Measure H Financial Overview Highlights

and

Bond Projects Update_______________________________

Presented to the Board of Trustees

10/14/2020

Financial Overview Highlights

Additional funds from other sources increasedby $281,831 through Strong Workforce Program Funding

Financial Overview Highlights (continued)

Blue = Budget Decrease Red = Budget Increase

Financial Overview Highlights (continued)

Budget Change Detail

RPSTC Classroom Buildings

DepartmentOfficeReception

RPSTC Classroom Buildings (continued)

TypicalClassroomFurniture

TypicalOfficeFurniture

CTE Building

Project Complete

Classroom Computer Lab Furniture

CIS Building (continued)

Tehama Campus Student Services Building

Project Start: 9/2019

Est. Completion:11/2020

Tehama Campus Student Services Building (continued)

Projects Update

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Approval Received

Construction Commenced/To Commence:• Solar Project – East Parking Lot (substantially complete - waiting for PG&E)

Update: Distribution and network upgrades are targeted to be completed in the first quarter of 2021. Sunpower and PG&E engineers are in the final approval stages of the Net Generation Out Meter (NGOM) drawings. NGOM installation is required before PG&E can perform the final inspection of the project.

• Regional Public Safety Training Center Classroom Buildings (substantially complete –classrooms and offices 90% furnished)

• Northwest Campus Infrastructure – parking lot adjacent to RPSTC Classroom Buildings (project complete)

• CTE Building and Covered Storage (complete – classrooms and offices are fully furnished)

• Tehama Campus Student Services Building (to be completed 10/2020)

• CIS (Computer Information Systems) Building (to be completed 7/2021)

Projects Update (continued)

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

In Bid Process/Bid to be Awarded:

• HSUC Security Office: Sent out to bid September 24th; bid opening scheduled for October 15th.

Under DSA Review• None

Design / Construction Documents Phase• 200 Building (Library) Renovation: Kickoff meeting held September 25th.

September 3rd – Notified this project was one of 8 approved for accelerated state funding through trailer bill SB 115

Moved Prop 51 school facilities construction funding to the 2020-21 state budget

Effect: One year earlier start for this project!

Projects Update (continued)

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

State Funding – Things to NoteStrict Timelines:

Provided completion dates for phases that allowed our project to be accelerated

Reporting Compliance – Quarterly Reports / Reimbursements

Adjustments to Construction Budget:

• Inflation Adjustment

Budget is calculated using estimated inflation figures. When actual inflation figures are available, the budget will be increased or decreased accordingly.

• Bid Adjustment

If bid is greater than the estimate, the District will bear the excess cost.

If bid is less than the estimate, the District will share in the savings according to its proportionate funding percentage.

Projects Update (continued)

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Pre-Design Phase• 1300 Building Renovation

Pre-Design Phase - FPPs and IPPs (State Funding)

• 800 Building Renovation: The FPP for this project was approved by the Governing Board on June 10, 2020 and has been submitted to the Chancellor’s Office.

Other Projects

TrinityCampus

Shasta CollegeMain Campus

61 miles51 miles

Current/Upcoming Projects

• Network Switch Replacement (in process – replacement of core switch and network switches in buildings on the main campus)

• SC Main Campus Fiber Project (construction in progress – installation of data fiber from 700 Building to RPSTC site and CTE quad – Contractor: World Telecom & Surveillance, Inc.)

• Dorms Upgrade Project (data portion of project complete; painting and carpet replacement ongoing)

• Main Campus Old Oregon Trail Security Fencing and Gates (in design stage)

• Main Campus Signage (Wayfinding) Project (in process)

• Master Plan Landscaping Project (in process)

Completed Projects

179,000

TrinityCampus

Shasta CollegeMain Campus

61 miles

• 200 Building Exterior Infrastructure/ADA Walkway/Patio Project

• 2400 Building Electrical Upgrade

• Athletic Fieldhouse with Restrooms

• Campus Safety Relocation – Interior Remodel

• Campus Safety Site Work and ADA Paths of Travel

• Farm Building 4500 Shade Structure

• Gymnasium Air Conditioning

• HSUC Folding Wall Replacement

• Interior/Exterior Lighting Project – Prop 39 & Bond

• Northeast Campus Infrastructure

• Regional Public Safety Training Center – Phase One

• SC Main Campus Keying & Access Control

Completed Projects (continued)

179,000

Shasta CollegeMain Campus

61 miles

• SC Safety & Security Standards

• Shasta College Storage Building

• Summer 2019 Infrastructure Project

• Veterans Support & Success Center Building

18