mall expansion project

Click here to load reader

Post on 08-Aug-2015

25 views

Category:

Documents

1 download

Embed Size (px)

TRANSCRIPT

  1. 1. Engineering Design & Development Engineering Design & Development CITY -BALIWAG EXPANSION AS OF OCTOBER 15, 2014
  2. 2. Engineering Design & Development Engineering Design & Development I. PERMITS/CLEARANCES ITEM STATUS 1.0 Traffic Study SECURED 2.0 ECC SECURED 3.0 Barangay Clearance SECURED 4.0 Building Permits / Clearances ALL SECURED
  3. 3. Engineering Design & Development Engineering Design & Development II. OVER-ALL PROJECT STATUS Milestone Dates Construction Day One (Site Development) January 07, 2014 Construction Day One (Building) - March 07, 2014 Start of Fit-out Works - August 11, 2014 Concrete Topping Off(Flat Slab) - August 31, 2014 Tenant Preview - August 20, 2014 Concrete Topping Off (Ramp) - September 07, 2014 Water Tightness (Mall) - October 15, 2014 Tenant Turn over (Batch Plan No. 01) - September 30, 2014 Project Completion - October 31, 2014 Energization (New EMB) - November 20, 2014
  4. 4. Engineering Design & Development Engineering Design & Development Project Status
  5. 5. Engineering Design & Development Engineering Design & Development OVER-ALL PROJECT STATUS AS OF OCTOBER 15, 2014 Previous Projected (As of October 09, 2014) Prev. Actual Projected to Date Actual to Date Variance Equivalent in Days 89.15% 87.53% 92.15% 89.80% -2.35% Two (2) days Delayed
  6. 6. Engineering Design & Development Engineering Design & Development BREAKDOWN OF OVER-ALL PROJECT STATUS AS OF OCTOBER 15, 2014 Previous Projected (As of October 02, 2014) Prev. Actual Projected to Date Actual to Date Variance General Contractor (Concreting Works) 100.00% 100.00% 100.00% 100.00% 0.00% Architectural Works 63.00% 62.00% 65.25% 64.00% -1.25% Sanitary/Plumbing 79.30% 79.30% 82.40% 82.40% 0.00% Fire Protection 68.60% 68.60% 71.80% 71.80% 0.00% Mechanical 64.76% 64.14% 68.80% 68.10% -0.70% Electrical 67.40% 67.40% 70.95% 70.55% 0.40%
  7. 7. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS (4TH FLOOR)
  8. 8. Engineering Design & Development Engineering Design & Development PROGRESSPHOTOS MASONRY WORK Last Week This Week
  9. 9. Engineering Design & Development Engineering Design & Development PROGRESSPHOTOS Installed Glass Framing at BPO (3rd Floor Area) Installed Glass @ Ground Floor Area Status of Delivery - 100.00% Status of Installed IGU 60%
  10. 10. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS (RAMP AREA) Concreted Roof beam @ Helical Ramp
  11. 11. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS INSTALLED PRECAST FIN Last Week This Week
  12. 12. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Installed Drainage Pipe at Roof Deck Installed Gate Valve for Tenant Requirement
  13. 13. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Completion of Roughing-ins for Main Power Feederline and Telephone at Roof Deck Completion of Roughing-ins for Lightings, Power and Tenant Feederlines
  14. 14. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Completion of Droppings for Lightings at Mall Area
  15. 15. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Ongoing Wiring for Telephone and Data Provisions Installation of Intermediate Distribution Frame (IDF)
  16. 16. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS On-going Installation of Chilled Water Pipes Dropping of Sprinkler Heads at Ground and Second Floor (Tenant Area) On-going Installation of Supply and Kitchen Exhaust Duct
  17. 17. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS On-going Installation of Metal Furring and Ceiling Boards at Ground Floor Mall Area
  18. 18. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS On-going Installation of Metal Furring and Ceiling Boards at 2nd Floor Mall Area
  19. 19. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Installed Escalator 1 & 2
  20. 20. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Installed Gypsum Board @ 2nd Floor
  21. 21. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS On-going installation of Floor Tiles at Ground Floor
  22. 22. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS On-going installation of Floor Tiles at 2nd Floor
  23. 23. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Waterproofing @ 4th Floor
  24. 24. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Installed Roof sheet at Canopy
  25. 25. Engineering Design & Development Engineering Design & Development EMB RETROFITTING WORKS Stressed Tendons @ Genset Room Stressed Tendons @ Chiller Room Stressed Tendons @ Sub-station Stressed Tendons @ Girder
  26. 26. Engineering Design & Development Engineering Design & Development PROGRESS PHOTOS Installed I-Columns and I-Beams at EMB
  27. 27. Engineering Design & Development Engineering Design & Development MECHANICAL WORKS (68.10%) GROUND FLOOR : CHILLED WATER PIPE SECOND FLOOR : CHILLED WATER PIPE
  28. 28. Engineering Design & Development Engineering Design & Development ELECTRICAL WORKS (70.55%) Ground Floor : Ongoing Wiring for Lightings Second Floor : Ongoing Wiring for Lightings
  29. 29. Engineering Design & Development Engineering Design & Development Ground Floor : Ongoing Wiring for Power Provision and Convenience Outlets ELECTRICAL WORKS (70.55%) Second Floor : Ongoing Wiring for Power Provision and Convenience Outlets
  30. 30. Engineering Design & Development Engineering Design & Development Second Floor : Ongoing Wiring for Fire Detection & Alarm System FIRE DETECTION & ALARM SYSTEM WORKS (71.00%) Ground Floor : Ongoing Wiring for Fire Detection & Alarm System
  31. 31. Engineering Design & Development Engineering Design & Development Ground Floor : Installed Roughing- ins for Structured Cabling Second Floor : Installed Roughing- ins for Structured Cabling STRUCTURED CABLING WORKS (61.00%)
  32. 32. Engineering Design & Development Engineering Design & Development Second Floor : Water Supply Distribution System Layout Ground Floor: Water Supply Distribution System Layout SANITARY /PLUMBING WORKS - (82.40%)
  33. 33. Engineering Design & Development Engineering Design & Development Fourth Floor : Water Supply Distribution System Layout Third Floor: Water Supply Distribution System Layout SANITARY /PLUMBING WORKS - (82.40%)
  34. 34. Engineering Design & Development Engineering Design & Development Second Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout Ground Floor : Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout SANITARY /PLUMBING WORKS - (82.40%)
  35. 35. Engineering Design & Development Engineering Design & Development SANITARY /PLUMBING WORKS - (82.40%) Fourth Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout Third Floor: Sewer, Waste and Vent System Layout, Storm Drainage and FCU/AHU System Layout
  36. 36. Engineering Design & Development Engineering Design & Development FIRE PROTECTION WORKS (71.80%) Second Floor : Installation of Crossmain and BranchlineGround Floor: Installation of Branchline
  37. 37. Engineering Design & Development Engineering Design & Development FIT-OUT WORKS Second Floor :Ground Floor: Cyberzone Fit-Out Works (69.10%) Mall Fit-Out Works (45.00%)
  38. 38. Engineering Design & Development Engineering Design & Development TILE WORKS (55.00%) Second Floor : Installed Tiles at Mall AreaGround Floor: Installed Tiles at Mall Area
  39. 39. Engineering Design & Development Engineering Design & Development RETROFITTING WORKS (45.01%)
  40. 40. Engineering Design & Development Engineering Design & Development III. DESIGN ISSUES RFI/RFA ITEMS/ DESCRIPTION ATTN DATE ISSUED DATED NEEDED STATUS A. STRUCTURAL WORKS 1.0 RFI-ST-036 Seismic Gap between Partition of Existing Mall & Mall Expansion JSLA 9-21-14 October 16, 2014 2.0 RFI-ST-040 Structural Details of Stair at EMB JSLA 9-21-14 October 16, 2014 RESOLVED 3.0 RFA-ST-019 Proposed Location of CHB Wall Partition @ AHU room due to conflict of Exhaust Duct & Kitchen Supply Duct Block out & Riser JSLA 10-14-14 October 16, 2014 B. ARCHITECTURAL WORKS 1.0 RFI-AR-036 Finish of Ramp Slab Soffit Parapet Wall (Ramp) & 4th floor Parking JSLA 9-21-14 October 16, 2014 RESOLVED 2.0 RFI-AR-037 Elevation details of EE Room & Telco Rooms at 4th Floor Roof Deck JSLA 9-23-14 October 15, 2014 RESOLVED 3.0 RFI-AR-044 Provide schedule of the following for New EMB - Doors Cyclone wire partition JSLA 10-14-14 October 15, 2014 RESOLVED
  41. 41. Engineering Design & Development Engineering Design & Development Phase 1 GENERAL WORK SCHEDULE Phase 2 BIDDING and AWARD STATUS Phase 3 SITE DEVT WORKS Phase 4 CONSTRUCTION PHASE
  42. 42. Engineering Design & Development Engineering Design & Development IV. PROCUREMENT (OSM) REBARS Overall Rebars Requirements (kgs.) = 2,341,166.43kgs Delivered On Site = 1,932,394.89 kgs Balance Remaining = 58,771.54 kgs CEMENT IN BULK Overall Estimated Cement Requirements (Bags) =