materi kuliah crash program
TRANSCRIPT
-
7/21/2019 Materi Kuliah Crash Program
1/14
CRASH PROGRAM
-
7/21/2019 Materi Kuliah Crash Program
2/14
Construction Management
Construction management is here taken to be the
management of any aspects of the construction industry
It includes aspects of project management and general
management
Management applies to any kind of organisation
It applies to all organisational levels
The aim of managers is to create a surplus
Managing is concerned with productivity; this implies
effectiveness and efficiency
-
7/21/2019 Materi Kuliah Crash Program
3/14
Crashing of networks
Considerations
Distinction should be made between directcosts (i.e. costs of resources used) and
indirect costs(i.e. time-related costs such as
head office service costs etc.)
Willingness to do crash program ? ( case in one of developing countries)
Purposes
To reducethe normal project
duration to achieve contractual time
requirements.
To optimisethe project cost.
-
7/21/2019 Materi Kuliah Crash Program
4/14
Crash t ime Normal t ime
Act iv i tydurat ion
Ac
tiv
ityd
irec
tco
st
Time and cost relationshipActivity duration and resources demand are very closely
related. As the activity time changes so will the resource
requirement and hence the direct cost.
Crash point
Normal point
-
7/21/2019 Materi Kuliah Crash Program
5/14
Crash t ime Normal t ime
Act iv i tydurat ion
Ac
tiv
ityd
irec
tco
st
The relationship is usually simplified asshown below.
Time-cost relationship (cont.)
Crash cost
s lope
-
7/21/2019 Materi Kuliah Crash Program
6/14
COST SLOPE
Semakin cepat usaha akselerasi, semakin besar
kebutuhan akan sumberdaya tambahan dan
semakin besar pula peningkatan biayanya.
Costslope = c
t= crash cost - normal cost
normal duration - crash duration
-
7/21/2019 Materi Kuliah Crash Program
7/14
Methods of reducing activity duration
Possible methods of reducing (crashing) of activityduration:
Use of more shifts
Use of overtime
Use of additional equipment
Use of bigger gang size
Restructure organization based on split task( e.g. split task under construction management consultant)
Use of alternative construction method or sequence
Use of alternative materials Use of simple design (re-design) but it needs:
Pro-active monitor (in advance)
Agreement among parties involved
Within budget
-
7/21/2019 Materi Kuliah Crash Program
8/14
The crashing procedure
Perform the timing calculations for the projectnetwork using the normal durationsto identify thecritical path.
Examine activities on the critical path to select theone which can be shortened for least cost.
Shorten this activity as much as possible. This will bedetermined by the following:
Until the activity crash durationis reached.
Until the project required lengthis reached.
Until another path becomes critical. In this case,several activities need to be shortenedsimultaneously.
-
7/21/2019 Materi Kuliah Crash Program
9/14
A
B C D E
F
120
20 40 30 50
Example project
60Ac tivi ty N. du rat ion
(days)
C. durat ion
(days)
N.co st C.co st C.co st
/day
B 20 15 1800 2800
A 120 100 12000 14000
C 40 30 16000 22000
D 30 20 1400 2000E 50 40 3600 4800F 60 45 13500 18000
Tot .. dir ect co st 48300 63600
Ind irect co st = 200/day
-
7/21/2019 Materi Kuliah Crash Program
10/14
A
B C D E
F
120
20 40 30 50
60Ac tivi ty N. du rat ion
(days)
C. durat ion
(days)
N.co st C.co st C.co st
/day
B 20 15 1800 2800
A 120 110 12000 14000
C 40 30 16000 22000
D 30 20 1400 2000E 50 40 3600 4800F 60 45 13500 18000
Tot .. dir ect co st 48300 63600
Example project (cont.)
200
200
300
120
60
600
-
7/21/2019 Materi Kuliah Crash Program
11/14
Calculations
Act iv ity 140 (days ) 130 (days ) 120 (days) 115 (days ) 110 days)
A
B C D E
F
120
20 40 30 50
60
(200)
(200) (600) (60) (120)
(300)
A
B
C
DE
F
D.cost
Ind.cost
Tot.cost
48300
28000
76300
20*
+600
48900
26000
74900
40*
+1200
50100
24000
74100
115
15*
+1000
+1000
52100
23000
75100
+1000
+3000
+1500
35
55
110*
57600
22000
79600
-
7/21/2019 Materi Kuliah Crash Program
12/14
110 115 120 130 140
Projectdurat ion
Pro
jec
ttotalcos
t
10000
20000
30000
40000
50000
60000
70000
80000
Min imum cos t
-
7/21/2019 Materi Kuliah Crash Program
13/14
STUDI KASUS
Seorang kontraktor mendapat pekerjaan membangun
sebuah rumah dengan nilai kontrak Rp. 919.000.000,00
selama 40 minggu. Manajer proyek, yang diangkat untuk
mengelola proyek itu, menemukan sejumlah kesalahan
serius dalam proses estimasi durasi, yang menyangkut
kegiatan-kegiatan vital. Kesalahan ini menyebabkan
proyek dapat tertunda selama 8 minggu. Perjanjian
kontrak memasukkan sebuah klausul denda yang
besarnya adalah Rp. 2.000.000,00 per mingguketerlambatan.
Pertanyaan : Tindakan apa yang dapat ditempuh ?
-
7/21/2019 Materi Kuliah Crash Program
14/14
Rekapitulasi nilai kontrak sebagai berikut (dalam rupiah) :
Biaya langsung 714.000.000
Overhead cost (4 jt/minggu) 160.000.000
Laba 45.000.000
Biaya Total 919.000.000
Setelah mempelajari permasalahannya, manajer proyek
berhasil mengidentifikasi lima kegiatan yang durasinya dapatdireduksi :
Kegiatan Durasi Normal Durasi minimal Biaya per
minggu (Rp.)
B 5 3 4,5 juta
C 11 9 3,5 juta
E 8 6 4,0 juta
G 11 7 3,0 juta
J 10 8 11,0 juta