M41 Merri Creek to MCG Water Main Renewal Project July 2017
Key project dates
July 2017
Edinburgh Gardens, Fitzroy North George Street, Fitzroy
The M41 water main supplies drinking water to over 350,000 residents and businesses in Melbourne’s inner suburbs. It runs from Merri Creek, Northcote to Wellington Parade, East Melbourne.
The existing water main is almost 100 years old and deteriorating. Leaks have created significant community disturbance during emergency repair works.
M41 water main repair works
Project completionLate 2019
Construction Begins late 2017
Functional designLate 2016 - Mid 2017
Project announcementLate 2016
Stakeholder and community engagement
More information For more information about the M41 Merri Creek to MCG Water Main Renewal Project and to register for updates:
Phone 1800 316 713Email [email protected] www.yoursay.melbournewater.com.au/m41
For general enquiries contact Melbourne Water:Phone 131 722 Email [email protected]
Have your say Melbourne Water wants to hear your feedback on the
M41 Merri Creek to MCG Water Main Renewal Project.
Your feedback will be considered as part of the project’s planning process.
Visit our website or contact us via our email address: [email protected]
TTY and Interpreter Services: TTY 133 677 Interpreter 131 450
July 2017
M41 project team members will be available to discuss project planning and answer questions at our community information sessions:
1. Date: Thursday 10 August 2017 Time: 4pm to 8pm Location: Fitzroy Town Hall, Napier Street, Fitzroy
2. Date: Saturday 12 August 2017 Time: 11am to 3pm Location: Bargoonga Nganjin, North Fitzroy Library, 182 St Georges Road, Fitzroy North
M
ERRI
CRE
EK
NICHOLSON ST NICHOLSON ST
BRUNSWICK ST
ALB
ERT
ST
WELLINGTON ST
SMITH ST
WELLINGTON ST
CLARENDON ST
HODDLE ST
PUNT RD
MARK ST
HO
LDEN
ST
ST GEORGES RD
PARK
ST
FITZROYHIGH SCHOOL
GEO
RG
E ST
EAD
ES S
T
JAMIESO
N ST
MELBOURNEMUSEUM
ROYALEXHIBITIONBUILDING
FITZROYGARDENS
MELBOURNECRICKET GROUND
ROYAL BOTANICGARDENS
FALCONER ST ALBERT ST
MERRI PDE
BRU
NSW
ICK
RD
RATHDOWNE ST
LYGON STLYGON ST
ST GEORGES RD
APPERLEY ST
FITZROY
FITZROY NTH
MELBOURNE CBD
EAST MELBOURNE
CARLTON
YARR
A RIVER
PARLIAMENT HOUSE
ST PATRICK’S CATHEDRAL
RUSHALL
FLINDERS ST
VIC
TOR
IA P
DE
GER
TRU
DE
ST
WEL
LIN
GTO
N P
DE
GEORGE STGEORGE ST
ALE
XA
ND
RA
PD
E
JOH
NST
ON
ST
QU
EENS PD
E
COLLINGWOOD
EDINBURGHGARDENS
OTHER WORKS IN THE AREA
Alexandra Parade main drain re-decking project
Melbourne Water is also working in the local area to replace deteriorating parts of roof panels protecting the main drain that runs under the Alexandra Parade median. The drain safely carries stormwater away from local suburbs to avoid extensive flooding during heavy rainfall.
The areas highlighted on the map above show where the work will take place. A number of trees are growing over the drain and may need to be removed for construction works to take place. We will be able to provide further information regarding tree removal once the contractor has been appointed in mid-2017.
For more information visit www.melbournewater.com.au/alexandraparade email [email protected] or telephone 1800 316 713
NORTHERNCONNECTION
POINT
SOUTHERNCONNECTION
POINT
SCO
TCH
MER
ST
BENNETT ST
Project overview Melbourne Water has worked with our design contractor
John Holland-KBR to develop a preferred option, shown
on the map above. The preferred option takes into
consideration a number of important factors such as social
and environmental impacts, as well as technical
constraints and cost.
Community feedback has also been incorporated in the design
process. We heard from many residents and local community
members about the importance of trees, particularly mature
trees and parkland, and we will avoid tree removal where possible.
We are committed to returning any parkland to original
or improved condition.
In some places, such as Bennett and Falconer Streets, the
preferred option differs from the existing alignment. Some
residents will experience construction disruption although the
existing M41 water main does not currently run through their
street. We apologise in advance for this inconvenience and
we will talk directly to these residents. Residents are also able
to contact us or attend one of our community sessions for
more information.
Next Steps Once Melbourne Water has informed the community about
the preferred option and gathered feedback, the process
to appoint a construction contractor for the detailed design
and construction works will occur. We expect this process
to take place in late 2017.
We will continue to engage with key stakeholders, community
members and local business throughout this process and seek
further feedback. The contractor will also further engage local
people during construction to gain a better understanding
of any needs, issues or concerns about the project.
Replacing the M41 water main is a major construction project.
The water main is 1150mm in diameter and will require
excavation of a large trench so that it can be installed.
While we are committed to retaining all mature trees in
Edinburgh Gardens, some local impacts may include vegetation
and tree removal, increased dust, noise, local road closures and
associated traffic disruption. We apologise in advance for any
disruption caused by these essential works.
M41 Merri Creek to MCG Water Main Renewal Project July 2017
M41 PREFERRED OPTION
EXISTING M41 WATER MAIN
MAP NOT TO SCALE.NB. ROUTE IS NOT YET FINAL AND SUBJECT TO CHANGE.
TUNNEL UNDER MAIN ARTERIAL
ALEXANDRA PDE MAIN DRAIN PROJECT
ROUTE TO BE DETERMINED
Artist’s impression of the construction zone at George Street, Fitzroy
We heard from residents about the importance of parkland and mature trees in the local community.