WELCOME LOW – INVESTMENT PROJECTS DEAR ALL, Here are 53 Micro / SSI units, requiring investment ranging between Irs 50 lakhs to Irs 2 crores, and are economically attractive, high on market demand and have very fast payback period. 1 SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852 Email: [email protected]

Upload: burhaan-alias-azad

Post on 04-Aug-2015

16 views

Category:

Documents


0 download

TRANSCRIPT

WELCOME LOW – INVESTMENT PROJECTS

DEAR ALL,

Here are 53 Micro / SSI units, requiring investment ranging between

Irs 50 lakhs to Irs 2 crores, and are economically attractive, high on market demand and have very fast payback period.

1

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

1. AIR AND OIL FILTERS

2

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

1. AIR AND OIL FILTERS

LAND REQUIRED : 5,000 sq ftPLANT CAPACITY : 120,000 /

YEARCOST OF PLANT, MACHINE & WORKING CAPITAL : DependsMANPOWER REQ’D : 15PAYOUT PERIOD : 2 - 3 YEARS

3

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

2. ALUMINIUM VENETIAN BLINDS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

2. ALUMINIUM VENETIAN BLINDS

LAND REQUIRED : 4000 sq ftPLANT CAPACITY : 180,000 sq met /

yearCOST OF PLANT, MACHINE & WORKING CAPITAL : 30 LakhsMANPOWER REQ’D : 8PAYOUT PERIOD : 2 - 3 YEARS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

3. ALUMINIUM FOIL

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

3. ALUMINIUM FOIL

LAND REQUIRED : 1000 sq ftPLANT CAPACITY : / yearCOST OF PLANT, MACHINE & WORKING CAPITAL : 10 LakhsMANPOWER REQ’D : 5PAYOUT PERIOD : 2 - 3 YEARS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

4. AUTO CONTROL CABLES

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

4. AUTO CONTROL CABLES

LAND REQUIRED : 3000 sq ftPLANT CAPACITY : 250,000 /

yearCOST OF PLANT, MACHINE & WORKING CAPITAL : 50 LakhsMANPOWER REQ’D : 8PAYOUT PERIOD : 2 - 3 YEARS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected] 9

5. BAKERY PRODUCTS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

5. BAKERY PRODUCTS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 10 Lakhs / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 30 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS

11

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

6. BARBED WIRE

12SMB ENVIRONMENTAL PROJECTS P LTD.

Mobile: +919860240852 Email: [email protected]

6. BARBED WIRE

- LAND REQUIRED : 2,000 sq ft - PLANT CAPACITY : 600 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 50 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS

13

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

7. BITUMEN MODIFIED ASPHALT

14

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

7. BITUMEN MODIFIED ASPHALT

- LAND REQUIRED : 10,000 sq ft - PLANT CAPACITY : 72000 / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 75 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS

15

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

8. BELT FASTENERS

16

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

8. BELT FASTENERS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 36,000 BOXES / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 55 Lakhs - MANPOWER REQ’D : 17 - PAYOUT PERIOD : 3 YEARS

17

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

9. BOLTS AND NUTS

18

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

9. BOLTS AND NUTS

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 3,000 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 175 Lakhs - MANPOWER REQ’D : 20 - PAYOUT PERIOD : 3 YEARS max

19

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

10. CARD BOARD BOXES

20

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

10. CARD BOARD BOXES

- LAND REQUIRED : 2500 sq ft - PLANT CAPACITY : 150,000 / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 55 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS max

21

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

11. CATTLE & POULTRY FEED

22

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

11. CATTLE & POULTRY FEED

- LAND REQUIRED : 12,000 sq ft - PLANT CAPACITY : 2500 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 75 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

23

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

12. CHAINLINK FENCING

24

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

12. CHAINLINK FENCING

- LAND REQUIRED : 2,000 sq ft - PLANT CAPACITY : 12 T / DAY - COST OF PLANT, MACHINE

& WORKING CAPITAL : 10 Lakhs - MANPOWER REQ’D : 6 - PAYOUT PERIOD : 3 YEARS max

25

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

13. CORN FLAKES

26

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

13. CORN FLAKES

- LAND REQUIRED : 20,000 sq ft - PLANT CAPACITY : 300 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 55 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

27

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

14. CORRUGATED CEMENT SHEETS

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +9198602852 Email: [email protected]

14. CORRUGATED CEMENT SHEETS

LAND REQUIRED : 10,000 sq ftPLANT CAPACITY : 200 SHEETS / DAYPLANT & MACH: 20 LAKHSWORKING CAPITAL: 5 LAKHSMANPOWER REQ’D: 15PAYOUT PERIOD: 2.5 YEARS

29

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

15. CORRUGATED FIBRE BOARD

30

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

15. CORRUGATED FIBRE BOARD

- LAND REQUIRED : 40,000 sq ft - PLANT CAPACITY : 16 Lakhs / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 105 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

31

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

16. CORRUGATED MS SHEETS

32

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

16. CORRUGATED MS SHEETS

- LAND REQUIRED : 5,000 sq ft - PLANT CAPACITY : 30,000 / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 80 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

33

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

17. DEHYDRATED ONION & GARLIC

34

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

17. DEHYDRATED ONION & GARLIC

- LAND REQUIRED : 12,000 sq ft - PLANT CAPACITY : 300 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 35 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS max

35

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

18. DETERGENT POWDER

36

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

18. DETERGENT POWDER

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 15000 / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 40 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

37

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

19. DIE CASTING UNIT

38

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

19. DIE CASTING UNIT

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 100 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 60 Lakhs - MANPOWER REQ’D : 7 - PAYOUT PERIOD : 3 YEARS max

39

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

20. EGG TRAYS

40

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

20. EGG TRAYS

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 10 Lakhs / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 45 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

41

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

21. ELASTIC TAPES

42

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

21. ELASTIC TAPES

- LAND REQUIRED : 2,500 sq ft - PLANT CAPACITY : 20 Lakh M / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 25 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

43

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

22. ESSENCE EXTRACTION

44

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

22. ESSENCE EXTRACTION

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 450 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 45 Lakhs - MANPOWER REQ’D : 7 - PAYOUT PERIOD : 3 YEARS max

45

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

23. EGG ALBUMIN

46

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

23. EGG ALBUMIN

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 300 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 195 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS max

47

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

24. FILE FASTENERS

48

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

24. FILE FASTENERS

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 300,000 / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 15 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

49

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

25. FLAVORED MINERAL WATER

50

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

25. FLAVORED MINERAL WATER

- LAND REQUIRED : 7000 sq ft - PLANT CAPACITY : 5000 lit / day - COST OF PLANT, MACHINE

& WORKING CAPITAL : 95 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS max

51

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

26. FRUIT, JAM, JELLY

52

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

26. FRUIT, JAM, JELLY

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 100,000 Kg / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 25 Lakhs - MANPOWER REQ’D : 5 - PAYOUT PERIOD : 3 YEARS max

53

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

27. GINGER GARLIC PASTE

54

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

27. GINGER GARLIC PASTE

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 10,000 Kg / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 8 Lakhs - MANPOWER REQ’D : 3 - PAYOUT PERIOD : 2 YEARS max

55

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

28. HDPE WOVEN SACKS

56

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

28. HDPE WOVEN SACKS

- LAND REQUIRED : 7,000 sq ft - PLANT CAPACITY : 250 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 95 Lakhs - MANPOWER REQ’D : 20 - PAYOUT PERIOD : 3 YEARS max

57

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

29. LAUNDRY SOAP

58

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

29. LAUNDRY SOAP

- LAND REQUIRED : 6,000 sq ft - PLANT CAPACITY : 150 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 22 Lakhs - MANPOWER REQ’D : 7 - PAYOUT PERIOD : 3 YEARS max

59

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

30. LEATHER BELTS

60

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

30. LEATHER BELTS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 150,000 Pc / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 15 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

61

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

31. LEATHER GARMENTS

62

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

31. LEATHER GARMENTS

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 15,000 Pc / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 40 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS max

63

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

32. LEATHER PURSES & HANDBAGS

64

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

32. LEATHER PURSES & HANDBAGS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 60,000 Pc / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 15 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 3 YEARS max

65

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

33. LEATHER SHOPPING BAGS

66

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

33. LEATHER SHOPPING BAGS

- LAND REQUIRED : 2,000 sq ft - PLANT CAPACITY : 20,000 Pc / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 12 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

67

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

34. MICROCELLULAR SHEETS

68

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

34. MICROCELLULAR SHEETS

- LAND REQUIRED : 7,000 sq ft - PLANT CAPACITY : 75,000 sheets / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 55 Lakhs - MANPOWER REQ’D : 25 - PAYOUT PERIOD : 3 YEARS max

69

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

35. MS BINDING WIRE

70

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

35. MS BINDING WIRE

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 720 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 30 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

71

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

36. OIL MILL

72

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

36. OIL MILL

- LAND REQUIRED : 15,000 sq ft - PLANT CAPACITY : 3000 T / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 225 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 4 YEARS max

73

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

37. ORANGE SQUASH

74

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

37. ORANGE SQUASH

- LAND REQUIRED : 5,000 sq ft - PLANT CAPACITY : 36,000 Lit / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 30 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

75

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

38. PAPER CUPS & GLASSES

76

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

38. PAPER CUPS & GLASSES

- LAND REQUIRED : 2,500 sq ft - PLANT CAPACITY : 50 Lakhs / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 7 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

77

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

39. PAPER NAPKINS

78

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

39. PAPER NAPKINS

- LAND REQUIRED : 2,500 sq ft - PLANT CAPACITY : 300 MT / YEAR - COST OF PLANT, MACHINE

& WORKING CAPITAL : 100 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS max

79

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

40. PAPER PIN & GEM CLIPS

80

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

40. PAPER PIN & GEM CLIPS

- LAND REQUIRED : 2,000 sq ft - PLANT CAPACITY : 500 Pc / minute - COST OF PLANT, MACHINE

& WORKING CAPITAL : 25 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 3 YEARS max

81

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

41. PLASTIC BLOW MOULDING

82

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

41. PLASTIC BLOW MOULDING

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 150 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 75 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

83

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

42. POLYETHEN COLLAPSIBLE TUBES

84

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

42. POLYETHEN COLLAPSIBLE TUBES

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 72 Lakh Tubes / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 80 Lakhs - MANPOWER REQ’D : 11 - PAYOUT PERIOD : 3 YEARS max

85

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

43. POTATO / BANANA WAFERS

86

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

43. POTATO / BANANA WAFERS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 150 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 50 Lakhs - MANPOWER REQ’D : 7 - PAYOUT PERIOD : 3 YEARS max

87

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

44. PVC PIPES & FITTINGS

88

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

44. PVC PIPES & FITTINGS

- LAND REQUIRED : 4,000 sq ft - PLANT CAPACITY : 150 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 45 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS max

89

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

45. PVC WIRE & CABLE COATINGS

90

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

45. PVC WIRE & CABLE COATINGS

- LAND REQUIRED : 3,000 sq ft - PLANT CAPACITY : 100 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 60 Lakhs - MANPOWER REQ’D : 8 - PAYOUT PERIOD : 3 YEARS max

91

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

46. SCHOOL BAGS ( CANVAS)

92

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

46. SCHOOL BAGS ( CANVAS)

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 15000 Pc / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 12 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS max

93

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

47. SPECTACLE FRAMES

94

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

47. SPECTACLE FRAMES

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 10 lakh Pcs / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 10 Lakhs - MANPOWER REQ’D : 12 - PAYOUT PERIOD : 3 YEARS max

95

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

48. THERMO FORM PLASTICS

96

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

48. THERMO FORM PLASTICS

- LAND REQUIRED : 1,500 sq ft - PLANT CAPACITY : 400 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 50 Lakhs - MANPOWER REQ’D : 5 - PAYOUT PERIOD : 3 YEARS max

97

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

49. WAX CANDLES

98

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

49. WAX CANDLES

- LAND REQUIRED : 2,500 sq ft - PLANT CAPACITY : 150 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 30 Lakhs - MANPOWER REQ’D : 9 - PAYOUT PERIOD : 3 YEARS max

99

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

50. WELDED WIRE MESH

100

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

50. WELDED WIRE MESH

- LAND REQUIRED : 10,000 sq ft - PLANT CAPACITY : 3600 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 175 Lakhs - MANPOWER REQ’D : 15 - PAYOUT PERIOD : 4 YEARS max

101

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

51. WHEAT FLOUR MILL

102

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

51. WHEAT FLOUR MILL

- LAND REQUIRED : 2,500 sq ft - PLANT CAPACITY : 150 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 25 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 4 YEARS max

103

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

52. WIRE NAILS

104

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

52. WIRE NAILS

- LAND REQUIRED : 5,000 sq ft - PLANT CAPACITY : 600 T / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 40 Lakhs - MANPOWER REQ’D : 7 - PAYOUT PERIOD : 4 YEARS max

105

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

53. WOOD SCREWS

106

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]

53. WOOD SCREWS

- LAND REQUIRED : 7,000 sq ft - PLANT CAPACITY : 9 Mil Pcs / year - COST OF PLANT, MACHINE

& WORKING CAPITAL : 25 Lakhs - MANPOWER REQ’D : 10 - PAYOUT PERIOD : 4 YEARS max

107

SMB ENVIRONMENTAL PROJECTS P LTD. Mobile: +919860240852

Email: [email protected]