lwc-04 on whimpey creek horizontal plastic belt pod screen
DESCRIPTION
Need for other types of POD screens Idea to build a horizontal plastic belt screen Fabrication crew talking about ideas and materials Jim Jones contacted Hydrolox and ordered plastic belt materials after discussions with their Engineers Harvey Goddard assigned to take lead on projectTRANSCRIPT
LWC-04LWC-04On Whimpey CreekOn Whimpey Creek
Horizontal Plastic Horizontal Plastic Belt POD ScreenBelt POD Screen
Process – Start to FinishProcess – Start to Finish
• Design ideas• Contact Hydrolox and purchase materials• Overcoming problems during fabrication• Input from engineer• Changes during fabrication• Finding a site for installation• Installation• Monitoring and evaluating screen operation
• Need for other types of POD screens• Idea to build a horizontal plastic belt
screen• Fabrication crew talking about ideas and
materials• Jim Jones contacted Hydrolox and
ordered plastic belt materials after discussions with their Engineers
• Harvey Goddard assigned to take lead on project
Monitoring and EvaluationMonitoring and Evaluation
• 2.47 cfs design flow• Hydrolox Series 1800 mesh top with 37%
open area• 1.10 cfs measured flow• Water level was to low to accurately
evaluate both sweeping velocity and velocity through the screen