December 20, 2013 Manitoba Wildlands 1
Review Process:
2) Canadian Environmental Assessment Agency reviews Keeyask Generation and Transmission Projects jointly3) Clean Environment Commission reviews Keeyask Generation Project and holds hearings
Legend:Canadian Environmental Assessment Act ‐Canadian Environmental Assessment Act from 1992 applies to Keeyask Generation ProjectDescription ‐ events, documents, motions, activities of Clean Environment Commission and Canadian Environmental Assessment AgencyURLs ‐ If links are broken, email [email protected] for a copy of the documentAcronyms list ‐ Master list available at the end of document
Links:Manitoba Public registry ‐ http://www.gov.mb.ca/conservation/eal/registries/Canadian Environmental Assessment Agency ‐ http://www.ceaa‐acee.gc.ca/Clean Environment Commission ‐ http://www.cecmanitoba.ca/Keeyask Limited Hydro Partnership ‐ http://keeyask.comBipole III Clean Environment Commission Hearings Events Chart ‐ http://manitobawildlands.org/pdfs/MWL‐CEC‐BP3ChronologyEvents‐19Mar13‐11thVersionUpdate‐FNL.pdf
Color Coding: CEAA = Canadian Environmental Assessment Agency New Additions to Chronology ChartCEC = Clean Environment CommissionMBHY = Manitoba Hydro and Proponent of KeeyaskCEC ParticipantsMB Gov =All branches of Manitoba Government Other federal government bodies
Manitoba Hydro Keeyask Generation & Transmission Projects Chronology Chart
Date Modified & Version: December 20, 2013 ‐ V37
1) Manitoba Conservation and Water Stewardship‐Environment Approvals Branch ‐ reviews Keeyask Generation and Transmission Projects separately and oversees; Environment Act Proposals, Scoping Documents, Environmental Impact Statements, Technical Reports, filings and review comments
Clean Environment Commission and Canadian Environmental Assessment Agency
December 20, 2013 Manitoba Wildlands 2
Date Description URL Source NotesJan 9, 2014 CEC Hearings in Winnipeg MB will be
extended to this week‐ as of Nov 8, 2013
CEC Week 8 (Thursday)
Jan 8, 2014 CEC Hearings in Winnipeg MB will be extended to this week‐ as of Nov 8, 2014
CEC Week 8 (Wedensday)
Jan 7, 2014 CEC Hearings in Winnipeg MB will be extended to this week‐ as of Nov 8, 2015
CEC Week 8 (Tuesday)
Jan 6, 2014 CEC Hearings in Winnipeg MB will be extended to this week‐ as of Nov 8, 2016
CEC Week 8 (Monday)
Dec 16, 2013 CAC submits edited documents CEC Particpants
Dec 16, 2013 CEC submits revised Hearing Schedule CEC Jan 6 ‐ 9, 2014
Dec 16, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 12,2013.pdf
CEC Dec 12,2013 Transcript
Dec 16, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 11,2013.pdf
CEC Dec 11,2013 Transcript
Dec 13, 2013 CEC submits revised Hearing Schedule CEC Jan 6 ‐ 9, 2014
Dec 13, 2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 12,2013 Exhibit List
Dec 12, 2013 Cross Examination of MMF President Panel Presentation
Proponent
December 20, 2013 Manitoba Wildlands 3
Date Description URL Source NotesDec 12, 2013 Cross Examination of KK Expert
Witnesses Presentations on Traditional Land Use
CEC Particpants
CFLGC, MMF, MWL
Dec 12, 2013 KK Expert Witnesses Presentations on Traditional Land Use
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
Terry Dick, D'Arcy Linklater (Presentations KK‐004 to KK‐025)
Dec 12, 2013 Cross Examination of CAC Expert Witness Presentation on Adaptive Management
CEC Particpants
CFLGC, MMF, MWL
Dec 12, 2013 Cross Examination of CAC Expert Witness Presentation on Adaptive Management
Proponent
Dec 12, 2013 CAC Expert Witness Presentation on Adaptive Management
http://www.cecmanitoba.ca/resource/hearings/39/Diduck, Fitzpatrick Keeyask Final_Nov 25, 2013.pdf
CEC Particpants
Drs. A.Diduck and P. Fitzpatrick (Presentations CAC‐032)
Dec 12, 2013 KK submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Dec 12, 2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 11,2013 Exhibit List
Dec 12, 2013 CEC Hearings in Winnipeg MB extended‐ as of Nov 1, 2013
CEC Week 7 (Thursday)
Dec 11,2013 Cross Examination of Fox Lake First Nation Youth Panel Presentation
CEC Particpants
CAC
Dec 11,2013 Cross Examination of PFN Panel Presentation
CEC Particpants
CAC, CFLGC, MWL
Dec 11,2013 Peguis First Nation (PFN) Panel Presentation
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
(Presentations PFN‐005 to PFN‐009)
December 20, 2013 Manitoba Wildlands 4
Date Description URL Source NotesDec 11,2013 MMF submits undertakings to CEC CEC
Particpants
Dec 11,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 9,2013.pdf
CEC Dec 9,2013 Transcript
Dec 11,2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 10,2013 Exhibit List
Dec 11,2013 CEC Hearings in Winnipeg MB extended‐ as of Nov 1, 2014
CEC Week 7 (Wedensday)
Dec 10,2013 Cross Examination of Fox Lake First Nation Youth Panel Presentation
CEC Particpants
MWL
Dec 10,2013 Cross Examination of CFLGC Expert Witnesses Presentation
Proponent
Dec 10,2013 CFLGC Expert Witnesses Presentation http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
Dr. P Kulchyski, Dr. S Maclachlan, A. Pawlowska( Presentation CFLGC‐
008 to ‐0012)Dec 10,2013 Fox Lake First Nation Youth Panel
Presentationhttp://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
( Presentation CFLGC‐001 to ‐007)
Dec 10,2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 9,2013 Exhibit List
Dec 10,2013 CEC Hearings in Winnipeg MB extended‐ as of Nov 1, 2015
CEC Week 7 (Tuesday)
Dec 9, 2013 Fox Lake First Nation Youth Panel Presentation
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
( Presentation CFLGC‐001 to ‐007)
December 20, 2013 Manitoba Wildlands 5
Date Description URL Source NotesDec 9, 2013 MMF submits undertakings to CEC CEC
Particpants
Dec 9, 2013 CEC Hearings in Winnipeg MB extended‐ as of Nov 1, 2016
CEC Week 7 (Monday)
Dec 6, 2013 CEC submits revised Hearing Schedule CEC Dec 9, 2013 ‐ Jan 9, 2014
Dec 6, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 5,2013.pdf
CEC Dec 5,2013 Transcript
Dec 6, 2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 5,2013 Exhibit List
Dec 5, 2013 Cross Examination of KHLP Moving Forward as Partners on Environmental Matters
CEC Particpants
PIM, MWL, CAC
Dec 5, 2013 KHLP Moving Forward as Partners on Environmental Matters
Proponent ( Presentation KHLP‐069)
Dec 5, 2013 Cross Examination of PIM Expert Witness Cumulative effects assesmment and mitigaton measures proposed Presentation
CEC Particpants
CAC, CFLGC, MWL
Dec 5, 2013 Cross Examination of PIM Expert Witness Cumulative effects assesmment and mitigaton measures proposed Presentation
Proponent
December 20, 2013 Manitoba Wildlands 6
Date Description URL Source NotesDec 5, 2013 PIM Expert Witness Cumulative effects
assesmment and mitigaton measures proposed Presentation
http://www.cecmanitoba.ca/resource/hearings/39/PIM‐008 Issues of Concern Presentation Luttermann.pdf
CEC Particpants
A. Lutterman (Presentation PIM‐008)
Dec 5, 2013 KK submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Dec 5, 2013 CAC submits edited documents CEC Particpants
Dec 5, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 4,20131.pdf
CEC Dec 4,2013 Transcript
Dec 5, 2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 4,2013 Exhibit List
Dec 5, 2013 CEC Hearings in Winnipeg MB extended‐ as of Sept 18, 2013
CEC Week 6 (Thursday)
Dec 4, 2013 Cross Examination of PIM Panel The Nature, Health, Economy, Territory and Rights Presentation
Proponent
Dec 4, 2013 PIM Panel The Nature, Heatlh, Economy, Territory and Rights Presentation
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Particpants
(Presentation PIM‐002 to PIM‐004)
Dec 4, 2013 Cross Examination of MMF Expert Witness Traditional Land Use and Knowlwege (TLUK) Presentation
CEC Particpants
CAC, CFLGC
Dec 4, 2013 Cross Examination of MMF Expert Witness Traditional Land Use and Knowlwege (TLUK) Presentation
Proponent
December 20, 2013 Manitoba Wildlands 7
Date Description URL Source NotesDec 4, 2013 MMF Expert Witness Traditional Land
Use and Knowlwege (TLUK) Presentation
CEC Particpants
P.M. Larcombe (Presentation MMF‐008)
Dec 4, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 3,2013.pdf
Dec 3,2013 Transcript
Dec 4, 2013 CEC Keeyask Hearing Exhibits list released
Dec 3,2013 Exhibit List
Dec 4, 2013 CEC Hearings in Winnipeg MB extended ‐ as of sept 18, 2013
CEC Week 6 (Wednesday)
Dec 3, 2013 MMF Expert Witness Traditional Land Use and Knowlwege (TLUK) Presentation
http://www.cecmanitoba.ca/resource/hearings/39/MMF‐008 TLUKS Presentation P. Larcombe.pdf
CEC Particpants
P.M. Larcombe (Presentation MMF‐008)
Dec 3, 2013 Cross Examination of MMF Expert Witness Socio‐Economic Information Gaps Presentation
CEC Particpants
MWL
Dec 3, 2013 Cross Examination of MMF Expert Witness Socio‐Economic Information Gaps Presentation
Proponent
Dec 3, 2013 MMF Expert Witness Socio‐Economic Information Gaps Presentation
http://www.cecmanitoba.ca/resource/hearings/39/MMF‐007 Socioecon Info Gaps Presentation M. Birnie.pdf
CEC Particpants
M. Birnie (Presentation MMF‐007)
Dec 3, 2013 Cross Examination of Expert Witness Ungulate Information Gaps Presentation
CEC Particpants
CAC
Dec 3, 2013 Cross Examination of MMF Expert Witness Ungulate Information Gaps Presentation
Proponent
December 20, 2013 Manitoba Wildlands 8
Date Description URL Source NotesDec 3, 2013 MMF Expert Witness Ungulate
Information Gaps Presentation http://www.cecmanitoba.ca/resource/hearings/39/MMF‐005 Ungulate Information Gaps Presentation A. Stewart.pdf
CEC Participants
A. Stewart (Presentation MMF‐005)
Dec 3, 2013 Cross Examination of MMF Panel Harvesters Presention
Proponent
Dec 3, 2013 MMF Panel Harvesters Presentation CEC Participants
Dec 3, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Dec 2,20131.pdf
CEC Dec 2,2013 Transcript
Dec 3, 2013 CEC Keeyask Hearing Exhibits list released
CEC Dec 2,2013 Exhibit List
Dec 3, 2013 CEC Hearings in Winnipeg MB extended‐ as of Sept 18, 2013
CEC Week 6 (Tuesday)
Dec 2, 2013 Cross Examination of MMF Panel Community Presention
Proponent
Dec 2, 2013 (Manitoba Metis Federation) MMF Panel Community Presentation
http://www.cecmanitoba.ca/resource/hearings/39/MMF‐003 Concerns and Issues of the Manitoba Metis Community Presentation.pdf
CEC Participants
(Presentation MMF‐003)
Dec 2, 2013 Cross Examination of MWL Expert Witness Presentation on Ecosystem Monitoring
CEC Participants
CFLGCDec 2, 2013 Cross Examination of MWL Expert
Witness Presentation on Ecosystem Monitoring
Proponent
December 20, 2013 Manitoba Wildlands 9
Date Description URL Source NotesDec 2, 2013 MWL Expert Witnesses Presentation
on Ecosystem Monitoringhttp://www.cecmanitoba.ca/resource/hearings/39/MWL‐011 Ecosystem Monitoring Presentation A. McHugh.pdf
CEC Participants
(Presentation MWL‐011)
Dec 2, 2013 Cross Examination of MWL Expert Witness Presentation on Sustainable Development and Sustainability
CEC Participants
CFLGCDec 2, 2013 Cross Examination of MWL Expert
Witness Presentation on Sustainable Development and Sustainability
Proponent
Dec 2, 2013 MWL Expert Witnesses Presentation on Sustainable Development and Sustainability
http://www.cecmanitoba.ca/resource/hearings/39/MWL‐009 Sustainability and Sustainable Devt Presentation A. Clarke.pdf
CEC Particpants
Dr. A. Clarke (Presentation MWL‐009)
Dec 2, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 26,2013 Exhibit List
Dec 2, 2013 CFLGC submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Dec 2, 2013 CEC Hearings in Winnipeg MB extended‐ as of Sept 18, 2013
CEC Week 6 (Monday)
Nov 29, 2013 CEC submits revised Hearing Schedule CEC Dec 2, 2013 ‐ Jan 9, 2014
Nov 29, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 28,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 10
Date Description URL Source NotesNov 28, 2013 Cross Examination of MWL Expert
Witness Presentation on Wildlife VECs, Habitat Quality
Proponent
Nov 28, 2013 MWL Expert Witnesses Presentation on Wildlife VECs, Habitat Quality
http://www.cecmanitoba.ca/resource/hearings/39/MWL‐007 Habitat Quality Models, SAR and Wildlife VECs Soprovich.doc1.pdf
CEC Participants
D. Soprovich (Presentation MWL‐007)
Nov 28, 2013 Cross Examination of MWL Expert Witness Presentation on Life Cycle Assessment (LCA)
Proponent
Nov 28, 2013 MWL Expert Witnesses Presentation on Life Cycle Assessment (LCA)
http://www.cecmanitoba.ca/resource/hearings/39/MWL‐004 Life Cycle Assessment Protocol Coldstream28Nov2013.pdf
CEC Participants
J. Salazar and M.Botwick (Presentation MWL‐004)
Nov 28, 2013 MMF submits Late Filing Expert Witness Presentations, Reports, Submissions
CEC Participants
Nov 28, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 27,2013 Exhibit List
Nov 28, 2013 CEC Hearings in Winnipeg predicted to end
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 2
CEC
Week 5 (Thursday)Nov 28, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC
Week 5 ( Thursday)Nov 27, 2013 Cross Examination of KHLP Moving
Forward as Partners on Environmental Matters
CEC Participants
CFLGC
December 20, 2013 Manitoba Wildlands 11
Date Description URL Source NotesNov 27, 2013 KHLP Moving Forward as Partners on
Environmental MattersProponent ( Presentation KHLP‐069)
Nov 27, 2013 Cross Examination of CAC Expert Witnesses Socio‐Economics
CEC Participants
MWL, CFLGC, PIM, CACNov 27, 2013 Cross Examination of CAC Expert
Witnesses Socio‐EconomicsProponent
Nov 27, 2013 Cross Examination of PFN Expert Witness on Shoreline modelling and Inundation
CEC Particpants
CAC, CFLGC, PIM
Nov 27, 2013 Cross Examination of CAC Expert Witnesses on Shoreline modelling and Inundation
Proponent
Nov 27, 2013 Peguis Expert Witness Presentation on Shoreline modelling and Inundation
http://www.cecmanitoba.ca/resource/hearings/39/PFN‐004 Identifying Shoreline Changes Flanders_Peguis presentation.pdf
CEC Particpants
D.Flanders (Presentation PFN‐003)
Nov 27, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 26,2013.pdf
CEC Nov 26,2013 Transcript
Nov 27, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 26,2013 Exhibit List
Nov 27, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 4
CEC
Week 5 ( Wednesday)
December 20, 2013 Manitoba Wildlands 12
Date Description URL Source NotesNov 26, 2013 Cross Examination of CAC Expert
Witnesses Socio‐EconomicsCEC Participants
CFLGC, MWLNov 26, 2013 Cross Examination of CAC Expert
Witnesses Socio‐EconomicsProponent
Nov 26, 2013 CAC Expert Witnesses Presentation on Socio‐Economics
http://www.cecmanitoba.ca/resource/hearings/39/CAC‐029 CED Assessment of the Keeyask Model Buckland and O'Gorman.pdf
CEC Participants
Dr.J.Buckland and Dr M. O'Gorman (Presentations CAC‐029)
Nov 26, 2013 Cross Examination of CAC Expert Witnesses on Health Impact Asssesment, HHRA
CEC Participants
CFLGC, MWLNov 26, 2013 Cross Examination of CAC Expert
Witnesses on Health Impact Asssesment, HHRA
Proponent
Nov 26, 2013 CAC Expert Witnesses Presentation on Health Impact Asssesment, HHRA
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Participants
MD. L. Murray, Dr. Breese and Dr.Brown
(Presentations CAC‐023 and CAC‐026)
Nov 26, 2013 MMF submits Expert Witness Presentations, Reports, Submissions
CEC Participants
Nov 26, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 25,2013.pdf
CEC Nov 25,2013 Transcript
Nov 26, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 25,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 13
Date Description URL Source NotesNov 26, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 4
CEC
Week 5 ( Tuesday)Nov 25, 2013 Moving Forward as Partners on
Environmental Mattershttp://www.cecmanitoba.ca/resource/hearings/39/KHLP‐069 Moving Forward as Partners.pdf
Proponent ( Presentation KHLP‐069)
Nov 25, 2013 Cross Examination of Terrestrial Environment Panel ( Continued from Nov 4, 2013)
CEC Particpants
CAC (Presentation KHLP‐042)
Nov 25, 2013 MWL submits Expert Witness Presentation, Reports, Submissions
CEC Particpants
Nov 25, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 5
CEC
Week 5 ( Monday)Nov 20,2013 Peguis submits Expert Witness
Presentations, Reports, SubmissionsCEC Particpants
Nov 19,2013 CAC submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Nov 18,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 14,2013.pdf
CEC Nov 14,2013 Transcript
Nov 18, 2013 Keeyask Hearings Adjourned for the Week of Nov 18 , 2013
CEC Mandatory CEC Hearings Break Nov 18 to Nov 21, 2013
December 20, 2013 Manitoba Wildlands 14
Date Description URL Source NotesNov 15,2013 CEC submits revised Hearing Schedule CEC Nov 25, 2013 ‐ Jan 9, 2014
Nov 15, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 14,2013 Exhibit List
Nov 14, 2013 Public Presentation by Janet McIvor, I. Disbrowe, M. Wavey, M. Mazurat, R. Spence, G. Kichekeesik, N. McIvor, J. Kitchekeesik
http://www.cecmanitoba.ca/resource/hearings/39/WPG‐007 Presentation from Janet McIvor and her family.pdf
Nov. 14 2013 Transcript
Nov 14, 2013 Public Presentation by Will Braun, InterChurch Council on Hydropower
http://www.cecmanitoba.ca/resource/hearings/39/WPG‐006 Presentation from Will Braun, Nov14.pdf
CEC Particpants
(Presentation WPG‐006)
Nov 14, 2013 Public Presentation by Cheryl Kennedy Courcelles
http://www.cecmanitoba.ca/resource/hearings/39/WPG‐005 Presentation from Cheryl Kennedy Courcelles, Nov14.pdf
CEC Particpants
(Presentation WPG‐005)
Nov 14, 2013 Public Presentation by Allan Ciekiewicz http://www.cecmanitoba.ca/resource/hearings/39/WPG‐004 Presentation from Allan Ciekiewicz Presentation, Nov14.pdf
CEC Particpants
(Presentation WPG‐004)
Nov 14, 2013 Public Presentation by Solange Garson Nov 14 2013 Transcript
Nov 14, 2013 Public Presentation by Selena Saunders
http://www.cecmanitoba.ca/resource/hearings/39/WPG‐003 Presentation from Selina Saunders, Hydro effects my livelihood.pdf
CEC Participants
(Presentation WPG‐003)
December 20, 2013 Manitoba Wildlands 15
Date Description URL Source NotesNov 14, 2013
7:00pm‐9:00pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 6
CEC
Week 4 (Thursday)Nov 14, 2013 Cross Examination of CAC Expert
Witness Presentation on Sustainability Assessment
CEC Particpants
CFLGC, PIM, MWL
Nov 14, 2013 Cross Examination of CAC Expert Witness Presentation on Sustainability Assessment
Proponent
Nov 14, 2013 CAC Expert Witness Presentation on Sustainability Assessment
http://www.cecmanitoba.ca/resource/hearings/39/CAC‐020 Sustainability Assessment Gibson.pdf
CEC Particpants
Dr.Robert Gibson (Presentation CAC‐020)
Nov 14, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts%20‐%20Keeyask%20Winnipeg%20Hearing%20Nov%2013,2013.pdf
CEC Nov 13,2013 Transcript
Nov 14, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 13,2013 Exhibit List
Nov 14, 20131:30pm‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 6
CEC
Week 4 ( Thursday)Nov 14, 2013
CEC submits revised Hearing ScheduleCEC
Nov 25, 2013 ‐ Jan 9, 2014Nov 13, 2013 Cross Examination of CAC Expert
Witness on CaribouCEC Particpants
MWL, PFN, FLCGC
December 20, 2013 Manitoba Wildlands 16
Date Description URL Source NotesNov 13, 2013 Cross Examination of CAC Expert
Witness on Caribou Proponent
Nov 13, 2013 CAC Expert Witness Presentation on Caribou ‐ Dr. J. Schaefer
http://www.cecmanitoba.ca/resource/hearings/39/CAC‐017 Caribou and the Keeyask project, Presentation.pdf
CEC Particpants
James Schaefer (Presentation CAC‐017)
Nov 13, 2013 Cross Examination of CAC Expert Witness on Lake Sturgeon
CEC Particpants
MWL, Peguis, CFLGC
Nov 13, 2013 Cross Examination of CAC Expert Witness on Lake Sturgeon
Proponent
Nov 13, 2013 CAC Expert Witness Presentation on Lake Sturgeon ‐ Dr. S. Peake
http://www.cecmanitoba.ca/resource/hearings/39/CAC‐013 Lake Sturgeon Mitigation at Keeyask‐Concerns and Advice, (Presentation) S. Peake.pdf
CEC Particpants
Dr. Stephan Peake (Presentation CAC‐013)
Nov 13, 2013 CAC Expert Witness Presentations, Reports, Submissions
CAC
Nov 13, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 12,2013.pdf
CEC Nov 12,2013 Transcript
Nov 13, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 12,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 17
Date Description URL Source NotesNov 13, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 7
CEC
Week 4 ( Wednesday)Nov 12, 2013 Cross Examination of CAC Expert
Witness Presentation on Cumulative Effects Assessment
CEC Particpants
CFLGC, PIM, MWL, Peguis
Nov 12, 2013 Cross Examination of CAC Expert Witness Presentation on Cumulative Effects Assessment
Proponent
Nov 12, 2013 CAC Expert Witnesses' Presentation on Cumulative Effects Assessment ‐Dr. Gunn & Dr. Noble
http://www.cecmanitoba.ca/resource/hearings/39/CAC‐009 Noble and Gunn CEA Presentation.pdf
CEC Particpants
Dr. Bram Noble and Dr. Jill Gunn (Presentation CAC‐009)
Nov 12, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 8
CEC
Week 4 ( Tuesday)Nov 8, 2013 CEC releases their descision on all
motions discussed at the CEC Motions Hearing Oct 17, 2013
http://www.cecmanitoba.ca/hearings/ ‐ 1
CEC Decisions for CFLGC, PIM, Peguis Motions
Nov 8 ,2013 CEC submits revised Hearing Schedule CEC Nov 12‐14, 2013 and Nov 25‐Dec 12, 2013
Nov 8, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 7,2013.pdf
CEC Nov 7,2013 Transcript
Nov 8, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 7,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 18
Date Description URL Source NotesNov 7, 2013 Cross Examination of Keeyas
Evaluation of the Keeyask Generation Project ‐Cree Nation Presentations (Continued)
CEC Particpants
CAC,PIM,FLCG,Peguis, CFLGC
Nov 7, 2013 Public Presentation by members of Shamattawa First Nation
CEC Particpants
(Presentation WPG‐002)
Nov 7, 2013 CAC submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Nov 7,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 6,20131.pdf
CEC Nov 6,2013 Transcript
Nov 7 ,2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 6,2013 Exhibit List
Nov 7, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 10
CEC
Week 3 ( Thursday)Nov 6, 2013 Cross Examination of Keeyas
Evaluation of the Keeyask Generation Project ‐Cree Nation Presentations
CEC Particpants
CAC
Nov 6 ,2013 Keeyask Evaluation of the Keeyask Generation Project ‐Cree Nation Presentations
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐050 Environmental Evaluation of the Keeyask Generation Project Nov 6, 2013‐CNP.pdf
Proponent (Presentation KHLP‐050)
December 20, 2013 Manitoba Wildlands 19
Date Description URL Source NotesNov 6, 2013 Cross Examination of Socio‐Economic
Environment, Resource Use and Heritage Resources Panel (Continued)
CEC Particpants
CFLGC, MMF, MWL
Nov 6,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts%20‐%20Keeyask%20Winnipeg%20Hearing%20Nov%205,2013.pdf
CEC Nov 5,2013 Transcript
Nov 6, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 5,2013 Exhibit List
Nov 6, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 11
CEC
Week 3 (Wednesday)Nov 5, 2013 Cross Examination of Socio‐Economic
Environment, Resource Use and Heritage Resources Panel
CEC Particpants
Peguis, CAC, PIM, CFLGC
Nov 5, 2013 CAC submits Expert Witness Presentations, Reports, Submissions
CEC Particpants
Nov 5, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Nov 4,2013.pdf
CEC Nov 4,2013 Transcript
Nov 5, 2013 CEC Keeyask Hearing Exhibits list released
CEC Nov 4,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 20
Date Description URL Source NotesNov 5, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 12
CEC
Week 3 ( Tuesday)Nov 4, 2013 Public Presentation by Baldur Nelson http://www.cecmanitoba.ca/resource/
hearings/39/Wpg‐001 Presentation from Baldur Nelson Nov. 4, 20132.pdf
CEC Particpants
(Presentation WPG‐001)
Nov 4, 2013
7:00pm‐9:00pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 13
CEC
Week 3 (Monday)Nov 4,2013 Socio‐Economic Environment,
Resource Use and Heritage Resources Panel
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐044 Socio‐economic, Resource Use and Heritage Resources.pdf
Proponent (Presentation KHLP‐044)
Nov 4, 2013 Cross Examination of Terrestrial Environment Panel ( Continued from Oct 31, 2013)
CEC Particpants
** This Panel was paused and will resume at a later date‐ CAC still has
Cross Examination
Nov 4, 20131:30pm‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC
Week 3 (Monday)Nov 1, 2013 CEC submits revised Hearing Schedule CEC CEC extends Hearings into an extra
week Nov 4‐ Dec 11,2013
Nov 1, 2013 CEC Keeyask Hearing Transcript released on CEC website
CEC Oct 31,2013 Transcript
Oct 31, 2013 Cross Examination of Terrestrial Environment Panel
CEC Particpants
CFLGC,Peguis, MWL, PIM, MWL, CAC
December 20, 2013 Manitoba Wildlands 21
Date Description URL Source NotesOct 31, 2013 CEC Keeyask Hearing Transcript
released on CEC websitehttp://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Oct 30,2013.pdf
CEC Oct 30,2013 Transcript
Oct 31, 2013 CEC Keeyask Hearing Exhibits list released
CEC Oct 30,2013 Exhibit List
Oct 31, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 4
CEC
Week 2 (Thursday)Oct 30,2013 Terrestrial Environment Panel http://www.cecmanitoba.ca/resource/
hearings/39/KHLP‐042 Aquatic & Terrestrial Environment ‐ Part 2.pdf
Proponent (Presentation KHLP‐042)
Oct 30,2013 Cross Examination of Aquatic Environment Panel (Continued)
CEC Particpants
PIM, CFLGC
Oct 30,2013 MBHY created a digital map book of all maps used in Project Description Panel and Physical Panel presentations
http://keeyask.com/wp/keeyask‐generation‐project‐cec‐hearings‐project‐description‐physical‐environment‐map‐book‐october‐2013
Proponent (Presentation KHLP‐038)
Oct 30, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Oct 29,2013.pdf
CEC Oct 29,2013 Transcript
Oct 30, 2013 CEC Keeyask Hearing Exhibits list released
CEC Oct 29,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 22
Date Description URL Source NotesOct 30, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 5
CEC
Week 2 (Wednesday)Oct 29,2013 Cross Examination of Aquatic
Environment PanelCEC Particpants
MWL, Peguis, CAC
Oct 29,2013 Aquatic Environment Panel Proponent (Presentation KHLP‐041)
Oct 29,2013 PIM submits a Expert Witness Resume CEC Particpants
Oct 29,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/KeeyaskOct2813.pdf
CEC Oct 28,2013 Transcript
Oct 29, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 6
CEC
Week 2 (Tuesday)Oct 28, 2013 Cross Examination of Physical
Environment PanelCEC Particpants
MWL, Peguis, MMF, CAC, CFLGC and then PIM (KK did not attend)
Oct 28, 2013 Physical Environment Panel Proponent (Presentation KHLP‐040)
Oct 28, 2013 CEC Keeyask Hearing Exhibits list released
CEC Oct 28,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 23
Date Description URL Source NotesOct 28, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 7
CEC
Week 2 (Monday)Oct 25, 2013 CEC submits revised Hearing Schedule CEC Oct 28 ‐ Dec 5, 2013
Oct 25, 2013 CFLGC submits a Expert Witness Resume
CEC Particpants
Oct 25, 2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Oct 24,2013.pdf
CEC Oct 24,2013 Transcript
Oct 24, 2013 Cross Examination of Regulatory Environmental Assessment‐Approach Methods and Processes Panel
CEC Particpants
MWL, Peguis, MMF, CAC, CFLGC and then PIM (KK did not attend)
Oct 24, 2013 Keeyask Generation Project Regulatory Environmental Assessment‐Approach Methods and Processes (Continued)
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐039 Approach, Methods and Processes Vicky Cole Oct 23, 20131.pdf
Proponent (Presentation KHLP‐039)
Oct 24,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/keeyaskoct23.pdf
CEC Oct 23,2013 Transcript
Oct 24,2013 CEC Keeyask Hearing Exhibits list released
CEC Oct 23,2013 Exhibit List
December 20, 2013 Manitoba Wildlands 24
Date Description URL Source NotesOct 24, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 8
CEC
Week 1 (Thursday)Oct 23, 2013 Keeyask Generation Project Regulatory
Environmental Assessment‐Approach Methods and Processes Panel
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐039 Approach, Methods and Processes Vicky Cole Oct 23, 20131.pdf
Proponent (Presentation KHLP‐039)
Oct 23, 2013 Cross Examination of Project Description Panel
CEC Particpants
MWL, Peguis, MMF, CAC, CFLGC and then PIM (KK did not attend)
Oct 23, 2013 Project Description Panel http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐037 Keeyask Project Description, Marc St. Laurent Oct 23, 20131.pdf
Proponent (Presentation KHLP‐0037)
Oct 23, 2013 Introduction to the Collaborative Two Track Approach Panel
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐036 Two Track Assessment Approach Oct 23, 20131.pdf
Proponent *This Panel was not Cross Examined Vicky Cole, Shawna Pachal, Joe Keeper
(Presentation KHLP‐036)
Oct 23,2013 MBHY releases Heritage Field Studies 2012
http://www.cecmanitoba.ca/resource/hearings/39/KHLP‐048 Updates on Keeyask Heritage Field Studies 2012‐13.pdf
Proponent (Presentation KHLP‐048)
Oct 23,2013 CEC Keeyask Hearing Undertakings list released
CEC Oct 22,2013 Undertakings List
Oct 23,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Oct 22,20131.pdf
CEC Oct 22,2013 Transcript
December 20, 2013 Manitoba Wildlands 25
Date Description URL Source NotesOct 23,2013 CEC Keeyask Hearing Exhibits list
releasedCEC Oct 22,2013 Exhibit List
Oct 23, 20139:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 9
CEC
Week 1 ( Wednesday)Oct 22,2013 Cross Examination of KHLP Partnership
Presentation by CEC Participants PanelCEC Particpants
MWL, Peguis, MMF, CAC, CFLGC,PIM
Oct 22,2013 KHLP Partnership Presentation Panel Continued
Proponent Shawna Pachal(MBHY), Ted Bland(YFFN), George Neepin(FLCN), Victor Spence with Roy Flett and Roy
Ouskun(TCN)Oct 22,2013 CEC submits revised Hearing Schedule CEC October 23 ‐ 24
Oct 22,2013 CEC Keeyask Hearing Transcript released on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Keeyask Winnipeg Hearing Oct 21,2013.pdf
CEC Oct 21,2013 Transcript
Oct 22, 2013 CEC Keeyask Hearing Exhibit list released
CEC Oct 21, 2013 Exhibit List
Oct 22, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 10
CEC Week 1 (Tuesday)
December 20, 2013 Manitoba Wildlands 26
Date Description URL Source NotesOct 21,2013 KHLP Partnership Presentation Panel Proponent Shawna Pachal(MBHY), Ted
Bland(YFFN), George Neepin(FLCN), Victor Spence with Roy Flett and Roy
Ouskun(TCN)Oct 21,2013 Opening Statements from KHLP
Partnership PanelProponent Ken Adams, FLCN, YFFN, WLFN,TCN
Oct 21,2013 Opening Statements By all Participants CEC Particpants
MWL, Peguis, MMF, CAC, CFLGC and then PIM (KK did not attend)
Oct 21, 2013 MCWS Opening Statements MCWS Director of Administraion Ms.Tracey Braun
Oct 21,2013 MBHY Opening Statements Proponent MBHY Lawyer Mr. Doug Bedford
Oct 21, 2013 CEC Opening Statements CEC CEC Chair Mr. Terry Sargeant
Oct 21, 2013
9:30am‐4:30pm at Ft. Garry Spa and Conference Centre, 222 Broadway, Winnipeg, MB Week 1 ( Monday)
December 20, 2013 Manitoba Wildlands 27
Date Description URL Source NotesOct 21, 2013 CEC Hearings Begin in Winnipeg MB http://www.cecmanitoba.ca/hearings/i
ndex.cfm?hearingid=39 ‐ 2CEC CEC hearings predicted to conitnue
for 5 weeks (Monday to Thursday), ending Nov 28, 2013.
Oct 18, 2013 Second version of the Hearing Schedule released
CEC Not available yet Agenda dates: Nov 4‐Dec 5
Oct 18, 2013 Motions transcript now available on CEC website
http://www.cecmanitoba.ca/resource/hearings/39/Transcripts ‐ Motions Hearing Oct 17, 2013.pdf
CEC
Oct 18, 2013 KHLP releases a summary of every panel that will be presenting as the Proponent
Proponent not yet available
Oct 18, 2013 CEC releases their descision on all motions discussed at the CEC Motions Hearing Oct 17, 2013
CEC Their explanation will be released to the participants at a later date
Oct 18, 2013 The Proponent submits an additional Resume
MBHY Original Deadline; Oct 7 ,2013
December 20, 2013 Manitoba Wildlands 28
Date Description URL Source NotesOct 17, 2013 CEC Motions Hearing http://www.cecmanitoba.ca/resource/
hearings/39/KEEYASK MOTIONS HEARINGS final.pdf
CEC Winnipeg Convention Centre, Millennium Room; 9:00am (NOT 10:00am)
Oct 17, 2013 Proponent Releases list of Panel members for Hearings
MBHY not available yet
Oct 16, 2013 First version of the Hearing Schedule released
CEC Not available yet Agenda dates: Nov 4‐Dec 5
Oct 15, 2013 First version of the Hearing Schedule released
CEC Not available yet Agenda dates: Oct 21 ‐31
Oct 15,2013 The Proponent submits an additional Resume
MBHY Original Deadline; Oct 7 ,2013
Oct 11, 2013 Public Registry 5550.00 Keeyask Generation Project Updated May 2013 postings
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MB‐Gov Last Updated May 24, 2013
December 20, 2013 Manitoba Wildlands 29
Date Description URL Source NotesOct 11, 2013 CEC Releases Kaweechiwasihki
Presentation exhibits http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC 3 submissions in total
Oct 11, 2013 CEC Releases Cross Lake written submissions
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC 30 submissions in total
Oct 11, 2013 CAC submits an additional Resume CEC Particpants
Original Deadline; Oct 7, 2013
Oct 11, 2013 All Transcripts from the Northern Community Hearings are available
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Gillam, Bird , York Factory, Thompson, Split Lake, Cross Lake
Oct 11, 2013 CAC (Consumers Association of Canada) withdraws Motion to the CEC
CEC Particpants
Oct 10, 2013 Manitoba Wildlands Submit Support Letters for three Motions
CEC Particpants
Motions Submitted by: PFN, PIM, CAC (CAC withdrawn Motion Oct 11, 2013)
December 20, 2013 Manitoba Wildlands 30
Date Description URL Source NotesOct 10, 2013 Kaweechiwasihk Submits Witness list,
Outlines,CVsCEC Particpants
Filed late due to some technical difficulties
Oct 10, 2013 The Propnent KHLP ( Keeyask Hydropower Limited Partnership) Submits Response to Peguis First Nation and Pimicikamak Notices of Motion
MBHY
Oct 10, 2013 MBHY Repsonse to CEC Participant Motions
http://www.cecmanitoba.ca/resource/hearings/39/Report ‐ Keeyask Pre‐Hrg Mtg ‐ Sep 2013.pdf
MBHY Noon (12:00pm) deadline
Oct 9, 2013 The Propnent KHLP ( Keeyask Hydropower Limited Partnership) Submits Response to CFLGC Notice of Motion
MBHY
Oct 7,2013 Pimicikamak Submits Witness list, Outlines,CVs
CEC Particpants
Noon (12:00pm) deadline
Oct 7, 2013 Concerned Fox Lake Grassroots Citizens Submits Witness lists, Outlines, CVs
CEC Particpants
Noon (12:00pm) deadline
December 20, 2013 Manitoba Wildlands 31
Date Description URL Source NotesOct 7, 2013 Manitoba Metis Federation Submits
Witness list, Outlines and CVsCEC Particpants
Noon (12:00pm) deadline
Oct 7, 2013 Consumers Association of Canada Submits Wintess list, Outlines and CVs
CEC Particpants
Noon (12:00pm) deadline; Additional CV sent out Oct 10, 2013
Oct 7, 2013 The Propnent KHLP ( Keeyask Hydropower Limited Partnership) Submits Witness list, Outlines and CVs
MBHY Noon (12:00pm) deadline
Oct 7, 2013 Peguis First Nation Submits Witness list, Outlines and CVs
CEC Particpants
Noon (12:00pm) deadline
Oct 7, 2013 Manitoba Wildlands Submits Witness list, Outlines and CVs
CEC Participants
Noon (12:00pm) deadline
Oct 7, 2013 Prefiling deadline for witnesses in Keeyask Hearing
CEC Noon (12:00pm) Deadline
Oct 4, 2013 Keeyask Generation Project Public Hearing Schedule posted for Day 1
CEC Day 1 October 21, 2013‐ not yet available
December 20, 2013 Manitoba Wildlands 32
Date Description URL Source NotesOct 4, 2013 Keeyask Motions Hearing Agenda
postedhttp://www.cecmanitoba.ca/resource/hearings/39/KEEYASK MOTIONS HEARINGS final.pdf
CEC October 17,2013 ; Millenium Room 9:00am NOT 10:00am
Oct 2, 2013 Consumers Association of Canada (CAC) Submits Notice of Motion
CEC Particpants
not yet available
Oct 2, 2013 Concerned Fox Lake Grassroots Citizens (CFLGC) Submits Notice of Motion
CEC Particpants
not yet available
Oct 2, 2013 Filing of other Motions to the CEC, and any written responses to motions that are already filed
http://www.cecmanitoba.ca/resource/hearings/39/Report ‐ Keeyask Pre‐Hrg Mtg ‐ Sep 2013.pdf
CEC Noon (12:00pm) Deadline
Oct 1, 2013 CEC Hearing Thomspon area community meeting
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Thompson Juniper Centre( 108 Nelson Rd.) 9:00am‐5:00pm
Sept 30, 2013 Concerned Fox Lake Grassroots Citizens (CFLGC) Submits Support letter for PIM and PFN Motions
CEC Particpants
not yet available
Sept 30, 2013 CEC Hearing Thomspon area community meeting
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Thompson Juniper Centre ( 108 Nelson Rd.) 7:00pm‐9:00pm
Sept 30, 2013 CEC Hearing Transcript‐York Factory http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Public Hearing in York Factory on September 26, 2013
Sept 30, 2013 CEC Hearing Transcript‐Bird Reserve http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 3
CEC Public Hearing in Bird Reserve on September 25, 2013
December 20, 2013 Manitoba Wildlands 33
Date Description URL Source NotesSept 30, 2013 CEC Hearing Transcript‐Gillam http://www.cecmanitoba.ca/hearings/i
ndex.cfm?hearingid=39 ‐ 3CEC Public Hearing in Gillam on
September 24, 2013
Sept 27, 2013 Solange Garson, Councillor TCN Submits First Exhibit
CEC Participants
not yet available
Sept 24, 2013 CEC Hearing Gillam area community meeting
CEC Gillam Rec Centre ( 235 Mattonabee Ave) 7:00pm‐ 9:00pm
Sept 24, 2013 CEC Hearing Gillam area community meeting
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 2
CEC Gillam Rec Centre ( 235 Mattonabee Ave) 3:00pm ‐ 5:00pm
Sept 16, 2013 CEC September 10 Pre hearing Conference Report
http://www.cecmanitoba.ca/resource/hearings/39/Report ‐ Keeyask Pre‐Hrg Mtg ‐ Sep 2013.pdf
CEC
Sept 16, 2013 CEC‐Pre hearing Transcript http://www.cecmanitoba.ca/resource/hearings/39/Transcripts%20‐%20Keeyask%20Pre‐hearing%20Sep101.pdf
CEC
Sept 10, 2013 CEC Participant Peguis First Nation submits motion
CEC Participants
Noon (12:00pm) deadline
Sept 10, 2013 CEC Participant Pimicikamak submits motion
CEC Participants
Noon (12:00pm) deadline
December 20, 2013 Manitoba Wildlands 34
Date Description URL Source NotesSept 10, 2013 CEC Pre‐Hearing Press Conference CEC
ParticipantsConference Rm 16, Winnipeg Convention Centre 3:00pm
Sept 10, 2013 CEC Pre‐Hearing meeting at Convention Centre
http://www.cecmanitoba.ca/resource/hearings/39/AGENDA Pre‐hearing September 10, 2013.pdf
CEC Millennium room, Winnipeg Convention Centre 10:00am
Sept 4, 2013 CEC submits a single Round 2 IR ‐ Late CEC Participants
Rd 2 CEC‐IR‐102c based on response to Rd 1 CEC‐IR‐0021
Sept 4, 2013 Pubic Registry still has not been updated
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MB‐Gov Public Registry for Keeyask Generation last updated May 24, 2013
September 4, 2013 MBHY sends paper copies to Participants 2 additions to the Preliminary Monitoring Plans
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/preliminary‐environmental‐protection‐program
MBHY Posted on website August 14, 2013. Preliminary Aquatic Effects Monitoring Plan and Preliminary Fish Habitat Compensation Plan
Sept 4, 2013 MBHY sends paper copies to Participants an addition to Supplemental Filing #1 ‐ Errata Part 2
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis/supplemental‐filing‐1
MBHY The First Errata list (from supplemental filing # 1) was submitted April 26, 2013.This document is dated August, 2013
Sept 4, 2013 MBHY sends paper copies to Participants the Responses to Requests for Additional Info from TAC and Public Reviews Round #3
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/response‐to‐requests‐for‐information/round‐3
MBHY Posted on website August 23, 2013
December 20, 2013 Manitoba Wildlands 35
Date Description URL Source NotesAug 23, 2013 Keeyask Generation Project Public
Hearing Schedule posted http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 2
CEC Postings for Hearing Schedule not Pre‐Hearing Schedule
August 16, 2013 MBHY submits responses to Round 2 IRs
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/responses‐to‐information‐requests‐cec‐new/cec‐round‐2
MBHY MBHY includes responses to MWL Round 2 IRs sent August 15, 2013
Aug 16, 2013 Clean Environment Commission (CEC) deadline for Manitoba Hydro (MBHY) to respond to round 2 Information Request (IR) from CEC and participants
CEC MBHY provided 16 days by CEC to respond to round 2 IRs from CEC and participants
Aug 15, 2013 MWL (Manitoba Wildlands) Submits 14 IRs
CEC and Particpants
MWL submits a total of 14 Round 2 IRs based on to the 26 lost ( and not acknowledged between May and July 15, 2013 Round 1 IRs MBHY)
Aug 14, 2013 Deadline responses for outstanding Manitoba Wildlands IRs (2nd Round)
CEC and Participants
26 outstanding IRs were responded to by MBHY after deadline. Final batch of the response to outstanding IRs were received by CEC and Participants July 31, 2013
Aug 1, 2013 CAC submits additional IRs to MBHY after deadline (2nd round )
CAC additional IR was excluded from original 2nd round batch of Irs submitted July 31, 2013
December 20, 2013 Manitoba Wildlands 36
Date Description URL Source NotesJuly 31, 2013 Kaweechiwasihki submits Final Batch
of IRs to MBHY (2nd round)KK Ist and Final batch contained 4 Irs
July 31, 2013 Pimicikamak First Nation (PCN) submits Final batch of IRs to MBHY (2nd round)
PFN Final batch contained 2 IRs , for a total of 6 IRs
July 31, 2013 CEC submits Final batch of IRs to MBHY (2nd round)
CEC Final batch contained 2 IRs , for a total of 19 IRs
July 31, 2013 MBHY filed final 6 outstanding IR reponses regarding Manitoba Wildlands round 1 IRs
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/responses‐to‐information‐requests‐cec‐new/responses‐to‐information‐requests‐cec‐rd‐1http://keeyask.com/wp/the‐project/environmental‐assessment‐
MBHY All Participants have received hard copies of the 26 outstanding MWL IRs from round 1
July 31, 2013 Concerned Fox Lake Grassroots Citizens (CFLGC) submits 1st batch of IRs to MBHY( 2nd round)
CFLGC 1st and final batch contained a total of 8 Irs
July 31, 2013 Pimicikamak First Nation (PCN) submits 1st batch of IRs to MBHY (2nd round)
PCN 1st Batch contained 4 IRs, for a total of 6 IRs submitted
December 20, 2013 Manitoba Wildlands 37
Date Description URL Source NotesJuly 31, 2013 Manitoba Wildlands submits final
batch of IRs to MBHY (2nd round)MWL Final batch contained 5 IRs, for a total
of 18 IRs submitted
July 31, 2013 Manitoba Metis Federation (MMF) submits Final batch of IRS to MBHY (round 2)
MMF Final and only batch of IRs contained a Report with IR responses included
July 31, 2013 Peguis First Nation submits Final batch of IRs to MBHY (round 2)
PFN Final batch contianed 12 IRs, for a total of 33 IRs submitted
July 31, 2013 Peguis First Nation submits 2nd batch of IRs to MBHY (2nd round)
PFN 2nd batch contained 10 IRs for a total of 33 IRs submitted
July 31, 2013 Manitoba Wildlands submits 1st batch of IRs to MBHY (2nd round)
MWL 1st batch contained 13 IRs, for a total of 18 IRs submitted
December 20, 2013 Manitoba Wildlands 38
Date Description URL Source NotesJuly 31, 2013 Peguis First Nation submits 1st batch
of IRs to MBHY (2nd round)PFN 1st batch contained 11 IRs, for a total
of 33 IRs submitted
July 31, 2013 Consumers Association of Canada (CAC) submits 1st batch of IRs to MBHY (2nd round )
CAC 1st batch contained 8 IRs , for a total of 62 IRs submitted and 1 letter to the CEC
July 31, 2013 CEC submits 2nd batch of IRs to MBHY (2nd round )
CEC 2nd batch contained 7 Irs, for a total of 19 IRs submitted
July 31, 2013 CEC deadline for round 2 IRs from CEC and participants to MBHY
CEC Round 2 IRs submitted to MBHY can only ask additional questions relating to IRs submitted during round 1
July 30, 2013 CEC submits 1st batch of IRs to MBHY (2nd round )
CEC 1st Batch contained 10 IRs, for a total of 19 IRs submitted
December 20, 2013 Manitoba Wildlands 39
Date Description URL Source NotesJuly 29, 2013 MBHY provides number system for the
2nd Round of IRsMBHY Numbering system for 2nd Round of
IRs in the CEC Hearing Directive or Process Guidelines was not found
July 26, 2013 MBHY filed 8 outstanding IR reponses regarding Manitoba Wildlands IRs (second batch 3:00pm)
http://keeyask.com/wp/wp‐content/uploads/2013/07/CEC‐Round‐1‐Web‐Version‐July‐26‐1130‐am.pdf
MBHY Second Batch of outstanding IRs have been added to the Keeyask website. There are still 6 outstanding Irs. Submission of round 2 IRs is two weeks after the date of each rd 1 IR response.
July 26, 2013 MBHY submits Supplemental filings#3 http://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis/supplemental‐filing‐3‐new
MHBY Correction to previous statement about no notification from KHLP about Supplemental Filing#3: There was an email sent on July 20th. Hard copies received by Participants Aug 1, 2013
July 26, 2013 MBHY sent hard copy of updated Supplemental Filings # 2 to participants
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis/supplemental‐filing‐2‐new‐2
MBHY
July 24, 2013 MBHY filed 13 outstanding IR reponses regarding Manitoba Wildlands Irs (first batch 3:15pm)
http://keeyask.com/wp/wp‐content/uploads/2013/07/CEC‐Round‐1‐Web‐Version‐July‐24‐2‐pm.pdf
MBHY Second Batch of outstanding IRs have been added to the Keeyask website. There are still 13 outstanding Irs. Submission of round 2 IRs is two weeks after the date of each rd 1 IR response.
December 20, 2013 Manitoba Wildlands 40
Date Description URL Source NotesJuly 15, 2013 CEC deadline for MBHY responses to
round 1 IRs CEC MBHY provided 45 days to respond to
round 1 IRs from CEC and participants
July 15, 2013 Cumulative Effects Assessment Summary (CEC RD 1‐ IR‐0020)
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/responses‐to‐information‐requests‐cec‐new/responses‐to‐information‐requests‐cec‐rd‐1
MBHY Found in the Reposnse to Information Requests‐CEC Round 1
July 15, 2013 MBHY fails to answer MWL IRs 61‐68 (CEC RD 1‐ IR‐0020)
CEC Participants
CEC Secretary adjusts timetable as all participants need all IR reponses MWL will be completed
July 15, 2013 MBHY submits Responses to round #1 Information Requests , filed by CEC and participants
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/responses‐to‐information‐requests‐cec‐new/responses‐to‐information‐requests‐cec‐rd‐1
MBHY Not yet on the Public Registry
July 13, 2013 MBHY submits updates of EIS Supplemental Filings round #2
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis/supplemental‐filing‐2‐new‐2
MBHY Updates to Project Description Information and Caribou Sections
July 13,2013 MBHY submits two outstanding responses to Requests for Additional Info from TAC and Public Reviews Round #2
http://keeyask.com/wp/wp‐content/uploads/2013/05/Responses‐to‐Request‐for‐Additional‐Information‐from‐TAC‐Public‐Reviewers‐Round‐2‐secured.pdf
MBHY CEAA‐0014, EC‐0026, EC‐0027, EC‐0031 are now complete. Not in public registry yet (including previous additions on July 2,2013)
December 20, 2013 Manitoba Wildlands 41
Date Description URL Source NotesJuly 2, 2013 MBHY submits two outstanding
responses to Requests for Additional Info from TAC and Public Reviews Round #2
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/response‐to‐requests‐for‐information/response‐to‐requests‐for‐additional‐information‐round‐2
MBHY not on public Registry yet (July 2,2013)
June 28, 2013 MBHY Keeyask Generation Project posts Preliminary Monitoring Plans on Keeyask website
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/preliminary‐environmental‐protection‐program
MBHY These Preliminary Monitoring Plans are not yet on the Public Registry
June 18 , 2013 CEC emails participants about providing binders and CDs with the Responses to Round #1 of IRs
CEC Response delivery Date has not yet released
June 4, 2013 York Factory Cree Nation (YFCN) submits 1st batch of IRS to MBHY
YFCN 1st batch contained 13 IRs.
June 3, 2013 CEC submits 8th batch of IRs to MBHY CEC 8th batch contained 12 IRs for a total of 90 IRs submitted
May 31, 2013 Pimicikamak First Nation (PCN) submits 3rd bactch of IRs to MBHY
PCN 3rd batch contained 2 IRs, for a total of 8 IRs submitted.
May 31, 2013 PCN submits 2nd batch of IRs to Manitoba Hydro (MBHY)
PCN 2nd batch contained 3 IRs, for a total of 6 IRs submitted
December 20, 2013 Manitoba Wildlands 42
Date Description URL Source NotesMay 31, 2013 PCN submits 1st batch of IRs to MBHY PCN 1st batch contained 3 IRs.
May 31, 2013 Manitoba Metis Federation (MMF) submits 2nd batch of IRS to MBHY
MMF IR about the resource economy. 2nd batch contained 1 IR, for a total of 39 IRs submitted
May 31, 2013 Consumers Association of Canada (CAC) submits 4th batch of IRs to MBHY
CAC 4th batch contained 15 IRs, for a total of 110 IRs submitted
May 31, 2013 CAC submits 3rd batch of IRs to MBHY CAC 3rd batch contained 19 IRs, for a total of 94 IRs submitted
May 31, 2013 Peguis First Nation submits 7th batch of IRs to MBHY
Peguis 7th batch contained 4 IRs, for a total of 47 IRs submitted
May 31, 2013 Manitoba Wildlands (MWL) submits 5th batch of IRs to MBHY
MWL 5th batch contained 3 IRs, for a total of 86 IRs submitted
May 31, 2013 MWL submits 4th batch of IRs to MBHY
MWL 4th batch contained 22 IRs, for a total of 83 IRs submitted
December 20, 2013 Manitoba Wildlands 43
Date Description URL Source NotesMay 31, 2013 Peguis First Nation submits 6th batch
of IRs to MBHYPeguis 6th batch contained 4 IRs, for a total
of 43 IRs submitted
May 31, 2013 Peguis First Nation submits 5th batch of IRs to MBHY
Peguis 5th batch contained 10 IRs, for a total of 39 IRs submitted
May 31, 2013 MWL submits 3rd batch of IRs to MBHY
MWL 3rd batch contained 13 IRs, for a total of 60 IRs submitted
May 31, 2013 MWL submits 2nd batch of IRs to MBHY
MWL 2nd batch contained 24 IRs, for a total of 47 IRs submitted
May 31, 2013 CAC submits 3rd batch of IRs to MBHY CAC 3rd batch contained 8 IRs, for a total of 74 IRs submitted
May 31, 2013 Peguis First Nation submits 4th batch of IRs to MBHY
Peguis 4th batch contained 5 IRs, for a total of 28 IRs submitted
December 20, 2013 Manitoba Wildlands 44
Date Description URL Source NotesMay 31, 2013 Peguis First Nation submits 3rd batch
of IRs to MBHYPeguis 3rd batch contained 8 IRs, for a total
of 23 IRs submitted
May 31, 2013 CAC submits 2nd batch of IRs to MBHY CAC IRs addressing adaptive environment management. 2nd batch contained 5 IRs, for a total of 65 IRs submitted
May 31, 2013 CEC deadline for round 1 Information Requests (IRs) to MBHY
CEC IRs are submitted by CEC and participants to MBHY requesting additional information on issues identified within the EIS and Supporting Volume materials
May 30, 2013 MMF submits 1st batch of IRs to MBHY
MMF 1st batch contained 38 IRs.
May 30, 2013 MWL submits 1st batch of IRS to MBHY
MWL 1st batch contained 23 IRs.
December 20, 2013 Manitoba Wildlands 45
Date Description URL Source NotesMay 30, 2013 Peguis First Nation submits 2nd batch
of IRs to MBHYPeguis 2nd batch contained 9 IRs, for a total
of 15 IRs submitted
May 30, 2013 Peguis First Nation submits 1st batch of IRS to MBHY
Peguis Total of 6 IRs submitted
May 30, 2013 CEC submits 7th batch of IRs to MBHY CEC 7th batch contained 9 IRs, for a total of 77 IRs submitted
May 29, 2013 CAC submits 1st batch of IRs to MBHY CAC Total of 60 IRs submitted
May 26, 2013 CEC submits 6th batch of IRs to MBHY CEC 6th batch contained 12 IRs, for a total of 66 IRs submitted
May 23, 2013 MBHY Keeyask Generation Project round 3 ‐Public Engagement Program Winnipeg open house
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/public‐involvement/current‐public‐involvement‐events
MBHY MBHY conducting round 3 of the Keeyask Generation Project Public Engagement Program
December 20, 2013 Manitoba Wildlands 46
Date Description URL Source NotesMay 23, 2013 CEC submits 5th batch of IRs to MBHY CEC IRs addressing mercury monitoring,
predictions, analysis, geographic limits, etc. 5th batch contained 7 IRS for a total of 54 IRs submitted
May 20, 2013 CFLGC submits 1st batch of IRs to MBHY, containing 17 individual IRs.
CFLGC Total of 17 IRs submitted by participants
May 16, 2013 MBHY Keeyask Generation Project round 3 ‐Public Engagement Program Thompson open house
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/public‐involvement/current‐public‐involvement‐events
MBHY MBHY conducting round 3 of the Keeyask Generation Project Public Engagement Program
May 15, 2013 CEC circulates 3rd draft of CEC participant contact list
CEC Updated to include new participant, Pimicikamak Okimowin
May 9, 2013 CEC circulates 2nd draft of CEC participant contact list
CEC Updated to include new participant Kaweechiwasihk Inninuwuk
May 9, 2013 CEC submits 4rd batch of IRs to MBHY, containing 5 individual IRs.
CEC IRs focus on bioaccumulation of mercury in wildlife. 4th batch contains 5 IRs for a total of 47 IRs submitted
May 8, 2013 CEC submits 3rd batch of IRs to MBHY, including 8 individual IRs.
CEC 3rd batch contained 8 IRs, for a total of 42 IRs submitted
December 20, 2013 Manitoba Wildlands 47
Date Description URL Source NotesMay 7, 2013 CEC submits single IR to MBHY CEC IR about cummulative effects to First
Nation communities. Total of 35 IRs submitted by CEC
May 3, 2013 MCWS posts MBHY response to round#1 of Keeyask Transmission Project Supplemtnatal Information Request by TAC and Public review
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/ktp‐tac‐public‐rd‐1ir‐responses.pdf
MCWS The request by TAC and Public review was forwarded by MB‐EAB, on January 18th 2013, to MBHY (MBHY response was released April 26, 2013)
May 1, 2013 CEC submits single IR to MBHY CEC IR about health risk assessment. Total of 34 IRs submitted by CEC
Apr‐May, 2013 MBHY conducts round 3 of Public Engagement Program
http://keeyask.com/wp/wp‐content/uploads/2012/01/Keeyask‐Newsletter‐R3_WEB.pdf
MBHY MBHY meets with public to review Keeyask Generation Project Environmental Impact Statement (EIS) (Posted on KHLP website).
http://keeyask.com/wp/wp‐content/uploads/2012/11/Responses‐to‐Request‐for‐Additional‐Information‐from‐TAC‐Public‐Reviewers‐Round‐2.pdf
Posted on KHLP Website April 29, 2013
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/responses‐tac‐round‐2/responses_tac_round_2.pdf
Posted on Manitoba Public Registry May 24, 2013
Apr 26, 2013 MBHY submits responses to round #2 requests for additional information from TAC and pulic reviewers
MBHY
December 20, 2013 Manitoba Wildlands 48
Date Description URL Source Noteshttp://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis
Updates to Keeyask Generation EIS materials submitted by MBHY (Posted on KHLP website April, 2013).
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
Posted on Manitoba Public Registry on May 24, 2013
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/preliminary‐environmental‐protection‐program
Preliminary EnvPP is incomplete, sections required (Posted on KHLP website April 26, 2013).
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
Posted on Manitoba Public Registry on May 24, 2013
Apr 23, 2013 CEC submits 2nd batch of IRs to MBHY CEC 2nd batch containing 14 IRs, for a total of 33 IRs submitted
Apr 22, 2013 CEC submits 1st batch of IRs to MBHY, containing 19 individual IRs.
CEC 1st batch of IRs dealt with a variety of issues. Total of 19 IRs submitted by CEC
Apr 26, 2013 MBHY submits Keeyask Generation Project EIS supplemental filing #1 to Manitoba Conservation & Water Stewardship (MCWS)
MBHY
Apr 26, 2013 MBHY submits Preliminary Keeyask Environmental Protection Program
(EnvPP) for review by public
MBHY
December 20, 2013 Manitoba Wildlands 49
Date Description URL Source NotesApr 18, 2013 CEC circulates CEC pre‐hearing
meeting reportCEC Pre‐hearing meeting held on April 11,
2013 at the Winnipeg convention Centre
Apr 12, 2013 CEC circulates transcripts from CEC pre‐hearing meeting
CEC Pre‐hearing meeting held on April 11, 2013 at the Winnipeg Convention Centre
Apr 12, 2013 1st draft of CEC participant contact list circulated
CEC
Apr 11, 2013 Clean Environment Commission (CEC) Keeyask Generation Project pre‐hearing meeting
http://www.cecmanitoba.ca/resource/hearings/39/AGENDA Pre‐hearing April 11 2013 .pdf
CEC Introduction of CEC hearing participants, CEC panel and CEC process for Keeyask Generation Project
Apr, 2013 http://keeyask.com/wp/the‐project/environmental‐assessment‐process/preliminary‐environmental‐protection‐program
EnvPP contains 15 sections, some of which are incomplete. Posted on KHLP/MBHY website April 2013
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
Posted on Manitoba Public Registry May 24, 2013
MBHYMBHY posts Preliminary Environmental Protection Progam (EnvPP) on KHLP/MBHY website.
December 20, 2013 Manitoba Wildlands 50
Date Description URL Source NotesFeb 15, 2013 CEC Participant Assistance Application
Package (PAP) duehttp://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39 ‐ 2
CEC Application for participant funding to participate in CEC hearings for Keeyask Generation Project
Feb 13,2013 Environmental Protection Operations Division‐Environment Canada, submits addendum to round #1 supplemental information requests to MBHY
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/part_9.pdf
Environment Canada
Addendum to Fedreal comments, submitted February 19, 2013
Feb 2013 MB‐Gov EAB posts Keeyask Transmission Environment Act Proposal (EAP) Technical Advisory Committee (TAC) and public review comments online
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/index.html
MB‐Gov EAB Request Responses to TAC Public comments round#1 from MBHY
Jan 18, 2013 Technical Advisory Committee (TAC) and Public Review request for Supplemental Information in Keeyask Transmision Project round #1 to MBHY
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/index.html
MB‐EAB This request was forwarded by the MB‐EAB to MBHY This request is currently not found on MB public registries website
Jan 7, 2013 MB‐Gov EAB deadline for public comments on Keeyask Transmission Project Environment Act Proposal (EAP)
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/index.html
MB‐Gov EAB Comments submitted to MB‐Gov EAB
Dec 21, 2012 Canadian Environmental Assessment Agency (CEAA) deadline for public comments on Keeyask Generation and Transmission Projects ‐ Environmental Effects Summary
CEAA Comments submitted to CEAA
December 20, 2013 Manitoba Wildlands 51
Date Description URL Source NotesNov 28, 2012 MB‐Gov EAB advertises public
comment period for Keeyask Transmission Project EAP
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/ad_5614.pdf
MB‐Gov EAB Advertised public notice in Thompson Citizen and WFP
Nov 21, 2012 CEAA invites public comments on MBHY Keeyask Generation and Transmission Projects ‐ Environmental Effects Summary
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=83603
CEAA Environmental Effects Summary based on Keeyask Generation EIS. Comments submitted to CEAA
Nov 21, 2012 MBHY submits Keeyask Transmission Project Environmental Assessment Report (ESR) and Technical Reports to MCWS and CEAA
http://www.gov.mb.ca/conservation/eal/registries/5614keeyask_transmission/index.html
MBHY Keeyask Transmission ESR and Technical Reports available through Public Registry and CEAA website
Nov 19, 2012 MBHY submits responses to round #1 requests for additional information from the Technical Advisory Committee (TAC) and public reviews
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MBHY Keeyask Generation EIS TAC and public comments forwarded by MB‐Gov EAB
Nov 16,2012 CEC hearings for MBHY Keeyask Generation Project announced by Manitoba Conservation and Water Stewardship (MCWS)
http://news.gov.mb.ca/news/index.html?item=15562
MCWS MCWS announces CEC hearing. Confirms province has initiated a Crown‐Aboriginal consultatation process
Nov 14, 2012 Minister of MCWS requests Clean Environment Commission (CEC) hearings for Keeyask Generation Project, includes terms of reference
http://www.cecmanitoba.ca/hearings/index.cfm?hearingid=39
MCWS MCWS Minister Gord Mackintosh sends letter to CEC Chair, directing CEC hold public hearings for proposed Keeyask Generation Project. Terms of reference for the CEC hearings enclosed
December 20, 2013 Manitoba Wildlands 52
Date Description URL Source NotesSept 20, 2012 MB‐Gov EAB TAC and Public comment
deadline on Keeyask Generation Project EIS
MB‐Gov EAB Comments due to MB‐Gov EAB
July 14, 2012 MB‐Gov EAB ad notice of Keeyask Generation Project EIS review in Winnipeg Free Press (and other publications July 14‐21)
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/5550_eis_ad.pdf
MB‐Gov EAB Notice posted in WFP and various other publications
July 6, 2012 MBHY submits Keeyask Generation Project EIS and Supporting Volumes to MB‐Gov EAB and CEAA
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/eis
MBHY MB‐Gov EAB to review and approve EIS submissions (Posted on KHLP website, July 2, 2012)
Apr 3, 2012 CEAA Funding Review Committee's Report on Aboriginal Funding Envelope
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=55008
CEAA Participant Funding Program (PFP)
Mar 28, 2012 CEAA deadline for public comments on the Keeyask Generation and Transmission Projects draft EIS guidelines
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=54452
CEAA Written comments submitted to CEAA
December 20, 2013 Manitoba Wildlands 53
Date Description URL Source NotesFeb ‐ May 2012 no exact date
MBHY conducts round 2 of Public Engagement Program
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/public‐involvement/public‐involvement‐documents
MBHY MBHY revisited Aboriginal and Non‐Aboriginal communities in northern Manitoba and other potentially affected areas. MBHY also met with interested organizations contacted from round 1Feb 29, 2012 CEAA public notice of comment period
to review draft EIS guidelines document
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=54452
CEAA CEAA annouces public comment period to review draft EIS guidelines document
Feb 29, 2012 CEAA Draft EIS Guidelines for MBHY Keeyask Generation and Transmission Projects
http://www.ceaa‐acee.gc.ca/050/documents‐eng.cfm?evaluation=64144
CEAA Document prepared by CEAA
Feb 29, 2012 CEAA Participant Funding Program Report
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=54427
CEAA CEAA released the Participant Funding Program‐Regular Funding Envelope‐Funding Review Committees Report Entitled "Allocation of Federal Funds for the Environmental Assessment of the Keeyask Generation Project"
Feb 29, 2012 CEAA announces recipients of Federal funding for participation in the Keeyask Generation and Transmission projects Environmental Assessment
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=54425
CEAA
December 20, 2013 Manitoba Wildlands 54
Date Description URL Source NotesFeb,2012 MCWS posts Keeyask Generation
Project Environment Act Proposal (EAP) and Final Scoping Document (SD) TAC and public comments online
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MCWS TAC and public comments posted on Manitoba public registry for final SD
Jan 31, 2012 Public comment deadline on the conduct of the CEAA Keeyask Generation and Transmission Projects and conduct of Comprehensive study
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=53501
CEAA CEAA review of the Keeyask Generation and Transmission Projects, determined that project is subject to Comprehensive Study List Regulations and an Environmental Assessment
Jan 31, 2012 CEAA federal funding application deadline for Keeyask Generation Project
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=53503
CEAA Application submitted to CEAA
Jan 31, 2012 CEAA and MCWS Keeyask Generation and Transmission Projects EAP and Final SD public comments deadline‐ dates are listed in the public advertisement for Notice of Environment Act Proposal
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
CEAA MCWS
Comments submitted to both CEAA and MCWS. CEAA requesting comments on Keeyask Generation and Transmission Projects. MCWS requesting comments only on Keeyask Generation Project
Jan 1, 2012 CEAA and MCWS notice of EAP and Final SD in Winnipeg Free Press (WFP) and other publications ‐ Indicated in the advertisement for Notice of Environment Act Proposal
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
CEAA MCWS
Joint CEAA and MCWS deadline for EAP and SD comments. All reviews under the Environment Act must be advertsied
December 20, 2013 Manitoba Wildlands 55
Date Description URL Source NotesDec 15, 2011 CEAA federal funding announced for
Keeyask Generation and Transmission Projects Environmental Assessment
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=53503
CEAA
Dec 15, 2011 CEAA invites public comments on the Keeyask Generation and Transmission Projects and conduct of the CEAA Comprehensive Study
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=53501
CEAA CEAA background document about Keeyask Generation and Transmission Projects to assisted public review
Dec 15, 2011 CEAA releases Keeyask Generation and Transmission Projects Background Information Document
http://www.ceaa‐acee.gc.ca/050/documents/53536/53536E.pdf
CEAA Background document to assist public review of projects
Dec 13, 2011 CEAA public notice ‐ Commencement of Keeyask Generation and Transmission Projects Environmental Assessment. Mention of Keeyask Infrastructure
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=80054
CEAA CEAA announced that an Environmental Assessment for Keeyask Generation and Transmission projects was required, pursuant to the Canadian Environmental Assessment Act
Dec 9, 2011 MBHY files Keeyask Generation Project Draft SD to CEAA and MCWS for public review
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MBHY Draft SD seek to lay out the requirements for Environmental Impact Statement
Dec 9, 2011 MBHY submits Environment Act Proposal Form (EAP) to MCWS for public review
http://www.gov.mb.ca/conservation/eal/registries/5550keeyask/
MBHY All applications for a Manitoba Environment Act license begin with an Environment Act Proposal Form (EAP), submitted to MCWS
December 20, 2013 Manitoba Wildlands 56
Date Description URL Source NotesNov 29, 2011 CEAA announces commencement of
Comprehensive Study of Keeyask Generation and Transmission Projects
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=80054
CEAA CEAA begins comprehensive study of the Keeyask Generation Project, pursuant to Canadian Environmental Assessment Act
Aug 31, 2011 CEAA receives Keeyask Generation and Transmission Projects description from MBHY
http://www.ceaa‐acee.gc.ca/050/document‐eng.cfm?document=88077
CEAA CEAA receives Keeyask Generation project description from MBHY, to determine if Comprehensive Study and Environmental Assessment should be conducted
May 9, 2011 MBHY submits Draft Description of Keeyask Generation Project to Major Projects Management Office (MPMO) of Natural Resources Canada
Not available online MPMO Document assists MPMO in fulfilling federal mandate of providing federal coordination, management and accountability for major resource projects
May 2008 MBHY initiates round 1 of Keeyask Generation Project Public Involvement Program
http://keeyask.com/wp/the‐project/environmental‐assessment‐process/public‐involvement/public‐involvement‐documents
MBHY MBHY required to engage with the public to seek feedback on the Keeyask Generation Project
December 20, 2013 Manitoba Wildlands 57
Date Description URL Source NotesAcronyms: CAC = Consumers Association of
Canada (Manitoba) CEAA = Canadian Environmental Assessment Agency CEC = Clean Environment Comission CFLGC = Concerned Fox Lake Grassroots Citizens EAP= Environmental Act Proposal EIS = Env. Impact Statement EnvPP = Environmental Protection Program ESR = Environmental Study Report FLCN = Fox Lake Cree Nation IRs = Information Requests/Responses KHLP = Keeyask Hydropower Limited Partnership KK = Kqweechiwasihk Inninuwuk (York Factory Cree Nation) MCWS = Manitoba Conservation and Waterstewardship
MB‐Gov = Manitoba Government MB‐Gov EAB = Environmental Approvals Branch MBHY = Manitoba Hydro MMF = Manitoba Metis Federation MWL = Manitoba Wildlands NFAAT = Needs For And Alternatives To Peguis = Peguis First Nation PILC = Public Interest Law Centre SD = Scoping Document TAC =Technical Advisory Committee TCN = Tataskeyak Cree Nation WLCN = War Lake Cree Nation WEA = Whelan Enns Associates Inc. WFP = Winnipeg Free Press YFCN = York Factory Cree Nation
December 20, 2013 Manitoba Wildlands 58