managingtripleconstraint aam
DESCRIPTION
Presentacion para Alumnos de distintas Universidades del Capitulo del PMI Lima en la Universdad del PacificoTRANSCRIPT
Managing Triple Constraint
Project Scope ManagementProject Cost ManagementProject Time Management
Aldo Arecco Mayo
Senior Project Manager
Triple Constraint
Quadruple Constraint
Triple Constraint Process
Top five reasons why project management fails TOP FIVE REASONS- TECH PROJECT
Failure to Manage Culture Change Lack of Commitment Pass Failures Inadecuate Planning Is not about the tools!
Project Scope Management The processes required to ensure that the project
includes all the work required, and only the work required, to complete the project successfully
Why Do We Manage Scope? Can’t manage schedule and budget if scope is out of
control (Triple Constraint) Scope docs are used to manage expectations
Scope Management Key Points What is scope management
Checking to ensure that one is completing work Saying No to additional work not in the charter Preventing extra work
Work Breakdown Structure (WBS) Foundation of the project, all planning and controlling
is based on the WBS Identifies all work to be performed, if it is not in the
WBS it does not need to be done Graphical picture of work
Scope Management Key Points
TIME
COSTSCOPE
QualityWBS
Estimating
Network Diagrams
Staffing
Risk
How Do We Manage Scope? Five processes
Scope Planning Scope Definition Create WBS Scope Verification Scope Control
Scope Planning
Scope Definition
Create WBS
Scope Verification
Scope Control
Scope Definition
• Change Control System• Documentation, tracking, and approvals
required to change project scope• Configuration Management System
• Documentation, tracking, and approvals required to change product scope
• Management by Objectives (MBO)• Establish unambiguous and realistic
objectives• Periodically evaluate if objectives are being
met• Take corrective action
Project Time Management
• “The processes required to accomplish timely completion of the project”
• Why Time Management?1. Part of triple constraint, can’t manage one
without the others (scope, time, and quality) 2. Second hardest section on the test behind
integration
How Do We Manage Time?
• Six processes• Activity Definition• Activity Sequencing• Activity Resource Estimating• Activity Duration Estimating• Schedule Development• Schedule Control
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Activity DefinitionEnterprise Environmental Factors
Organizational Process Assets
Project Scope Statement
Decomposition
Templates
Rolling wave planning
Expert judgment
Planning component
Inputs OutputsTools & Techniques
Work Breakdown StructureWBS Dictionary
Project Management Plan
Activity List
Activity Attributes
Milestone List
Requested Changes
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Activity Definition
• Rolling Wave Planning – Progressive planning where near term work is broken down in detail and distant work is kept at a higher WBS level
• Planning Component – WBS items that cannot be broken down into work packages are put in a:
• Control Account – High level planning dates for the scope to be defined
• Planning Package – Package includes scope to be completed but no activities
Activity Sequencing
Project Scope Statement
Activity List
Activity Attributes
Precedence diagramming method (PDM)
Arrow diagramming method (ADM)
Schedule network templates
Dependency determination
Applying leads and lags
Inputs OutputsTools & Techniques
Milestone List
Approved Change Requests
Project Schedule Network Diagrams
Activity List Updates
Activity Attributes Updates
Requested Changes
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Precedence Diagramming Method (PDM)
• Commonly called Activity on Node (AON), most commonly used sequencing method
• Boxes are used to represent tasks with arrows used for dependencies
• Four types of dependencies Finish to Start – Task must finish before next one
can start Finish to Finish – One task must finish before the
other can finish Start to Start – One task must start before the
other can start Start to Finish – One task must start before the
other can finishActivity
A
Activity
B
NodeDependency
Arrow Diagramming Method (ADM)
• Commonly called Activity on Arrow (AOA)• Boxes are used to represent dependencies with arrows used for
tasks• Only Finish to Start relationships• Can use “dummy” activities
• Used for CPM and PERT estimating methods
Task
Dependency
Activity
A
Method Comparison
StartBuild Foundation
Build Walls
Install Grass
Build Roof Finish
Start Build Foundation
Build Walls
Build Roof
Finish
Install Grass
PDM (AON) Method
ADM (AOA) Method
Activity Resource Estimating
Enterprise Environmental Factors
Organizational Process Assets
Activity List
Expert judgment
Alternatives analysis
Published estimating data
Project management software
Bottom-up estimating
Inputs OutputsTools & Techniques
Activity AttributesResource Availability
Activity Resource Requirements
Activity Attributes Updates
Resource Breakdown Structure
Resource Calendar Updates
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Project Management Plan
Requested Changes
Activity Duration Estimating
Enterprise Environmental FactorsOrganizational Process Assets
Project Scope Statement
Expert judgment
Analogous estimating
Parametric estimating
Three-point estimates
Reserve Analysis
InputsOutputs
Tools & Techniques
Activity List
Activity Resource Requirements
Activity Duration Estimates
Activity attributes updates
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Resource Calendar
Activity Attributes
Project Management Plan
• Risk Register• Activity Cost
Estimates
Schedule Development
Enterprise Environmental FactorsOrganizational Process Assets
Project Scope Statement
Schedule network analysis
Critical path method
Schedule compression
What-if analysis
Resource leveling
Critical chain method
Project management software
Applying calendars
Adjustable leads and lags
Schedule model
Inputs Outputs
Tools & Techniques
Activity List
Activity Resource Requirements
Schedule baseline
Activity attributes updates
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Resource Calendar
Activity Attributes
Project Management Plan
• Risk Register• Activity Cost
Estimates
Project schedule
Schedule model data
Resource requirements updates
Requested changesProject management plan updates
• Schedule management plan updates
Project calendar updates
Schedule Control
Schedule Management Plan
Schedule Baseline
Schedule network analysis
Critical path method
Schedule compression
What-if analysis
Resource leveling
Critical chain method
Project management software
Applying calendars
Adjustable leads and lags
Schedule model
Inputs
Outputs
Tools & Techniques
Performance reports
Schedule baseline updates
Requested changes
Activity Definition
Activity Sequencing
Activity Resource Estimating
Activity Duration Estimating
Schedule Development
Schedule Control
Approved Change Requests
Schedule model data updates
Performance measurements
Organizational process assets updates
Activity list updates
Recommended corrective actions
Activity attribute updatesProject Management Plan updates
Other Important Terms
• Lag – Inserted waiting time between tasks• Free Slack – Available delay time without
impacting start of successor• Total Slack – Amount of time a task can be
delayed without delaying project completion date
• Project Slack – Amount of time a project can be delayed without impacting completion dates imposed by client
• Crashing – Adding resources to critical path items to shorten schedule
• Fast Tracking – Performing critical path tasks in parallel rather than series
• Resource Leveling – Adjusting completion dates of tasks
Project Cost Management
Cost is a resource sacrificed or foregone to achieve a specific objective, or something given up in exchange.
Costs are usually measured in monetary units, such as dollars or Taka’s.
Project Cost Management includes the processes required to ensure that the project is completed within an approved budget.
Project Cost Management Processes
Cost estimating: Developing an approximation or estimate of the costs of the resources needed to complete a project.
Cost budgeting: Allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.
Cost control: Controlling changes to the project budget.
Basic Principles of Cost ManagementMost members of an executive board have a better understanding and are more interested in financial terms than IT terms, so IT project managers must speak their language.
Profits are revenues minus expenses.
Life cycle costing considers the total cost of ownership, or development plus support costs, for a project.
Cash flow analysis determines the estimated annual costs and benefits for a project and the resulting annual cash flow.Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars. Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms.Direct costs are costs that can be directly related to producing the products and services of the project. Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs.
Earned value ManagementThe earned value Management involves developing these key values for each schedule activity, work package, or control account:
Planned value (PV). PV is the budgeted cost for the work scheduled to be completed on an activity or WBS component up to a given point in time. Earned value (EV). EV is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period. Actual cost (AC). AC is the total cost incurred in accomplishing work on the schedule activity or WBS component during a given time period. This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV (e.g., direct hours only, direct costs only, or all costs including indirect costs). Cost variance (CV). CV equals earned value (EV) minus actual cost (AC). The cost variance at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. Formula: CV= EV - AC Schedule variance (SV). SV equals earned value (EV) minus planned value (PV). Schedule variance will ultimately equal zero when the project is completed because all of the planned values will have been earned. Formula: SV = EV - PV These two values, the CV and SV, can be converted to efficiency indicators to reflect the cost and schedule performance of any project. Cost performance index (CPI). A CPI value less than 1.0 indicates a cost overrun of the estimates. A CPI value greater than 1.0 indicates a cost underrun of the estimates. CPI equals the ratio of the EV to the AC. The CPI is the most commonly used cost-efficiency indicator. Formula: CPI = EV/AC Schedule performance index (SPI). The SPI is used, in addition to the schedule status to predict the completion date and is sometimes used in conjunction with the CPI to forecast the project completion estimates. SPI equals the ratio of the EV to the PV. Formula: SPI = EV/PV
Questions ?
Thank You !!