los angeles unified school district facilities services division facilities construction contracts...

60
LOS ANGELES UNIFIED SCHOOL DISTRICT LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY: GEMARIE GUZMAN & THOMAS WARD PREQUALIFICATION UNIT

Upload: elmer-norton

Post on 01-Jan-2016

222 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

LOS ANGELES UNIFIED SCHOOL LOS ANGELES UNIFIED SCHOOL DISTRICTDISTRICT

FACILITIES SERVICES DIVISIONFACILITIES SERVICES DIVISION

FACILITIES CONSTRUCTION FACILITIES CONSTRUCTION CONTRACTSCONTRACTS

THE DISTRICT’S PREQUALIFICATION

PROGRAM

PRESENTED BY:

GEMARIE GUZMAN & THOMAS WARD

PREQUALIFICATION UNIT

Page 2: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prequalification ProgramPrequalification Program

It is the intent of the District to do business with quality contractors by identifying such contractors through a uniform system of rating bidders to obtain the best quality construction for the lowest price practicable under the circumstances.

The District’s prequalification programs are adopted pursuant to Public Contract Code 20111.5, 20111.6 and 20919.4.

Requires all contractors interested in bidding either formal or informal, competitively bid public works projects to prequalify before submitting a bid to the District

Provides standard on-going prequalification enrollment for prospective bidders

Page 3: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prequalification TypesPrequalification Types

Safety (Informal) Prequalificationo Required to bid informal contracts, JOC job orders, and

other projects for which safety prequalification is required.

Subcontractor Prequalification (MEP)o Required for Mechanical, Electrical, and Plumbing

subcontractors on formal contracts Formal Prequalification

o Required to bid formal contracts, JOC Contracts, 17406 Project-Specific Prequalification

Page 4: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prospective Bidders Interested in Prospective Bidders Interested in Bidding on INFORMAL District Bidding on INFORMAL District

Projects:Projects: Informal District contracts, $86,000 or less, are bid through the

Local District Maintenance & Operations Offices. Information on Informal contracts may be found on the LAUSD M & O Web Site @ http://mo.laschools.org/fis/existing-facilities/m-and-o/bidwalks/

Contacts and telephone numbers to the Local M & O offices are located in the Construction Bidder’s Handbook, available on the web site at http://www.laschools.org/new-site/bidding-opportunities/

Prospective bidders interested in bidding on Informal District contracts only need to be Safety prequalified.

The Contractor Safety Prequalification Questionnaire may be obtained by visiting the Prequalification website @ http://www.laschools.org/new-site/prequalification/forms.

Submit Informal Questionnaires directly to Prequalification by fax to 562-654-9499 or email to [email protected].

Page 5: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Construction Contractor Construction Contractor Safety PrequalificationSafety Prequalification

ContractorApplicantOverview

For the LAUSD School Repair and Construction Program

Page 6: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Safety Prequalification Questionnaire: Four primary sections

Sources needed to complete the Questionnaire: ◦(a) Your Insurance Carrier or Broker ◦(b) Company files

Page 7: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

IMPORTANT NOTES:IMPORTANT NOTES:

Safety Prequalification only applies to firms performing construction work for the School Repair and Construction Program.

It does not apply to suppliers, vendors and service contracts.

Page 8: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prequalification is valid for one (1) year.

Each firm must reapply prior to expiration.

Renewals: Your firm’s safety and loss history will be considered during the renewal process.

The Safety Prequalification Questionnaire is included in the Prime and Subcontractor Prequalification.

IMPORTANT NOTES:IMPORTANT NOTES:

Page 9: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

BASIC REQUIREMENTS:BASIC REQUIREMENTS:

Current and valid California Contractor’s License in good standing with the California State License Board (CSLB)

Applicant name must match the same name on the CSLB license

Page 10: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

BASIC REQUIREMENTS:BASIC REQUIREMENTS:

Workers’ Compensation (WC) insurance policy◦ required of all companies, including companies

with no employees (‘owner-operator’)◦ NO EXCEPTIONS

WC policy must identify the name of the Applicant ◦ You will be required to provide proof of

coverage in the form of a Certificate of Insurance if it does not appear on the CSLB

Page 11: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Useful Tips:Useful Tips:

Fill in every blank. Write “N/A” if not applicable.

Make sure your answers are legible. (If it can’t be read, it can’t be processed!)

Evaluation of your Questionnaire will not be completed until all information is complete and all fields are properly filled out.

Do NOT send us anything we don’t ask for in the questionnaire.

Page 12: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Applicant Applicant InformationInformation

Page 13: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:
Page 14: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Section A: Insurance Section A: Insurance InformationInformation

Page 15: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

A multiplier based on your firm’s Workers’ Compensation loss claim history that causes your insurance premiums to go up, or down.

It impacts the cost of your firm doing business.

Base Rate (Premium Rate) x EMR = Your insurance cost (Modified Rate)

What is the Experience What is the Experience Modification Rate (EMR)?Modification Rate (EMR)?

Page 16: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Where does EMR come Where does EMR come from?from?

The EMR is not calculated by your insurance broker or carrier.• California (intrastate) EMRs are

calculated by the WCIRB (Workers Compensation Insurance Rating Bureau).

• Interstate EMRs are calculated by NCCI (National Council on Compensation Insurance).

Page 17: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

In simple terms, the EMR is a ratio of actual claims dollars incurred by your firm compared to the industry average value for firms that do the same kind of work you do.◦Good history causes it to go down.◦Adverse history causes it to rise.

It is desirable to have an EMR < 1.0.◦1.0 is considered to be “average”.

Page 18: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

If you DON’T have an If you DON’T have an EMR:EMR:

You must provide copies of your firm’s Workers’ Compensation Loss Runs for each of the last three years, along with your questionnaire.

Contact your Insurance Carrier or Broker to obtain your Loss Runs.

If you are a brand new company you will have neither an EMR nor loss runs. Please note this in writing on the questionnaire.

Page 19: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

What the EMR means to What the EMR means to you:you:

Let’s say you, Fred, are bidding against Joe and Bob. ◦Your EMR is 1.0, ◦Joe’s is 0.5, and ◦Bob’s is 2.0.

Page 20: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Let us also assume that your bids are identical with respect to time, material and labor hours, and include $10,000 as the manual (base) rate for Workers’ Comp.

◦Your insurance would cost you $10,000.◦Joe would pay $5,000 for the same insurance.

◦Bob would pay $20,000 for the same insurance.

Page 21: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Who gets the job?◦JOE!

Who says safety doesn’t pay?

Page 22: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

You can learn what your EMR is (if you have one) by contacting your Workers’ Compensation Insurance carrier.

We will verify your answers.Applicant may be disqualified if either

its (a) current EMR, or (b) average EMR for the most recent three-year period, is above 1.00, in which case, the District will determine, based on information submitted, whether Applicant has satisfied the requirements of Section A.

Page 23: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Enter only one (1) NAICS code

Section B: Incidence RatesSection B: Incidence Rates

Page 24: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

If you don’t know your firm’s NAICS Code, visit the Facilities Vendor Registration web site at: http://mo.laschools.org/lausd-vendor/register-aeClick on “View NAICS” to see a list of codes, orType specialty trade in Primary box to get applicable code.

Page 25: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Incidence Rates...Incidence Rates...…are based on employee injuries

and illnesses and total company man-hours per CALENDAR YEAR, not insurance policy year.

They:◦are not based on OSHA inspections or

citations/violations.◦can be computed for every contractor EVEN IF THERE ARE NO OSHA ‘RECORDABLE’ CASES.

Page 26: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

A work-related injury or illness must be recorded if it resulted in:◦Death or dismemberment◦Loss of consciousness◦Days away from work◦Restricted work activity or job transfer◦Medical treatment beyond first aid

Specific information on how to evaluate whether an incident is to be considered OSHA recordable can be found at www.osha.gov/recordkeeping

Page 27: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Refer to your OSHA 300 Logs and/or your Loss Runs and injury/illness records to determine the number of injury cases you have incurred.

Company hours is the total sum of all work hours by all employees (including those of a sole proprietor/owner) for the calendar year.

Complete all information in this section of the questionnaire! Fill in every blank EVEN IF THE ANSWER IS “0.”

Information Used for Information Used for CalculatingCalculating

Incidence RatesIncidence Rates

Page 28: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:
Page 29: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

The formula used to calculate the incidence rates was established by the U.S. Department of Labor - Bureau of Labor Statistics. ◦It’s been around for decades –

it’s THE standard formula for everyone.

Calculating Your Calculating Your Incidence RatesIncidence Rates

Page 30: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Your rates are compared against the national average rates for your NAICS code. See Table 1 at http://www.bls.gov/iif/oshwc/osh/os/ostb3958.pdf

When an employer calculates the company’s rates, the answer is a rate of incidents (injuries) per 200,000 hours (100 people working 8 hours a day, 50 weeks a year) - regardless of how many hours the contractor worked!

Page 31: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

In 2012, a company has 1 OSHA recordable injury which did not involve lost workdays. The company worked 20,000 hours that year.◦The Total Case Incidence Rate is:

(1 x 200,000) / 20,000 = 10.0◦The Lost Workday Case Incidence Rate is:

(1 x 200,000) / 20,000 = 10.0◦The No Lost Workday Case Incidence Rate

is: (0 x 200,000) / 20,000 = 0.0

Sample rate calculations:Sample rate calculations:

Page 32: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

A company has 4 OSHA recordable injuries in 2014. Three cases were lost-workday injuries. One case did not involve lost workdays. The company worked 30,000 hours that year.◦The Total Case Incidence Rate is:

(4 x 200,000) / 30,000 = 26.7

◦The Lost Workday Case Incidence Rate is: (3 x 200,000) / 30,000 =

20

◦The No Lost Workday Case Incidence Rate is: (1 x 200,000) / 30,000 = 6.7

Page 33: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:
Page 34: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

If you are a new firm, please add a note on your forms that informs us of this.

A new firm will be expected to have very few, or possibly no, company hours.

We will verify this by checking the effective date of your Contractor’s License.

Page 35: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Section C: OSHA Citation Section C: OSHA Citation HistoryHistory

Page 36: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

This section looks at your firm’s OSHA citation history.

It considers 4 types of citations:◦serious◦willful◦failure to abate◦repeat.

Page 37: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

You must report all such citations that your firm has received.

If you are contesting or appealing an applicable citation and it has not reached final resolution, you must still report the citation!

Page 38: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

The classification of the citation itself is important, but we also look at:◦what happened◦what corrective action was taken

◦your firm’s safety program to see that it meets minimum Cal/OSHA and Labor Code requirements

Page 39: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Citations are public information.Citation information for all employers is available using the “Establishment Search” at www.osha.gov

Your answers will be verified.◦We will check the last five years as stated in the Questionnaire!

Page 40: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Section D: Safety Policy & Section D: Safety Policy & Procedure QuestionsProcedure Questions

Page 41: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Read each question carefully.The questions are based on Cal/OSHA and California Labor Code requirements.

Understand what it is asking.◦The source regulation is listed with every question (Labor Code or Cal/OSHA).

Page 42: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

You may be required to provide documentation for any or all of your answers - be prepared!

A “yes” answer implies that you have documentation available for review for that item if you are asked to provide it!

Page 43: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Certification:Certification:

Page 44: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Your firm’s Insurance Broker or Insurance Carrier Loss Control (Safety) Department,

Cal/OSHA Consultation,Trade Associations your firm belongs to,Internet construction safety sources

Still have questions?Still have questions?Here are some sources for additional

information:

Page 45: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

ContractorApplicantOverview

Formal & Formal & Subcontractor Subcontractor PrequalificationPrequalification

Page 46: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prequalification TypesPrequalification Types

Safety (Informal) Prequalificationo Required to bid informal contracts, JOC job orders, and

other projects for which safety prequalification is required.

Subcontractor Prequalification (MEP)o Required for Mechanical, Electrical, and Plumbing

subcontractors on formal contracts Formal Prequalification

o Required to bid formal contracts, JOC Contracts, 17406 Project-Specific Prequalification

Page 47: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Formal & Subcontractor Formal & Subcontractor PrequalificationPrequalification

Questionnaire is designed to thoroughly evaluate a contractor’s:Safety HistoryQuality and WorkmanshipPast PerformanceBonding/Insurance/LicensingFinancial Capabilities

Page 48: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Formal & Subcontractor Formal & Subcontractor PrequalificationPrequalification

Complete the most current Prime Contractor Prequalification Questionnaire or Subcontractor Prequalification Questionnaire

Have a current and active California Contractors License

Receive and maintain Safety Approval via the Safety Prequalification section of the Questionnaire

Meet the Mandatory and General Qualifications requirements

Provide bonds by a California-admitted surety company

Page 49: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Formal & Subcontractor Formal & Subcontractor PrequalificationPrequalification

Provide proof of Workers’ Comp and Liability coverage by an Insurance Company licensed to do business in California

Provide references of projects completed within the last 36 months

Submit a current financial statement (at least balance sheet and income statement)

Achieve passing score on PART V. Scorable Questions

Achieve passing Contractor Performance Score Prequalification approval is valid for one (1) year.

Page 50: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Contractor Contractor Performance ScorePerformance Score

Contractor performance history will be measured according to two separate components, Field and Compliance.

Field Component (Maximum Score 50, Passing Score 35)

◦ Average score of Contractor Performance Evaluations for the last three (3) LAUSD contracts.

◦ Applicant must receive an average score of at least 35 points to prequalify.

Page 51: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Compliance Component (Maximum Score 50, Passing Score 35):

1.Labor Compliance

2.Project Stabilization Agreement (PSA)

3.Bid Issues/Protests

4.Assessments

5.Failure to comply with LAUSD contract Warranty requirements

For details, see Field and Compliance Scoring Summary on the Prequalification web page at http://www.laschools.org/new-site/prequalification/forms

Page 52: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Subcontractor Subcontractor PrequalificationPrequalification

PCC 20111.6 requirement for Mechanical, Electrical and Plumbing subcontractors on projects of $1 million or more.

LAUSD has applied this requirement to all formal contracts and JOC job orders.

License classes affected:

Page 53: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Effective April 15, 2015

• Subcontractor Prequalification will apply to all listed subcontractors.

• If safety prequalified only, subcontractors must complete Prime or Subcontractor questionnaire.

• The list of Approved Subcontractors will be posted on the Facilities Contracts web site.

• Prime and subcontractors must be approved at least five days prior to bid date.

Subcontractor Prequalification Subcontractor Prequalification Program ExpansionProgram Expansion

Page 54: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Formal PrequalificationFormal Prequalification

Prequalification program implemented pursuant to PCC 20111.5 and 20919.4.

Required to bid as a prime contractor on formal projects, including JOC and 17406

Assigned a bid rating based on bonding and experience

Page 55: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

THREE LEVELS OF FORMAL PREQUALIFICATION BASED ON EXPERIENCE::

Level IEntitled to bid on contracts in an amount not to exceed $350,000.Non-LAUSD experience: Within the past three (3) years, at least three (3) public or private works as either a prime contractor or a subcontractor with cumulative contract value totaling at least $500,000.LAUSD experience: Within the past three (3) years, at least three (3) LAUSD contracts as either a prime contractor or a subcontractor, with cumulative contract value totaling at least $100,000.

Page 56: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Level IIEntitled to bid on contracts in an amount not to exceed $5,000,000.Non-LAUSD experience: Within the past three (3) years, at least three (3) public or private works as either a prime contractor or a subcontractor with cumulative contract value totaling at least $2,000,000.LAUSD experience: Within the past three (3) years, at least three (3) LAUSD contracts as either a prime contractor or a subcontractor, with cumulative contract value totaling at least $500,000.

THREE LEVELS OF FORMAL PREQUALIFICATION BASED ON EXPERIENCE::

Page 57: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

THREE LEVELS OF FORMAL PREQUALIFICATION BASED ON EXPERIENCE::

Level IIIEntitled to bid on contracts in an amount in excess of $5,000,000.Non-LAUSD experience: Within the past three (3) years, at least three (3) public or private works as either a prime contractor or a subcontractor with cumulative contract value totaling at least $10,000,000.LAUSD experience: Within the past three (3) years, at least three (3) LAUSD contracts as either a prime contractor or a subcontractor, with cumulative contract value totaling at least $7,000,000.

Page 58: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

DIR Public Works Contractor DIR Public Works Contractor Registration RequirementsRegistration Requirements

• Senate Bill 854 - public works contractor registration program.

• Effective March 1, 2015 - All Contractors and subcontractors listed on a bid must be registered (informal, formal and JOC).

• Effective April 1, 2015 - All contractors and subcontractors working on any public works contract awarded on or after this date must be registered.

Page 59: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

QUESTIONS???QUESTIONS???

Page 60: LOS ANGELES UNIFIED SCHOOL DISTRICT FACILITIES SERVICES DIVISION FACILITIES CONSTRUCTION CONTRACTS THE DISTRICT’S PREQUALIFICATION PROGRAM PRESENTED BY:

Prequalification UnitPrequalification UnitContact InformationContact Information

Phone: (213) 241-2651Fax: (562) 654-9499Email:

[email protected] site:

www.laschools.org/new-site/prequalification