may 2013 ireland case study - schools bundle 3 ppp project

25
May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

Upload: lenard-woods

Post on 17-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

May 2013

Ireland

Case Study - Schools Bundle 3 PPP Project

Page 2: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

Background

Page 3: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

Track Record in Ireland of successful PPPs

• First a question……

How Many to Date?

(A) 18

(B) 25

(C) 10

3

Page 4: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

Track Record in Ireland of successful PPPs

• Historic 9 Major inter-urban motorways/by-passes 4 Education PPPs, including 15 schools International Convention Centre Major Criminal Courts Complex Motorway Services Stations contract

• And recently….. N11 Roads Contract (April 2013) and Schools Bundle 3 (November 2012) A further Roads Contract is scheduled to close by end 2013

4

Page 5: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

However……

• Black clouds emerging after 2007

• Government Finances increasingly under pressure

• Affordability constraints emerged

• Leading to many project cancellations

• Increasingly negative environment for delivering infrastructure

5

Page 6: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

6

NDFA: statutory body with dual mandate

• Established under legislation in 2003 Report to Minister for Finance

• Statutory financial adviser on capital projects >€20m Project financial assessments Issue formal “Value for Money” Opinions

• Delivery agent for State Authorities for PPPs except transport and regional authorities Administer the procurement and construction phases Hand back to sponsor / PPP contract management

The Department for Public Expenditure and Reform is responsible for PPP policy matters and for issuing guidance in the area.

Who is the NDFA?

Page 7: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

The Schools Bundle 3 PPP Project

Page 8: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

8

The Project

• Now, another question……..

What is the expected increase in pupils in the primary school system between now and 2018?

(A) 25,000

(B) 35,000

(C) 45,000

Page 9: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

9

The Project

• Third Bundle in the Irish Department of Education and Skills Schools PPP Programme

• €100m construction contract generating more than 1,600 direct and indirect jobs during construction

• Design, Build, Finance and Maintain PPP contract (25 yr. term) - Procured by means of Negotiated Procedure

• EIB had confirmed project met its eligibility requirements & historically a strong supporter of Irish projects including the schools programme

• Method of Payment – Monthly Unitary Charge payable by Government

• Construction and Availability risk passed to PPP Co

Page 10: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

The Project

• The project comprised 8 Schools on 7 sites, providing accommodation for 5,700 Pupils

School Pupil No's

Gaelcholaiste, Letterkenny 350

Doughiska Community School 650

Doughiska Primary School 450

Ballinamore Community School 400

Doon Secondary School 850

Tramore Secondary School 1,000

Athlone Community School 1,000

Gorey Community School 1,000

Locations

Page 11: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

11

Procurement Step Date

OJEU Notice August 2010

Issue of ITN December 2010

Tenders Received July 2011

Appointment of PT (BAM PPP) September 2011

Target Financial Close March 2012

The Timelines

Procurement Step Date

OJEU Notice August 2010

Issue of ITN December 2010

Tenders Received July 2011

Appointment of PT (BAM PPP) September 2011

Target Financial Close November 2012

Original Actual

7 month delay????

Page 12: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

12

The Issues – Funding… Funding… Funding !

• Issue 1: The Financial Crisis!!!....2007 onwards

• Significant contraction of PF funding market - not only an Irish issue

• Insufficient funders remaining in Irish PPP market to finance all tenderers

• Remaining funders also unwilling to carry out due diligence until PT stage

• Prompted use of Negotiated Procedure for Schools Bundle 3 PPP in place of Competitive Dialogue, with committed financing deferred to PT stage

• Authority generated term sheet issued to tenderers during procurement

Page 13: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

13

The Issues – Funding… Funding… Funding !

• Issue 2: The EU/ ECB/ IMF programme for Ireland….2010 onwards

• In short Ireland’s credit rating has gone from AAA (S&P, Jan 2007) to BBB+ (S&P present) & the PF funding constraints experienced across Europe were amplified in Ireland

• Led to remaining international PF banks exiting Irish market

• Furthermore Irish banks had huge recapitalisation requirements due to the collapse in the Irish property market and their ratings plummeted to typically BB levels

• Therefore Authority/PT concluded that potential funding was limited to Bank of Ireland (“BoI”) & EIB

Page 14: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

14

The Issues – EIB & Irish Banks

• However

• EIB’s co-funding requirements meant a mismatch between EIB & Irish Banks!!

EIB (AAA ) + Irish Banks (c. BB)

Enter the National Pensions Reserve Fund (“the NPRF”).

The NPRF was established to meet as much as possible of the costs of Ireland's social welfare and public service pensions from 2025 onwards. Split across two portfolios, the discretionary portfolio (value €6.4bn March 2013) and directed portfolio (value €8.8bn March 2013). The Fund is controlled and managed by the National Pensions Reserve Fund Commission.

Page 15: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

15

The Issues – EIB & Irish Banks

With the NPRF….

EIB (AAA) + Bank of Ireland (BB) + NPRF

Final Funding Structure

Facility Provider

Equity Bridge Facility BoI

Senior Debt Facility EIBBoI

Committed Standby Senior Debt Facility NPRF

Page 16: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

16

The Outcome

• Successful financial close reached in November 2012 - with only 7 month delay!

• Construction progressing well …. as you can see in following slides

(Aerial photos taken Feb 2013)

Page 17: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

17

Athlone, Co. Westmeath 1,000 pupils

before after

Page 18: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

18

Ballinamore, Co. Leitrim 400 Pupils

before after

Page 19: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

19

Doon, Co. Limerick 400 Pupils

before after

Page 20: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

20

Doughiska, Co. Galway Primary & Post Primary 1,100 Pupils

before after

Page 21: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

21

Gorey, Co. Wexford 1,000 Pupils

before after

Page 22: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

22

Letterkenny, Co. Donegal 350 Pupils

before after

Page 23: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

23

Tramore, Co. Waterford 1,000 Pupils

before after

Page 24: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

24

Best Education Project, EuropeIRISH SCHOOLS

The Outcome

Page 25: May 2013 Ireland Case Study - Schools Bundle 3 PPP Project

National Development Finance AgencyTreasury Building | Grand Canal Street | Dublin 2 | Ireland

www.ndfa.ie

Brian Murphy, Chief Executive D +353 1 664 0246 M +353 862346992 E [email protected]