mall expansion project

50
Engineering Design & Development CITY -BALIWAG EXPANSION AS OF OCTOBER 15, 2014

Upload: engr-m-eguia-phd

Post on 08-Aug-2015

32 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

CITY -BALIWAG EXPANSION

AS OF OCTOBER 15, 2014

Page 2: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

I. PERMITS/CLEARANCES

ITEM STATUS

1.0 Traffic Study SECURED

2.0 ECC SECURED

3.0 Barangay Clearance SECURED

4.0 Building Permits / Clearances

ALL SECURED

Page 3: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

II. OVER-ALL PROJECT STATUS Milestone Dates

Construction Day One (Site Development) – January 07, 2014

Construction Day One (Building) - March 07, 2014

Start of Fit-out Works - August 11, 2014

Concrete Topping Off(Flat Slab) - August 31, 2014

Tenant Preview - August 20, 2014

Concrete Topping Off (Ramp) - September 07, 2014

Water Tightness (Mall) - October 15, 2014

Tenant Turn over (Batch Plan No. 01) - September 30, 2014

Project Completion - October 31, 2014

Energization (New EMB) - November 20, 2014

Page 4: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

• Project Status

Page 5: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

OVER-ALL PROJECT STATUS AS OF OCTOBER 15, 2014

Previous Projected

(As of October 09, 2014) Prev. Actual Projected to Date Actual to Date Variance

Equivalent in

Days

89.15% 87.53% 92.15% 89.80% -2.35% Two (2) days

Delayed

Page 6: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

BREAKDOWN OF OVER-ALL PROJECT STATUS AS OF OCTOBER 15, 2014

Previous Projected (As of October 02, 2014)

Prev. Actual Projected to Date Actual to Date Variance

General Contractor (Concreting Works)

100.00% 100.00% 100.00% 100.00% 0.00%

Architectural Works 63.00% 62.00% 65.25% 64.00% -1.25%

Sanitary/Plumbing 79.30% 79.30% 82.40% 82.40% 0.00%

Fire Protection 68.60% 68.60% 71.80% 71.80% 0.00%

Mechanical 64.76% 64.14% 68.80% 68.10% -0.70%

Electrical 67.40% 67.40% 70.95% 70.55% 0.40%

Page 7: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS (4TH FLOOR)

Page 8: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESSPHOTOS MASONRY WORK

Last Week This Week

Page 9: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESSPHOTOS Installed Glass Framing at

BPO (3rd Floor Area)

Installed Glass @

Ground Floor Area

Status of Delivery - 100.00%

Status of Installed IGU – 60%

Page 10: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS – (RAMP AREA)

Concreted Roof beam

@ Helical Ramp

Page 11: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS – INSTALLED PRECAST FIN

Last Week This Week

Page 12: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Installed Drainage Pipe at Roof

Deck Installed Gate Valve for Tenant

Requirement

Page 13: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Completion of Roughing-ins for Main

Power Feederline and Telephone at Roof

Deck

Completion of Roughing-ins for

Lightings, Power and Tenant Feederlines

Page 14: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Completion of Droppings for

Lightings at Mall Area

Page 15: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Ongoing Wiring for Telephone and Data

Provisions

Installation of Intermediate Distribution

Frame (IDF)

Page 16: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

On-going Installation of Chilled

Water Pipes

Dropping of Sprinkler Heads at Ground

and Second Floor (Tenant Area)

On-going Installation of Supply and Kitchen Exhaust Duct

Page 17: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

On-going Installation of Metal Furring and Ceiling

Boards at Ground Floor Mall Area

Page 18: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

On-going Installation of Metal Furring and Ceiling Boards

at 2nd Floor Mall Area

Page 19: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Installed Escalator 1 & 2

Page 20: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Installed Gypsum Board @ 2nd Floor

Page 21: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

On-going installation of Floor Tiles at Ground Floor

Page 22: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

On-going installation of Floor Tiles at 2nd Floor

Page 23: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Waterproofing @ 4th Floor

Page 24: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Installed Roof sheet at Canopy

Page 25: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

EMB RETROFITTING WORKS

Stressed Tendons

@ Genset Room

Stressed Tendons

@ Chiller Room

Stressed Tendons

@ Sub-station

Stressed Tendons

@ Girder

Page 26: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROGRESS PHOTOS

Installed I-Columns and I-Beams at EMB

Page 27: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

MECHANICAL WORKS – (68.10%)

GROUND FLOOR : CHILLED WATER PIPE SECOND FLOOR : CHILLED WATER PIPE

Page 28: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

ELECTRICAL WORKS – (70.55%)

Ground Floor : Ongoing Wiring for Lightings

Second Floor : Ongoing Wiring for Lightings

Page 29: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Ground Floor : Ongoing Wiring for Power Provision and Convenience Outlets

ELECTRICAL WORKS – (70.55%)

Second Floor : Ongoing Wiring for Power Provision and Convenience Outlets

Page 30: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Second Floor : Ongoing Wiring for Fire Detection & Alarm System

FIRE DETECTION & ALARM SYSTEM WORKS – (71.00%)

Ground Floor : Ongoing Wiring for Fire Detection & Alarm System

Page 31: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Ground Floor : Installed Roughing-ins for Structured Cabling

Second Floor : Installed Roughing-ins for Structured Cabling

STRUCTURED CABLING WORKS – (61.00%)

Page 32: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Second Floor : Water Supply Distribution System Layout

Ground Floor: Water Supply Distribution System Layout

SANITARY /PLUMBING WORKS - (82.40%)

Page 33: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Fourth Floor : Water Supply Distribution System Layout

Third Floor: Water Supply Distribution System Layout

SANITARY /PLUMBING WORKS - (82.40%)

Page 34: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Second Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout

Ground Floor : Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout

SANITARY /PLUMBING WORKS - (82.40%)

Page 35: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

SANITARY /PLUMBING WORKS - (82.40%)

Fourth Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout

Third Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout

Page 36: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

FIRE PROTECTION WORKS – (71.80%)

Second Floor : Installation of Crossmain and

Branchline Ground Floor: Installation of Branchline

Page 37: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

FIT-OUT WORKS

Second Floor : Ground Floor:

Cyberzone Fit-Out Works

(69.10%)

Mall Fit-Out Works

(45.00%)

Page 38: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

TILE WORKS – (55.00%)

Second Floor : Installed Tiles at Mall Area Ground Floor: Installed Tiles at Mall Area

Page 39: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

RETROFITTING WORKS (45.01%)

Page 40: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

III. DESIGN ISSUES RFI/RFA

ITEMS/ DESCRIPTION ATTN DATE ISSUED DATED NEEDED STATUS

A. STRUCTURAL WORKS

1.0 RFI-ST-036 – Seismic Gap between Partition of Existing Mall & Mall Expansion

JSLA 9-21-14 October 16, 2014

2.0 RFI-ST-040 – Structural Details of Stair at EMB JSLA 9-21-14 October 16, 2014 RESOLVED

3.0 RFA-ST-019 – Proposed Location of CHB Wall Partition @ AHU room due to conflict of Exhaust Duct & Kitchen Supply Duct Block out & Riser

JSLA 10-14-14 October 16, 2014

B. ARCHITECTURAL WORKS

1.0 RFI-AR-036 – Finish of Ramp Slab Soffit Parapet Wall (Ramp) & 4th floor Parking

JSLA 9-21-14 October 16, 2014 RESOLVED

2.0 RFI-AR-037 – Elevation details of EE Room & Telco Rooms at 4th Floor Roof Deck

JSLA 9-23-14 October 15, 2014 RESOLVED

3.0 RFI-AR-044– Provide schedule of the following for New EMB - Doors – Cyclone wire partition JSLA 10-14-14 October 15, 2014 RESOLVED

Page 41: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

Phase 1

GENERAL WORK SCHEDULE

Phase 2

BIDDING and AWARD STATUS

Phase 3

SITE DEV’T WORKS

Phase 4 CONSTRUCTION

PHASE

Page 42: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

IV. PROCUREMENT (OSM)

REBARS Overall Rebars Requirements (kgs.) = 2,341,166.43kgs Delivered On Site = 1,932,394.89 kgs Balance Remaining = 58,771.54 kgs CEMENT IN BULK Overall Estimated Cement Requirements (Bags) = 311,100.00 Bags Delivered On Site = 280,000.00 Bags Balance Remaining = 31,100.00 Bags CEMENT IN BAGS Overall Estimated Cement Requirements (Bags) = 21,000.00 Bags Delivered On Site = 8,500.00 Bags Balance Remaining = 12,500.00 Bags

Page 43: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

(RETROFITTING WORKS)

IV. STATUS UPDATE AT EXISTING EMB CIVIL / ARCHITECTURAL WORKS

Page 44: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

TIMELINE OF

FIT-OUT WORKS

Page 45: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

CYBERZONE SCHEDULE

Page 46: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

MALL SCHEDULE

Page 47: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

SUMMARY OF

PROJECT COST REPORT

Page 48: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROJECT COST REPORT

Page 49: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

PROJECT COST REPORT

Page 50: Mall Expansion Project

Engineering

Design &

Development

Engineering

Design &

Development

CITY -BALIWAG EXPANSION

THANK YOU