losinger marazzi vision and deployment of bim · losinger marazzi - d.chevarin ¦ buildingsmart at...
TRANSCRIPT
Damien Chevarin – Head of BIM Management
Losinger Marazzi – Vision and deployment of BIM
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 2
Summary
1. BIM by Losinger Marazzi2. Use cases3. BIM at the new Limmattal hospital4. Conclusion
BIM by Losinger Marazzi
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 3
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 4
Why deploy BIM?
Complexity of projects
Customer Requirements
Multiple partners
Increasingdigitalisation
Anticipation Quality
Collaboration Efficiency
Our BIM development priorities
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 5
Customer relationship
Project Management
Site management
Our BIM development priorities
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 6
Customer relationship
Project Management
Site management
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 7
Dataorganisation: agility
Customer Geometer Architect
Architect
MEP engineers
STR engineer
EngineersGen. Contractor + All Partners
Gen. Contractor Gen. Contractor
Room by room 3D Model
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 8
Workflow
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 9
Data is our priority
3D model (from our partners)
Centralized and collaborative database
detailled definition of each element
Use cases2
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 10
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 11
Urban regeneration projects and Smart CitiesSustainable neighborhood Les Vernets – Geneva (GE)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 12
Visualization and validation with VRDecision supports / Digital mock-up
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 13
Digital mock-upClinic CIC Riviera – Clarens (VD)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 14
Business presentation with on site augmented realityLogistics building and offices – Plan-les-Ouates (GE)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 15
Design Management
BIM coordination by Losinger Marazzi (with external partner for few projects)
Use of IFC for 3D-model and BCF for the issues
Software: Solibri Model Checker
Hotel – Grand-Saconnex (GE)
Coordination meeting
BIM COORDINATOR
STRUCTURE ENGINEER
PROJECT MANAGEMENT
ARCHITECTS
MEP ENGINEERS
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 16
End-of-design documentationNeuroscience Laboratories – Prilly (VD)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 17
BIM on site
Proof of concept of multiplesolutions in progress
Neuroscience Laboratories – Prilly (VD)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 18
Delivery & logistics on siteSustainable neighborhood Eikenøtt Building A2 – Gland (VD)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 19
Prefabrication and construction methodsStudent housing – Zurich
BIM at the new Limmattal hospital3
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 20
A pilot project
The first hospital project in Switzerland in design-to-cost
One of the first projects with BIM
Voluntary approach from multiple partners to implement a BIM-process
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 21
Workflow and organisation
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 22
1st Use case: data management
Why?- To support customer relations management- To integrate the right information into the documentation
How?- at the beginning: an Excel-sheet (XX Mo with Macro)- during the optimization: dRofus (with connection to 3D-Models)
Which use cases?- View of all the rooms for execution- Quantities check (Project vs Roombook)
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 23
2nd Use Case: Coordinated Model
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 24
3rd Use Case: Quantities
Check the quantities and the costs of the project in the design phase
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 25
4th use case: Manage the time schedule
• Manage the time schedule with:- An efficient production of the “room by room” drawing (6 views)- A quality control with 3D-Model
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 26
main entrance
All Users
3D Model «Revit
Server»
3D Model
«Nova»
2D Plan «Allplan»
Database«dRofus»
Mergedmodel
«Glue»
Control model
«Field»
LearnModel«HTC»
Customers X X
Architects X X
Civil engineers X
MEP engineers X X
BIM Management X X X X X
Design Manager X X X X
Construction workers
X X X
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 27
Use of file formats
Design Execution FM Comments
IFC Yes Yes ? Models exchange
BCF No No No Technology not compatible
COBie No Test ?Test between 3dmodel+database
and Maximo
RVT Yes Yes ?
NWD Yes Yes ? Used also for the “BIM2Field”
FBX No Yes ?
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 28
Conclusion4
Losinger Marazzi - d.chevarin ¦ buildingSMART at the new Limmattal hospital ¦ 23.06.2017 29