Making Greenways Greener: Developing a Sustainable Trail in
Ramsey County
Ramsey County 2007 Lower Afton Road Trail Project
By Commissioner Victoria Reinhardt
andBridget Beck
![Page 2: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/2.jpg)
Deciding to Build a Green TrailPolicy Background
• Citizens want a trail for Bike and Ped Safety
• Parks and Corrections own the land
• Segment is short and is a vital connection for the East Metro trail system.
![Page 3: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/3.jpg)
Waste Shingles as a Resource
• Shingles are 15.2% of Construction and Demolition Waste (2006)
• 300,000 Tons of Roofing Waste per Year
• 20% of Demolition Landfill Space. (2004)
• 91% of Residential Roofing Waste is Asphalt Shingles
![Page 4: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/4.jpg)
Collaboration for Results
• Recognizing the role that everyone plays
• Public health has the material
• Public Works has a potential market
• Parks has a project to help demonstrate the use of post consumer tear off shingles.
![Page 5: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/5.jpg)
Project Overview
• Project Consisted of Utilizing Recycled Products– Tear Off Shingles in Bituminous Mix– Recycled Plastics in Retaining Wall – Recycled Plastic/Rubber Pavers– Class 7 Aggregate (“gravel”) base– Reuse of sand in Rain Gardens– Benches have recycled plastics– Utilizing natural soil erosion material– HDPE Pipe– Natural Products
![Page 6: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/6.jpg)
Bituminous Pavement Design
• Project was State Aid approved
• Mn/DOT Engineered HMA Spec.– Early involvement of Mn/DOT– County required 5% tear off shingles!– Option to have RAP – Utilized type PG 58-28 virgin asphalt binder oil– Minimum of 70% virgin asphalt binder in mix
![Page 7: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/7.jpg)
LAT Project RAS Spec
– Shingles shall be ½-inch minus– Free of nails, other metal, plastic, wood, glass,
other debris (less than 0.5 percent)– County to approved plans for:
• Where to source the tear-off shingles supplies
• How debris will be sorted out from shingles
![Page 8: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/8.jpg)
LAT Project RAS Spec(continued)
– Suppilers written certification that the shingles are in compliance
– County and Mn/DOT staff shall inspect recycling operations
– Samples of final RAS product shall be provided to County and Mn/DOT
![Page 9: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/9.jpg)
Source of Sorted Shingles
• 75% sorted on site at the roofing job– J Zac, Inc. roofing company– Hauled by Veit– Minor contamination
• 25% supplied from transfer station– Veit Industries– Minimal contamination
![Page 10: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/10.jpg)
![Page 11: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/11.jpg)
![Page 12: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/12.jpg)
![Page 13: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/13.jpg)
Omann’s Grinding Process: Phase I
• Ground to 8” minus
• Removed 95% of nails
• Removed most of the remaining contamination
![Page 14: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/14.jpg)
![Page 15: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/15.jpg)
![Page 16: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/16.jpg)
![Page 17: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/17.jpg)
![Page 18: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/18.jpg)
Omann’s Grinding Process: Phases II and III
• Removed remaining nails• Removed all metallic material• Ground shingles to a very fine consistency
7/16 – inch minus• Provided very clean product
to Midwest Asphalt
![Page 19: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/19.jpg)
![Page 20: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/20.jpg)
![Page 21: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/21.jpg)
• Utilized oil in shingles as partial replacement of virgin asphalt oil
• Used recycled shingles at 5% in place of recycled asphalt pavement (RAP)
Bituminous Supplier & Installer:Midwest Asphalt
![Page 22: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/22.jpg)
![Page 23: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/23.jpg)
![Page 24: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/24.jpg)
![Page 25: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/25.jpg)
![Page 26: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/26.jpg)
Project Notes
• Normal request for bids– Multiple bidders
• Supports MN/DOT tear-off research
• Technical feasibility not economic costs and benefits– Savings on asphalt binder
![Page 27: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/27.jpg)
Concerns/Lessons Learned With Tear off Shingles
• Warm weather• Wind• Ground Shingle stockpile - tacky• HMA – tacky
![Page 28: Making Greenways Greener: Developing a Sustainable Trail in Ramsey County Ramsey County 2007 Lower Afton Road Trail Project By Commissioner Victoria Reinhardt](https://reader036.vdocuments.mx/reader036/viewer/2022070111/5515727655034691418b511d/html5/thumbnails/28.jpg)
Making Greenways Greener: Developing a Sustainable Trail in
Ramsey County
Presenters:Ramsey County Commissioner
Victoria Reinhart – 651-266-8363Bridget Beck – 651-266-7121