Page 1: March 11, 2014 Bill Chang csudh/csug

March 11, 2014

Bill Chang

http://www.csudh.edu/csug

Campus Systems Users Group

CSUG

Page 2: March 11, 2014 Bill Chang csudh/csug

Agenda

PeopleTools Upgrade 8.53 Portal Upgrade 8.53 MP 12.00/12.01 TouchNet Upgrade CFS Upgrade Email MS Exchange Upgrade Other Project Updates Questions

Page 3: March 11, 2014 Bill Chang csudh/csug

PeopleTools Upgrade 8.53

Production start March 21 @ 5pm Validation on March 22

– Begins when upgrade is CMS is completed

Page 4: March 11, 2014 Bill Chang csudh/csug

4

Portal Upgrade 8.53

Production upgrade March 18 @ 8pm Complete by 12midnight No functional changes; only cosmetic changes

Page 5: March 11, 2014 Bill Chang csudh/csug

5

MP 11.03/12.00/12.01

Testing to complete by March 18 in HADHSTG Production on March 25 @ 8pm

Page 6: March 11, 2014 Bill Chang csudh/csug

6

TouchNet Upgrade

Upgrade TouchNet 6.5 production March 11 (Today) – in progress

To be completed by end of today

Page 7: March 11, 2014 Bill Chang csudh/csug

7

CFS 9.2 Upgrade

Pass 3 validation and acceptance testing in progress

Upgrade Production Apr 25th Post Go-Live system validation - TBD

Page 8: March 11, 2014 Bill Chang csudh/csug

8

Email Upgrade

Microsoft Exchange upgrade begin April 1 Upgrading to Exchange 2013 More storage space

http://www4.csudh.edu/it/services/email/exchange2013/index

Page 9: March 11, 2014 Bill Chang csudh/csug

Other Project Updates CHRS

– On hold per CMS Absence Management

– Go-Live date revised to October 2014 Data Warehouse

– Completed dashboards in development

– Production servers being built

– Production go-live in April 2014

Page 10: March 11, 2014 Bill Chang csudh/csug

Questions

?