Main Street Streetscape
Project Update May 12, 2014
Agenda
Main Street Streetscape Project Update
Review Options
Staff Recommendations
Schedule
Streetscape Options
Streetscape Ultra-Lite – Oak Ave to 14th Street - $850,000 Gateway arches, walls, pavers Limited utility relocation – electric, stormwater
Streetscape Lite – 13th Street to 14th Street - $1,352,000 Gateway arches, walls, pavers Some Utility relocation – electric, water, wastewater, stormwater, fiber
Entire Project – 9th Street to 14th Street - $3,872,000* Gateway arches, walls, pavers All Utility relocations – electric, water, wastewater, stormwater, fiber
* Current estimated project cost; includes additional underground for Magnolia and 10% contingency
Pros and Cons
Streetscape Ultra-Lite - $850,000
Cons Leaves gap between 9th Street and Oak Ave Does not have desired full impact Covers old utilities with new work Prolongs construction related hassles and
inconveniences
Pros Reduces project cost Contains project cost to CRA budget
Pros and Cons
Streetscape Lite - $1,352,000
Cons Leaves gap between 9th Street and 13th Street Does not have desired impact
Pros Reduces project cost Contains project cost to CRA budget Has slightly larger impact
Pros and Cons
Entire Project - $3,872,000
Cons Total project cost exceeds GLCRA ability to fund Requires utility cash/CIP funds for FY 14
Pros Completes entire project – 9th - 14th Street Now Isolates construction related hassles and
inconveniences Funds available from utility cash & CRA debt financing Project has immediate impact for Downtown Leesburg
Staff Recommendations
Complete entire project – 9th - 14th Street– Transfer cost of utility relocation to utilities
• Electric - $1,150,000• Water/wastewater - $375,000• Stormwater - $427,500• Communications $60,000• Streetlights $200,000• Streetscape (GLCRA) $1,307,500• Contingency $352,000• Total $3,872,000
– Negotiate transfer agreement with County• County participation in the project will reduce GLCRA costs
– Fund GLCRA project costs with bank loan
Going Forward
May 12 – Authorize Project and Approve Design Task Order
June 23 –Design Complete
July 14 – Approve Final Design; Advertise
August 25 – Award Construction Contract
September – Begin Construction
March 2015 – Construction Complete
Main Street Gateway
Main Street Streetscape
Questions?
.