M-25 over Harbor Beach Creek

Upload: kayla-munoz

Post on 26-Mar-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Page 2: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Bridge to Culvert Replacement• $1.27M Programmed Cost

– $270,000 Innovative Bridge Research and Deployment Program Federal Grant

Existing Harbor Beach Creek Bridge

Page 3: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Composite Arch Culvert System

• aka “Bridge in a Backpack”

Page 4: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

“Bridge in a Backpack”

Installing arches

Composite decking

Arches inflatedand formed

Page 5: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

“Bridge in a Backpack”Filling arches with concrete

FasciaBackfill to road

Page 6: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Traffic currently detoured

• Fix Life of >75 years

• Every Day Counts

• Faster + Cheaper + Safer + Smarter = Better

Existing Harbor Beach Creek Bridge

Page 7: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Started in Spring 2012

• Original completion date August 25

Sixteen 12” diameter arch tubes arriving at project site

Page 8: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Arch end section

Inlet holes for concrete

Page 9: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Large lateral forces from arches required battered piles

First arch rib install

Page 10: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Reinforcement for arch end anchoring into abutment

Multiple arch tubes installed

Page 11: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Arch tube installation complete

Finishing concrete around arch tube endings

Page 12: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Composite decking installation

Page 13: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Expansive Self Consolidating Concrete (SCC) slump flow test

Measuring slump flow

Page 14: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

Filling arches from top with SCC

Sounding for voids – 8/9

Page 15: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Challenges:• Still need a conventional deep foundation• Remote project location, readi-mix supplier 1 hour away• Issues with SCC remaining fluid and workable long enough• Concrete setting too fast in arch ribs causing voids

• Working with AIT to resolve issues:• Revising SCC mix with additional admixtures• Drilling additional holes in arch ribs to fill voids with grout• Identify high stress areas via finite model to avoid drilling in those

locations

Page 16: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• When arches complete and composite with concrete, a 7” concrete overlay will be cast over the composite decking for lateral stability

• Decorative composite finish will be placed on headwalls and wingwalls

• Placement of roadway fill and pavement section

Page 17: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

M-25 over Harbor Beach Creek

• Design specifications recently voted on and approved by AASHTO Subcommittee on Bridges and Structures

Page 18: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

MDOT CFRP Implementation: Building bridges for the 21st century

AASHTO Subcommittee on Bridges & Structures

Technical Committee T-6 Austin, TX, July 9, 2012

Matt Chynoweth, Engineer of Bridge Field Services

Page 19: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Existing Structure

Two span simply supported prestressed I-beam structure in poor condition (based on NBIS ratings)

MDOT CFRP Deployment• Pembroke over M-39 Bridge Replacement

Page 20: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Materials stored at Detroit Maintenance Garage through winter and spring of 2011

MDOT CFRP Deployment• Pembroke Bridge CFCC cables

Page 21: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Special provisions for handling instructions were written for installation

MDOT CFRP Deployment• NEFMAC Grid installation

Page 22: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Finished installation

MDOT CFRP Deployment• NEFMAC Grid installation

Page 23: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Measuring deck deflections, deck strains and PT tendon loads

MDOT CFRP Deployment• Monitoring and Data Collection

Page 24: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

MDOT CFRP Deployment• Complete Pembroke Structure

Photos taken October 2011

Page 25: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Existing structure

Project let January 2012

MDOT CFRP Deployment• M-50/US-127 BR over NS RR

Page 26: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Cables were double sheathed and fed into 5” conduits

MDOT CFRP Deployment• M-50 Bridge CFCC cables

Page 27: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Cables were double sheathed and fed into 5” conduits

MDOT CFRP Deployment• M-50 Bridge CFCC cables

Page 28: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Fabricator’s stressing chair: cables stressed to 75 kips, then 150 kips once deck is placed & cured

MDOT CFRP Deployment• M-50 Bridge CFCC cables

Page 29: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Load cells placed on dead end measure micro-strain, which is converted to force

MDOT CFRP Deployment• M-50 Bridge CFCC cables

Page 30: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Steel/CFRP stirrups along the span

Steel/CFRP stirrups at diaphragms

Transverse ducts for TPT

Steel/CFRP prestressing strands

Page 31: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Next Steps

Other research:

• MDOT project OR14-24: Evaluating Long Term Capacity and Ductility of Carbon Fiber Reinforced Polymer prestressing and post tensioning strands subject to long term losses, creep, and environmental factors

• To begin in FY 2013

• NCHRP 12-97: Design Guidelines for Field Deployment CFRP prestressed beams in Bridge Construction

• MDOT submitted research idea

Page 32: M-25 over Harbor Beach Creek. Bridge to Culvert Replacement $1.27M Programmed Cost –$270,000 Innovative Bridge Research and Deployment Program Federal

Thank you

Questions?