Mailing List1) Managing Director, MPPTCL Jabalpur (Fax 0761-2664141)2) Chairman & Managing Director, MSETCL, Mumbai (Fax 26595401)3) Managing Director, GETCO, Vadodara (Fax 0265-2337918)4) Managing Director, CSPTCL, Raipur (Fax 0771-2241141)5) Executive Director,(SEF&CE), PGCIL, Gurgaon (0124-2571760)6) Executive Director, WRTS-I, PGCIL, Nagpur (Fax 0712-2641471)7) Executive Director, WRTS-II, PGCIL, Vadodara (Fax 0265-2487544)8) General Manager, POSOCO,WRLDC, Mumbai (Fax 28202630)9) Chief Engineer (Trans. Projects), GETCO, Vadodara (Fax 0265- 2339066)10) Chief Engineer (Trans.), CSPTCL, Raipur (Fax 0771-2574246)11) Executive Director (Trans. & Project), MPPTCL, Jabalpur (Fax 0761-2665593 )12) Chief Engineer (Trans. Project), MSETCL, Mumbai (Fax 26598587)13) General Manager (Projects), PGCIL, WRTS-I, Nagpur (Fax 0712- 2646585)14) General Manager (Projects), PGCIL, WRTS-II, Vadodara (Fax 0265- 2487544)15) Head Sterlite Transmission Bhopal.16) CEO(RPTL), WR Transmission (Gujarat), Pvt. Ltd., Gurgaon (Fax 0124-3917982)17) Head Adani Transmission India Ltd. Ahmedabad.18) Chief Electrical Engineer, Elect. Deptt., Goa (Fax 0832-2222354)19) Executive Engineer(Projects), Electricity Deptt., UT of DNH, Silvasa (Fax 0260-

2642338)20) Executive Engineer, Electricity Deptt., UT of DD, Daman (Fax 0260-2250889)21) Regional Executive Director(W), NTPC, Mumbai (Fax 28259364, 28257769)

Page 3: Mailing List - wrpc.gov.in

Minutes of Transmission scheme progress Review Meeting (TRM)held on 17th April, 2018 at WRPC, Mumbai

The meeting to review ongoing transmission projects in Western Region

was held on 17th April 2018 at WRPC, Mumbai and the list of participants is

placed at Annexure-1.

Member Secretary, WRPC warmly welcomed the participants in the

meeting. He stated that in line with the decision taken in 34th TCC/WRPC

meeting, the TRM meeting is being conveyed on regular basis to closely monitor

& review the progress of ongoing transmission projects in WR. He stated that

the issue of poor participation in last TRM meeting which was held on

09/10/2017 was flagged during 35th WRPC meeting and after detailed

discussion, 35th TCC/ WRPC suggested the constituents to ensure sufficient

participation in the TRM meetings.

Member Secretary, WRPC also stated that during the discussion in this

meeting, the status of progress of ongoing transmission projects related to

Transmission lines, Sub-stations, ICTs, Reactors etc. would be taken and

review of progress would also be made. He further stated that apart from the

reviewing the status of ongoing projects, the other associated issues like

Railway crossing works, ROW related issues, other constraints etc which are

decelerating the planned progress of transmission schemes shall also be

discussed & matter will be addressed at appropriate forum to resolve the

issues. He also mentioned that the deviation in completion target is a matter of

great concern as it may result into idle capital investment of the stake holders.

This happens due to number of factors and one of the major factors

contributing delay in completion of transmission projects is non-readiness of

downstream network. He therefore requested all the utilities to ensure timely

completion of downstream networks so that there is no unnecessary delay in

Page 4: Mailing List - wrpc.gov.in

completion of projects. He informed that CEA is also monitoring the progress of

ongoing transmission projects nation-wide.

He informed that many new Transmission elements at 220 kV, 400kV

and 765 kV level were added to the grid till March 2018. Many Transmission

line projects are under construction at 220 kV, 400kV and 765 kV level in

Western Region. 6262 Ckt-Km , 12345 MVA transfer Capacity, 3588 MVAR Line

Reactors Capacity, 1550 MVAR Bus Reactors, and STATCOM of 675 MVAR at

Solapur & Satana S/s Capacity added from April 2017 to March 2018 in WR

grid. He stated that there are several 765 kV Transmission line are coming in

Western Region.

He also informed that progress of transmission line projects planned by

CEA and CTU are normally in line with the anticipated commissioning dates,

however sometimes there is considerable delay in the completion of

downstream transmission line due to several constrains. This may cause

difficulty in the evacuation of Power and sometimes might limit the

Transmission capability of the existing network. Therefore it is important to

ensure the completion of STU planned downstream networks as per the

timeline of whole project. He also informed that inter regional line of 400 kV

and 765 kV, play crucial role in strengthening of the National Grid and

therefore delay in completion of the same is undesirable. The construction of

several crucial inters regional transmission line projects such as WR-NR, WR-

ER, WR-SR viz. HVDC 800kV Raigarh-Pugalur (Western Region

Portion)(WR_SR), LILO of 765kV S/C Satna - Gwalior T/L at Orai S/S(WR-NR)

and 765kV D/C Banaskantha - Chittorgarh (Part-I) T/L (under green corridor)

(WR_NR), are under progress & expected to commission within targeted date.

He also informed that in line with the Renewable energy target set by

GoI, several Renewable energy generation projects are coming in the Western

Region. Evacuation of this large quantum of renewable energy would become

one of the crucial tasks in near future and therefore new Green corridors are

up coming in the Western Region.

Page 5: Mailing List - wrpc.gov.in

He appreciated the presence of almost all the Transmission agencies in

the meeting unlike last TRM wherein participation was poor due to which many

issues could not be discussed in that meeting. He requested all the agency to

ensure same participation in future TRMs

He once again requested all representatives to actively participate in

meeting, so that issues can be resolved amicably.

With the above opening remarks, he requested Superintending Engineer (Opn),

WRPC to take up the agenda items for discussion.

I Status of progress of ongoing transmission schemes/lines:

Superintending Engineer (Opn.), WRPC stated that the progress of

ongoing transmission schemes under construction which are being executed by

GETCO, MPPTCL, CSPTCL, MSETCL, PGCIL, Adani transmission, Sterlite

transmission & Essar Transmission would be reviewed regularly under

following categories:-

a) Progress of transmission schemes associated with evacuation and system

strengthening scheme for CTU connected Generating Station including

IPP.

b) Progress of interconnected transmission schemes (downstream network)

associated with PGCIL Sub-station and other transmission agencies.

c) Progress of transmission schemes and system strengthening schemes set

up through TBCB projects.

d) Progress of Intra-state transmission schemes.

e) Review of progress of ongoing transmission schemes/lines planned in

Standing Committee meeting.

f) Review of progress of ongoing transmission schemes/lines under green

corridor projects.

Page 6: Mailing List - wrpc.gov.in

SE (Opn), WRPC requested EPTCL to update the present status of

construction of 400kV D/C Mahan Sipat transmission line.

EPTCL( Essar Power Transmission Company Ltd)Representative from EPTCL informed to the forum about the progress of

construction of 400kV D/C Mahan Sipat transmission line. He stated that out

of total 37 route km length of this transmission line, stringing work for the 10

route km is in progress. He further informed that all the required resources

have been mobilized to ensure completion within time. However he informed

that they are facing severe ROW issues for which local administration support

has been taken. He ensured that the 400kV D/C Mahan - Sipat line would be

completed by the end of June 2018.

SE (Opn), WRPC requested ATIL (Adani Transmission India Ltd.) to update

the present status of construction of 400/220 kV Morena sub-station.

ATIL (Adani Transmission India Ltd.)

Representative from Adani Power (ATIL), informed that 400/220 kV Morena

sub-station was planned to complete in March 2018 but considering the pace

the ongoing work, the project is anticipated to be completed in the month of

May, 2018.

SE (Opn), WRPC requested POWRGRID, WRTS-I and WRTS-II to update the

present status of construction of various ongoing transmission schemes

/projects of WRTS-I

POWRGRID, WRTS-IRepresentative from POWRGRID, WRTS-I intimated that target date for LILO of

Lonikhand-Kalwa at Navi Mumbai GIS-JSL/LS Cable would be September

2018. He also intimated that there is severe RoW in construction of 400 KV

Page 7: Mailing List - wrpc.gov.in

Wardha-Aurangabad Line (Upgradable to 1200 kV Voltage Level Regarding

progress of 800 kV Raigarh-Pugalur (Western Region Portion), he informed that

WR portion will be completed by March 2019, earlier against the original target

date of September 2019. He stated that LILO of Korba- Budipadar -CSEB CKT

at 400/220kV Raigarh S/S is still pending. Representative from CSPTCL

informed that he would convey the message to their managements for early

charging. Representative from POWRGRID, WRTS-I also raised the concern of

downstream network at 400/220 kV Pune SS (Talegaon). In reply, MSETCL

representative informed that there is severe ROW issues associated with the

downstream line. Regarding Navi Mumbai 2x315, 400/220 kV downstream

network, MSETCL representative informed that tenderisation is under process.

SE(Opn), WRPC requested all concern STU to take up the issue of delay in

completion of downstream network with their top management so that

constraints can be removed and completion timeline of downstream line of the

STUs can be ensured to match with completion timeline of associated CTU

network In case of severe ROW, STUs could take the help of local

administration of their States to resolves ROW issues amicably among the

stakeholders.

POWRGRID, WRTS-IIGM, POWRGRID, WRTS-II intimated that the Green Energy corridor projects

will be ready as per the scheduled date of October, 2018. However, the

charging of these corridors depends on the readiness of the renewable power in

Bhuj area. He also intimated that renewable power generation in Bhuj area is

not expected before October, 2018. He intimated that the charging of the Green

Energy corridor projects may take longer time than the expected i.e Nov 2018

or further. He raised the concern of downstream network of STU with PGCIL

S/S.

After detailed discussion as recorded above, SE (Opn), stated that the updates

related to ongoing transmission schemes/ projects of STUs is required to be

Page 8: Mailing List - wrpc.gov.in

obtained. For this purpose, he requested all representative to give updated

status one by one highlighting constraints, deviation, anticipated date of

completion etc.

GoaRepresentative from Goa electricity department intimated that the state

department has appointed M/s RECTPCL as PMC Consultant for execution of

the 220KV D/C line from 400KV Colvale substation to 220KV Tuem substation,

220KV D/C line from 400KV Colvale to 220KV Substation at Saligao, 220KV

D/C line from 220KV Cuncolim substation to proposed 220KV GIS substation

at Verna, 220KV D/C line from proposed Sub-station at Verna to the existing

sub-station at Kadamba Transmission lines. Tender is floated on EPC basis.

He also intimated that M/s RECTPCL has been appointed as PMC Consultant

for carrying out the work at 220/110/33KV Gas Insulated Sub-station (GIS) at

Tuem sub-station, 220/33KV Gas Insulated Sub-station (GIS) at Saligao,

220/110/33KV Gas Insulated Sub-station (GIS) at Verna.

MSETCLRepresentative from MSETCL intimated that LILO on 220KV Bhugaon to

Warora–I line for 400KV Warora S/S is facing severe RoW constrains. He also

intimated that work to be carried out under police protection.

He informed about the status of the progress of MSETCL downstream networks

and the same is attached here with as Annexure – A.

MPPTCLRepresentative from MPPTCL informed the status of the progress of the 400kV

and 220kV transmission lines. He also informed about the progress of the

400/220kV and 220/132kV S/S in Maharashtra. Further, he intimated the

status of the downstream transmission line associated to the 400kV Alkud S/S,

Page 9: Mailing List - wrpc.gov.in

400kV Kudus, 220kV Nagewadi S/s, 220kV Loni Deokar s/s. The same is

updated and attached here as Annexure A.

GETCORepresentative from GETCO intimated that few transmission lines are facing

severe RoW problems which are 220kV D/C Gavasad - Salejada line, 400kV

D/C Mundra-Zerda Line No. 1 (Package-III), 220kV D/C BECL - Botad line etc.

He also informed about the status of the transmission lines and the same is

updated and attached here as Annexure- A.

STERLITERepresentative from STERLITE intimated that the 765KV Khandwa 1&2 Line

Bays with 765/400KV 2X1500 MVA Substation at Khandwa and 3X80MVAR

Line Reactors at BDTCL , Dhule are scheduled to be commissioned by July,

2019. He also intimated the status of Progress of Ongoing Transmission

Schemes is updated and attached here as Annexure- A.

II. The Status of unutilized 220kV line bays at existing S/S in WRCTU (PGCIL) representative and the representatives from STUs whose down

stream lines emanating from ISTS Substation intimated the status of progress

of their respective transmission systems. The updated status is as follows:

Sl ISTS Substation Voltage ratio inuse

220kV Lines emanatingfrom Substation

No ofckt

Updated status on WRPC TRMmeeting (April 17.04.2018)

1 Raipur (PG) 3x315MVA,400/220 kV

Raipur (PG) – Doma 220 kVD/c 2

Commissioned on 30.11.2017

2 Mapusa (PG) 3x315MVA,400/220kV

Mapusa – Cuncolin 220 kVD/c 2

NIT under preparation.Anticipated completion date Sep

2020

3 Pirana 2x315MVA,400/220kV Pirana – Barjadi 220 kV D/c 2

92 locations out of which 29foundations,18 erection

completed. Severe ROW issue,LoI 23rd march 2017

Page 10: Mailing List - wrpc.gov.in

Sl ISTS Substation Voltage ratio inuse

220kV Lines emanatingfrom Substation

No ofckt

Updated status on WRPC TRMmeeting (April 17.04.2018)

4 Boisar 2x315 +500MVA,400/220kV Boisar – STU line S/c 1

3 (8) foundations completed.4excavations completed.2.37 km

stringing is balance. June2018.Row issue in four places.

5 Magarwada 2x315MVA,400/220kV

Magarwada – Ringanwada220 kV D/c 2 Commissioned Nov 2017.

6 Wardha 2x315MVA,400/220kV

Wardha – Yavatmal 220kVD/CYavatmal-Ghatodi.(LILO at Yavatmal)

2

PGCIL:2 bays completed in2012.Two bays in 2017. 2 no.s

ghatoli bays.MAHA: 35 foundations balance.

111 completed.Erection 37completed. Stringing 84(84Ckm)

balance.Section1Sec 2: 2(36) completed.20Ckm

balance.Sec 3: Lilo Ghatoli full balance.

7 Solapur2x315

+1x500MVA,400/220kV

Solapur – Bhale (MS) 220kVD/cSolapur – Narangwadi (MS)220kV D/c

2&2

PG:6 bays.solapur kumbhali2015 charged oct 15.

3 bays left

4 th bay charged at 220KV.Maha:

Solapur – Bhalwane (MS)220 kV D/c 2

8 Damoh 1 x 500 MVA400/220 kV

LILO of 2nd 220 kV Circuitof Damoh(MPPTCL) – Sagar220 kV line at Damoh(PGCIL) 400 kV S/S (1km)

1

Charged 28.08.2017

9 Vadodara GIS 2 x 500 MVA,400/220 kV

220 kV Venkatpura-Vadodara D/C Line220 KV Jambua – VadodaraD/C Line

4

220 kV Venkatpura- VadodaraD/C Line Charged 14.04.2018.220 KV Jambua – VadodaraD/C Line target date jan 2019.

III. Status of under Construction 220 KV line bays at New S/S /Extensions in existing S/S in WR

CTU (PGCIL) representative and the representatives from the STUs whose

down stream lines emanating from the ISTS Substations intimated the status of

progress of their respective transmission systems. The updated status is as

follows

S. No. ISTS Substation ProposedBays

220kV Lines emanatingfrom Substation

Noof

cktStatus of 220kV

lines

Updated status onWRPC TRM meeting(April 17.04.2018)

Page 11: Mailing List - wrpc.gov.in

S. No. ISTS Substation ProposedBays

220kV Lines emanatingfrom Substation

Noof

cktStatus of 220kV

lines

Updated status onWRPC TRM meeting(April 17.04.2018)

1 Betul GIS 2x315MVA, 400/220 kV 4

Betul (PG) - Betul D/C220 kV line (3 Km) 2 Line charged

on 21.07.2017

Betul (PG) - Betul D/C220 kV line (3 Km) oneckt target date march2019.(Dec 18 original)

119(135) tower erectioncompleted. Stringing is

fully pending.

LILO of Sarni - Pandhurna220kV line at BetulGIS(PGCIL) 400 kV S/s(41 Km)

2Targeted to becompleted by

Dec-2018

2 Morena (TBCB) 2 x315, 400/220 kV 4

i) LILO of one circuit ofMalanpur – Mehgaon220kV line at Morena(TBCB) 400kV S/s (8Kmfrom Loc. No.12).ii) Morena(TBCB)400 -Sabalgarh 220kV DCDSline (92Km) with LILO ofone circuit ofMorena(TBCB)400 -Sabalgarh 220kV line atMorena 220kV S/s ofMPPTCL (0.5Km)

4 Planned

MP: 1) 16/01/2018.2) Jun 2018 target.

217 locations,199 foundcompleted. 172 towererection completed.2*28.2Ckm completed.

3)

3 NaviMumbai 2 x315, 400/220 kV 4 STU line 4 Planned

Jun 2018 PGCIL targetdate. Maha: tenderunder process. 112

Ckm(Mar 2019 targetdate)

4

Indore (PG) 2x500MVA,400/220 kV

6

Indore (PG) – Indore (MP)220 kV D/c 2

Targeted to becompleted by

Dec-2018

December 2018

Dec 2018

Yet to be decided.

Indore (PG) – Ujjain (MP)220 kV D/c 2

Targeted to becompleted by

Dec-2018Name of the line Yet to bedecided. 2 To be planned

by MP

5Itarsi (PG) 1x500MVA,400/220 kV

2

LILO of 2nd 220kV circuitof Itarsi (MPPTCL) -Hoshangabad 220 kV lineat Itarsi (PGCIL) 400kVS/s (Existing)

2Line charged

on 09.08.2017

Completed in aug.2017

6 Parli (PG) 2x500MVA, 400/220 kV 6 Parli (PG) - Harngul 220

kV D/c 2 UCMaha: Dec 2018.

7Parli (PG) 2x500MVA, 400/220 kV 6 Osmanabad (MS) - Parli

(PG) 220 kV S/c

2 UC

Under constructionUnder constructionUnder construction

1 UC

Page 12: Mailing List - wrpc.gov.in

S. No. ISTS Substation ProposedBays

220kV Lines emanatingfrom Substation

Noof

cktStatus of 220kV

lines

Updated status onWRPC TRM meeting(April 17.04.2018)

1 UC

8

Mapusa (PG)3X315 MVA,400/220 2 Mapusa - Tuem 220kV

D/c 2 UC

Pg: jul 2018 schedule:Goa: comml bid open11.04.18 target is 3

years.

9Satna (PG)1x500MVA,400/220kV

2

LILO of one circuit ofSatna (MPPTCL) -Chhatarpur 220 kV lineat Satna (PGCIL) 400 kVS/s (3Km)

2Line charged

on 23.11.2017

10

Navsari2x315MVA +1x500MVA,400/220kV

2 Navsari – Bhestan 220kVD/c line - Planned

11Rewa PS2x500MVA,400/220kV

6 Rewa UMSPP – Rewa PS220kV 3xD/c line -

Targeted to becompleted

Barsita Desh &Ramnagar byJune-2018and Badwarby Dec-2018

Jun 2018 2 lines areexpected. One in Dec

2018.

12Khandwa S/S500MVA,400/220kV

2 STU Line -

Targeted to becompleted byJune-2018

Targeted to becompleted by June-

2018

13Raigharh400KV/220KVs/s .

LILO of RaigharhBhudhipadar ckt 2.

Pg: Bays ready in2014.

CSPTCL: issue ofinstallation of PLCC/

protection isequipment to be

decided/settled. Issueswith OPTCL, ER.

14 Pune substation400/220KV. 6

220KV Urse 1 &2.220KV Chakan(chinchwada)1 &2.

Scheduled Oct 2010. 2no. of bays connected

in 2015.Maha: Not yet

planned.

The status of progress of ongoing transmission schemes/lines is attached in

Annexure–A.

IV. Date and venue of next meeting:

The date and venue of the next meeting will be communicated separately.

Meeting ended with thanks to the Chair.

***************

Page 13: Mailing List - wrpc.gov.in

Sl.No. Organisation, Name & Designation Mobile No. E-mail AddressANNEXURE -1

I WRPC1 Shri A. Balan, M.S. 9483540528 [email protected] Shri J.K. Rathod, S.E. 9987910799 [email protected] Shri L.K.S. Rathore, E.E. 9833371844 [email protected] Shri P. Peddi Reddy, A.D.-I 7840894702 [email protected] Shri B.V. Sandeep, A.D.-I 8527622170 [email protected]

II MPPTCL6 Shri Deepak Joshi, S.E. 9425804907 [email protected]

III CSPTCL7 Shri Ashok Kumar Verma, S.E. 9425234043 [email protected]

IV GETCo8 Shri Keyur Pandya, D.E.(Project) 8238042371 [email protected]

V MSETCL9 Ms. Karuna Khewalkar, Addl. E.E. 9820831266 [email protected] Shri Suhas Chaudhari, A.E.E. 9833815239 [email protected]

VI Goa Electricity Dept.11 Shri John A.P., E.E. 9422641183 [email protected]

VII WRLDC, POSOCO12 Smt. Sachala Mishra, D.G.M. 9869450223 [email protected] Smt. Pushpa S., Asst. G.M. 9869404482 [email protected] Shri S.S. Raghuwanshi, C.M. 9427615762 [email protected] Shri Absar Ahmad, Sr. Eng. 8080484278 [email protected] Shri M. Venkateswara Rao, Eng. 8452928806 [email protected]

VIII POWERGRID17 Shri Rajesh Kumar, G.M. 9428504055 [email protected] Shri Abhinav Verma, D.G.M. 9428504062 [email protected] Shri Patanjali Sharma, D.G.M. 9422311684 [email protected]

IX ESSAR POWER20 Shri Sachidanand Bhiyode, E.D. 9909993545 [email protected]

X ADANI POWER LTD.21 Shri Manank Bhatt, Mgr. 9825805203 [email protected]

XI STERLITE POWER22 Shri Prashant Karpe, Mgr. 8390152777 [email protected] Shri Abhishek Pandey, Mgr. 8966903790 [email protected]

LIST OF PARTICIPANTS FOR THE TRM MEETING AT WRPC, MUMBAI ON 17.04.2018

Page 14: Mailing List - wrpc.gov.in

ANNEXURE-A

A Odisha Generation Phase-II Transmission Limiteda) ROW issue: Severe RoW issue In Raigarh District(ear SKSindustrial Belt) :10locations foundation and erection pending due to agitationin Reserve Forest. Will be cleared soonb)Forest Clearences: Forest/Wildlife clearance obtained fromMOEF

d) PTCC Clearance for CG portion anticipated by 25th April'18

e) For early commissioning of line readiness of bay atJharsuguda and Raipur end Substations need to beexpedited.

B Khargone Transmission Limited

1

765KV D/C Khandwa Pool (KTL)-Indore (PGCIL) Hexa AAAC ZebraLine July'2018 All Statutory Approvals has been received.Check Survey completed.Planned for Early Commissioning before COD-July'2019.NH Approval is pending at PIU, Indore, NHAI

2

765KV D/C Khandwa Pool (KTL)-Dhule (BDTCL) Hexa AAAC ZebraLine July'2018 All Statutory Approvals has been received.Check Survey completed.Planned for Early Commissioning before COD-July'2019.NH Approval is pending at PIU, Indore, NHA3

LILO of one CKT of 400KV D/C Khandwa-Rajgarh at NTPC,Khargone (Twin ACSR Moose) February'2018 Line Completed as per COD-February'2018.Electrical Inspector Clearance received.4

400KV D/C Khargone TPP Switchyard (NTPC)-Khandwa Pool(KTL) Quad AAAC Moose Line July'2019 Check Survey not started yet.

Jun-181 Jharsuguda – Raipur 765 kV D/C (hexa) line 

Remark

STERLITEA) Status of Progress of Ongoing Transmission Schemes undertaken by Transmission Utility as on 20.09.2017

Sr.No Name of Transmission lineAnticipatedcompletion

Target

Page 15: Mailing List - wrpc.gov.in

ANNEXURE-A

1 2 9 10

1765KV Khandwa 1&2 Line Bays with 3X80MVAR LineReactors at BDTCL ,Dhule

Jun'18 Work under Progress.

2 765/400KV 2X1500MVA Substation at Khandwa March'19 Work under Progressearly commissioning expected (4momnth before COD)

Issues in detail if any

NAME OF ORGANISATION : Khargone Transmission Limited

STERLITESTATUS OF CONSTRUCTION ON ONGOING/UNDER IMPLEMENTATIONS SUBSTATIONS

SI. NO. Name of Substation Expected date ofcompletion

Page 16: Mailing List - wrpc.gov.in

Name of Utility: Electricity Department

Status of on-going Transmission line in Goa

Sr.No. Name of Transmission line Length

in ckmTotal

locationFoundationcompleted

Towererected

Stringingcompleted

Anticipatedcompletion

targetRemarks

1Erection of 220KV D/C line from 400KV Colvalesubstation to 220KV Tuem substation.Estimated cost : Rs.10.32 crores

17 ckm 2 1/2 years target

2Erection of 220KV D/C line from 400KV Colvale to 220KVSubstation at Saligao. Estimatedcost: Rs.40 crores

40 ckm 2 1/2 years target

3Erection of 220KV D/C line from 220KV Cuncolimsubstation to proposed 220KV GIS substation at Verna.Estimated cost Rs.29.70 crores

44 ckm

4Erection of 220KV D/C line from proposed Sub-station atVerna to the existing sub-station at Kadamba. Estimatedcost Rs.36.10 crores

60 ckm

The Department has appointed M/s RECTPCL as PMCConsultant for execution of the said project. Tender is floatedon EPC basis. Techno-Commercial bids are opened on11/04/2018.

The Department has appointed M/s RECTPCL as a PMCConsultant. NIT is under preparation.

The Department has appointed M/s PFC Consulting as PMCConsultant for preparation of DPR & other related tenderingactivities.

The Department has appointed M/s PFC Consulting as PMCConsultant for preparation of DPR & other related tenderingactivities.

Page 17: Mailing List - wrpc.gov.in

Name of Utility: Electricity Department

Status of on-going EHV Sub-stations

Civil Structure Structure Expected

1Design, supply, erection, testing and commissioningof 220/110/33KV Gas Insulated Sub-station (GIS) atTuem sub-station. Estimated cost Rs.88 crores

2

Design, supply, erection, testing and commissioningof 220/33KV Gas Insulated Sub-station (GIS) atSaligao.Estimated cost Rs.181 crores

3

Design, supply, erection, testing and commissioningof 220/110/33KV Gas Insulated Sub-station (GIS) atVerna.Estimated cost Rs.241 crores

M/s RECTPCL has been appointed as PMCConsultant for carrying out the said work. Tender isalready floated on EPC basis. Techno-commercialbids are opened on 11/04/2018.

M/s RECTPCL has been appointed as PMCConsultant for carrying out the said work. NIT isunder preparation

M/s PFC Consulting has been appointed as PMCConsultant. NIT is under preparation.

Sr.No. Name of sub-station Cumulative Progress till date

Page 18: Mailing List - wrpc.gov.in

Stub SettingCompleted

TowerErected

StringingCompleted(Nos.) (Nos.) (Ckm)

(A)1 Utran CCPP (374 MW)

Commissioned - Nov'09i 220kV D/C Gavasad - Salejada line 194.000 313 273 192 51.740 Mar-19 WIP (Severe RoW problems)2 Sikka Unit 3 & 4 (2 x 250= 500 MW)

C.O.D. - Dec'12i LILO to Sikka from 220kV Jamnagar – Jetpur ckt. No.2 116.934 189 189 189 116.934 Mar-18 Line charged on 31.03.2018.(B)3 Adani Power, Mundra (Bid-02)

(2011-12)(1000 MW) Feb’12400kV D/C Mundra-Zerda Line No. 1 (Package-I) 160.000 260 163 123 0.000 At present matter under dispute.400kV D/C Mundra-Zerda Line No. 1 (Package-II) 190.000 284 103 65 0.000 At present matter under dispute.400kV D/C Mundra-Zerda Line No. 1 (Package-III) 314.000 453 187 87 0.000 Mar-19 WIP (Severe RoW problems)

Total 664.000 997 453 275 0.0004 Essar Power, Vadinar (Bid-3) (2011-12)

(1000 MW) C.O.D. -Aug'11400kV D/C Vadinar - Amreli line (Package-I) 116.850 168 168 168 116.850 -- 400kV Hadala-Jetpur made LILO at Amrelithrough Vadinar-Amreli line (Pkg-1) at400kV D/C Vadinar - Amreli line (Package-II) 118.260 173 173 173 118.260 -- Line charged on 66kV voltage from 66kVJetpur-Virpur line on 22.01.2016.400kV D/C Vadinar - Amreli line (Package-III) 120.940 192 136 94 0.000 -- LOA issued on 05.03.2018.

Total 356.050 533.00 477 435 235.1105 GSEG Extension Phase-I (350 MW)

C.O.D. - Nov'11i 220kV D/C GSEG - Mota line 111.060 182 110 95 41.818 Jan-19 WIP6 Bhavnagar Energy Co.Ltd. (BECL)

(2 x 300 = 600 MW)i 220kV D/C BECL - Botad line 190.000 292 182 142 33.798 Dec-18 WIP (Severe RoW problems)(C)

i 400kV LILO to Dehgam from Wanakbori - Soja line No.2 12.000 23 16 6 0.000 June-18 WIPii 220kV D/C Vyankatpura-Waghodia (765kV PGCIL) line 29.000 57 57 57 29.000 Feb-18 Line charged on 16.02.2018 & load taken

on 14.04.2018.iii 220kV D/C Pirana - Barejadi Line 44.960 92 29 18 0.000 June-18 WIPiv 220kV D/C Jambuva - Vadodara (765kV PGCIL) line 67.960 131 26 23 0.000 Jan-19 WIP

(D)

(E)

i 400kV Mundra - Hadala LILO to Halvad 89.400 136 124 93 3.712 Dec-18 WIPii 400kV D/C Amreli - Kasor line (Part-1)

(Amreli Gantry to AP-28)160.950 238 211 181 0.000 Mar-19 WIP (Severe RoW problems)

iii 400kV D/C Amreli - Kasor line (Part-2)(AP-28 to AP-44)

164.340 235 235 230 113.740 Dec-18 WIP (Severe RoW problems)iv 400kV D/C Amreli - Kasor line (Part-3)

(AP-44 to Kasor Gantry)145.264 206 175 158 47.752 Mar-19 WIP (Severe RoW problems)

Total 470.554 679 621 569 161.492v 400kV D/C Vadavi - Halvad Line (Package-I) (From

Vadavi to AP-41) with ACSR Twin Moose conductor146.404 215 206 204 132.982 Sept-18 WIP

vi 400kV D/C Vadavi - Halvad Line (Package-II) (FromHalvad to AP-41) with ACSR Twin Moose conductor

144.420 196 120 11 0.000 Mar-19 WIPvii 400kV D/C Varsana - Halvad Line (Package-I) (From

Varsana to AP-44) with ACSR Twin Moose conductor143.388 224 184 176 19.440 June-18 WIP

viii 400kV D/C Varsana - Halvad Line (Package-II) (From AP-44 to Halvad) with ACSR Twin Moose conductor

93.804 154 33 5 0.000 Mar-19 WIPix LILO of one ckt. of 400kV D/C Vadavi-Zerda line at Veloda

(Sankhari) S/s30.460 45 45 45 30.460 Jan-18 Line charged on 30.12.2017.

x LILO of one ckt. of 400kV D/C Kosamba-Chorania line at400kV Sanand-II GIDC S/s. 90.000 132 124 121 73.620 May-18 WIP

xi LILO of 400kV D/C Vadinar-Hadala Line No.1 at 400kVKalawad S/s 8.018 13 13 13 8.018 Jan-18 Line charged on 18.01.2018.

xii LILO of 400kV D/C Vadinar-Hadala Line No.2 at 400kVKalawad S/s 7.630 13 13 13 7.630 Jan-18 Line charged on 18.01.2018.

xiii LILO of one ckt. Of 400kV D/C Kosamba-Chorania line at400kV Pachchham S/s 46.000 72 62 58 2.728 Sept-18 WIP

Status of Ongoing Transmission Projects in Gujarat (April - 2018)

Sr.No. Name of Transmission lines Length in

Ckt. Km.Total

Locations

PRESENT STATUS(As on 12.04.2018) Anticipated

CompletionTarget

Remarks

Intrastate transmission schemes

Transmission Schemes associated with State Generating Stations

Transmission Schemes associated with IPP

i

i

Transmission Schemes associated with PGCIL Substation

Transmission schemes through IPTC route - NIL

Page 19: Mailing List - wrpc.gov.in

Stub SettingCompleted

TowerErected

StringingCompleted(Nos.) (Nos.) (Ckm)

(A)

Sr.No. Name of Transmission lines Length in

Ckt. Km.Total

Locations

PRESENT STATUS(As on 12.04.2018) Anticipated

CompletionTarget

Remarks

Transmission Schemes associated with State Generating Stations

xiv 400kV D/C Wanakbori TPS (Existing Switchyard) -Wanakbori Unit No. 8 Line (Tie Line) 2.728 5 5 5 2.728 May-18 Line work completed.

xv 400kV D/C Wanakbori-Soja line (Pkg-1) 121.758 186 171 169 104.896 June-18 WIPxvi 400kV D/C Wanakbori-Soja line (Pkg-2) 91.412 157 91 91 12.418 Aug-18 WIPxvii 400kV D/C Soja-Zerda line (Pkg-1) 133.660 223 188 184 60.026 June-18 WIP

xviii 400kV D/C Soja-Zerda line (Pkg-2) 135.262 224 181 169 72.296 Nov-18 WIP

xix LILO of one ckt. of 400kV D/C Ukai-Kosamba line at400kV Vav S/s

62.000 106 81 75 35.908 Jul-18 WIPxx LILO of one ckt. of 400kV D/C Jhanor-Navsari line at

400kV Vav S/s20.000 34 23 14 0.000 June-18 WIP

xxi 400kV D/C Hadala-Shapar line 124.340 198 95 78 0.000 Mar-19 WIPxxii 400kV D/C Bhogat-Kalawad line 260.570 444 64 32 0.000 Mar-20 WIPxxiii 400kV D/C Bhachunda - Varsana Line 276.160 499 93 23 0.000 June-20 WIP

xxiv LILO of both ckt. of 400kV D/C Mundra - Zerda line at400kV Charanka S/s 25.760 43 23 7 0.000 July-18 WIP

xxv 220kV LILO at Kukma S/S from one Ckt. of Shivlakha -Nanikhakhar line with ACSR Zebra conductor

34.000 54 50 48 30.658 May-18 WIPxxvi 220KV D/C Halvad - Sadla line 76.000 124 101 101 59.100 Dec-18 WIP (Severe RoW problems)xxvii 220KV D/C Bhatiya - Kalawad line 238.000 373 176 127 10.514 Mar-19 WIP (Severe RoW problems)xxviii 220KV D/C Kalawad - Kangasiyali line 111.880 191 177 159 63.700 Dec-18 WIP (Severe RoW problems)xxix Termination of one D/C line of 220KV Achhaliya-Jambuva

line at Vyankatpura (Jarod) S/S68.386 128+2G 124 124 30.658 June-18 WIP

xxx 220kV Vadavi-Chhatral line LILO at 220kV Santej S/s(Work for Initial part from Santej)

50.660 88 69 60 0.600 Mar-18 Tender under acceptance.xxxi 220kV D/C Vadavi-Sanand DFCC line 61.080 108 54 41 0.000 Dec-18 WIPxxxii 220kV D/C Botad-Chorania line 103.240 196 92 77 0.000 Dec-18 WIPxxxiii 220kV D/C Jamnagar-Hadala line 139.360 238 238 238 139.192 Sept-17 Line charged from Hadala S/s to location

No. 2 near Jamnagar S/s on 25.08.2017.xxxiv 220kV Amreli-Dhasa line LILO at 220kV Botad S/s 99.980 186 151 150 85.994 June-18 WIPxxxv LILO of 220kV Sankhari-Jangral line at Veloda (Sankhari)

S/s4x14.206 +2x3.663 =

42-M/C + 12-D/C = 54

54 54 60.488 Sept-17 Line charged on 23.09.2017.xxxvi 220kV D/C Kheralu-Dharewada (DFCC) line 53.360 97 70 52 0.000 LOA issued on 05.03.2018. / WIPxxxvii 220kV D/C Soja-Journang (DFCC) line 43.420 75 51 35 0.000 LOA issued on 05.03.2018. / WIPxxxviii 220kV D/C Palanpur-Amrigadh DFCC Line 80.000 144 119 64 0.000 Dec-18 WIPxxxix 220kV D/C Gavasad-Bhayali DFCC Line 47.364 84 84 84 47.364 May-18 WIPxxxx 220kV LILO to Jhanor S/s from 220kV Haldarwa-Zadhadia

Line13.580 23 23 23 13.458 Dec-17 Line charged upto loc. No. 1 at Zhanor

end on 27.05.2017.xxxxi LILO of 220kV S/C Kasor-Vartej line and 220kV S/C

Karamsad-Vartej line at 400kV Pachchaam S/s on M/Ctower

38.620 29-M/C + 04-D/C = 33 29 26 0.000 Dec-18 WIP

xxxxii LILO of both circuit of 220kV D/C Nyara-Thebda line atKalawad S/s

20.800 17 17 17 19.168 Oct-17 Line charged upto loc. No. 1 at Kalawadend on 16.10.2017.xxxxiii LILO of one circuit of 220kV D/C Achhaliya-Vyankatpura

line at 220kV Kawant S/s166.626 280 280 280 166.626 Oct-18 Line charged on 30.03.2018.

xxxxiv LILO of one circuit of 220kV D/C Kadana-Godhara line at220kV Zalod S/s

124.000 223 216 195 26.690 Dec-18 WIPxxxxv LILO of one circuit of 220kV D/C Akrimota-Nakhatrana line

at 400kV Bhachunda S/s51.700 83 83 83 53.160 Jan-18 Line charged on 20.12.2017.

xxxxvi LILO of one circuit of 220kV D/C Hadala-Sartanpar line at220kV Wankaner S/s

12.880 16 14 14 0.000 June-18 WIPxxxxvii 220kV D/C Radhanpur-Sankhari line 95.640 152 152 152 58.498 Aug-18 WIPxxxxviii LILO of 220kV D/C Nyara-Thebda line at Moti Gop S/s on

M/C tower59.360 59 44 39 0.000 Sep-18 WIP

xxxxix 220kV D/C Bhogat-Moti Gop line 138.960 251 64 46 0.000 Sep-19 WIPxxxxx 220kV D/C Chorania-Salejada line 134.540 240 121 104 0.000 Mar-19 WIPxxxxxi LILO of 220kV S/C Tappar-Hadala Line at 220kV Vondh

S/s3.540 7 7 7 3.540 Dec-17 Line charged on 06.07.2017.

xxxxxii 220kV D/C Bhogat - Bhatiya Line 26.000 53 28 25 0.000 June-18 WIPxxxxxiii 220kV D/C Bhogat - Ranavav Line 140.000 248 80 38 0.000 Dec-18 WIP

xxxxxiv LILO of 220kV S/C Chorania - Salejada line at 220KVBagodara S/s 3.520 9 9 9 3.520 June-17 Line charged on 01.06.2017.

xxxxxv 220kV LILO of both ckt. of 220kV D/C Mobha - Mangrolline at 220kV Amod S/s 57.000 66 52 16 0.000 June-18 WIP

Page 20: Mailing List - wrpc.gov.in

Stub SettingCompleted

TowerErected

StringingCompleted(Nos.) (Nos.) (Ckm)

(A)

Sr.No. Name of Transmission lines Length in

Ckt. Km.Total

Locations

PRESENT STATUS(As on 12.04.2018) Anticipated

CompletionTarget

Remarks

Transmission Schemes associated with State Generating Stations

xxxxxv LILO of 220kV Lalpar - Sartanpar line at 220kV WankanerS/s 37.000 72 28 0 0.000 Jan-19 WIP

xxxxxvi 220kV D/C Bhilad - Sarigam line and LILO of 220kV Vapi -Tarapur line at 220kV Sarigam S/s 25.600 33 9 4 0.000 Jul-18 WIP

xxxxxvii LILO of one circuit of 220kV D/C Gandhinagar – Chhatralline at 400kV Vadavi S/s 24.720 52 28 22 0.000 Mar-19 WIP

xxxxxviii LILO of 220kV GSEG - Kim line and 220kV GSEG - Mora -Kim line at 220kV Velanja S/s

7.040 12 7 5 0.000 May-18 WIP

xxxxxix 220kV D/C Asoj - IOCL lineO/H -

2x26.128 &U/G - 2x4.8

94 13 0 0.000 WIP (Deposit Work)

xxxxxx Hot line stringing of 132KV LILO to Bhomiyavadar fromSikka -Ranavav ckt.1 100.000 NA NA NA 97.000 Mar-18 WIP / RoW issue.

xxxxxxi 132kV D/C Haldarwa-Trasla (DFCC) line 24.050 48 32 28 0.000 June-18 WIPxxxxxxii 132kV D/C Ode-Manjusar line 55.374 103 103 103 55.374 Jul-17 Line charged on 30.05.2017.xxxxxxiii 132kV D/C Tilakwada-Chotaudepur line 140.000 237 237 237 140.000 Jul-17 Line charged on 06.07.2017.xxxxxxiv LILO of One circuit of 132kV D/C Dhuvaran-Vatva line at

Mehmdabad S/s25.840 52 51 48 21.736 May-18 WIP

xxxxxxx LILO of both circuit of 132kV D/C Wankaner-Varsamediline at Mota-Dahisara S/s.

8.000 12 7 5 0.000 May-18 WIPxxxxxxxi LILO of one circuit of 132kV D/C Wankaner-Jamnagar line

at Tankara S/s.3.400 7 7 7 3.400 Sept-17 Line charged on 27.09.2017.

xxxxxxxii LILO of one ckt of 132kV D/C Tilakwada - Chhotaudepurline at 220kV Kawant S/s

57.720 118 0 0 0.000 Nov-18 A/T given on 06.11.2017.xxxxxxxiii LILO of 132kV S/C Junagadh -Talala line at 220kV Shapur

S/s23.900 46 33 27 0.000 June-18 WIP

xxxxxxxiv LILO of 132kV S/C Gondal - Haripur line at 220kVVisavadar S/s

37.920 70 35 29 0.000 June-18 WIP

xxxxxxxv LILO of 132kV S/C Ranasan - Vijapur line at 220kVChiloda S/s 7.816 15 6 0 0.000

Page 21: Mailing List - wrpc.gov.in

ANNEXURE-A

Anticipated

completion target

1 2 8 9

1400KV Babhaleshwar-Kudusline.(Naneghat to Padgha-II)

Dec-18

Forest:150.32haFirst stage approval received:FC-111/MH-11/2016-NGP/2561dt.21.09.2017Railway:1]Railway track crossing (Span 146-147) - Proposal submitted vide 1512dt.09.05.13 to SDEE CST, resubmitted on dt.13.03.2015. SDEE, CST insistedto go for 400kV underground installations. However, vide 83 dt.02.09.16,MSETCL informed that 400kV underground installation is not possible andrequested to grant NOC as per proposal.2] 100kV Rly Power line crossing (Span 145-146 & 147-148):- Proposalsubmitted vide letter no.2353 dt.31.10.12 to SDEE Kalyan, resubmitted on13.03.2015. Revised drawings submitted vide 25 dt.22.02.16 to SDEEKalyan. Again revised drawings are submitted vide 109 dt 04.09.2017.Approval awaited.ROW:cases filed Collector, Thane vide L.No. 250 dt.08.03.2017.Foundation ROW (12 locs):• Loc 146,147,152, 136,137, 138,169,170,171,172, 173, 182AErection ROW (9 locs):• S/C4,131,132,139, 140, 143, 144,159,199

2400KV LILO on Padghe-Tarapur for400KV Kudus s/s

Sep-18scheme is revised vide MBR 126/04 dt 23.02.2018 as LILO on both ckts of400 kV Tarapur -Padghe line with Twin conductor(4.6 Km)

3400 KV D/C Jejuri-HinjewadiLine(Jejuri-Wainjhar) Package-I.

Dec-18Forest: Loc 56,57submitted at DFO vide 560 dtd 13-04-15.ROW: loc 86,87 submitted to SDO Haveli vide no 1158 dtd 15/06/16.

4400 KV D/C Jejuri-Hinjewadi Line(Wainjhar- Hinjewadi) Package-II.

Dec-18

Forest: 17.25 Ha.12 nos. (loc.9/0,10/0, 44/0, 44/1, 44/2,45/0,46/0, 47/0, 48/0, 49/0, 49/1,50/0)Compliance submitted to DCF Pune. DCF Pune filled Part-II but pending forwant of FRA Certificate( FRA certificate to be obtained from CollectorPune). Gram Sabha resolution is awaited from village Man.ROW: i) dt 18.05.13: SDO Haveli-4 nos (18/0,20/0,21/0,22/0 ) At resultstage.ii) Dt21.07.16 : SDO Maval- 8 nos (loc 36/0,36/1,36A/1,36A/2,37/0,36B/0,37/1,37/2)iii) Dt 18.05.13: SDO Haveli-1 no (26/1).Iv) Dt 15.02.17: SDO Mulshi - 3nos (40/0, 39/4,39/5)v) Dt 09.01.14 : SDO Bhor- 5nos(12/0, 12/1, 12/3, 24/0, 24/1)vi) Dt 01.03.13 : SDO Bhor 1 no(17/0).

MSETCLStatus of ongoing transmission projects under MSETCL

SN Name of transmission line Remarks

A) 400 kV Projects

MSETCL ONGOING Page 1

Page 22: Mailing List - wrpc.gov.in

Anticipated

completion target

SN Name of transmission line Remarks

5400 KV DCQ BBLR-Kudus line (uptoNaneghat)

Dec-18

Forest Clearance issue:Nashik Zone - 32 Ha, 27 locsFirst stage approval received vide no. FC-111/MH- 1 I /2016- NGP/256l dtd 21.09.2017.ROW issue:Nashik Zone : 28 locs, cases filed at SDO Manchar, orders awaited.Foundation ROW (5 nos):1 no filed vide no. 1616 on dt. 02.06.14 (Loc 316).2 nos filed vide no.1718 on dt. 11.06. 14 (Loc G297/4, G297/15)2 nos filed vide no. 1817 on dt. 21.06.14 (loc GSC7, G297/ 13).Erection ROW :22 nos filed vide no. 940 on dt. 24.05. 16 (Loc G244. GSC- 1, GSC-2, GSC-3,GSC- 4, G253, G257, G260, G261, G263, G268, G269, G272, G273, G288,G297/ 16, 306, 311, 314, 332, 343, 344).01 no. filed vide no. 114 on dt. 20.01.2017 (Loc. 125)Orders awaited.The variation in locations and line length is due to diversion of route due toGMRT.Wastage due to GMRT:FDN: 79 nos.TE: 60 nos.Will be dismantled.

6 220 KV DC Chandrapur MIDC toBallarshah line ( IInd Circuit)

Mar-17 CKT-I commissioned on 28.09.16. and CKT-II on 12.03.2017

7 220 kV Ch'pur -II - Ch'pur MIDC(Tadali)

Mar-18 Commissioned on 31-03-2018

220kV DC Balapur- Malegaon line,Part-I220kV DC Balapur- Malegaon line,Part-II220kV DC Balapur- Malegaon line,Part-III220kV DC Balapur- Malegaon line,Part-IV220 KV DCDC Akola - Anjangaonline, Part-I220 KV DCDC Akola - Anjangaonline, Part-II220 KV DCDC Akola - Anjangaonline, Part-III

10220KV DC Kalmeshwar-Warud line(B.C substation source line)

Sep-18

Balance line work is being excuted in parts on Risk & Cost basis. 3 Nos. ofLOAs are placed & 2 Nos of LOAs are being placedForest: Katol- Warud section : 0.7456 ha.Approved vide 4171 dt 23.11.2015Kalmeshwar- Katol section:(14.09 ha) forest involvement bypassed inrevised route.ROW:1) 05 loc 5/2,5/6, 9/1, 9/2, 11/2.Proposal submission: dt 20.10.2014Order awaited from Collector,Nagpur2) Loc. Nos. 27/2,28/1,28/4,28/5Proposal submission: L. no 2664 dt 05-10-2015 and after panchnama againsubmitted vide L.No.534 dt 2.2.2016 Order awaitedfromCollector,AmravatiRailway:a)Railway track crossing : loc.no.AP 10-AP11 Kalmeshwar- Katolsection. Proposal submitted on 20.09.2014to Sr. DEE Nagpur. Approval awaited b)Railway track crossing : loc.no.AP 4-AP5 Katol- Warud section. Proposal submitted on 20.09.2014to Sr. DEE Nagpur.Apporoval awaited.11 220KV Partur-Nagewadi DC line Mar-18 Line commissioned on 30/03/2018.

12 220 kV Kumbhargoan Krishnoor line(foundation & ETC)

Mar-18 Ckt-II commissioned on 25/03/2018.

B) 220 kV Projects

8

9

Commissioned on 10.08.2017

Dec-17 Commissioned on 18-12-2017

MSETCL ONGOING Page 2

Page 23: Mailing List - wrpc.gov.in

Anticipated

completion target

SN Name of transmission line Remarks

13 220KV DC Malegaon-Kalwan line(B.C substation source line)

Dec-17 Line commissioned on 14.11.2017

14220KV D/C Pimpalgaon -Eklahareline for Pimpalgaon SS(B.C substation source line)

Sept.-2018

Constraints:1) Loc. No 134/5 - work stoppedFoundation completed at Loc. 37 & 46.2) Loc. No. 37: The land owners (2) are asking for crop compenationcheque before erection & stringing work. Work will be done under policeprotection.3) Loc. No 46: The land owners is asking for huge crop compenation chequebefore erection & stringing work. Work will be done under policeprotection.4) Material shortage: Tenderisation for balance shortfall material (exceptavailable material at MSETCL ) in process.

15220KV LILO on Bhigwan-Walchandnagar for Loni Deokar SS

Commissioned on 31.03.2017

16 220KV Lamboti-Vairag line Commissioned on 30.03.2017

17220kV DC Warora-Wardha II(Bhugaon) Commissioned on 16.05.2017

18LILO on 220KV Bhugaon to Warora–Iline for 400KV Warora Ss

Jun-18

ROW:Severe ROW at LOC 6/0 ,Prohibitory order received form collector ,Chandrapur vide L.No 81 dt7.6.2014Work to be carried out under police protection

19220kV DC line from Deoli (PGCIL)-Ghatodi (upto Yavatmal)

Sept.-2018

To complete the work speedily, seperate order is placed on M/s Neha for220 kV line from Deoli to LILO point upto Yawatamal. Work stared byagency from 9.4.2018.ROW:(44 Loc)Prohibitory order received from collector Wardha Videi) 29/2014 dt 15.06.2016, Loc No.8 (1 no)ii) 35/2015 dt 6.5.2016 ,Loc No.28,38,42,44,52,55 (6 nos)iii) 67 /2016 dt 6.5.2016 , Loc No. 12A,12,13,14,15,16, 20/1,20/2, 20/5,20/6,20/7, 20/9,25,34 (14 nos)iv) 30/2014 dt 22.6.2016 ,Loc No. 56 (1 no)v) 32/2015 dt 30.12.2015 ,Loc No.4,4A,4B,4C,4D,3,5,9,10, 10A,10B,10C,10D, 10E,10F,17,18,20/3,20/4,20/8,20/10,27 (22 nos)

20220KV MC LILO on both circuits ofWaluj-Jalna at 400KV Taptitanda SS

Dec.2017 Commissioned on 11/05/2017.

21 220KV Dc Nagewadi-Taptitanda line Mar-18 Commissioned on 09/02/2018.

22220kV MC Kopargaon tap-Babhaleshwar

Dec-18

ROW:Foundation: Locs. [7]Order Awaited [7] : 54, 74, 75, 76, 79, 100, 101.Erection: Locs. [6]Order Awaited [6] : 102, 103, 104, 105, 106, 107.For all 13 locations - Submitted vide 2004, dt.11-07-2014 to Collector,Ahmednagar.Railway Crossing:1) Locs : 12, 13Submitted vide 3338, dt.14.12.2012 to SDRM, South western Rly Solapur.2) Locs : 55, 56Submitted vide 3339, dt. 14.12.12 to SDRM, South western Rly Solapur.Constriants:Agency has stopped all work since 26.06.2016.

MSETCL ONGOING Page 3

Page 24: Mailing List - wrpc.gov.in

Anticipated

completion target

SN Name of transmission line Remarks

23220KV D/C cable feeder for bypassing 400/220KV Kalwasubstation

Feb-17 Commissioned on 09.03.2017

24 220KV Borivali - Boisar M/C line Jan-17 Commissioned on 29.04.2017

25 220kV SCDC Kandalgaon-Dasturi line Dec-18Short closure of scheme is approved vide No. CMD-13 dt 4.1.2018 ,balance work is to be executed on Risk & cost basis.

26220kV DC line from 220kV Phaltans/s to Walchandnagar s/s

Dec-17DC Portion commissioned on 12/08/2017 and MC portion commissionedon 28/12/2017.

27220 kV D/C line from 400 kV PGCIL(Kumbhari) S/Stn to Bale S/Stn

Sep-18

ROW: Loc 50,51 (2 nos) submitted vide63 dtd 06/01/2016 to SDO Solapur-II. P.O. received vide 2016 / 697 dtd 23/01/18.However, farmer againasked for partial modification. Compliance submitted vide no 314 dtd26/03/2018.

28220KV LILO on Pandharpur -Malinagar for 220KV Bhalwani SS

Jun-18

ROW: 1) Loc 39 (1 no) submitted vide 1334 dtd 27/09/16 to SDO Akluj,Malshiraj2) Loc 5,6 ( 2nos) for Foundation and Loc 43,44,45&46 ( 4 nos) for erectionSubmitted vide no 62 dtd 18/01/2018 to SDO Akluj, Malshiraj.

29LILO on 220kV Chinchwad- Apta for400kV Talegaon s/s up to point nearUrse Ss.

Mar-18 Scheme partial termination (Pkg-A) approved vide 1134 dtd 30/01/2018.

30

Conversion of existing S/CChinchwad - Apta line in to M/C linefor portion between Chinchwadsubstation to prop. 220 kV PGCILTalegaon line LILO point (Loc. No.50)

Sep-18

31 220kV SCDC Karad- Koyna line Sep-18 Partial line charged from loc 8 to 144 on dtd 15/02/2017. For balancework, Tender under process.

32

2) (a) 220 kV LILO line on 220 kVKolshet-Wada line D/C on M/Ctower at 400 kV Kudus S/s -- 6.2 km (b) LILO on 220kV Padghe-Wadaline up to 400kV Kudus S/s bystringing 3rd & 4th Ckt on M/Ctowers at (a) above—6.2 km

Nov-18

Forest :Area involved 9.4 ha (Appr)Online submission of proposal: FP/ MH/TRANS/30180/2017 dt 9.11.2017Online queries raised on dt 9.11.2017 are complied on dt 20.11.2017Joint inspection carried out on dt 25.1.2018 with forest officer

33220kV M/C LILO on 220kV Tarapur-Borivali & Boisar-Ghodbandar linefor 400kV Kudus S/s - 27 kms

Jul-19

Forest :Area involved 26 ha(Appr)online proposal submission : FP/ MH/ TrANS /30204/2017 dt 13.11.2017Queries raise online dt 15.11.2017 are complied on dt 20.11.2017

Excavation started.

MSETCL ONGOING Page 4

Page 25: Mailing List - wrpc.gov.in

Progress of Downstream NetworkSr No Name of Substation Scope Name of Associated downstream line Progress Remark

1) LILO on 220kV Vita-Miraj at 400kV Alkud Ss - 18 kMsF: 51/51;E: 45/51;ckm: 5.644/28.

2) LILO on 220kV Mhaisal-Jath -23 kMs LOA placed recently.1) LOA placed on M/s AnandElectricals.2) Check Survey under process.

2) (a) 220 kV LILO line on 220 kV Kolshet-Wada line D/Con M/C tower at 400 kV Kudus S/s -- 6.2 km (b) LILO on 220kV Padghe-Wada line up to 400kV KudusS/s by stringing 3rd & 4th Ckt on M/C towers at (a)above—6.2 km

F : 6/50;E : 0/50;Ckm : 0/25.37;

220kV M/C LILO on 220kV Tarapur-Borivali & Boisar-Ghodbandar line for 400kV Kudus S/s - 27 kms

F : 0/92;E : 0/92;Ckm : 0/94.2;

LOA placed recentlyexcavation of Loc. No. 59,60 & 60A is in progress.

1) 132 kV LILO on existing 132kV Jalna (old)- Jafrabadline at 220 kV Jalna (Nagewadi) s/s –15 km

F : 15/47;E : 0/47;Ckm : 0/21.04

2) Construction of 132 kV MC line on MC tower by LILOon existing 132 kV Jalna (old) - Partur -15 kMs

Line not Tenderised

3) Construction of LILO on one ckt of existing 132kVJalna-Rajur DC Line at 220kV Jalna MIDC S/S– 5 kMs

Line not Tenderised

4) 132 kV LILO on existing 132kV Jalna (MIDC) to 220kVJalna S/S at 220 kV Jalna (Nagewadi)– 0.5 kMs

F : 2/3;E : 1/3;Ckm : 0/0.77

1) 132 KV SCDC Line from proposed 220 KV Loni Deokars/s to Indapur s/s – 30.0 Km.

Line not Tenderised

2) 132 KV SCDC Line from proposed 220 KV Loni Deokars/s to Bawda s/s – 10.0 Km.

Line not Tenderised

1 400kV Alkud S/S400/220kv, 3 x167 MVA ICT -1 nowith bays.

2 400kV Kudus

1) 2 x 500MVA,400/220KV ICTS

with bays.2) 1 x 167MVA400/220KV, 1

Phase ICT spare

3 220kV Nagewadi S/s

100MVA 220/132kV ICTs with bays -

- 2 nos.50 MVA 220/33 kVT/Fs with bays -- 2

nos

4 220kV Loni Deokar s/s

i) 2 x 100 MVA,220/132 KV ICTswith associated

Bays

Page 26: Mailing List - wrpc.gov.in

ANNEXURE-A

Stringingcompleted

1 2 7 8 9400KV LINE

1400 KV DCDS (Quad moose) line from Shri Singa Ji TPS (Stage-II) toPithampur

2x38.04 Sept'2018 Work under progress

2 400 KV DCDS (Quad moose) line from Pithampur to Badnawar 2x4.2 Sept'2018 Work under progress

3LILO of 400KV Seoni-Bhilai SC line at 400KV SubstationBalaghat/Kirnapur

0 Dec'2018 Work under progress.

4LILO of both circuit of 400KV Nagda-Rajgarh line at 400KV SubstationBadnawar

0 Dec'2018 Worek under progress.

220 KV LINE

1 220kV DCDS line from Gwalior(Malanpur) - Morena 2x29.765 Line charged on 16.02.2017

2 2nd Cirkuiting of 220 Kv Satna - Chhatarpur Double Circuit line 37 Mar'2019

3Upgradation of 132KV D/C Indore-II (Jaitpura) - Indore(N/Z) line oncomposite multi circuit monopole

4LILO of one Ckt of 220kv Indore-II (Jaitpura) - Indore(400KV) line at220kv S/S Indore(N/Z) (2x0.5+2x4+4x6.7)

5LILO of one Ckt of 220kv DCDS Ashta - Dewas line at 220kv S/SChapda 0 Sept'2019

6 220Kv DCDS line from Pithampur-Depalpur line 0 Sept'2019

7220Kv FCFS line for LILO of both Ckt. Of Badnagar -Ratlam D/C line at400Kv S/s Badnawar 0 Dec'2018

8 220Kv DCDS Julwaniya- Kukshi 0 Sept'2019

9 220Kv DCSS Shujalpur- Narsinghgarh line 0 Dec-19

10220Kv DCDS line Morena(400KV S/s CWRTL Adani Group) - Sabalgarhwith LILO of one circuit of line at 220 KV S/s Morena June'2018

10.a

(a). 220 KV DCDS line from Morena (400 KV S/s CWRTL Adani) -Morena(Jarerua) 220 S/s 2x24.685 Charged on 31.03.2018

10.b

(b). 220 KV DCDS line from Morena (Jarerua) 220kV - Sabalgarh 220S/s 2x28.2 June'2018

11 LILO of one ckt. Malanpur - Mehgaon at 400 KV S/s Morena(Adani) 2x7.396 charged on 16.01.2018

13 LILO of 2nd ckt. Of Bansagar - Satna 220Kv line at Kotar 220 KV S/s. 4x3.231 +2x2.462 Line charged on16.10.2017

A) Status of Progress of Ongoing Transmission Schemes undertaken by Transmission Utility as

Present statusas on 31.03.2018

Anticipatedcompletion

Target

NAME OF THE ORGANISATION- M.P.POWER TRANSMISSION CO. LTD.

2x4.474 + 2x0.49+ 4x5.689

1st ckt charged on22.02.2017. 2nd cktcharged on 23.2.2017.3rd ckt charged on31.03.2017.

Sl.No. Name of Transmission Line Remarks

Page 27: Mailing List - wrpc.gov.in

Stringingcompleted

1 2 7 8 9

Present statusas on 31.03.2018

Anticipatedcompletion

Target

NAME OF THE ORGANISATION- M.P.POWER TRANSMISSION CO. LTD.

Sl.No. Name of Transmission Line Remarks

14LILO of both circuit of Indore-II (Jaitpura)) - Ujjain 220Kv line at Indore(PGCIL) 765KV Substation

0 Dec'2018

15LILO of 2nd circuit of Damoh (MPPTCL) - Sagar 220KV line at Damoh(PGCIL)400KV Substation

1.184 Line charged on 28.08.2017

16LILO of 2nd circuit of Itarsi (MPPTCL) - Hoshangabad 220KV line atItarsi (PGCIL) 400KV Substation

2x0.06 Line charged on 09.08.2017

17LILO of one circuit of Satna (MPPTCL) - Chhatarpur 220KV line atSatna(PGCIL) 400KV Substation

3.92 Line charged on 05.10.2017

18LILO of One Ckt. Of Bhopla - Hoshangabad DC line at 220 KV S/sAdampur

NIL Sept'2019

19220 KV DCDS line for LILO of One Ckt. Of 220 KV DCDS Indore - Indore-II (Jaitpura) line at Mangaliya.

2x0.198 Line charged on 30.10.2017

20220 KV DCDS Khandwa(400kV PGCIL) - Chhanera line (Earlier MalwaTPS -Chhanera)

0 Sept'2018

21LILO of both Ckt. Of Badod - Kota/Modak 220 KV Line at 220 KV S/sSuwasara

4x0.80 May'2018

22LILO of 2nd Ckt. Of Badod - Kota/Modak 220 KV Line at 220 KV S/sBhanpura

NIL charged on 16.03.2018

23LILO of 2nd Ckt. Of Nagda - Neemach 220 KV Line at 220 KV S/sDaloda

0 Oct'2018

24220 KV DCDS line for Interconnection of 400 KV S/s Betul with 220 KVS/s Betul

2x1.88 Line charged on 21.07.2017

25 LILO of 220 kV Sarni - Pandhurna at 220 Kv S/s Betul 0 Mar'2019

26 LILO of 2nd Ckt. Of Birsinghpur - Amarkantak 220 KV line at Shahdol220 KV S/s

4x5.6+2x0.198 charged on 06.02.2018

Page 28: Mailing List - wrpc.gov.in

Land Acquisition(%)

civil workscompletion

(%)

structure Transformer &substation equipment

Recevied (%)

structure, Transformersubstation equipment

Erected (%)

1 2 3 4 5 6 7 8 9 101 400 KV S/s Balaghat/Kirnapur 400/132/33 2x100 100 100 99 99 Dec'2018 Work under progress.2 400 KV S/s Badnawar 400/220/132 2x315 100 100 100 98 Dec'2018 Work under progress.

3Installation of 315 MVA 400/220 KVAddl. X-mer at 400 KV S/s Bhopal (SukhiSevaniya)

400/220 1x315 100 100 100 100 June'2018 Work under progress

4Installation of 315 MVA 400/220 KVAddl. X-mer at 400 KV S/s Chhegaon

400/220 1x315 100 100 100 100 completed X-mer charged on 17.11.2017

5Upgradation of 132 KV North Zone S/s atIndreo - 220 KV 220/132 KV 2x160 100 35 10 0 Dec'2018

6220/33 KV pooling S/s at Badwar (RUMS-I)

33/220 KV 3x100 NIL NIL NIL NIL Dec'2018

7220/33 KV pooling S/s at Barsita Desh(RUMS-I)

33/220 KV 3x100 100 100 98 91 June'2018 work under progress.

8220/33 KV pooling S/s atRamnagar(RUMS-I)

33/220 KV 3x100 100 98 97 73 Sept'2018 work under progress.

9220/33 KV pooling S/s at Suwasara(Goojarkhedi RUMS-II)

33/220 KV 3x100 100 100 99 99 completed

1st X-mer charged on24.05.2017 & 2nd X-mercharged on 12.08.2017 & 3rdon 27.03.2018

10 220/132 KV S/s Chapda (Upgradation) 220/132 KV 1x160 100 12 0 0 Sept'2019

STATUS OF CONSTRUCTION OF ONGOING/UNDER IMPLEMENTATIONS SUBSTATIONSNAME OF ORGANISATION- M.P. POWER TRANSMISSION Co. LTD.

Status as on : : 31.03.2018

Expected dateof Completion

RemarksSl.No.

Name of Sub-Station

VoltageRatio

Capacity inMVA

Cummulative Progress till date

Page 29: Mailing List - wrpc.gov.in

Land Acquisition(%)

civil workscompletion

(%)

structure Transformer &substation equipment

Recevied (%)

structure, Transformersubstation equipment

Erected (%)

NAME OF ORGANISATION- M.P. POWER TRANSMISSION Co. LTD.Status as on : : 31.03.2018

Expected dateof Completion

RemarksSl.No.

Name of Sub-Station

VoltageRatio

Capacity inMVA

Cummulative Progress till date

11 220/132 KV Depalpur (Upgradation) 220/132 KV 1x160 100 46 0 0 Sept'201912 220 KV S/s Adampur 220/33 KV 2x50 100 43 0 0 Sept'201913 220/132 KV S/s Kukshi (Upgradation) 220/132 KV 1x160 100 56 0 0 Sept'2019

14 220 KV S/s Morena 220/132 KV 1x160 100 100 100 100 completedCharged on 31.12.2016 from132 KV side & charged on18.03.2017 from 220 kV

15 220 KV S/s Mangliya 220/132 KV 1x160 100 100 100 100 completed charged on 30.10.201716 220 KV S/s Chhanera (Upgradation) 220/132 KV 2x160 100 99 93 84 Sept'2018 Work under progress17 220/132 KV S/s Suwasara 220/132 KV 2x160 100 100 100 100 May'2018 Work under progress

18 220 KV S/s Shahdol (Upgradation) 220/132 KV 1x160 100 100 100 100 completedcharged on 05.12.2017 (from132kV) & 06.02.2018 (from220kV)

19Installation of 160 MVA 220/132 KVAddl. X-mer at 220 KV S/s Betul

220/132 KV 1x160 100 100 100 100 Dec'18 Work under progress

20Installation of 160 MVA 220/132 KVAddl. X-mer at 220 KV S/s Sidhi

220/132 KV 1x160 100 100 100 100 completedX-mer charged on13.01.2017

21Installation of 160 MVA 220/132 KVAddl. X-mer at 220 KV S/sPandhurna

220/132 KV 1x160 100 100 100 100 completedX-mer charged on

14.11.2017

Page 30: Mailing List - wrpc.gov.in

Sl. No. ISTS SubstationVoltageRatio in

UseStatus of Bays 220kV Lines emanating from Substation No. of Ckt. Status of 220kV

Lines

1 Pirana 2x315MVA,400/220kV

2 nos. Bays ready since19/03/2015 (WRSS-6) Pirana - Barejadi 220kV D/c 2 GETCO may

update

2 Boisar2x315 +500MVA,

400/220kV1 no. Bay ready since 30/05/2015 Boisar - STU line S/c 1 MSETCL may

update

3 Magarwada 2x315MVA,400/220kV

2 nos. Bays ready since03/11/2014 Magarwada - Ringanwada 220kV D/c 2 D&D may update

4 Damoh1x500MVA

,400/220kV

2 nos. Bays ready since Nov'16LILO of 2nd 220kV Ckt. Of Damoh(MPPTCL) - Sagar 220kV line at Damoh(PGCIL) 400kV S/s (1kM)

1 Line charged on28.08.2017

5 Vadodara GIS 2x500MVA,400/220kV Bays ready since May'2017 220kV Venkatpura - Vadodara D/C line

220kV Jambua - Vadodara D/C line 4 GETCO mayupdate

Sl. No. ISTS Substation ProposedBays Commissioning Schedule 220kV Lines emanating from Substation No. of Ckt. Status of 220kV

Lines Remarks

Betul (PG) - Betul D/C 220kV Line (3kMs.) 2 Work Completed Line charged on

21.07.2017

LILO of Sarni - Pandhurna 220kV line atBetul GIS (PG) 400kV S/s (41 kMs.) 2 Under

Construction

Targeted to becompleted byMarch 2019

Indore (PG) - Indore (MP) 220kV D/c(2x4Km) 2

UnderConstruction

Targeted to becompleted by Dec-

2018Indore (PG) - Ujjain (MP) 220kV D/c(2x4Km) 2

UnderConstruction

Targeted to becompleted by Dec-

2018Name of remaining 2 Nos. feeders fromIndore(PGCIL) 765kV S/s shall beintimated at later stage.

2 To be planned byMP -

3 Itarsi (PG) 1x500MVA,400/220kV 2 July '18 (WRSS-14)

LILO of 2nd 220kV Ckt. Of Itarsi(MPPTCL) - Hoshangabad 220kV line atItarsi (PGCIL) 400kV S/s (Existing)

2 Work Completed Line charged on09.08.2017

1.1 Status of unutilized 220kV Line Bays at Existing Substation in WR

1.2 Status of Under Construction 220kV Line Bays at New Substation / Substation Extension in WR

1 Betul GIS 2x315MVA,400/220kV 4 August '17 (Mauda-II)

2 Indore (PG) 2x500MVA,400/220kV 6 July '18 (WRSS-14)

Page 31: Mailing List - wrpc.gov.in

4 Satna (PG) 1x500MVA,400/220kV 2 Jun / July '18 (WRSS-16)

LILO of one Ckt. Of Satna (MPPTCL) -Chhatarpur 220kV line at Satna (PGCIL)400kV S/s (3 Kms.)

2 Work Completed Line charged on23.11.2017

5 Navsari GIS 2x315MVA +1x500MVA, 400/220kV 2 May '18 (DGEN Power) Navsari - Bhestan 220kV D/c _ Planned GETCO may update

6 Rewa PS 2x500MVA, 400/220kV 6 August '17Rewa UMSPP - Rewa PS 220kV 3xD/cline. (Barsita Desh, Ramnagar andBadwar)

_ UnderConstruction

Targeted to becompleted

Barsita Desh &Ramnagar by June-

2018 and Badwar by

7 Khandwa S/s 1x500MVA,400/220kV 2 September '19 Khandwa (PGCIL) – Chhanera 220kV D/C

line (40Km). _ UnderConstruction

Targeted to becompleted by June-

2018

Sl. No. ISTS Substation ProposedBays Commissioning Schedule 400kV Lines emanating from Substation No. of Ckt. Status of 400kV

Lines Remarks

1 Indore (PG) 400kV 2 July '18 (WRSS-16) Indore (PG) - Ujjain (MP) 400kV D/c(85Km) 2 Under

Construction

Targeted to becompleted byMarch-2019

2 Vadodara GIS 400kV 2 May '18 (DGEN Power) DGEN TPS (Dahej) - Vadodara GIS 400kVD/C 2 Planned

DGEN may updatethe status ofadvance plan

3 Vindhyachal Pool 400kV 2January '18 (IPPs in Chhattisgarh

& Other Generation Projects inWR)

Vindhyachal (IV/V) STPP NTPC -Vindhyachal Pool (PG) 400kV D/C 2 UC Adani may update

4 Gwalior GIS 400kV 2January '18 (IPPs in Chhattisgarh

& Other Generation Projects inWR)

Gwalior - Morena 400kV D/C 2 UC Adani may update

5 Rajgarh 400kV 1 May '18 (Khargone TPS Project) Khargone TPS - Rajgarh (PG) 400kV S/C 1 UC Sterlite may update

1.4 Status of Under Construction 765kV Line Bays at New Substation / Substation Extension in WR

1.3 Status of Under Construction 400kV Line Bays at New Substation / Substation Extension in WR

Page 32: Mailing List - wrpc.gov.in

Sl. No. ISTS Substation ProposedBays Commissioning Schedule 765kV Lines emanating from Substation No. of Ckt. Status of 765kV

Lines Remarks

1 Vindhyachal Pool 765kV 1March '18 (IPPs in Chhattisgarh& Other Generation Projects in

WR)

Sasan UMPP - Vindhyachal Pool 765kVS/C 1 UC Adani may update

2 Indore (PG) 765kV 2 May '18 (Khargone TPS Project) Khandwa PS (TBCB) - Indore (PG) 765kVD/C 2 UC Sterlite may update

Page 33: Mailing List - wrpc.gov.in

Status of Ongoing TransmissionProgress in Chhattisgarh (As on

Stubssetting[Nos.]

TowerErected[Nos.]

StingingCompleted[CK

M]

As per order REVISED

(A)Transmission schemes associated withevacuation and system strengtheningscheme for own Generating Station.

(B)

Transmission schemes associated withevacuation and system strengtheningscheme for Generating Station set upby IPP

(C) Interconnected Transmission schemesassociated with PGCIL sub-station

(D)Transmission schemes and systemstrengthening schemes set up throughIPTC route

(E) Intra State transmission Schemes1 400kV line

1.1 400kV DCDS Raipur(Raita) - Jagdalpur(DCDS) 657 903 903 903 657 May'14 Dec'16 Work completed.Charged on

1.2 LILO of 400kV Raita-Jagdalpur atDhamtari

2 4 19-Aug Oder placed on21.02.18

2 220kV line2.1 2nd circuiting of 220 KV Korba-Bishrampur

line(DCSS)155 143.00 June'15 18-Apr Work in progress.

2.2LILO of 220kV Urla-Khedamara(Bhilai) line onMulticircuit tower at Borjhara 1 4 4 4 0.924 Dec'17 Line charged on

16.12.20172.3 Mungeli-Kawardha 77 123 123 117 32.1 June'18 Work in progress.

2.4

LILO of 220 KV Mopka-Bhatapara Circuit &220 KV Mopka-Siltara Circuit on multicircuittower at proposed 220/132 KV S/s at Dherdehi(Bilaspur)

64 116+16 62 41 June'18 Work in progress.

2.5 LILO of Gurur-Barsoor at Narayanpur 0.22 2 Order placed on16.01.2018

2.6 Barsoor-Jagdalpur 175 290 20 June'18 Work in progress.

2.7 220 KV Gurur - Kurud (Dhamtari ) line 74 120 19-Aug Order placed on21.02.2018

2.8 LILO of Korba - Bishrampur for 220 KV S/s ChHURION Multi Ckt Tower 18 30 4 months for HOS Order placed on

20.03.2018

NIL

NIL

NIL

NIL

Anticipated Completion Target REMARKSS. No. NAME OF TRANSMISSION LINELength in Circuit

Km

Total Loc.[Nos.]

Present Status

Page 34: Mailing List - wrpc.gov.in

Sl. No. ISTS Substation Voltage Ratioin Use

No of existing220kV line Bays

220kV Lines emanating from Substation Status of 220kV lines to be connected bySTU

1 400/ 220 kV Raigarh SS 2x315 MVA,400/220kV 4 Nos(i)RAIGARH -CSEB CKT-1(ii)RAIGARH -CSEB CKT-2(iii)RAIGARH -CSEB CKT-3- Bay charged upto fewtowers for Antitheft .(iv)RAIGARH -BUDIPADAR CKT-1 -Bay chargedupto few towers for Antitheft .

LILO of Korba- Budipadar -CSEB CKT at400/220kV Raigarh ss is pending.2 400/220 kV Mapusa SS 3x315 MVA,400/220kV 6 Nos (i) 220 kV Mapusa- Amona ckt(ii) 220 kV Mapusa- Ponda ckt(iii)220 kV Mapusa - Tivim ckt -1(iv) 220 kV Mapusa - Tivim ckt -2

(i) 220 kV Mapusa - Saligao ckt -1(ii) 220 kV Mapusa - Saligao ckt -23  765/400/220 KV Solapur SS 2x315 MVA &1x500 MVA,400/220kV  6 Nos i) 220 KV Solapur Kumbhari Ckt - Iii) 220 KV Solapur Kumbhari Ckt - IIiii) 220 KV Solapur Jejuriv)(400kV Solapur -Karad line is temporarilycharged at 220kV level by MSETCL)

i) 220 KV Solapur Narangwadi Ckt - Iii) 220 KV Solapur Narangwadi Ckt - II

4 400/220 kV Pune SS (Talegaon) 3x315 MVA,400/220kV  6 Nos i) 220 kV Talegao -1(MSETCL )ii)220 kV Talegao - 2(MSETCL )i)220 kV Urse -1(MSETCL)ii)220 kV Urse -2 (MSETCL)iii)220 kV Chakan -1(MSETCL)iv)220 kV Chakan -2 (MSETCL)

5 765/400/220KV Wardha Substation 2x315 MVA,400/220kV 06 Nos i) 220kV Deoli-Wardha S/Cii) 220kV Deoli-Bhugaon S/Ciii) 220kV Deoli-Badnera S/Civ)220kV Deoli-Pusad S/Ci) Deoli-Ghatoli Ckt#1ii) Deoli-Ghatoli Ckt#2

6 400/220kV Raipur SS 3x315 MVA,400/220kV 6 Nos i) Urlaii) Khedamaraiii) Bhilai 3iv) Doma (Earlier Bhatapara)i) Doma 1 (not connected)ii) Doma 2 (not connected)CSEB lines7 400/220kV Navi Mumbai GIS SS 2x315 MVA,400/220kV 02 Nos Nil 2 nos new lines

Sl. No. ISTS Substation Voltage Ratioin Use

No of 220kV lineBays under

construction220kV Lines emanating from Substation Status of 220kV lines to be connected by

STU

1 400/220 kV Mapusa SS 3x315 MVA,400/220kV 2 Nos As mentioned above (i) 220 kV Mapusa - Tuem ckt -1(ii) 220 kV Mapusa - Tuem ckt -22 400/220kV Parli SS 2x500 MVA,400/220kV 04 Nos Nil i. LILO of one circuit of Parli - Harangul 220 kVline at Parli (PG) substation.ii. LILO of Parli - Osmanabad 220 kV S/C line atParli (PG) substation.

1.1 Status of unutilized 220kV Line Bays at Existing Substation in WR-I

1.2 Status of Under Construction 220kV Line Bays at New Substation / Substation Extension in WR-I

Page 35: Mailing List - wrpc.gov.in

Date: 10.04.2018PGCIL WR-1

1 LILO of Lonikhand-Kalwa at Navi Mumbai GIS-JSL/LS Cable

2011 Sep'17 In line with decision of 41st meeting of Standing Committee Meeting heldon 21.12.16, joint site visit was carried out on 07.04.2017 by CEA, CTU &MSETCL for ascertaining the implementation feasibility of 220 kV outletfrom 400/220 KV GIS Navi Mumbai POWERGRID Substation. Inmeeting, MSETCL said that due to ROW issue, it is not possible for themto lay 220 kV Line and same to be included in proposed modified TS forproviding ISTS 400 KV feed to NaviMumbai(to be implemented throughTBCB route). Accordingly, the implementation of transmission system,which includes 400 KV ISTS feed and laying of new 220 KV Lines for400/220 KV GIS Navi Mumbai connection needs to be expedited.

Target date Sep 2018

2 400 KV Wardha-Aurangabad Line (Upgradable to1200 kV Voltage Level)

2014.00 Feb'19 Severe RoW problems. 1 tower balance

3 765 KV Aurangabad-Padghe Tr. Line 2015.00 Dec'17 Commissioned in Dec'17

4 400 kV Padghe (PGCIL)-Padghe(MSETCL)/Kudus Tr. Line

2015.00 Dec'17 Commissioned in Dec'17

5 400 KV Solapur(NTPC)-Solapur(PG) Line-2 2016.00 Sep'17 Commissioned in Sep'17

6 400 KV Aurangabad-Boisar Line(WR-I portion) 2015.00 Dec'17 Commissioned in Dec'17

7 765 kV D/C Jharsuguda-Dharamjaygarh 2016.00 May'18 Work under progress 8 towers balance

8 800kV Raigarh-Pugalur(Western Region Portion) Sep-19 Mar'19 Work under progress.

POWERGRID WARORA TRANSMISSION LTD (TBCB Project)

StatusAnticipated

completion

Target

RemarkS.N Name of Transmission Line Actualtarget date

Page 36: Mailing List - wrpc.gov.in

13 765 kV D/C Gadarwada-Warora TL ,Part-3 Nov-17 May'18 Work under progress Works completed. Finalchecking under

progress.14 LILO of both Ckts. Of 400 kV Wardha-Parli at

WaroraNov-18 May'18 All Works completed except final Tapping of Existing 400KV D/C Wardha

Parli TL.Tapping planned in Second/Third Week of April'18.

Works completed. Finalchecking under

progress.

POWERGRID PARLI TRANSMISSION LTD (TBCB Project)14 765 kV D/C Warora-Parli Line Jan-18 May'18 Work under progress Stringing approx 10km

balance.15 765 KV D/C Parli - Solapur TL Jan-18 Apr'18 Works completed. Final

checking underprogress.

16 400 KV D/C Parli - Parli TL Jan-18 Apr'18 Works completed. Final

B) Completed Transmission projects in year 2017-18 so Far - POWERGRID (WESTERN REGION-I)

1 765 KV Aurangabad-Padghe Tr. Line2 400 kV Padghe (PGCIL)-Padghe

(MSETCL)/Kudus Tr. Line3 400 KV Solapur(NTPC)-Solapur(PG) Line-24 400 KV Aurangabad-Boisar Line(WR-I portion)

S.N Name of Transmission Line

Page 37: Mailing List - wrpc.gov.in

1 400kV D/C Kakrapar APP - Vapi T/L. 233.6 29-Jun-172 400kV D/C Kakrapar APP - Navsari GIS T/L. 76.9 29-Jun-173 400kV D/C (Quad) Mauda-II - Betul GIS T/L 173.0 24-Aug-174 400kV D/C (Quad) Betul GIS - Khandwa T/L. 337.2 24-Aug-175 LILO of 400kV D/C Mundra UMPP - Limbdi T/L at Bhachau S/s. 45.3 30-Oct-176 400kV D/C Aurangabad - Boiser (Part-II) T/L. 338.1 29-Dec-177 400kV D/C Kala - Kudus T/L 120.1 31-Dec-178 LILO of 400kV D/C Vindhyachal - Jabalpur (2nd Circuit 3&4) T/L atREWA Pooling Station. 115.7 Charged on 24-Mar-189 765kV D/C Jabalpur Pool - Orai T/L. 721.2 Charged on 25-Mar-18

10 LILO of 765kV S/C Satna - Gwalior T/L at Orai S/S. 36.7 Charged on 25-Mar-18Under Consultancy

9 220kV D/C Magarwada - Ringanwada T/L. 12.3 01-Nov-17Under TBCB Route

10 765kV D/C Jabalpur Pool - Gadarwara T/L. 204.5 31-May-17

Completed Transmission Line Projects in FY 2017-18WR-2

Sr. No. Name of Transmission Line Length in Ckt. Km. Date of Completion

Page 38: Mailing List - wrpc.gov.in

ANNEXURE-A

1 765kV D/C Banaskantha - Chittorgarh (Part-I) T/L. Nov-18 Oct-182 765kV D/C Banaskantha - Chittorgarh (Part-II) T/L. Nov-18 Oct-183 400kV D/C Banaskantha - Sankheri (GETCO) T/L. Oct-18 Oct-184 765kV D/C Bhuj - Banaskantha (Part-I) T/L. Oct-18 Oct-185 765kV D/C Bhuj - Banaskantha (Part-II) T/L. Oct-18 Oct-186 765kV D/C Bhuj - Banaskantha (Part-III) T/L. Oct-18 Oct-187 765kV D/C Bhuj - Banaskantha (Part-IV) T/L. Oct-18 Oct-188 765kV D/C Bhuj - Banaskantha (Part-V) T/L. Oct-18 Oct-189 400kV D/C Banaskantha (Radhanesda) - Banaskantha (PG)T/L. Mar-19

Anticipated

CompletioRemarks

(A) Status of Progress of On-going Transmission schemes undertaken by Transmission Utility as on 12th April 2018WR-2

Sr. No. Name of Transmission Line

Page 39: Mailing List - wrpc.gov.in

ANNEXURE-A

1 400kV D/C Mundra UMPP - Bhuj T/L. Oct-18 Scheduled for dec 18Under TBCB Route2 765kV D/C Vindhyachal - Jabalpur (Part-I) T/L. Jun-18 Sep-183 765kV D/C Vindhyachal - Jabalpur (Part-II) T/L. Jun-18 Sep-184 765kV D/C Vindhyachal - Jabalpur (Part-III) T/L. Jun-18 Sep-185 765kV D/C Vindhyachal - Jabalpur (Part-IV) T/L. Jun-18 Sep-186 765kV D/C Gadarwara STPP - Warora (Part-I) T/L. May-187 765kV D/C Gadarwara STPP - Warora (Part-II) T/L. May-18

(A) Status of Progress of On-going Transmission schemes undertaken by Transmission Utility as on 12th April 2018WR-2

AnticipatedCompletion

TargetRemarksSr. No. Name of Transmission Line

Page 40: Mailing List - wrpc.gov.in

Sl. No. ISTS SubstationVoltage Ratioin Use

Status ofBays

220kVLines

emanating from

Substation

No. ofCkt.

Status of220kV Lines

1 Pirana 2x315MVA,400/220kV2 nos. Baysready since19/03/2015 (WRSS-

Pirana -Barejadi220kV D/c 2 GETCO mayupdate2 Boisar 2x315 +500MVA,400/220kV

1 no. Bayready since30/05/2015Boisar -Borivalli220kV S/c 1 MSETCL mayupdate

3 Vadodara GIS 2x500MVA, Bays readysince 220kVVenkatpura - 4 GETCO mayupdate4 Betul GIS 2x315MVA, Bays readysince LILO ofSarni - 2 MPPTCL mayupdate5 Rewa PS 2x500MVA, Bays readysince RewaUMSPP - 3 MPPTCL mayupdateSl. No. ISTS Substation Propos

edCommissi

oning765kVLines

No. ofCkt.

Status of765kV Lines

Remarks1 Vindhyachal Pool 765kV 1 Bays readysince Sasan UMPP -Vindhyachal 1 UC Adani mayupdateSl. No. ISTS Substation Propos

edCommissi

oning220kVLines

No. ofCkt.

Status of220kV Lines

RemarksIndore (PG) -Indore (MP)220kV D/c 2Indore (PG) -Ujjain (MP)220kV D/c 2Future 2 To be plannedby MP2 Navsari GIS 2x315MVA + 1x500MVA, 400/220kV 2 May '18(DGEN Navsari -Bhestan _ Planned GETCO mayupdate3 Khandwa S/s 1x500MVA, 400/220kV 2 September'19 (WRSS- Khandwa(PG) - 2 UC MPPTCLmay updateSl. No. ISTS Substation Propos

edCommissi

oning400kVLines

No. ofCkt.

Status of400kV Lines

Remarks1 Indore (PG) 400kV 2 July '18(WRSS-16) Indore (PG) -Ujjain (MP) 2 UC MPPTCLmay update2 Vadodara GIS 400kV 2 May '18(DGEN DGEN TPS(Dahej) - 2 Planned DGEN mayupdate the3 Gwalior GIS 400kV 2 January '18(IPPs in Gwalior -Morena 2 UC Adani mayupdate4 Rajgarh 400kV 1 May '18(Khargone KhargoneTPS - 1 UC NTPC Bay isUnderSl. No. ISTS Substation Propos

edCommissi

oning765kVLines

No. ofCkt.

Status of765kV Lines

Remarks1 Indore (PG) 765kV 2 May '18(Khargone Khandwa PS(TBCB) - 2 UC Sterlite mayupdate

MPPTCLmay update

1.4 Status of Under Construction 765kV Line Bays at New Substation / Substation Extension in

1.1 Status of unutilized 220kV Line Bays at Existing Substation in WR

Status of unutilized 765kV Line Bays at Existing Substation in WR

1.3 Status of Under Construction 400kV Line Bays at New Substation / Substation Extension in

1.2 Status of Under Construction 220kV Line Bays at New Substation / Substation Extension in

1 Indore (PG) 2x500MVA, 400/220kV 6 July '18(WRSS-14) Targeted to becompleted byMarch-2019

Page 41: Mailing List - wrpc.gov.in

ANNEXURE ATRANSMISSION SCHEMES BEING IMPLEMENTED BY ADANI TRANSMISSION LIMITED

A Status of Progress of Ongoing Transmission lines undertaken by Transmission Utility as on 12.04.2018

ADANI TRANSMISSION LTD

I Sipat Transmission Limited

1 Sipat STPS - Bilaspur 765 KV S/C May'18 Bilaspur Bay (PG) completion required by May'18 Nov 18 schedule date2 Bilaspur - Rajnandgaon 765 KV D/C Completed Mar'18 Bilaspur Bay (PG) completion required by May'18 Scheduled mar 19

II Raipur - Rajnandgaon Warora Transmission Limited

1 Raipur - Rajnandgaon 765 KV D/C Completed in May'17 Raipur (PG) Bay is ready Scheduled nov 182 Rajnandgaon - Warora 765 KV D/C Oct'18 Severe ROW in Maharashtra Scheduled nov 18

III Chhattisgarh - WR Transmission Limited

1 Gwalior - Morena 400 KV D/C Completed in Sept'17 scheduled may 18

2 Vindhyachal STPS - IV & V - Vindhyachal Pool 400 KV D/C Completed in Dec'17 Sucessfully charged on 15th Mar'18 scheduled jan 19

3 Sasan UMPP - Vindhyachal Pooling Station 765 KV S/C Completed in Nov'17 scheduled nov 184 Raigarh (Kotra) - Champa (Pool) 765 KV S/C May'18 PGCIL 765 kV Bay at Raigarh & Champa pool required

by May'18scheduled nov 18

5 Champa (Pool) - Dharamjaygarh 765 KV S/C May'18 PGCIL 765 kV Bay at Champa pool & Dharamjaigarhrequired by May'18

scheduled nov 18

6LILO of one ckt of Aurangabad - Padghe 765 KV D/C line atPune

Nov'182 Nos. 765 kV Bays at Pune required by Sept'18.Severe ROW.

scheduled mar 19

1 765 kV Rajnandgaon Substation Completed in Nov'17 Scheduled nov 182 400/220 kV Morena Substation Completed in Mar'18 scheduled may 18B Completed Transmission Projects in year 2016-17 so far:

Sr.No.

Name of Transmission Line

NIL

WRPCrecord

Sr.No. Remark

Anticipated CompletionTargetName of Transmission Line

Sr.No.

Name of Sub station Anticipated CompletionTarget

Remark

Page 1 of 1

Page 42: Mailing List - wrpc.gov.in

ANNEXURE-A

Stub settingcompleted

Towererected

Stringingcompleted

1400kV D/C Mahan Sipattransmission line

674 942 942 942 599.84 Jun-18out of 37 km stringingunder progress in 10 routekm.Severe Row issues.

Remark:1. Extremely heavy ROW challenges in Balrampur, Surajpur District of CG.2. Farmers are demanding very high compensation and not allowing labour to enter field to carry out stringing activity.3. Working under police protection in Singrauli district of MP & Balrampur district of Chhattisgarh.

EPTCLA) Status of Progress of Ongoing Transmission Schemes undertaken by Transmission Utility as on 31.03.2018

Sr.No Name of Transmission lineLength inCkt Km

TotalLocation

Present Status as on 31.03.2018 Anticipatedcompletion

TargetRemark