Marina-Salinas Multimodal Corridor Conceptual Plan. Fort Ord Reuse Authority January 10, 2013. Partner Agencies. Why?. Regional Context. Marina. Blanco Rd ADT : 23,100. Salinas. Hwy 68 ADT : 54,000. Project History. Marina. 1997 Base Reuse Plan. Salinas. Agriculture Impacts. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Marina-Salinas Multimodal Corridor Conceptual Plan

1

Marina-Salinas Multimodal Corridor Conceptual Plan

Fort Ord Reuse AuthorityJanuary 10, 2013

Page 2: Marina-Salinas Multimodal Corridor Conceptual Plan

2

Partner Agencies

Page 3: Marina-Salinas Multimodal Corridor Conceptual Plan

3

Why?

Congestion Safety Economy

Page 4: Marina-Salinas Multimodal Corridor Conceptual Plan

4

Regional Context

Salinas

MarinaBlanco Rd ADT: 23,100

Hwy 68 ADT: 54,000

Page 5: Marina-Salinas Multimodal Corridor Conceptual Plan

5

Project History

Salinas

Marina1997 Base Reuse Plan

Wildlife Habitat

Agriculture Impacts

Terrain

CSUMB Impacts

2010 MOA

Page 6: Marina-Salinas Multimodal Corridor Conceptual Plan

6

Overview

Page 7: Marina-Salinas Multimodal Corridor Conceptual Plan

7

Project Scope

Phase 1 - Alignment• Which route?

• Opportunities/Constraints

• Stakeholder Input

• Adopt Alignment

?

Page 8: Marina-Salinas Multimodal Corridor Conceptual Plan

8

Project Scope

Phase 2 – Corridor Elements

• What will the corridor look like?

• What will it cost?

• Roadway Cross-Sections

• Intersections

Page 9: Marina-Salinas Multimodal Corridor Conceptual Plan

9

Corridor Elements

Page 10: Marina-Salinas Multimodal Corridor Conceptual Plan

10

Study Area

Page 11: Marina-Salinas Multimodal Corridor Conceptual Plan

11

Study Area

Page 12: Marina-Salinas Multimodal Corridor Conceptual Plan

12

Project Schedule

Kick-Off (Sept./Oct.

2013)

PH 1 Community Workshops (Feb2014)

Adopt Preferred Alignment (Mar/April

2014)

PH 2 Community Workshops (May/Jun

2014)

Adopt Preferred Corridor Elements (Jul/Aug

2014)

Adopt Final Conceptual Plan (Oct.

2014)

Page 13: Marina-Salinas Multimodal Corridor Conceptual Plan

13

Questions?