ls1 general planning and strategy for lhc, lhc injectors
DESCRIPTION
LS1 general planning and strategy for LHC, LHC injectors. LHC Performance Workshop Chamonix 2012 K. Foraz. Outline. General frame Injectors LHC machine : Main activities and risks Organization Conclusion. General frame Injectors LHC machine : Main activities and risks Organization - PowerPoint PPT PresentationTRANSCRIPT
K. Foraz - LHC Performance Workshop 2012 1
EN
LS1 general planning and strategy for LHC, LHC injectors
LHC Performance Workshop Chamonix 2012
K. Foraz
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012 2
EN Outline
Feb. 8th 2012
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
K. Foraz - LHC Performance Workshop 2012 3
EN Draft 10 years plan (27/10/11)
Feb. 8th 2012
2012 2013 2014 2015 2016
2017 2018 2019 2020 2021
Operation period 1 (OP1) Long Shutdown 1 (LS1)
• Machine : Splices consolidation…• ATLAS: - Consolidation and new forward beam pipes• ALICE: detector completion• CMS:FWD muons upgrade + Consolidation & infrastructure
improvements• LHCb: consolidations
•Machine: Collimation & prepare for crab cavities & RF cryo system•ATLAS: new pixel detect. - detect. for
ultimate luminosity.•ALICE - Inner vertex system upgrade•CMS - New Pixel. New HCAL
Photodetectors. Completion of FWD muons upgrade•LHCb - full trigger upgrade, new vertex
detector etc.
Long Shutdown 2 (LS2)
Operation period 3 (OP3)
Operation period 2 (OP2)
OP2
LINAC 4 connection ?
K. Foraz - LHC Performance Workshop 2012 4
EN LS1 - Goal
Feb. 8th 2012
Take all measures for a safe and reliable operation of LHC @ 7TeV/beam
Full maintenance Consolidation & upgrade
LHC machine & experimentsInjectors
K. Foraz - LHC Performance Workshop 2012 5
EN LS1 - Time window
Feb. 8th 2012
• 20 months from Beam OFF to Beam ON– Actual total duration agreed between experiments and
machine• LHC machine: 20 months• ALICE: 12 months (up to 15 months)• ATLAS: 15 months (but from April 2013)• CMS: 20 months• LHCb: 12 months
Marzio: “ LHC experiments upgrade & maintenance”
K. Foraz - LHC Performance Workshop 2012 6
EN Requests Approval
Feb. 8th 2012
• Meetings being held with stakeholders to understand Goal of activities Time key drivers Support needed
• For accelerator complex: database of requests is being filled : LHC and injectors
To detect conflicts/overloads & to decide what is compulsory, what we can afford &what we have to postpone to LS2
Priorities set for LHC machine– P1: Beam to 6.5-7TeV, nominal performance– P2: Reliable operation– P3: CERN approved projects– P4: no CERN approved projects
• Mauro : “EN-CV upgrade & consolidation”• Francois: “EN-EL upgrade & consolidation”• Erk : “RF upgrade program in LHC injectors
and LHC machine“
K. Foraz - LHC Performance Workshop 2012 7
EN Outline
Feb. 8th 2012
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
K. Foraz - LHC Performance Workshop 2012 8
BA2
BA1
BA4
BA3
BA6
BA5
TI2
BA7
BA80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.
2013
2014
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lina
c 3
Lina
c 2
CTF
Lina
c 4
AD $
ELE
NA
HI-I
SOLD
ESPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012
Irrad
iate
d ca
bles
Irrad
iate
d ca
bles RF
Upg
rade
Dec
ablin
g ca
mpa
ign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
Power Converter Consolidation
Other groups: BI, CO works
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
• “Normal” Xmas shutdown (*2)• Survey: measurements, til, alignment• SPS:
• EL: clear unused cables & irradiated cables in SPS• RF upgrades• Power converter consolidation• Other groups works Courtesy D. McFarlane
V. Chohan
Will be detailed during
IEFC workshop
K. Foraz - LHC Performance Workshop 2012 9
BA2
BA1
BA4
BA3
BA6
BA5
TI2
BA7
BA80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.
2013
2014
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lina
c 3
Lina
c 2
CTF
Lina
c 4
AD $
ELE
NA
HI-I
SOLD
ESPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012
Irrad
iate
d ca
bles
Irrad
iate
d ca
bles RF
Upg
rade
Dec
ablin
g ca
mpa
ign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
Power Converter Consolidation
Other groups: BI, CO works
General Shutdown works: ABT, Magnets, RP, lifts…
Renovation of Vacuum control system
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
Cooling & Ventilation maintenance & renovation
RF maintenance & upgradeNew Access systemOther groups : BI, CO,…
New access system commissioning
• PS & PS booster• Renovation of vacuum control system• Cooling & ventilation maintenance and renovation• RF maintenance & upgrade• New access system • Other groups works• Interlock
InterlckInterlck
InterlckInterlck
Courtesy D. McFarlane V. Chohan
General Shutdown works: ABT, Magnets, RP, lifts…
K. Foraz - LHC Performance Workshop 2012 10
EN Injectors access system
Feb. 8th 2012
Rui: “Access strategy in the accelerator complex and experimental area”
Courtesy E. Sanchez
K. Foraz - LHC Performance Workshop 2012 11
BA2
BA1
BA4
BA3
BA6
BA5
TI2
BA7
BA80
TI8
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Sec.
6
Sec.
5
Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.
2013
2014
EN
Sec.
2
Sec.
1
Sec.
4
Sec.
3
Lina
c 3
Lina
c 2
CTF
Lina
c 4
AD $
ELE
NA
HI-I
SOLD
ESPS PS PS Booster
v v
General Shutdown works: ABT, Magnets, RP, lifts…
General Shutdown works: ABT, Magnets, RP, lifts…
Injectors
Feb. 8th 2012
Irrad
iate
d ca
bles
Irrad
iate
d ca
bles RF
Upg
rade
Dec
ablin
g ca
mpa
ign
Survey: Tilt & vertical - Quads
Survey
Surv
ey
Surv
ey
Power Converter Consolidation
Other groups: BI, CO works
Cold Checkout & Start-up
Renovation of Vacuum control system
Survey: Alignment maintenance
Survey: Vertical & Radial measurements & Alignment
InterlckInterlck
InterlckInterlck
Cooling & Ventilation maintenance & renovation
RF maintenance & upgradeNew Access systemOther groups : BI, CO,…
New access system commissioning
Cold Checkout & Start-up
Set u
p of
Arg
on
& X
enon
bea
m
(1)
Set u
p of
Arg
on &
Xe
non
beam
(2)
LIN
AC 4
com
miss
ioni
ng
AD h
all p
repa
ratio
n fo
r ELE
NA
CV
CTF
oper
ation
al d
ates
TBC
• Early 2014 :Cold check-out and Start up• LINAC3 : set up of Argon and Xenon beam• LINAC4 commissioning• CTF operational – dates TBC• HI-ISOLDE: Cooling & Ventilation works• AD & ELENA: AD hall preparation for ELENA
Courtesy D. McFarlane V. Chohan
K. Foraz - LHC Performance Workshop 2012 12
EN Outline
Feb. 8th 2012
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
K. Foraz - LHC Performance Workshop 2012 13
EN LHC machine – Time key drivers
Feb. 8th 2012
• Time key drivers in LHC machine– Superconducting circuits consolidation– Radiation To Electronics R2E– Maintenance
– …. And many other activities (already > 100 entries in the db for LHC machine)
K. Foraz - LHC Performance Workshop 2012 14
EN One typical sector
Feb. 8th 2012
Powering and ELQA tests prior to Warm-up (4+4 d)• qualify circuits except mains to 7TeV• fault localization..• CSCM (1 sector)
Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks
Maintenance & consolidationPreparation for & cool-down
Powering tests
Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ”
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 15
Splices
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Jean-Philippe : “LHC consolidation of the
superconducting circuits ”
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 16
Other superconducting circuits
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Magnets exchange
DN200
Consolidation of SAM
Inner triplets braid Connection Cryostat
Y lines
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 17
Maintenance
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryogenics : 18 weeks per cryoplant+ Maintenance of all the equipment: CV, EL, RF…, mainly in service areas
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
K. Foraz - LHC Performance Workshop 2012 18
EN R2E mitigation measures
Feb. 8th 2012
• Detailed & graphical schedules ready, except P7 in progress
Courtesy M. Barberan
Anne-Laure : “R2E strategy and activities during LS1 ”
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 19
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
R2E mitigation measures
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
R2E
R2E
R2E
Just in time for CD of s.12Delay by 2 wks CD of S.81
R2E
Delay Cool-down of 56 (1st sector)Delay Powering tests of 56But 1 month marginw.r.t s45
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
P7 to
be
final
ized
K. Foraz - LHC Performance Workshop 2012 20
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.
2013
2014
Jan.
EN Skeleton schedule – Physics to physics
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cold check-out & Beam Commissioning
Physics1 week stand-by 2014-2015
Ezio : What is the maximum reasonable energy
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 21
Risks (possible changes in schedule): IC trains
Feb. 8th 2012
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
From installation experience, first 2 sectors took ~ 20% longer
PT PTPT PT
PT PTPT PT
Powering Tests Powering
Tests Powering Tests Powering
Tests
Powering Tests
Powering Tests
Powering Tests Powering
Tests
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Cool-downCool-down
Cool-downCool-down
Cool-down
Cool-down
Cool-downCool-down
+ 20% +
20%
But leak detection and electrical tests at the end can reserve bad surprises in the last sectors…
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.
2013
2014
EN
K. Foraz - LHC Performance Workshop 2012 22
Risks (possible changes in schedule): R2E mitigation measures
Feb. 8th 2012
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Powering Tests Splices
Warm-up Preparation for cool-down
Cool-down
R2E
R2E
R2E
R2E
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering TestsPowering
Tests
Cool-downCool-down
Cool-downCool-down
Powering Tests
Cool-down
Cool-down
Cool-down
Powering Tests
Cool-down
P7 to
be
final
ized
P1 & P5 are tight in schedule : Effect of 6 weeks delay
No direct impact on end dates but will delay the powering tests of 3rd and following sectors.
Nov Dec Jan Feb Mar Apr May Jun0
1
2
3
4
5
6
7
Harwdware commissioning workload
6 weeks delay no delay
Nb
of s
ecto
rs
K. Foraz - LHC Performance Workshop 2012 23
S12P1 S23P2 S34P3 S45P4 S56P5 S67P6 S78P7 S81P8Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.Jan.Feb.Mar.Apr.MayJun.Jul.Aug.Sep.Oct.Nov.
Dec.
2013
2014
Jan.
EN Risk (possible changes in schedule): additional activities
Feb. 8th 2012
PT PTPT PT
PT PTPT PT
SplicesSplices
SplicesSplices
SplicesSplices
SplicesSplices
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cryo
Mai
nt.
Cold check-out & Beam Commissioning
Physics
-> 10KCSCM
CSCM preparation Warm-upWarm-up Warm-up Warm-upWarm-up Warm-up Warm-up
Warm-up
Powering Tests Powering
Tests Powering Tests
Powering Tests
Powering Tests
Powering Tests
Powering Tests
Cool-down
Cool-down
Cool-down
Cool-down Cool-down
CSCM
Cool-downCSCM
Cool-downCSCM
Powering Tests
Cool-downCSCM
CSCMCSCM
CSCM CSCM
Additional activities, especially those requiring supports from other groups can disorganize the global schedule, and induce delays.
CSCM tests in all sectors will cost around 4 weeks
K. Foraz - LHC Performance Workshop 2012 24
EN Outline
Feb. 8th 2012
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
K. Foraz - LHC Performance Workshop 2012 25
EN Organization
Feb. 8th 2012
• Schedule & logistics– Lots’of work still to be done in matter of schedule &
logistics for all the other activities w.r.t. skeleton schedule
• Preparation– ECR have to be written prior to works– Modification of the envelope of your equipment ICL– DIMR– Materials have to be ready in due time…..This has often induced
delays !!!
• Follow-up– Weekly coordination and scheduling meeting
Reiner : “QPS upgrade and machine protection during LS1 ” Miguel : “Vacuum upgrade”Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “
K. Foraz - LHC Performance Workshop 2012 26
EN Conclusions
Feb. 8th 2012
• Analysis of requests well advanced (LHC & experiments, injectors)
– w.r.t. priorities & resources & time & interaction between groups– New requests will be scrutinized, especially the support form
overloaded groups (VSC, EL, CV)
• “Skeleton” schedules for LHC machine & injectors ready
• Workload is huge and the schedule is tight
• Worksites have to be well prepared.Please do not forget layout, integration & safety