Measurement and PaymentModule #5
Prepared by
Dr. Randy R. RappJuly 2005
2005, Randy R. Rapp 2
Contractual Payment
• Lump-sum or fixed-price
• Unit-price
• Fixed-price with cost incentives
• Time and materials (T&M)
2005, Randy R. Rapp 3
Progress Payments
• Typically monthly• Contractor request maybe 10 days prior• Lump-sum vs. unit-price verification• Inspector role
– Measure quantity and type of work– Claims for extra work and change orders– Calculate payment due, minus retention– Prepare and forward recommendation
• Lump-sum vs. unit-price payment basis
2005, Randy R. Rapp 4
Conflicting Bases of Payments?
• Specification writer misunderstands?
• Lump-sum contract– Schedule of values OR– Cost-loaded critical path method (CPM)
network
• Unit-price– Neither schedule of values NOR– Cost-loaded CPM
2005, Randy R. Rapp 5
Payment Request Evaluation
• Lump-sum: completed work package– Discernable fraction thereof is usually OK– Consider change orders, if any
• Unit-price: quantity x unit-price– Measurement accuracy absolutely essential– Renegotiate unit-price, if quantity exceeds allowable
variation (15% to 25%)• Equipment and materials delivered but not yet
installed– Maybe pay actual cost for long-lead, high-cost items– Only if contract specifically stipulates
2005, Randy R. Rapp 6
Force Account
Day work• Measurement and Payment section OR• Changes and Extra Work section• “Reasonable” allowance for overhead and profit?• Categories
– Labor– Materials– Equipment
• Payment is full compensation for the work
2005, Randy R. Rapp 7
Force Account (Cont’d)
• Labor– Trade classification wage rate and numbers– Foremen included, not general supervisors– Any allowances?
• Materials: cost and freight• Equipment
– DOT rates or Rental Rate Book– Active and standby times
• Markups (p.85)
2005, Randy R. Rapp 8
Payment for Extra Work
• Often detailed in Supplementary General Conditions
2005, Randy R. Rapp 9
Payment for Mobilization
• Lump-sum contracts– Not included as a bid item: likely inflated– Include as a calculated allowance in separate
technical section, per contract requirements– Not a matter of Measurement and Payment
• Unit-price contracts– Properly in Measurement and Payment– Lump-sum amount stipulated in extended
column
2005, Randy R. Rapp 10
Partial Payments
• Partial waivers of lien (subs’ waivers maybe one payment behind prime contractor’s)
• Total cost pricing of change orders
• Forward pricing of change orders
• Retainage
• Liquidated damages
2005, Randy R. Rapp 11
Field Measurement for Payment
• Pipeline lengths– Beware delivered vs. plan or in-place– If in-place, measure centerline on top
• Earth and rock volume– Bank vs. compacted– Weight vs. volume (survey profile prior to work)
• Curbs: top edge toward street• Sewers: do not include manholes• Fence: plan or top rail in-place
2005, Randy R. Rapp 12
Field Measurement for Payment (Cont’d)
• Pavement– Areas or weights– Unit-prices for handwork vs. equipment
• Retaining walls– Inside vs. outside surface measurement– Calculate non-overlapping prism volumes
2005, Randy R. Rapp 13
Final Payment
• Additional requirements1. Pay all project debts2. Submit receipts, releases, waivers of lien3. Obtain consent of surety
• Besides retainage1. Liquidated damages2. Punch list work (1.5 to 2 times value)3. Liens already filed
• Upon filing Notice of Completion or Substantial Completion
– Sometimes time limitation to announce intent to file lien– Time limitation to actually file