Maine-Endwell Central School DistrictAugust 15, 2019
Agenda
2
• Proposed Capital Project Scope
• Financial Information
• Proposed Schedule
Maine-Endwell Central School DistrictAugust 15, 2019
Capital Project
8
Homer Brink Elementary School
• Carpet replacement
• Roof top unit replacement
• Provide building air conditioning
• Gym and classroom addition
• Miscellaneous areas of renovation
Maine-Endwell Central School DistrictAugust 15, 2019
Capital Project
9
Maine Memorial Elementary School
• Aluminum door replacement
• Gym wood flooring replacement
• Stage wood floor replacement
• HVAC split system replacement
Maine-Endwell Central School DistrictAugust 15, 2019
Capital Project
10
Middle School
• Exterior stair replacement
• Football field erosion
• Softball field infield turf
• Interior door replacement
• Gym floor replacement
• Library improvements
• Rooftop cooling unit replacement
• FCS room renovation
• Technology room renovation completion
• Secure vestibule renovation
Maine-Endwell Central School DistrictAugust 15, 2019
Capital Project
11
High School
• Additional sidewalk
• Tennis court replacement
• Pool parking lot reconstruction
• Rear parking lot reconstruction
• Door lockset replacement
• Sanitary pipe replacement
• Foundation wall repairs
• Gym floor refinishing
• Library renovations
• Auditorium renovation
• Exterior lighting replacement
• Gym air conditioning
Maine-Endwell Central School DistrictAugust 15, 2019
Capital Project
12
Bus Garage
• Waste oil tank replacement
• Lube oil storage system upgrade
• Parking lot asphalt reconstruction
• Parge masonry walls
• Lighting at fueling station
• Concrete pad at fueling station
• Sanitary grinder pump replacement
Maine-Endwell Central School DistrictAugust 15, 2019
Proposed Referendum Schedule
15
• June – October 2019 - Project design
• June 6, 2019 - Board of Education vote
• July – August 2019 - Public relations campaign
• August 15, 2019 - Public Meeting
• Sept 10, 2019 - Referendum date
• October 2019 – SED submission
• December 2019 – SED approval
• December 2019 - January 2020 - Bidding
• May 2020 – December 2021 - Construction