major project request...major project request 2019 - 21 biennium 09/08/2020 uwosh - 19g2t - heating...

9
Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 1 of 4 Agency Institution Facility ID Facility Name University of Wisconsin Oshkosh 285-0F-0061 Heating Plant Project ID Project Title 19G2T Heating Plant Chiller & Cooling Tower Replacement Project Intent This project provides investigation and research, pre-design, and design services in accordance with the DFDM Consultant Policy & Procedure Manual to fully build out a 4,200-ton chilled water plant by replacing the smallest chiller machine and its associated cooling tower. The chilled water plant, machines, controls, and piping will be evaluated to identify deficiencies, develop design solution alternatives, and recommend appropriate corrective measures. Project Description and Scope Project work includes replacing the 450-ton centrifugal chiller with associated cooling tower, pumps, piping, valves, controls, motors, and electrical service with a new 1,400-ton chiller and cooling tower. The new chiller unit and controls will be connected to and integrated with the existing chiller machines and controls to work in tandem. The expanded central chilled water plant will provide adequate capacity for all 22 buildings and/or building wing additions and 1,752,963 GSF connected. Background The chilled water plant addition (98179) was originally designed for the installation of three 1,400-ton chiller machines. The original plant was established in 1998 with two units and a combined 1,850-ton capacity. A direct-buried piping system was installed for the distribution of chilled water to campus facilities. Those initial facilities included Arts and Communications, Halsey Science Center and Reeve Memorial Union. This initial project installed one new 1,400-ton electric centrifugal water chiller and one refurbished 450-ton unit taken out of service at UW-Whitewater. In 2004, the chilled water plant was upgraded to its current 2,800-ton capacity (04H1S) by installing a second 1,400-ton chiller. Piping was extended to an additional five buildings where the existing chillers were 30 years old, past their life expectancy, and used regulated refrigerants (CFC an CHFS). These facilities included Clow Social Science Center/Nursing Education, Dempsey Hall, Elmwood Commons, Polk Library, and Swart Hall. From start-up of the expanded plant, there were leaks. Extensive repairs were completed in 2003, but these repairs failed to fully resolve the problems. Additional repairs were completed on the 450-ton cooling tower and both 1,400-ton cooling towers were replaced, with the expectation that the plant would be able to produce 3,250-tons of capacity. The chilled water system piping completed under the previous cooling towers replacement (12B2Q) project was designed and sized to facilitate this planned upgrade in capacity. This project was enumerated in 2019 Wisconsin Act 9 as one of five components in the combined systemwide utility repairs, renovations, and replacements request. Analysis of Need and Project Justification Buildings located on all of the UW System campuses are served by a variety of utilities, which are critical to their operation, and have a replacement value in the hundreds of millions of dollars. Repair, renovation, and replacement of these systems is a constant process requiring a substantial and consistent investment. Routine maintenance is supported by the operating budget. In addition, each biennium the UW system identifies critical repair and renovation projects to be funded through the capital budget, as well as replacements for systems beyond their expected service life and/or where repairs are no longer feasible. This proposed scope of work is considered to be the most efficient, practical, and economically justifiable to meet present and future needs of UW-Oshkosh. A campuswide central utility master plan was completed in 2010 and during the design process for the recent Fletcher Hall addition and renovation, the master plan conclusions and load demand data were updated to include the recent additions of Sage Hall and the Horizon Village, which reflected a total campus load of 3,093 tons. The Fletcher Hall addition and renovation added an additional 283 tons of load to the already overloaded chilled water system. The installation of a third chiller will allow several additional facilities to be connected including Albee Hall, Donner Hall, Evans Hall, Harrington Hall, Kolf Physical Education, and Stewart Hall.

Upload: others

Post on 29-Nov-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration

Major Project Request 2019 - 21 Biennium

09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 1 of 4

Agency Institution Facility ID Facility Name University of Wisconsin Oshkosh 285-0F-0061 Heating Plant

Project ID Project Title 19G2T Heating Plant Chiller & Cooling Tower Replacement

Project Intent

This project provides investigation and research, pre-design, and design services in accordance with the DFDM Consultant Policy & Procedure Manual to fully build out a 4,200-ton chilled water plant by replacing the smallest chiller machine and its associated cooling tower. The chilled water plant, machines, controls, and piping will be evaluated to identify deficiencies, develop design solution alternatives, and recommend appropriate corrective measures.

Project Description and Scope

Project work includes replacing the 450-ton centrifugal chiller with associated cooling tower, pumps, piping, valves, controls, motors, and electrical service with a new 1,400-ton chiller and cooling tower. The new chiller unit and controls will be connected to and integrated with the existing chiller machines and controls to work in tandem. The expanded central chilled water plant will provide adequate capacity for all 22 buildings and/or building wing additions and 1,752,963 GSF connected.

Background

The chilled water plant addition (98179) was originally designed for the installation of three 1,400-ton chiller machines. The original plant was established in 1998 with two units and a combined 1,850-ton capacity. A direct-buried piping system was installed for the distribution of chilled water to campus facilities. Those initial facilities included Arts and Communications, Halsey Science Center and Reeve Memorial Union. This initial project installed one new 1,400-ton electric centrifugal water chiller and one refurbished 450-ton unit taken out of service at UW-Whitewater. In 2004, the chilled water plant was upgraded to its current 2,800-ton capacity (04H1S) by installing a second 1,400-ton chiller. Piping was extended to an additional five buildings where the existing chillers were 30 years old, past their life expectancy, and used regulated refrigerants (CFC an CHFS). These facilities included Clow Social Science Center/Nursing Education, Dempsey Hall, Elmwood Commons, Polk Library, and Swart Hall. From start-up of the expanded plant, there were leaks. Extensive repairs were completed in 2003, but these repairs failed to fully resolve the problems. Additional repairs were completed on the 450-ton cooling tower and both 1,400-ton cooling towers were replaced, with the expectation that the plant would be able to produce 3,250-tons of capacity. The chilled water system piping completed under the previous cooling towers replacement (12B2Q) project was designed and sized to facilitate this planned upgrade in capacity. This project was enumerated in 2019 Wisconsin Act 9 as one of five components in the combined systemwide utility repairs, renovations, and replacements request.

Analysis of Need and Project Justification

Buildings located on all of the UW System campuses are served by a variety of utilities, which are critical to their operation, and have a replacement value in the hundreds of millions of dollars. Repair, renovation, and replacement of these systems is a constant process requiring a substantial and consistent investment. Routine maintenance is supported by the operating budget. In addition, each biennium the UW system identifies critical repair and renovation projects to be funded through the capital budget, as well as replacements for systems beyond their expected service life and/or where repairs are no longer feasible. This proposed scope of work is considered to be the most efficient, practical, and economically justifiable to meet present and future needs of UW-Oshkosh. A campuswide central utility master plan was completed in 2010 and during the design process for the recent Fletcher Hall addition and renovation, the master plan conclusions and load demand data were updated to include the recent additions of Sage Hall and the Horizon Village, which reflected a total campus load of 3,093 tons. The Fletcher Hall addition and renovation added an additional 283 tons of load to the already overloaded chilled water system. The installation of a third chiller will allow several additional facilities to be connected including Albee Hall, Donner Hall, Evans Hall, Harrington Hall, Kolf Physical Education, and Stewart Hall.

Page 2: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration

Major Project Request 2019 - 21 Biennium

09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 2 of 4

Department of Residence Life and Conferencing Services utilizes all of the campus residence halls during the summer to house camps, conferences and attendees to the major events in the City of Oshkosh including Experimental Air Adventure (EAA). This event alone brings thousands of local, national and international guests to the area. In order to offer the accommodations and provide a source of revenue to the campus, air conditioning is necessary. By offering these housing options during the summer, this allows our campus to keep the rates down for student residents during the academic year.

Consultant Requirements

Consultants should have specific expertise and experience in the design and coordination of campus chilled water systems, chilled water production and distribution equipment, cooling towers and related electrical and mechanical control systems as part of a design team. Work includes site surveys, acquiring field data, and verifying as-built conditions to assure accurate development of design and bidding documents, and production of necessary design and bidding documents. Consultants should indicate specific projects from past experience (including size, cost, and completion date) in their letter of interest and when known, include proposed consulting partners and specialty consultants.

The consultant will verify project scope, schedule, and budget estimates, and recommend modifications as required to complete the specified project intent. This project will develop a design solution, plans, and specifications beginning with the conclusions and recommendations documented in the 2010 campuswide central utility master plan (07A2Q) and the subsequent follow up analysis conducted during the design of Fletcher Hall Addition & Renovation (13B2B). A Design Report will be published at the 75% project development stage and be used as the basis for seeking construction authority from the University of Wisconsin Board of Regents and State of Wisconsin Building Commission. Upon release for construction, the consultant team will develop bid and construction documents and provide construction support services. The scope of services will also include an evaluation of issues related to plant operating efficiency and operability and final placement of the plant on the site identified below. Landscape protection and rehabilitation will be expected throughout the distribution route. The consultant team should have expertise in the design of institutional central chilled water systems comparable to those at other University of Wisconsin campuses and Wisconsin Division of State Facilities design guidelines.

Project Budget Funding Sources

Construction: GFSB: $ 0 Hazardous Materials: PRSB: $ 0 Total Construction: Cash [AGFU]: $ 301,000 Design Fees (Basic): Gifts: $ 0 Design Fees (Other): Grants: $ 0 Total Design Fees: BTF: $ 0

Contingency: Other (Please Describe): $ 0 Management Fees: Other (Please Describe): $ 0

Furnishings/Fixtures/Eqpt: Other (Please Describe): $ 0 Total Budget Estimate: $ 3,465,000 Total Funding Sources: $ 301,000

Project Schedule Project Contact (Institution)

A/E Selection: Oct 2020 Contact Name: JoAnn Rife Design Report: Oct 2021 Contact Email: <[email protected]>

Approval: Dec 2021 Contact Phone: (920) 424-2438 Bid Opening: Jun 2022 Start Project: Sep 2022

Substantial Completion: Apr 2023 Project Close Out: Dec 2023

Page 3: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration

Major Project Request 2019 - 21 Biennium

09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4

Project Scope Consideration Checklist Yes No

1. Will the building or area impacted by the project be occupied during construction? If yes, explain how the occupants will be accommodated during construction.

All project work will be coordinated through campus physical plant staff to minimize disruptions to daily operations and activities.

2. Is this project request an extension of another authorized project? If so, provide the project #...

3. Are hazardous materials involved? If yes, what materials are involved and

how will they be handled? Required hazardous materials abatement has been included in the estimated project schedule and project budget.

4. Will the project impact the utility systems in the building and cause disruptions? If yes, to what extent?

All project work will be coordinated through campus physical plant staff to minimize disruptions to daily operations and activities.

5. Will the project impact the heating plant, primary electrical system, or utility capacities supplying the building? If yes, to what extent?

This project expands the central chilled water plant capacity from 3,250-tons to 4,200-tons.

6. Are other projects or work occurring within this project’s work area? If yes, provide the project # and/or description of the other work in the project scope.

7. Have you identified the WEPA designation of the project, Type I, Type II,

Type III? Type III.

8. Is the facility listed on a historic register (federal or state), or is the facility listed by the Wisconsin Historical Society as a building of potential historic significance? If yes, describe here.

9. Are other studies, testing or investigations required to confirm the scope or

existing conditions? If yes, describe here.

10. Will the construction work be limited to a particular season or window of opportunity? If yes, explain the limitations and provide proposed resolution.

Project work is seasonal. Preferred project work schedule should be limited to late fall, winter, and/or early spring months if possible.

11. Will the project improve, decrease, or increase the function and costs of facilities operational and maintenance budget and the work load? If yes, to what extent?

12. Are there known code or health and safety concerns? If yes, identify and

indicate if the correction or compliance measure was included in the budget estimate, or indicate plans for correcting the work.

Page 4: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration

Major Project Request 2019 - 21 Biennium

09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 4 of 4

13. Are there potential energy or water usage reduction grants, rebates or

incentives for which the project may qualify (i.e. Focus on Energy <http://www.focusonenergy.com/> or the local utility provider)? If yes, describe here.

14. If this an energy project, indicate and describe the simple payback on state

funding sources in years and the expected energy reduction here.

Page 5: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration

University of Wisconsin - Oshkosh

Chilled Water Plant Concepts

Chilled Water Load Projections

Appendix "B"

UW-OSHKOSH - Campus Chilled Water Load Projections

Updated 8/10

Building Name Occupancy

Space

(Existing/

Future)

Building

Area (GSF)16

% of

Building

Cooled GSF/Ton

Estimated

Building Load

(Tons) GSF/Ton

Estimated

Building Load

(Tons)

Estimated

Building Load

(Tons)

Diversity

Factor

Plant Load

(Tons)

Plant Flow

(GPM)

Date

Online

Actual

Connected

Load (Tons)

GPR

Connected

Load (Tons)

PR

Connected

Load (Tons)

GPR

Area

(GSF)

PR Area

(GSF)

System Gain (1) N/A 104 104 1.00 104 2000

Halsey-S. Wing -Stage 1 Lab (Light) Existing (4) 59,036 100% 300 197 197 300 197 0.71 140 337 2000 197 197 59,036

Halsey-S. Wing -Stage 2 Lab (Light) Existing (4) 39,358 100% 300 131 197 200 131 0.71 94 225 2001 131 131 39,358

Halsey-N. Wing - Stage 1 Lab (Light) Existing (4) 41,124 100% 300 137 206 200 137 0.71 98 235 2001 137 137 41,124

Arts & Communications Theater (Performing Arts) Existing (5) 207,849 100% 250 831 350 594 594 0.76 452 1085 2000/2001 594 594 207,849

Reeve Memorial Union Addition #2 Food Service Facility Existing (4) 60,000 100% 200 300 300 200 200 0.81 162 388 2001 200 200 60,000

Halsey-N. Wing - Stage 2 Lab (Light) Existing (4) 87,316 100% 300 291 437 200 200 0.71 143 343 2002 200 200 87,316

Reeve Memorial Union Remodeling Food Service Facility Existing (4) 99,778 100% 200 499 279 357 357 0.81 289 693 2002 357 357 99,778

Taylor Residence Hall Ren & Addt'n Residence Hall Existing (6) 103,518 100% 350 296 498 208 208 0.67 139 333 2005 208 208 103,518

System Gain (2) N/A 95 95 1.00 95 2006

Dempsey Hall Office Existing (14) 150,497 26% 400 97 1038 145 97 0.62 60 144 2006 97 97 150,497

Polk Library Library Existing (11) 204,104 100% 550 371 361 565 371 0.52 194 466 2006 371 371 204,104

Swart Hall Classroom Existing (12) 67,800 100% 350 194 350 194 194 0.67 129 310 2006 194 194 67,800

Nursing Education /Clow Classroom Classroom Existing (8) 207,715 100% 350 593 350 593 593 0.67 395 949 2006 593 593 207,715

Sub-Total 1,328,095 3,938 3,955 3,478 2,494 5,508

New Academic Building Classroom Future (10) 186,483 100% 350 533 350 533 533 0.67 355 852 2011

Radford Hall Medical Clinic Existing (9) 32,969 100% 350 94 350 94 94 0.67 63 151 2015

Dempsey Hall Addt'n Remodeling Office Existing (14) 150,497 74% 400 279 350 319 279 0.62 173 414 2020

Albee Hall Gym (Recreational Facility - Pool) Existing/Parital 80,657 30% 500 48 N/A 50 48 0.52 25 61 2020

Harrington Hall Lab (Light) Existing 37,687 100% 300 126 126 0.71 90 215 2020

Donner Hall Residence Hall Existing 46,006 100% 350 131 131 0.67 88 210 ??

Webster Hall Residence Hall Existing 37,376 100% 350 107 107 0.67 71 171 ??

Sub-Total 571,675 1,318 996 1,318 864 2,073

Total 1,899,770 5,256 4,951 4,797 3,358 7,581

System Gain (3) N/A 19 19 1.00 19 2015

New Residence Hall Residence Hall Future 128,000 100% 350 366 350 366 366 0.67 244 585 2012

River Center Repl. (2.5 Times Larger) Food Service Facility Future 129,148 100% 200 646 646 0.81 523 1254 2012

Lincoln Center Office /Daycare Future 33,984 100% 400 85 85 0.62 53 126 2012

Campus Equity & Diversity Center Office Future 29,084 100% 400 73 73 0.62 45 108 2012

Fletcher Hall Residence Hall Existing 99,082 100% 350 283 283 0.67 189 453 2015

Evans Hall Residence Hall Existing 49,548 100% 350 142 142 0.67 94 226 2020

Stewart Hall Residence Hall Existing 49,548 100% 350 142 142 0.67 94 226 2020

Student Recreation & Wellness CenterGym (Recreational Facility) Existing (19) 101,000 100% 500 202 577 175 175 0.52 92 220 2030

Blackhawk Commons Food Service Facility Existing (19) 76,631 100% 200 383 279 275 275 0.81 223 534 2032

Scott Hall Residence Hall Existing 235,173 100% 350 672 672 0.67 448 1074 ??

Gruenhagen Conference Center Residence Hall Existing 234,380 100% 350 670 670 0.67 446 1071 ??

Sub-Total 1,165,578 3,662 835 3,546 2,467 5,876

Total 3,065,348 8,918 5,786 8,343 5,825 13,457

3,279 2,514 765 1,064,799 263,296

Notes: CHW GPR/PR Split 77% 23% 80% 20%

1. Distribution pump gain estimated at 318 HP = 67 Tons. Piping system gain estimated at 2% of 1850 Tons = 37 Tons.

2. Distribution pump gain estimated at 318 HP = 67 Tons. Piping extensions add an estimated 28 Tons.

3. Piping extensions add an estimated 19 Tons. 10.0oF ∆T

5. Arts & Communications total CHW coil capacity from builidng plans is 918 tons, which appears oversized. 350 GSF/Ton was used to estimate the actual load.

6. Taylor Hall cooling load is based on project design loads.

7. Elmwood Commons cooling load removed. Building will be geothermal heat pumps and no connection to chilled water is required.

11. Polk Library cooling load is based on 260 Tons for the north portion of the building and 300 Tons for the south portion.

12. Swart Hall cooling load is average GSF/Ton typical of use and structure. Current load is only 158 tons.

14. Dempsey Hall is only partially air conditioned (only 38,908 GSF is air conditioned as of 2007).

15. Items shown as shaded have some uncertainty and are subject to change

16. GSF in blue font taken from 5/2005 General Building Report

17. Minimum value of occupancy and actual data/notes above.

18. Current peak load is 2,168 tons and 5,200 GPM (e-mail from Chuck Hermes June 17, 2009).

19. Student Recreation and Blackhawk Commons cooling load is based on chiller size currently installed.

Chilled Water Plant Requirements (17)Building Characteristics Load Based on Occupancy

Load Based on Actual Data

and/or Notes Below

1,400 & 450 Ton Chillers in Plant

10. New Academic Building size is based on 35% Review Documents proposing 186,486 GSF be constructed. Cooling load based on 350 GSF per ton.

4. Halsey Science and Reeve Memorial Union cooling loads are the totals of specified CHW coils taken from building plans.

8. Nursing Ed/Clow Classroom Building load is based on AHU capacities, since the existing 360 ton chiller cooled both facilities but was inadequate to meet exisitng load.

9. Radford Hall is cooled by a 100 Ton chiller. When connected to the central CHW system the chiller will provide backup cooling during he shoulder months.

Second 1,400 Ton Chiller in Plant

Replace 450 Ton with 1,400 Ton Chiller

and/or South Campus Chilled Water Plant

E:\210jobs\210091.00\hvac\calcs\R & D Revised UW-OSH App - B.xlsx

Page 6: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration
Page 7: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration
Page 8: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration
Page 9: Major Project Request...Major Project Request 2019 - 21 Biennium 09/08/2020 UWOSH - 19G2T - Heating Plant Chiller & Cooling Tower Replacement page 3 of 4 Project Scope Consideration