls in operation and all circuits balanced to produce design conditions. 8.12.7 Contractor shall arrange the system manufacturer or factory trained Representative conduct on-site training for Clients personnel.

  • 64

    8.13- Chilled water pumps 8.13.1 While approving pumps, full hydraulic calculations and head of the pump to be verified in accordance with approved shop drawings. 8.13.2 Examine areas, equipment foundations, and conditions with installer present

    for compliance with requirements for installation and other conditions affecting pump performance.

    8.13.3 Check the alignment of pump and driver shafts after complete unit has been leveled on foundation.

    8.13.4 All systems shall be field tested and run on load, with all automatic controls in operation and all circuits balanced to produce design conditions. 8.13.5 Insulation on inlet and outlet is to be made as per specification to avoid

    condensing at the pipes.

    8.14- Chilled water piping 8.14.1 Provide automatic air eliminators at all high points on piping mains for chilled water system 8.14.2 Arrange all piping to prevent interference with other services and to achieve a neat satisfactory workmanship installation. 8.14.3 Provide adequate allowance for expansion and contraction of piping by providing expansion joints. 8.14.4 Install drain valves at lowest points for draining the system . The drainage 8.14.5 point to be located at easy to operate location. 8.14.5 Arrange piping to permit ease of equipment removal. 8.14.6 Install all valves in equipment rooms in accessible locations from the floor. 8.14.7 All valves should be of raised flange end type. Use Teflon gasket only for flange joints. 8.14.8 Valve should be checked for its proper installation as per aero pointing

    towards flow. 8.14.9 Mostly ball valve with working parts made of SS or Butter fly valve is to

    used in the chilled water piping system.

  • 65

    8.14.10 All valves are to be insulated as per specification. 8.14.11 All chilled water pipes should be of ASTM grade seam less class C. 8.14.12 Where required used long bend only. Avoid installing half bend. 8.14.13 All welding are to be done after making V at the pipe end. 8.14.14 After installation do the pressure testing of the piping before insulation.

    Pressure should be double then working pressure for 10-15 holding at pressure gauge.

    8.14.15 Apply zinc oxide paint followed by insulation as per specification and thickness. Make sure that there are no air pockets in the insulation.

    8.14.16 Apply aluminum cladding after insulation. Mark aero at intermediate places for flow of the liquid in side the pipes. 8.14.17 Before commissioning the system clean the piping with cleaning procedure.

    8.15- Chillers

    8.15.1 Connect inlet and outlet water piping to the chillers with flange joints. 8.15.2 Provide gate valves in piping upstream and downstream of the evaporator

    water boxes for isolating shells for maintenance. 8.15.3 Provide globe valve/balancing valve in out let line for pressure balancing and trim system.

    8.15.4 Provide vapour proof flow switches in the chilled water piping properly interlocked to ensure that units can operate only when the flow is established.

    8.15.5 Provide wells and taps for thermometers sensors and pressure gauges in chilled piping adjacent to inlet and outlet connections of evaporators.

    8.15.6 Provide drain valves to each water box. Provide vent cocks to each water box.

    8.15.7 Provide valves, pressure gauges, temperature gauges and all accessories as shown in the details on the drawings.

    8.15.8 Provide certified wiring schematics to the electrical division for chillers, associated equipment and controls. 8.15.9 Provide necessary wiring for control items, such as flow switches, temperature sensors etc., as recommended by the manufacturer.

  • 66

    8.15.10 Provide necessary power wiring from starter to chillers control panel,

    control power transformer as required, purge motor, oil pump motor, oil heater, motor protection system, etc. as recommended by the chillers supplier

    8.15.11 The manufacturer shall furnish a factory trained service engineer to supervise installation, field testing, and initial start-up of each chillers.

    8.15.12 The manufacturer shall also allow for a one-week training program of clients personnel to provide thorough understanding of supplied equipment, and full awareness of the daily checks and preventive maintenance procedures.

    8.15.13 Submit maintenance and operational manual.

    8.16- Air Handling Unit 8.16.1 Check material as per approved material submittal and install as shown on

    the drawings and according to AHU manufacturer's installation instructions. 8.16.2 Install units at appropriately made foundation above floor to insure proper

    condensate trap depth and condensate drainage piping. 8.16.3 Check for proper installation of filters and their specification. Check for filter

    integrity by using proper testing method. 8.16.4 Install air handling unit to provide for adequate service access. Co-ordinate

    location to ensure air handling unit does not infringe upon access or service clearances of other equipment.

    8.16.5 Lubricate fan bearings. Verify fan isolators have proper deflection. Check the cleanliness of equipment. Check for blower leveling. Check for belt tension. There should be 5% slip in the belt.

    8.16.6 Upon completion of installation of air handling units, start-up and operate equipment to demonstrate capability and compliance with requirements. Field correct malfunctioning components then re-test to demonstrate compliance.

    8.16.7 Furnish one spare set of fan drive belts per fan for each AHU.

  • 67

    8.17- Fan Coil Units 8.17.1 Install and level the fan coil properly. Location of the fan coil should be as per approved drawing. 8.17.2 At the time of testing and commissioning all the throw away filters shall be replaced by permanent washable filters for each fan coil unit. 8.17.3 Ensure that units are installed in such a way that all condensate from the drain pan flows freely 8.17.4 The actual location of thermostats should be decided at site coordinating with Arch. finishing details however the general location of the thermostat should be close to return duct in cash of ductable unit or it should be on the farthest corner in cash of unit installed in the room. 8.17.5 All FCU with duct should be installed with flex joints to avoid vibration

    isolation. 8.17. 6 Check for proper electrical wiring and speed controls wirings. 8.18.7 While commissioning check for current drawn and CFM of the machine. 8.18- Ductwork

    8.18.1 Insure ducts are manufactured with proper material and thickness as per approved material submittal.

    8.18.2 Insure ducts are manufactured and installed as per approved drawings. The routing of duct is proper and as per approved drawings.

    8.18.3 Insure all elbow has inside radius equal to the depth of the main duct.

    8.18.4 Provide access ports at convenient locations in all main ducts and main branch Takeoffs with airtight covers and extension sleeves through insulation to allow Air meter readings

    8.18.5 Paint visible internal surface behind each grille or register flat black. 8.18.6 Provide temporary capping of ductwork to prevent entry of foreign

    material during construction. 8.17.6 Clean duct systems with high power vacuum machines. 8.17.7 Carry out light test of each branch of the duct to insure no leakage in the

    system. All joints should be leak proof. 8.17.8 Any leak detected to be blinded with silicon pest.

  • 68

    8.19- Air Outlets 8.19.1 Verify inlet/outlet locations. 8.19.2 Verify the size of air terminals to achieve proper air pattern. 8.19.3 Verify ceiling and wall systems are ready for installation. 8.19.4 Ensure the noise generated by air terminals is within the permissible range. 8.19.5 Areas requiring no dirty extract will be pressurized by returning approximately

    10% less air than that supplied. such as corridors etc. 8.19.6 Areas requiring dirty extract, will be maintained under negative pressure by extracting volumes at 110% of the supply volume. Such as kitchen and washrooms.

    8.20- Air Filtration

    8.20.1 Access doors shall be provided for maintenance and renewal of filter elements and related items.

    8.20.2