management brent fultz california institute of technology report from the baseline review project...
Post on 22-Dec-2015
213 views
TRANSCRIPT
Management Brent Fultz
California Institute of Technology
• Report from the Baseline Review
• Project Execution Plan
• Purpose of IDT
Baseline Review March 14, 2002, Caltech
• First of its kind for SNS IDTs -- Technical and Management Review
• Jim Richardson (Chm), Steve Bennington, Collin Broholm, Richard Boyce, Jon Kapustinsky, David Lichty, Toby Perring, Frans Trouw
• Report from Committee received Sept, 2002. Generally very favorable. – We agree with most of the points. – We began response immediately after the review.
• DOE (Iran Thomas) wants a written response before Dec. 1.
Issues from ARCS Baseline Review
• Detectors inside vacuum
• Shielding
• Moderator poison depth
• Disk chopper
• Soller Collimators
• Software Plan
• Project management
- Project Execution Plan- Memorandum of Agreement (Caltech-SNS)- Budget Authority- Role of IDT- Reporting Requirements
Budget Authority Profiles
0
2000
4000
6000
8000
10000
12000
14000
16000
0 10 20 30 40 50 60
Months from start
Cu
mu
lati
ve b
ud
get
k$
Proposed
DOE
9/2001 9/2006
Project Execution Plan -- Now a BES Requirement
Concept: Given that a project plan exists, how does it get executed?
• Who does what? responsibilities / authority
(mostly inter-institutional, some intra-institutional)
• select measures of progress, approvals, funding
• identifies policy documents (MOA, construction standards, IP, ES&H)
• technical baseline for scope, cost, schedule
• control of changes to baseline (cost, schedule, scope)
Project Execution Plan -- Advice from IDT
• ARCS IDT can help on:- Milestones- Control of Changes in Cost, Configuration, Schedule- Role of Executive Committee- Close of Project
• ARCS IDT should know about:- Budget Authority- MOA- Contingency management
Milestones Level 2
Division of Materials Sciences and Engineering Approval
• Software Baseline Design January, 2003 • Confirm Detector in Vacuum Design February, 2003 • Place Guide Procurement February, 2003 • Place Vacuum Vessel Procurement December, 2003 • Begin Installation August, 2004 • Software Beta Release March, 2005 • Software Release 1.0 January, 2006 • Operational Readiness Review April, 2006 • Complete Installation September, 2006 • Commissioning Completed November, 2006 • End ARCS Project November, 2006
Change Control Thresholds
DOE MSE Div. Change Control Board
Technical Changes in Key Parameters: Changes in Design Parameters - 2.5 m secondary flight path Not Affecting the Key Parameters: - detectors to 140o e.g., deletion of frame overlap chopper, - guide in primary flight path switching of Fermi choppers
Schedule Any Delay in Level 1 Milestone Any Delay in Level 1 or 2 Milestone
Cost Any Increase in Total Project Cost Any Increase >$k 75 at WBS Level 2
Contingency Management
What Is It?
Best guess estimate of ARCS hardware is 10 M$
We are allowing for up to 12 M$
ARCS contingency is 20 %
(calculated by summing contingencies on all 220 tasks in WBS)
20% is reasonable, but not large.
Project Execution Plan -- How is Contingency Managed?
Requirement -- No carryover of funds between budget periods.
Approach -- Budget everything we can within the budget period.
Optimistic -- Best estimate is that we should end up 20% ahead on
funds, perhaps ahead of schedule.
Enlarge scope of project later.
Pessimistic -- Less work completed than we thought.
Descope project later.
Comment: DOE expectation is on time and on budget
(neither below nor above)
Project Execution Plan -- How is Contingency Managed?
Problem -- Rate of spending is not arbitrary.
Possibilities:
- work with BES to change BA profile (issue in Review)
- phased funding of detector contract
- large commitments near boundaries of budget periods
- launder money through subcontracts to National Labs
Role of IDT
Past:
IDT was essential in preparing the proposal (large group)
Executive Committee: Fultz, Abernathy, McQueeney, Beyermann, Nagler?, Osborn
Change Control Board: Abernathy, Fultz, McQueeney, ?
Future:
Later, near end of ARCS project in 2006, IDT will • organize scientific program• negotiate for beamtime (maybe)• friendly users during commissioning, testing instrument and sample environments (Big role-- this may be 2 years)
Role of IDT
Present Problem:
How to engage the IDT during construction?
Secure funds for sample environments
Test single crystal goniometer on Pharos
Use Pharos data to test ARCS software
(maybe with LRMECS, HRMECS, Mari, MAPS)
Sign in CCCP Restaurant:
“It is an insult to tip the waiter” (bribe the IDT)
Waiter: “Go ahead sir, insult me.”
Project Closure
• Readiness Review in Early 2006 (safety)• Transition of Documentation• Transition to Operations• Expect a role for IDT during commissioning• Software Release for ARCS• Report Lessons Learned• ARCS project ends when money ends -- Nov. 2006
Post – Project
• Role of IDT in formulating inelastic PAC• Expect a Big role for IDT during commissioning• Software Distribution to SEQUOIA, CNCS• Hardware maintenance by SNS
both spectrometer and sample environment equip.
Doug will be at Oak Ridge• Software maintenance by SNS
maintain open-source coalition