Main Building Utility Plan Phase 1 - Study. PRE-SUBMITTAL CONFERENCE May 14, 2008, 9:00 AM. Topics. Project Intent Project Scope of Services Project Milestone Schedule Tour of Project Site. Project Intent. Project Site. Proposed Buildings. Project Scope of Services – Basic Services. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Main Building Utility Plan Phase 1 - Study

Main Building Utility PlanPhase 1 - Study

PRE-SUBMITTAL CONFERENCE

May 14, 2008, 9:00 AM

Page 2: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Topics

Project Intent Project Scope of Services Project Milestone Schedule Tour of Project Site

Page 3: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Project Intent

Objectives: Deliverables: Need for as-installed utility

system documentation of existing utilities that serve the Main Building and surrounding Project Site

Utilities master planning for proposed facilities

Condition assessments of utility systems and equipment to support renewal / replacement decision-making.

Topographic Survey Drawings, Master Site Plan Drawings, Master Building System Drawings, and System Schematic Drawings

Utility master planning studies and recommendations for utility system upgrade projects

Technical assessments of systems and equipment

Page 4: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Project Site

Page 5: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Proposed Buildings

Page 6: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Project Scope of Services – Basic Services

Stage 1 - Documentation Site documentation Main Building documentation

Charles A. LeMaistre Clinic R. Lee Clark Clinic (Old Clark) R. Lee Clark Clinic (New Clark) Margaret and Ben Love Clinic

Page 7: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Project Scope of Services – Additional Services

Stage 2 – Main Building Documentation for remaining facilities

Stage 3 - Planning Evaluation of utility systems Development of planning scenarios in consideration

of facility demolition and/or renovation Project conceptual planning

Stage 4 - Technical Assessments Hydronic piping system Utility sub-metering Electrical equipment assessment and short circuit /

overcurrent protection device coordination study

Page 8: Main Building Utility Plan Phase 1 - Study

Capital Planning & ManagementBuilding Utilities DocumentationMaster System Drawings

1. Investigate, document, and create drawings per system using M. D. Anderson AutoCAD standard

2. Add confirmed project as-built information3. Field verify installation of main utilities and

equipment4. Update drawings and distribute for M. D.

Anderson review5. Produce final master system drawings based

on review commentsM. D. Anderson will maintain drawings with current system

information as renovation projects are completed

Page 9: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Example Floor Plan

Page 10: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Example Riser Diagram

Page 11: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Project Milestone Schedule

Task Completion Date

Firm Selection / RFQ ProcessPre-Submittal ConferenceLast Day to Submit RFI'sRFI Responses PostedOwner Receives QualificationsSelection Committee Meeting to Shortlist FirmsFirm InterviewsNotification of Apparent Most Qualified FirmSelected Firm Delivers Executed AgreementOwner Executes AgreementNTP with Basic ServicesDocumentation / PlanningProject Kick-off MeetingProject Team MobilizationOwner Receives Site DocumentationOwner Receives Stage 1 Main Building DocumentationOwner Receives Planning StudiesOwner Receives Remaining Main Building DocumentationTechnical AssessmentsOwner Receives Technical Assessments

Thu 8/28/08Wed 5/14/08Fri 5/23/08Fri 5/30/08

Wed 6/25/08Wed 7/9/08Fri 7/18/08

Tue 7/22/08Tue 8/5/08

Tue 8/26/08Thu 8/28/08Fri 4/9/10Thu 9/4/08Fri 9/12/08Fri 12/5/08Fri 1/16/09Fri 3/13/09Fri 4/9/10

Fri 4/16/10Fri 4/16/10

Page 12: Main Building Utility Plan Phase 1 - Study

Capital Planning & Management

Tour of Project Site

Equipment Rooms Old Clark / New Clark / LeMaistre Clinics

Site Service Corridor / Receiving Dock Electrical Transformer Vault