OPERATION FIELD MONTHLY REPORT PT. TEKNO BUANA GLOBALINDO MAY 2015 No. Dok : FRM- OPR-29 Rev : 00 1 1. EQUIPMENT NO PROJECT UNIT STATUS KETERANGAN 1 ADK 3 (ALSD 01) DWWT (ANK- ) Stand by Proyek telah berakhir (Posisi unit masih di lokasi proyek menunggu well ke-5) FLT (ANK- ) Stand by GENSET (PU- ) Stand by 2 ADK 4 (ALSD 04) DWWT (ANK- 25 ) Close Proyek telah berakhir FLT (ANK- 53) Close GENSET (PU- ) - 3 TATELY (BUDI#13) DWWT (ANK- 36) Close Proyek telah berakhir RO (ANK-32 ) Close GENSET (PU- 14) Close 4 ABS – RBB (RE-ENTRY SINAMAR#02 ) DWWT (ANK- 38) Standby Tidak ada penambahan limbah FLT (ANK- 40) Operasi GENSET (PU- 18) Operasi 5 DWWT (ANK- ) FLT (ANK- ) GENSET (PU- ) 6 DWWT (ANK- ) FLT (ANK- ) GENSET (PU- ) 7 DWWT (ANK- ) FLT (ANK- ) GENSET (PU- ) 2. PRODUCTION PROJECT ASPEK ADK 3 (ALSD 01) ADK (ALSD 04) Tately (BUDI #13) RBB (SINAMAR#02) DAY 133 47 14 68 TOTAL 490 m 3 57 m 3 634 m 3 742 m 3

Upload: tri-subakti

Post on 15-Sep-2015

222 views

Category:

Documents


3 download

DESCRIPTION

ok

TRANSCRIPT

OPERATION FIELD MONTHLY REPORTPT. TEKNO BUANA GLOBALINDOMAY 2015No. Dok : FRM-OPR-29Rev : 00

1

1. EQUIPMENT

NOPROJECTUNITSTATUSKETERANGAN

1ADK 3(ALSD 01)DWWT (ANK- )Stand byProyek telah berakhir (Posisi unit masih di lokasi proyek menunggu well ke-5)

FLT (ANK- )Stand by

GENSET (PU- )Stand by

2ADK 4(ALSD 04)DWWT (ANK-25 )CloseProyek telah berakhir

FLT (ANK- 53)Close

GENSET (PU- )-

3TATELY (BUDI#13)DWWT (ANK- 36)CloseProyek telah berakhir

RO (ANK-32 )Close

GENSET (PU-14)Close

4ABS RBB(RE-ENTRY SINAMAR#02)DWWT (ANK- 38)StandbyTidak ada penambahan limbah

FLT (ANK- 40)Operasi

GENSET (PU- 18)Operasi

5DWWT (ANK- )

FLT (ANK- )

GENSET (PU- )

6DWWT (ANK- )

FLT (ANK- )

GENSET (PU- )

7DWWT (ANK- )

FLT (ANK- )

GENSET (PU- )

2. PRODUCTION

PROJECTASPEKADK 3 (ALSD 01)ADK (ALSD 04)Tately (BUDI #13)RBB(SINAMAR#02)

DAY133471468

TOTAL TREATMENT490 m357 m3634 m3742 m3

KEGIATAN House Keeping Mengawasi level air limbah di mud pit, sellar , dan parit Transfer air dari parit dan sellar ke mud pit House Keeping Cek chemical, peralatan dan kelistrikan Mengawasi kondisi level air limbah di mud pit House Keeping Cek chemical, peralatan, dan kelistrikan Pretreatment limbah dengan kapur Proses treatment limbah Drain tangki DWWT Back wash skid filter House Keeping Cek chemical, peralatan dan kelistrikan Pretreatment air limbah dengan kapur Proses treatment air limbah Cek kondisi mud pit Transfer air bersih ke tangki air

PROGRAM RIG Swabbing Well Test Rig down

Swabbing Well Test Rig down Drilling Logging Cementing Swabbing Well Test Rig down Swabbing Kill well

3. STOCK CHEMICAL

PROJECTKIMIAADK 3(ALSD 01)ADK 4(ALSD 04)Tately(BUDI #13)ABS RBB(RE-ENTRY SINAMAR#02)

ASAM 2 jirigen13 jirigen15 jirigen16 jirigen

KAPUR 377 kg225 kg1500 kg950 kg

TCCA -13 kg4813 kg

PAC 1025 kg1200 kg2000800 kg

FLOKULAN 137,4 kg75 kg162,543.5 kg

4. SUMBER DAYA MANUSIA

NONAMA CREWPROJECTJABATANJUMLAH HARI KERJA

1Achmad AlbarTately (Budi#13)Operator11 (15 Mei 2015)

2Andriana CasmawanTately (Budi#13)Operator18 (15 Mei 2015)

3M. Ali MuhyiddinTately (Budi#13)Operator11 (15 Mei 2015)

4M. Ersa FauziTately (Budi#13)Operator20 (4 Mei 2015)

5Prayuda AdityaTately (Budi#13)Operator18 (15 Mei 2015)

6T. SoeprayitnoTately (Budi#13)KROH18 (15 Mei 2015)

7TimanTately (Budi#13)Operator20 (4 Mei 2015)

8Dede AfriansyahADK 3 (ALSD#01)Operator16 (6 Mei 2015)

9Deden SupriyantoADK 3 (ALSD#01)KROH5 (6 Mei 2015)

10Hendra Cipto S.ADK 3 (ALSD#01)KROH11 (1 Mei 2015)

11M. Husen RajabADK 3 (ALSD#01)Operator16 (6 Mei 2015)

12Rinto Agung P.ADK 3 (ALSD#01)Operator16 (6 Mei 2015)

13Agus NandiaADK 4 (ALSD#04)KROH15 (5 Mei 2015)

14Eri Ahmad R.ADK 4 (ALSD#04)Operator15 (5 Mei 2015)

15HartonoADK 4 (ALSD#04)Operator16 (6 Mei 2015)

16Tatan TarkawanADK 4 (ALSD#04)Operator15 (5 Mei 2015)

17Allan Firmansyah N.ABS-RBB (Re-entry Sinamar#02)Operator27 (5 Mei 2015)

18Dinda Asmoro P.ABS-RBB (Re-entry Sinamar#02)Operator12 (31 Mei 2015)

19Heri SetiawanABS-RBB (Re-entry Sinamar#02)Operator26 (31 Mei 2015)

20Jujun JunaediABS-RBB (Re-entry Sinamar#02)Operator21 (19 Mei 2015)

21M. Ersa FauziABS-RBB (Re-entry Sinamar#02)Operator12 (31 Mei 2015)

22Oman RohmanABS-RBB (Re-entry Sinamar#02)Operator21 (19 Mei 2015)

23Riki GunawanABS-RBB (Re-entry Sinamar#02)KROH21 (19 Mei 2015)

24TimanABS-RBB (Re-entry Sinamar#02)KROH12 (31 Mei 2015)

5. TECHNICAL

PROJECTHARI, TANGGALDESKRIPSI TEKNISPENANGGULANGANKETERANGAN

Tately(BUDI #13)Senin, 4 Mei 2015 Genset tidak bisa dimatikan dengan tombol indikator Dimatikan dengan cara menekan tombol emergency

ABS RBB(RE-ENTRY SINAMAR#02)Senin, 4 Mei 2015 Ketersediaan hose kurang dan banyak bocor Penggunaan hose seadanya dengan pengikatan karet ban agar tidak bocor

Senin, 4 Mei 2015 Genset tidak bisa nyala karena solenoid tidak bekerja Penggantian dengan solenoid

6. REPORTING

NOASPECTTARGETCAPAIANKETERANGAN

1Berita Acara1616

2Attendant List88

3Daily Report9191

4Equipment Checklist9391

5SPD & ST2020

6Logbook Genset65

7Logbook Chemical41Jarang dilakukan pengecekan

8Logbook Proses40Jarang dilakukan pengecekan

9Logbook Crew10330Jarang dilakukan pengecekan

Dibuat OlehDiperiksa Oleh

Operation EngineerOperation Manager

10 Juni 201510 Juni 2015