July 2021
EDMS No. 2433969 v11.2
Group Code: EN-AA
MS-4600/EN
Market Survey
Qualification Questionnaire
Supply of Industrial Controls and Safety Systems
Abstract
In order to be considered as a potential bidder for the forthcoming Invitation
to Tender, the respondent shall be either a single firm (hereinafter referred to
as “the Firm”) or a group of firms (hereinafter referred to as “the Group of
Firms1”).
The Firm or the Group of Firms shall demonstrate that they meet the
applicable qualification criteria by completing this Qualification
Questionnaire and by providing the requested documents and references.
1 The term “Group of Firms” means a consortium, joint venture or any other arrangement between legal entities for the joint submission
of a bid and the joint execution of the Contract but shall exclude any Subcontractors.
ii EDMS No. 2433969 v11.2
MS-4600/EN
TABLE OF CONTENTS
INFORMATION ABOUT THE FIRM OR THE GROUP OF FIRMS ..................................... 1 Names and Addresses........................................................................................................................ 1 Contact Persons ................................................................................................................................. 1
QUALIFICATION CRITERIA ..................................................................................................... 2 General .............................................................................................................................................. 2 Administrative situation .................................................................................................................... 3 Subcontracting................................................................................................................................... 3 Country of Origin .............................................................................................................................. 4 Obligations of the Lead Firm ............................................................................................................ 5 Size .................................................................................................................................................... 6
2.6.1 Number of Employees........................................................................................................................ 6 2.6.2 Global Annual Turnover ................................................................................................................... 9
Competence and Experience ........................................................................................................... 10 2.7.1 Functional Safety studies and Programmable Electronic Safety-related Systems .......................... 10 2.7.2 PLCs: Siemens (Step7, TIA Portal), Schneider (Premium, PL7 unity) ........................................... 11 2.7.3 Supervisory systems (SCADA) and middleware: (WINCC-OA, WinCC, PCVue) ........................... 12 2.7.4 Simulation and Test tools: SIMIT / SIMBABox, tests methods and tools ........................................ 12 2.7.5 Programming languages: Java, C, C++, Visual Basic, APEX ....................................................... 13 2.7.6 Communication systems: low level (field buses) and high level (Ethernet, TCP/IP) ...................... 14 2.7.7 Operating systems: VMWare, Windows, Linux CentOS .................................................................. 14 2.7.8 Databases: ORACLE, SQL Server .................................................................................................. 15 2.7.9 Software management tools: SVN, VersionDog, JIRA, GIT ............................................................ 16 2.7.10 Asset and Maintenance management system for software and hardware ....................................... 16 2.7.11 Certification in the development of safety systems and software applications ................................ 17
References ....................................................................................................................................... 18 Equipment and facilities .................................................................................................................. 18
2.9.1 Equipment ....................................................................................................................................... 18 2.9.2 Facilities .......................................................................................................................................... 18
Maintenance .................................................................................................................................... 19 2.10.1 Preventive maintenance .................................................................................................................. 19 2.10.2 Corrective maintenance .................................................................................................................. 19 2.10.3 On-call service ................................................................................................................................ 19
ADDITIONAL INFORMATION ................................................................................................ 20 Data privacy .................................................................................................................................... 20 Recognised trainer and auditors for IEC61508 & IEC 61511 ......................................................... 20 Miscellaneous .................................................................................................................................. 20
ANNEX .......................................................................................................................................... 21 PROJECT FORM: TO BE USED IN §2.7 .................................................................................. 21 REFERENCE FORM: TO BE USED IN §2.8 ............................................................................ 22 MAINTENANCE FORM: TO BE USED IN §2.10 .................................................................... 23
EDMS No.: 2433969 v11.2 1 MS--4600/EN
INFORMATION ABOUT THE FIRM OR THE GROUP OF FIRMS
Names and Addresses
Firms interested in participating in the forthcoming Invitation to Tender procedure as a member of a
Group of Firms shall return a SINGLE questionnaire for the Group of Firms, to be completed by the
Lead Firm2 and signed by each of its members.
The number of firms in the Group of Firms shall not exceed two.
Position Name of the Firm Address
Firm
Or Lead Firm
.......................................... ..................................................
Member No. 2 of the Group
of Firms (if applicable)
.......................................... ..................................................
Contact Persons
The Firm, or the Lead Firm, shall be able to make available for the entire duration of the Contract at
least one English or French-speaking commercial contact person and one English or French-speaking
technical contact.
In the case of a Group of Firms, only the contact persons of the Lead Firm shall be indicated below.
For Technical Matters
Name Tel Email
Mr / Mrs ...................................... ................................. ........................................................................
If absent:
Mr / Mrs ...................................... .................................. ........................................................................
2 If the bidder is a Group of Firms, its members shall jointly appoint one member from amongst them as their lead firm for all matters
concerning the Invitation to Tender and the Contract (the “Lead Firm”), except for the signature of the bid and of the Contract. The
members of the Group of Firms shall be jointly and severally liable for the performance of the Bidder’s and the Contractor’s
obligations under the Invitation to Tender and the Contract.
For Commercial and Administrative Matters
Name Tel Email
Mr / Mrs ...................................... .................................. ........................................................................
If absent:
Mr / Mrs ...................................... .................................. ........................................................................
2 EDMS No. 2433969 v11.2
MS-4600/EN
QUALIFICATION CRITERIA
General
2.1.1 CERN will invite to tender those Firms or Groups of Firms that have replied to the present
Market Survey by uploading this document into CERN’s e-survey system and are selected
on the basis of their compliance with the technical, financial and other qualification criteria
provided herein.
2.1.2 In particular circumstances, if CERN’s needs or interests so justify and if CERN considers
that a Firm or Group of Firms would be able to complete and fulfil its obligations under the
contract, CERN may select a Firm or a Group of Firms and invite it to tender even if it does
not fully meet the qualification criteria defined herein. In so doing, CERN will take into
account the provisions set out in the Appendix: “Selection and Adjudication Criteria for
Supply Contracts” and the estimated amount of the contract.
2.1.3 In addition, and with a view to improving the distribution of its purchases among its Member
States3, CERN may not select and invite to tender a Firm or Group of Firms:
according to the number of qualified firms from each Member State, taking into account
the Member State’s contribution to the CERN budget, the relevant industrial return
coefficient for that Member State (as set out in the Appendix: “Selection and
Adjudication Criteria for Supply Contracts”) and the estimated amount of the contract;
on the basis of its previous experience with the Firm or any member of the Group of
Firms;
if the Firm or a member of the Group of Firms has replied “yes” to at least one question
in § 2.2 below;
if the Firm or a member of the Group of Firms has made a false declaration in this
Qualification Questionnaire;
if CERN considers that the Firm or the Group of Firms may be unable to fulfil its
obligations under the contract due to the Firm’s or Group of Firm’s financial situation;
if the Firm or the Group of Firms proposes a Supply originating in an Associate Member
State, or an Associate Member State in the pre-stage to membership and the combined
total value of the commitments for the country concerned for the year in question,
covering all orders, contracts and personnel appointments, including the value of the
contract under consideration, would exceed the size of that country’s financial
contribution to the CERN budget for the financial year concerned (the “ceiling”). If, in
exceptional circumstances, CERN invites to tender a Firm in an Associate Member State
that has reached the ceiling, the Firm concerned shall be considered and treated as a
Firm proposing supplies or services originating in a well-balanced Member State,
irrespective of that Associate Member State’s industrial return coefficient at that stage.
3 http://home.cern/about/member-states
EDMS No.: 2433969 v11.2 3 MS--4600/EN
Administrative situation
Is the Firm, or any member of the Group of Firms, involved in or facing the threat of bankruptcy
proceedings, prosecution for debt, sequestration or any analogous situation arising from a similar
procedure provided for in law?
□ YES □ NO
If yes, in the case of a Group of Firms, please indicate which member(s): ..........................................
Has the Firm, or any member of the Group of Firms, been found guilty of or faced with the threat
proceedings for fraud, corruption, money laundering or any other illegal activity(ies)?
□ YES □ NO
If yes, in the case of a Group of Firms, please indicate which member(s): ...........................................
If the Firm, or any member of the Group of Firms, has replied “yes” to any of the above questions,
please provide any details that may be relevant for CERN in the framework of this Invitation to
Tender procedure.
Subcontracting4
Subcontracting is permitted for the execution of the Contract but is subject to CERN’s prior written
approval of each proposed Subcontractor. CERN reserves the right to refuse a Subcontractor and to
carry out verifications concerning the proposed Subcontractor(s).
CERN will be entitled to reject in whole or in part the proposal of a Firm or Group of Firms
concerning the subcontracting of its obligations, it being understood that in any event:
the Contractor shall not subcontract to a single Subcontractor Supplies and activities representing
an amount exceeding 50% of the total contract price; and
the management of the Contract shall not be subcontracted.
In addition, the following parts of the Supply shall not be subcontracted:
Preparation and submission of technical and financial proposals;
Project Management & Scheduling;
User requirements analysis;
Design & Development based on CERN requirements;
Maintenance activities.
4 The term “Subcontract(s)” shall mean any arrangement whereby the Contractor contracts with another legal entity (the Subcontractor),
except legal entities under its direct control, for the provision of a part of the Supply (including provision of sub-assemblies and
components or any part of the activities forming part of the Supply). The term “Subcontract(s)” shall include sub-subcontract(s).
4 EDMS No. 2433969 v11.2
MS-4600/EN
Does the Firm or the Group of Firms intend to subcontract any part of the Supply?
□ YES □ NO
If yes, please complete the table in § 2.4 below.
Country of Origin
For the Supply, the term “Country(ies) of Origin” means the country(ies) of manufacture or last major
transformation of the Supply (including sub-assemblies and components) by the Bidder and its
proposed Subcontractor(s).
In case the Supply includes activities (installation, maintenance, testing, etc…), the Country (ies) of
origin of such activities will be the country in which the firm performing them is established.
The Countries of Origin of the Supply shall be CERN Member States5.
However, for the Associate Member States, there are defined annual ceilings of the value of the
procurement expenditure in those countries (calculated on the basis of the State’s percentage
contribution to the CERN budget).
Therefore, if a Bidder intends to submit a Bid which includes a part of the Supply originating in an
Associate Member State, it must contact CERN forthwith and in any case no later than 14 days before
the submission deadline. CERN will, as soon as possible, inform the Bidder concerned if the proposed
share of the Bid or if the obligations to be allocated in these countries would remain within the defined
annual ceilings. If this would not be the case, the Bidder shall either reconsider the distribution of its
Bid or withdraw from the Invitation to Tender procedure.
It is understood that the above shall have no impact on the submission deadline.
5 The term “Member State(s)” means both full Member State(s) and Associate Member State(s) of CERN, except where expressly
stipulated otherwise: http://home.cern/about/member-states
EDMS No.: 2433969 v11.2 5 MS--4600/EN
In the case of a Single Firm:
Supply (or activities as listed
in section 2.1 of Technical
Description) foreseen under
the Contract
Name of the Firm and, if applicable
and known, of the proposed
Subcontractor(s)
Country(ies) of
Origin of each part
of the Supply
..................................................
...................................................................
.....................................
..................................................
...................................................................
.....................................
..................................................
...................................................................
.....................................
In the case of a Group of Firms:
Supply (or activities as listed
in section 2.1 of Technical
Description) foreseen under
the Contract
Name of the Lead Firm or of the
member of the Group of Firms and, if
applicable and known, of the proposed
Subcontractor(s)
Country(ies) of
Origin of each part
of the Supply
..................................................
.......................................................................
...................................
..................................................
.......................................................................
...................................
..................................................
.......................................................................
...................................
..................................................
.......................................................................
...................................
Obligations of the Lead Firm
In case of a Group of Firms, the following parts of the Supply shall be delivered by the Lead Firm
only:
Contract management;
Preparation and submission of technical and financial proposals;
Project Management & Scheduling;
6 EDMS No. 2433969 v11.2
MS-4600/EN
Size
2.6.1 Number of Employees
The Firm, or the members of the Group of Firms collectively, shall have at least:
15 engineers in the field of Industrial Controls and Safety Systems and software development,
specialised in functional safety, project management and quality assurance and certification
in the development of safety systems and software application. Including:
o Three engineers specialised in functional safety, of which at least one senior engineer
(with at least five years proven experience);
o Two senior engineers specialised in project management (with at least five years
proven experience);
o Two engineers specialised in quality assurance and certification in the development
of safety systems and software applications;
20 technicians in the field of Industrial Controls Systems and Safety Systems and software
development, specialised in Functional Safety-related studies and projects, mechanical and
electrical design and in the field of software development. Including:
o Five technicians specialised in Functional Safety-related studies and projects;
o Three draughtspersons mechanical and electrical (at least two electrical);
o Ten technical engineers / technicians in the field of software development;
Please complete one of the following tables, as appropriate.
In the case of a Single Firm:
2018 2019 2020
Number of employees
Overall (all activities)
Engineers in the field of Industrial
Controls and Safety Systems and
software development
Senior engineers specialised in
Functional Safety
Non senior engineers specialised in
Functional Safety
Senior engineers specialised in project
management
Engineers specialised in quality
assurance
Technicians in the field of Industrial
Controls Systems and Safety Systems
Technicians specialised in Functional
Safety
Draughtspersons - electrical
Draughtspersons - mechanical
Technicians in the field of software
development
EDMS No.: 2433969 v11.2 7 MS--4600/EN
In the case of a Group of Firms:
LEAD FIRM
2018 2019 2020
Number of employees
Overall (all activities)
Engineers in the field of Industrial
Controls and Safety Systems and
software development
Senior engineers specialised in
Functional Safety
Non senior engineers specialised in
Functional Safety
Senior engineers specialised in project
management
Engineers specialised in quality
assurance
Technicians in the field of Industrial
Controls Systems and Safety Systems
Technicians specialised in Functional
Safety
Draughtspersons - electrical
Draughtspersons - mechanical
Technicians in the field of software
development
MEMBER No. 2 OF THE GROUP OF FIRMS
2018 2019 2020
Number of employees
Overall (all activities)
Engineers in the field of Industrial
Controls and Safety Systems and
software development
Senior engineer specialised in
Functional Safety
Non senior engineers specialised in
Functional Safety
Senior engineers specialised in project
management
8 EDMS No. 2433969 v11.2
MS-4600/EN
Engineers specialised in quality
assurance
Technicians in the field of Industrial
Controls Systems and Safety Systems
Technicians specialised in Functional
Safety
Draughtspersons - electrical
Draughtspersons - mechanical
Technicians in the field of software
development
TOTAL FOR THE GROUP OF FIRMS
2018 2019 2020
Number of employees
Overall (all activities)
Engineers in the field of Industrial
Controls and Safety Systems and
software development
Senior engineer specialised in
Functional Safety
Non senior engineers specialised in
Functional Safety
Senior engineers specialised in project
management
Engineers specialised in quality
assurance
Technicians in the field of Industrial
Controls Systems and Safety Systems
Technicians specialised in Functional
Safety
Draughtspersons - electrical
Draughtspersons - mechanical
Technicians in the field of software
development
EDMS No.: 2433969 v11.2 9 MS--4600/EN
2.6.2 Global Annual Turnover
The Firm, or the members of the Group of Firms collectively, shall have an average global annual
turnover of at least the equivalent of five million Swiss francs over the last three years in the fields
covered by the future Contract. Please complete one of the following tables, as appropriate.
In the case of a Single Firm:
2018 2019 2020
Global Annual Turnover
...................................
.....................................
.....................................
In the field of Industrial
Controls Systems
In the field of Safety
systems
In the field of
maintenance of controls
and safety systems
In the case of a Group of Firms:
2018 2019 2020
LEAD FIRM
Global Annual Turnover
...................................
.....................................
.....................................
In the field of Industrial
Controls Systems
In the field of Safety
systems
In the field of
maintenance of controls
and safety systems
MEMBER No. 2 OF THE GROUP OF FIRMS
Global Annual Turnover
...................................
.....................................
.....................................
In the field of Industrial
Controls Systems
In the field of Safety
systems
In the field of
maintenance of controls
and safety systems
TOTAL ...................................................................................................................
10 EDMS No. 2433969 v11.2
MS-4600/EN
Competence and Experience
The Firm, or the members of the Group of Firms collectively, shall have a proven competence and
experience, and shall be able to provide experienced personnel in the technical fields that are
necessary to meet the requirements of the scope, complexity and volume specified in §2.1 and § 3.1
of Technical Description.
Is this criterion fulfilled for all the mentioned fields?
□ YES □ NO
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
2.7.1 Functional Safety studies and Programmable Electronic Safety-related Systems
Do you have competence and five years of proven experience in Functional Safety studies and
Programmable Electronic Safety-related Systems: IEC61508, Safety matrix, S7 Distributed Safety?
Yes No
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Use of HIRA, FMECA, FTA (IEC 61508) Yes □ No □
Design of Safety-related Systems Yes □ No □
Maintenance of Safety-related Systems Yes □ No □
EDMS No.: 2433969 v11.2 11 MS--4600/EN
2.7.2 PLCs: Siemens (Step7, TIA Portal), Schneider (Premium, PL7 unity)
Do you have competence and five years of proven experience in Siemens and Schneider PLCs?
Yes No
Siemens PLCs
Yes No
Schneider PLCs
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Hardware
Design of PLC-based control systems architecture Yes □ No □
Selection and integration of HW components Yes □ No □
Troubleshooting Yes □ No □
Software
Selection and integration of SW components Yes □ No □
Code design Yes □ No □
Programming in all IEC61131 languages Yes □ No □
Code testing, deployment and validation Yes □ No □
Error and fault diagnostics Yes □ No □
Maintenance of existing PLC programs Yes □ No □
12 EDMS No. 2433969 v11.2
MS-4600/EN
2.7.3 Supervisory systems (SCADA) and middleware: (WINCC-OA, WinCC, PCVue)
Do you have competence and five years of proven experience for at least two of the requested SCADA
Brands?
Yes No
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Installation of application software and specific
libraries Yes □ No □
Development of interfaces with online databases (SQL
Server, Oracle) Yes □ No □
Development of scripts and procedures in the SCADA
application Yes □ No □
Design of operators panels HMIs Yes □ No □
Configuration of drivers (OPC, Step7, Modbus) Yes □ No □
Design and configuration of client-server architecture Yes □ No □
Configuration of redundant architectures Yes □ No □
2.7.4 Simulation and Test tools: SIMIT / SIMBABox, tests methods and tools
Do you have competence and five years of proven experience in Simulation and Test tools?
Yes No
Test Tools
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
EDMS No.: 2433969 v11.2 13 MS--4600/EN
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
SIMIT/SIMBA Box Yes □ No □
Test methods and tools Yes □ No □
2.7.5 Programming languages: Java, C, C++, Visual Basic, APEX
Do you have competence and five years of proven experience for at least 3 of the requested
Programming languages Brands?
Yes No
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Java Yes □ No □
C, C++ Yes □ No □
Visual Basic Yes □ No □
APEX Yes □ No □
14 EDMS No. 2433969 v11.2
MS-4600/EN
2.7.6 Communication systems: low level (field buses) and high level (Ethernet, TCP/IP)
Do you have competence and five years of proven experience in the above-mentioned communication
systems?
Yes No
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Hardware
Design and configuration of communication hardware Yes □ No □
Troubleshooting Yes □ No □
Software
Use of Configuration tools Yes □ No □
Low-level diagnostics of communication protocols Yes □ No □
2.7.7 Operating systems: VMWare, Windows, Linux CentOS
Do you have competence and five years of proven experience in the following Operating Systems?
Yes No
VMWare
Yes
No
Windows
Yes No
Linux CentOS
EDMS No.: 2433969 v11.2 15 MS--4600/EN
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Installation and maintenance of operating systems
and RAID configuration storages. Yes □ No □
Use of OS diagnostics tools for system
administration purposes. Yes □ No □
2.7.8 Databases: ORACLE, SQL Server
Do you have competence and five years of proven experience in Oracle and SQL Server?
Yes No
Oracle
Yes No
SQL Server
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Development of SQL queries and scripts in
ORACLE and SQL Server. Yes □ No □
Development of applications in PL/SQL Developer
and SQL Server Management Studio. Yes □ No □
16 EDMS No. 2433969 v11.2
MS-4600/EN
2.7.9 Software management tools: SVN, VersionDog, JIRA, GIT
Do you have competence and five years of proven experience in software management tools?
Yes No
Software management tools for
automation systems
Software management tools for
software applications
If not, please explain why:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
Software management tools for automation systems Yes □ No □
Software management tools for software
applications Yes □ No □
2.7.10 Asset and Maintenance management system for software and hardware
Do you have competence and five years of proven experience in Asset and Maintenance management
system for software and hardware?
Yes No
INFOR EAM
GRAFANA
ZABBIX, Icinga
EDMS No.: 2433969 v11.2 17 MS--4600/EN
If not, please explain alternative solutions you might have experience with:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience for each field below and provide example projects using the
“Project Form” of the Annex.
Experience Reference
Project Id
INFOR EAM or other Computer Assisted
Maintenance Management Systems Yes □ No □
GRAFANA or other graphical monitoring system Yes □ No □
ZABBIX, Icinga or other open-source monitoring
system Yes □ No □
2.7.11 Certification in the development of safety systems and software applications
Do you possess a external organism certification for development of safety instrumented systems and
software applications (e.g. TUV, QualiSIL, etc..) ?
Yes No
If not, please explain alternative certifications you might have in this domain:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
If yes, please describe your experience in at least one project for the development of a safety
instrumented system compliant with IEC 61508. Please present in detail the quality assurance strategy
followed and the systems’ certification delivered by the concerned “Certification/Nuclear Authority
bodies” if required.
Please describe your experience for each field below and provide example projects using the “Project
Form” of the Annex.
18 EDMS No. 2433969 v11.2
MS-4600/EN
Experience Reference
Project Id
Development of a safety instrumented system
compliant with IEC 61508 Yes □ No □
Certification delivered by the concerned
“Certification/Nuclear Authority bodies” Yes □ No □
References
The Firm, or the members of the Group of Firms collectively, shall provide at least three relevant
references delivered over the last five years covering activities similar to those of the future Contract
in terms of scope, complexity and volume, as described in the technical description and consistent
with the competences listed in §2.7 above.
CERN reserves the right to verify and contact the referees provided. In addition, the Firm, or each
member of the Group of Firms, shall arrange a visit by CERN to the premises of any of its referees if
so requested.
Please use the annexed “Reference form” and duplicate it as necessary.
Equipment and facilities
2.9.1 Equipment
The Firm, or the members of the Group of Firms collectively, shall have available at the time of this
Market Survey the following equipment:
Engineering stations (at least two) with Siemens (Step7, TIA Portal)
and Safety matrix, S7 Distributed Safety: □ YES □ NO
Testing and Simulation platform (SIMIT station or equivalent): □ YES □ NO
Electrical CAD station (at least two): □ YES □ NO
SW configuration management system: □ YES □ NO
Documentation management system: □ YES □ NO
If not, please explain why for each equipment concerned:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
2.9.2 Facilities
The Firm or the members of the Group of Firms collectively shall have available at the time of this
Market Survey the following facilities, or shall be ready to have such facilities for the proper
performance of the Contract:
Storage area: □ YES □ NO
EDMS No.: 2433969 v11.2 19 MS--4600/EN
Electrical workshop: □ YES □ NO
Development and testing infrastructure
for industrial controls and safety systems: □ YES □ NO
If these facilities are already available, please detail (for information) their location and distance from
CERN:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
Maintenance
2.10.1 Preventive maintenance
The Firm, or the members of the Group of Firms collectively, shall have a regular proven experience
over each of last five years of performing preventive maintenance to customers, in the technical fields
and commercial products in the scope of this contract.
Is this criterion fulfilled?
□ YES □ NO
If yes, please provide a reference using the “Reference Maintenance” form of the Annex.
2.10.2 Corrective maintenance
The Firm or the members of the Group of Firms collectively, shall have a regular proven experience
over each of last five years of performing corrective maintenance to customers, similar to the service
specified in §2.2.2 of the Technical Specification.
Is this criterion fulfilled?
□ YES □ NO
If yes, please provide a reference using the “Reference Maintenance” form of the Annex.
2.10.3 On-call service
The Firm or the members of the Group of Firms collectively, shall have a proven experience in the
last five years of performing on-call service to customers, similar to the service specified in §2.2.3 of
the Technical Specification.
Is this criterion fulfilled?
□ YES □ NO
If yes, please provide a reference using the “Reference Maintenance” form of the Annex.
20 EDMS No. 2433969 v11.2
MS-4600/EN
ADDITIONAL INFORMATION
Data privacy
Is the Firm or any member of the Group of Firms able ensure that any processing of personal data is
made in accordance with a high level of data protection (GDPR or adequate level recognized by the
EU)?
□ YES □ NO
Recognised trainer and auditors for IEC61508 & IEC 61511
If you are a recognised trainer or auditor in the domain of functional safety and safety instrumented
systems, please provide references for participation to audits, forums and providing training in the
technical domains scope of the future Contract.
Miscellaneous
Please indicate any other information that may be relevant to this Market Survey:
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
................................................................................................................................................................
Date
Signature and stamp of the Firm
or of each member of the Group of Firms
EDMS No.: 2433969 v11.2 21 MS--4600/EN
ANNEX
PROJECT FORM: TO BE USED IN §2.7
PROJECT ID:
Name of the customer
Full address
Name, telephone and e-mail of the
person to be contacted in customer
organisation
Scope of the contract
Duration (start and end dates)
Approximate contract value
Quality and safety management
Information related to the systems
you developed (if applicable):
Please describe for each system developed: architecture,
model and quantity of the hardware equipment, project
phases.
Functional safety
PLCs
SCADA systems
Simulation and Test tools
and methods
Programming languages
Communication systems
Operating systems
Data Bases
Software management tools
Please duplicate this reference form as needed.
22 EDMS No. 2433969 v11.2
MS-4600/EN
REFERENCE FORM: TO BE USED IN §2.8
REFERENCE #x
Name of the customer
Full address
Name, telephone and e-mail of
the person to be contacted in
customer organisation
Scope of the contract
Duration (start and end dates)
Approximate contract value
Quality and safety management
Please duplicate this reference form as needed.
EDMS No.: 2433969 v11.2 23 MS--4600/EN
MAINTENANCE FORM: TO BE USED IN §2.10
MAINTENANCE ID:
Name of the customer
Full address
Name, telephone and e-mail of the
person to be contacted in customer
organisation
Scope of the contract and details of
the maintenance services provided
Duration (start and end dates)
Approximate contract value
Quality and safety management
Information for the systems you
maintained (if applicable):
Please describe for each system: architecture, model and
quantity of hardware equipment, tasks description.
Functional safety
PLCs
SCADA systems
Test tools
Programming languages
Communication systems
Operating systems
Data Base
Software management tools
Asset and Maintenance
Management systems
Please duplicate this reference form as needed.