Page 1: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3
Page 2: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

AJRT Regulating Tank 2x35.000m3 Areal View

Man Made River Project IV Phase - Ghadames Project

Page 3: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Al Jewaibyah Regulating Tank 2x35.000m3 Construction

Reservoir schematic overview

Page 4: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Sub-grade Verification Test

Standard Penetration Test (SPT)

Page 5: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Structural Fill

Structural Fill applied in layers over the sub-grade , level of achieved compaction determined over Field Density Test (FDT)

Page 6: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Plate Load Test

Conducted over the final layer of structural fill.

Page 7: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank - Structural Fill

Final layer of structural fill, compacted, leveled and ready for blinding concrete

Page 8: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Blinding Concrete

Blinding Concrete (Class C) Design: W=185kg/m3; Cement=300kg/m3; Agg=1.880kg/m3; Add=2.4kg/m3.

Page 9: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

AJRT Tank Bottom Slab

Formwork drawing - bottom slab plan

Page 10: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Base Slab - Corrosion Protection

2mm thick PE Sheeting between Blinding Concrete and Base Slab concrete as corrosion protection

Page 11: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Bottom Slab - Sections

Page 12: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Compressible Material

Extruded Polystyrene Type I (ASTM C578) laid on the top of Blinding Concrete (Class C)

Page 13: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Base Slab Reinforcement

Steel Reinforcing Works (ASTM A615):

-Ø>14mm GRADE 60, Yield Strength = 400MPa, deformed; -Ø=12mm GRADE 40, Yield Strength =280MPa, deformed; -Ø<12mm MILD Steel, Yield Strength =250MPa, round

Page 14: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Base Slab Formwork

RMD Kvikform Base Slab shutter with visible black corrosion protection (PE sheet) for later overlapping to vertical surface of the Reservoir wall.

Page 15: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Base Slab Formwork

RMD Kvikform, wall kicker 10cm height

Page 16: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant

New Batching Plant erected for supply of Regulating Tank concrete works

Page 17: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant

Page 18: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant & Cement Silos

Page 19: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant with Chiller, Silos,

Aggregate Separator

Page 20: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant Chiller

For regulation of concrete temperature in Saharan Desert climate. During the production, concrete temperature on delivery to the Site did not exceed 32°C although ambient temperature often reached 52°C.

Page 21: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant Controls

Page 22: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant

Automatic mixing & control

Page 23: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Batching Plant Aggregate Separators

Sand blowing for decrease of fine materials

Page 24: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Concrete Quality Control

Cylinder moulds for sampling of concrete

Page 25: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Fresh Concrete Quality Control - Workability

Slump Test

Page 26: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Fresh Concrete Quality Control –

Air Content

Page 27: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – Outlet Section Base

Slab Concrete

81nr of Base Slab modules (max width 15x15m). The sequential bay method of construction has been used with each consecutive bay having at least two adjacent free edges and not more than two adjacent edges continuous with previous bays

Page 28: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Concrete Works

Trowell of the Base Slab concrete surface, over applied curing compound BASF Masterkure 106D; SIKA

Page 29: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Base Slab Structural Concrete

Concrete Class A: (W=189kg/m3; C=386kg/m3; W/C=0.49 ; Agg=1.830kg/m3; Add=3,1kg/m3) Cement – Type II, ASTM C150; Additive BASF Lubricon L-200, BASF Melcret TB101 Type G

Page 30: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Construction Joints – Water Stop

SCP Ltd - 25x8mm Dual Seal Swellable Water Stop

Page 31: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Swellable Water Stop

SCP Ltd - 25x8mm Dual Seal Swellable Water Stop

Page 32: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Walls – Work Plan

Page 33: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Walls Formwork

RMD Kwikform Shuttering System

Page 34: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Walls Formwork

In total 55nr of Wall-segments installed with concrete, max modular wall-length = 15m’, height = 6.06m; width = 0.45m

Page 35: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Walls Formwork

Page 36: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Walls Concrete Installation

Page 37: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Construction Joint Base Slab / Walls /

Walls

SCP Ltd - 25x8mm Dual Seal Swellable Water Stop between each of 55nr modular wall-segments

Page 38: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Construction Joint Base Slab / Walls

SCP Ltd - 25x8mm Dual Seal Swellable Water Stop

Page 39: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Walls, Columns & Roof Slab - Sections

Page 40: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Columns Formwork

RMD Kwikform, Columns Ø400mm

Page 41: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Columns Formwork

RMD Kwikform Column-kickers

Page 42: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Columns (500nr)

500nr Columns Ø400mm Concrete Class A (W=189kg/m3; C=386kg/m3; W/C=0.49 ; Agg=1830kg/m3; Add=3.1kg/m3)

Page 43: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – Roof Slab Formwork

RMD Kwikform Scafffolding

Page 44: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Roof Slab - Sections

Page 45: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – Roof Slab Formwork

Page 46: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Partition Overflow

Wall

Partition Overflow Wall dividing Regulating Tank onto 2 separate Water Chambers (2x35.000m3)

Page 47: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Roof Slab Reinforcement Works

Access Manhole openings– DN600

Page 48: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Roof Slab Reinforcement Works

81nr of Roof Slab modules (max width 15x15m), with 25x8mm Dual Seal Swellable Water Stop in construction joint between each slab

Page 49: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Roof Slab Concrete Installation

Roof Slab d=300mm; Concrete Class A (W=189kg/m3; C=386kg/m3; W/C=0.49 ; Agg=1830kg/m3; Add=3.1kg/m3) Cement – Type II, ASTM C150; Additive BASF Lubricon L-200, BASF MELCRET TB101 Type G

Page 50: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank View during construction

Page 51: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Roof Slab

Survey verification of Roof Slab plywood formwork (behind visible tower-crane and concrete pouring of columns)

Page 52: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab

Reservoir height bottom to roof slab -6,06m, 500nr columns, 81nr base slab, 81nr roof slab modules (max width 15x15m), with 25x8mm Dual Seal Swellable Water Stop in construction joint between each slab

Page 53: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab

The sequential bay method of construction has been used with each consecutive bay having at least two adjacent free edges and not more than two adjacent edges continuous with previous bays

Page 54: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Access Manhole

Sealing of Tie-rod holes, finishing works remaining

Page 55: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Outlet Shafts & Overflow

Page 56: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Outlet Shafts & Overflow

Page 57: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Overflow Pipe

Penetration

Overflow Steel DN1600mm Pipe Nozzle (25x8mm Dual Seal Swellable Water Stop & elastic sealing 2x1.5cm)

Page 58: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – Overflow Pipe Wall

Closure of Wall Shutter

Page 59: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Overflow Pipe

Shutter gaps sealing, centering of the Steel DN1600 Pipe elevation

Page 60: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Shaft 1

Outlet Shaft with Steel DN1400mm Pipe

Page 61: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Shaft 2

Reinforcement Works on Outlet Shaft 2 with Steel DN1400mm Pipe

Page 62: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Outlet Shaft 1

Formworks

Page 63: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Outlet Shaft 1

Concrete Installation

Page 64: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Outlet Shaft 1

Page 65: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet & Drain Shaft

Page 66: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet & Drain Shaft

Page 67: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet Section – Integrated Surge Shaft

Regulating Tank Partition Wall visible at the back

Page 68: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Inlet & Surge Shaft

Inlet Pipes Steel DN1200mm

Page 69: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet & Tank Integrated Surge Shaft

Steel DN1200 Pipes

Page 70: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet Surge Shaft with Inlet DN1200 pressure

pipes

Wall’s reinforcement works, pipe nozzles positioning and anchoring in progress

Page 71: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Surge Shaft Wall Formworks

Page 72: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Surge Shaft

Page 73: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Surge Shaft Corrosion Protection

All buried concrete surfaces in contact with soil are protected by Coal Tar Epoxy coating, average dry film thickness 150 microns to give overall dry film thickness of 450microns. Underside of bottom slab protected by 2 PE sheets with friction coefficient <0.1

Page 74: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet Surge Shaft – Tank’s Base Slab gap

To be filled with Soil cement.

Page 75: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Surge Shaft – Compressible Material

Corrosion Protection: AmerCoat 78 HBB Resin Black + Cure (1:4); DoeCote 1080H + DoeClean 1080 (1:4)

Page 76: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Surge Shaft – Compressible Material

Corrosion Protection: -Compressible material – Polystyrene 5cm -- 3nr layers of Coal tar Epoxy (min 450 microns)

Page 77: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet Surge Shaft Soil Cement filling

Soil Cement Mix Design: W=300kg/m3; Cement = 140kg/m3 (5% of Soil mass); W/C=2.1; Agg=1760kg/m3; Add=0.44kg/m3

Page 78: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Tank’s Integrated Surge Shaft – Soil

Cement filling

Slump = 5 - 15cm; Minimal 7-days strength = 0.7MPa

Page 79: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Integrated Surge Shaft, Partition Wall between

Water Chambers

Page 80: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Inlet side overview

Page 81: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Overview during

construction

Page 82: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Drain Shaft – Reservoir

Sump

Base Slab reinforcement works, Drain Steel Pipe DN250mm, Sump (750x750x300mm)

Page 83: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Drain Steel Pipe DN250mm Wall

Penetration

Pipe nozzle wall penetration, swellable water stop, elastic sealant for prevention of water leakage.

Page 84: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Drain Shaft – Tank’s Sump

Internal Expansion Joint with Water Stop between Reservoir Sump and Drain Shaft

Page 85: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Drain Shaft – Tank’s Sump

Internal Expansion Water-Stop (400mm) left for connection with Drain Shaft

Page 86: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank view during

construction works

Page 87: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank view during construction

Supporting Tower Crane, Batching Plant Silos visible on the right side

Page 88: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Inlet Overflow Weir Wall

Height of Weir (Overflow Wall) top 50cm lower than Roof Slab bottom

Page 89: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Corner Walls

The sequential bay method of construction has been used with each consecutive bay having at least two adjacent free edges and not more than two adjacent edges continuous with previous bays

Page 90: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank View

Page 91: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Section View

Page 92: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Details

Page 93: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Details

Page 94: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab

Maintenance Opening 3x3m

Page 95: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab

Maintenance Opening 3x3m

Page 96: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab Maintenance

Opening 3x3m

View from inside of the tank

Page 97: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Roof Slab Works

Inlet Overflow Weir Wall visible on left side

Page 98: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Shaft 2

Assembling of Steel Pipes DN1400

Page 99: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Shaft 2

Welding of DN1400 Steel Pipes in protected environment. Reservoir Overflow DN1600 Steel Pipe visible on upper left side

Page 100: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Section

Outlet DN1400 Steel Pipes aligned and welded. Reservoir Overflow DN1600 Steel Pipe visible on upper left side

Page 101: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Piping DN1400

View towards downstream Pump Station

Page 102: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet Pipe – towards Pump

Station

Page 103: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet View

Steel DN1400 Pipes, Outlet Shafts Walls Reinforcement works visible

Page 104: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Inlet Section Shafts

Transition from DN1600 PCCP (Pre-stressed Concrete Cylinder Pipes) to DN1200 Steel Pipes

Page 105: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank View

Page 106: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet with Overflow

Discharge

Page 107: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet with Overflow

Discharge

Page 108: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank Outlet with Overflow

Discharge

Page 109: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Overflow Discharge

Page 110: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – on First Water

First Water on 4th November 2009

Page 111: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – on First Water

First Water on 4th November 2009

Page 112: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank – on First Water

First Water on 4th November 2009

Page 113: Man Made River Project IV Phase - Ghadames Project - AJRT Regulating Tank 70.000m3

Regulating Tank on First Water

First Water on 4th November 2009