logistics planning & control
TRANSCRIPT
SCHOOL OF ENGINEERING
P01 – GLOBAL EXPANSION
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Global Expansion
Phone-Innovative Technology Ltd is a local manufacturer of hand-phones. It produces a wide range of hand-phones from high-end smart phones to low-end phones with basic features, to cater to different groups of customers. . Currently Phone-Innovative Technology’s products are distributed and sold in Singapore (~80% of sales) and parts of West Malaysia (~20% of sales). Ever since its first product launch in January 2009, the company has been doing very well and its sales turnover has been increasing progressively. Figure 1A shows the company sales turnover over the last few quarters.
Figure 1A: Phone-Innovative Technology Sales Turnover (S$’000)
During a recent board meeting, the management team feels that the domestic market is too small and its growth limited. In order for the company to progress and to achieve continuous growth, Phone-Innovative Technology has to go global and sell their products in more cities world-wide. The management decides that Phone-Innovative Technology® Ltd will still retain its manufacturing operation in Singapore for the next 3 to 5 years. Jason is the Chief Operating Officer (COO) of the company. He has been assigned to form a task-force and propose some strategies for the new business requirement. Jason is fully aware of the increasing complexities when the company goes global.
SCHOOL OF
ENGINEERING
You have been selected to be part of Jason’s task-force. Your role today is to give advice and to provide some recommendation(s) so that the company can reduce the logistics risks.
School of Engineering
P01 – Global Expansion
• International Logistics Functions
• Global Logistics Issues, Goals
and Strategies
• Types of Logistics Intermediaries
• Outsourcing Logistics Operation
E222 – Logistics Planning And Control
School of Engineering
Definition of Logistics
Raw
materials
suppliers
1 2 3 4 5
Manufacturer Distributor Wholesaler Retailer
6
End-User
Obtain Produce Distribute
Activities include:• Transportation
• Forecasting
• Warehousing
• Materials handling
• Packaging
• Information processing
• Finance etc…
“Logistics is the art and science of obtaining, producing, and distributing material and
products so that the customer receives the right product in the right quantity at the right
time.” Source: APICS Dictionary
Supply Chain Community
School of Engineering
Factors Affecting Global Logistics
Strategies
• Rapid Product Introduction - Bringing products in a short time
across numerous regions
• Focused Market Needs - Customization, packaging, service
offering to meet varying customer requirements
• Quick Response Delivery – Distribute the right product at right
quantity and shortest time
• Expanded Services – Linking innovative, value-added
services (E.g. Installation, 24 hrs hotlines, asset tagging)
• Innovative Channels – Using minimal echelon, direct delivery
to reach customers rapidly at the lowest cost
School of Engineering
Global Logistics Issues to Overcome
Longer & less consistent response time • Longer distance involved
• Ocean shipment at slower speed with less consistency than land/air
transportation
• Additional documentation & arrangement. (E.g. Letter of credit and
custom clearance)
Order completeness & shipping accuracy • Higher costs of back orders and expedited shipment
• Shipping errors could result in expensive routing and replacement
Higher shipping damages• Harsh and variable global environment. (E.g. Road condition and type
of transport used)
• Cost & time to replace damaged items can be significant
School of Engineering
Key Logistics Goals
• Rapid responses to changesNew development in the market or a particular customers’ needs
• Minimum varianceE.g. Delivery time
• Minimum inventory to keep expenses down
• Movement consolidation By aggregating smaller shipments into larger ones
• High quality in logistics services as well as in
products
• Life cycle supportAbility to handle repairs, reuse, recycling or disposal as well as product
delivery
School of Engineering
Global Logistics Strategy Guidelines
From a long term strategic perspective
• Logistics planning should be integrated into the company’s
strategic planning process
• Logistics department need to be guided by a clear vision and
must measure output regularly
• Import/ export management should try to ensure integrated
management of all elements of the logistics supply chain,
from origin to destination
• Opportunities to integrate domestic and international
operations should be pursued to leverage total company
volumes with globally oriented carriers
School of Engineering
Tactical Logistics Strategies
Coordinating functions to create maximum value for
the customers • Logistics system is made up of interlocking, interdependent parts
• E.g. Transportation management, warehousing, packaging
Integrating the supply chain
Step 1: Locate in the right countries
Step 2: Develop an effective export-import strategy
Step 3: Select warehouse locations
Step 4: Select transportation modes & carriers
Step 5: Select the right number of partners
Step 6: Develop state-of-art information system
School of Engineering
Substituting information for inventory
•Use postponement centers
-Delay product assemble until actual order receipt (E.g. Dell- Build-to-
order)
•Track inventory precisely
- Using barcodes, RFID (radio frequency identification), GPS (global
positioning systems)
•Keep inventory in transit
•Don’t wait in line at customs
•Mix shipments to match customer needs
Pooling Risks• Reducing stock-outs by consolidating stock in centralized warehouse
-Reduces both safety stock & average inventory by centralizing inventory
Tactical Logistics Strategies
School of Engineering
Reducing supply chain partners to an effective number Reduce number of partners to reduce operating costs, cycle time,
and inventory holding costs
Factory
Two factory warehouses
Nine wholesale warehouses
350 retail stores
Consumers
This is a supply chain with three
echelons between the factory & the
consumers
•Two factory warehouses
•Nine wholesale warehouses
•350 retail stores
Echelons:• Add to operating expenses
• Hold inventory
• Add to cycle time
• Expect to make a profit
Nodes- Each of these nodes
represents an echelon in the
supply chain network
Tactical Logistics Strategies
School of Engineering
International Logistics Function
• Demand forecasting
• Order Management
• Packaging
• Labeling
• Documentation
• Customer service
• Parts & service support
• Production Scheduling
• Procurement
• Returned Products
• Inventory Management
•Transportation Management
• Materials Handling
• Warehouse & Distribution
Center Management (Hub
Management)
• Salvage & Scrap Disposal
etc… O
utb
ou
nd
Lo
gis
tic
s F
un
cti
on
sIn
bo
un
d L
og
isti
cs
Fu
nc
tio
ns
Ove
rall
Lo
gis
tic
s A
cti
vit
ies
School of Engineering
Intermediaries Roles & Responsibilities
Freight
Forwarder
• Most common intermediary in international logistics
• May assume responsibilities for the firm’s international distribution
and supply channel
• Offers services such as daily pickup, distribution, global shipping
capacity with multi-carriers, advice and preparing documents,
consolidation of freight from multiple shippers to a single
destination, bulk booking of freight space etc
Non Vessel
Operating
Common Carrier
(NVOCC)
• (Also called Consolidators or NVOs)
- Provide scheduled ocean shipping service without operating ships
- Leasing containers and selling space for Less-Than-Container-
Load (LCL) shipment
Export
Management
Companies
(EMC)
• Find and service markets overseas on behalf of domestic
manufacturers (i.e. prepare documentations, appointing forwarders,
arranging for special packing, procuring insurance)
Logistics Intermediaries (Export-Import Participants)
School of Engineering
Intermediaries Roles & Responsibilities
Export Packers • Assist exporter with special packaging requirements needed to
reach export markets.
Publication
Distributors
• Includes wrapping, destination sorting, addressing, handling
business reply mail, collection of subscription, data management.
Goods
Surveyors
• To inspect quality of goods , measure the weight, or determine the
extent of damage that have occurred while goods were in transit.
Parts Banks • Assist the manufacturer to store important parts for repair
throughout the world
Container
Leasing
Companies
• Lease containers to companies or individual carrier for intermodal
movements;
Export Trading
Companies
(ETC)
• Buy manufacturer's goods , take title, and then sell these goods in
the export market
(Note: Most of these roles can be taken on by major integrated logistics service providers)
Logistics Intermediaries (Export-Import Participants)
School of Engineering
3rd & 4th Party Logistics Providers
Third-party logistics (3PL) 3PL takes over some or all logistics functions & performs them itself
• May be a specialized provider that focuses on airmail, or over-the-road transport
or warehouse
• May also be a multipurpose logistics provider capable of taking over the entire
logistics function
Fourth-party logistics (4PL)• Logistics specialist takes over entire logistics operation &
subcontract some or all particular functions
• Sometimes still called 3PL, but presence of subcontractor
makes it a 4PL setup
• Coordinates efforts of sub-contractors on client’s behalf;
typically charge a fee for its service, not a markup
• Also known as Lead Logistics Provider (LLP)
• Key role of IT in managing the process (e.g. SAP, Oracle)
School of Engineering
Importance of 4PL
•Integrate & Manage Logistics Network
•Work across regions
•Globally integrated Information
Network
•Business Process Redesign
•Manage customer service level
•Emphasize their unique values to
differentiate themselves from
traditional 3PLs
School of Engineering
Contract Manufacturer (CM)
• Firm that manufactures components or products for
another “hiring” firm
Also known as Electronic Manufacturing Services (EMS)
• A form of outsourcing
• Contract manufacturers (CM) drive down the cost of
production through economies of scale (EOS)
• It allows the hiring company to obtain the components
or products without needing to own and operate a
factory
School of Engineering
Global Logistics Outsourcing
• Globalization of marketplace has fueled growth in
global logistics
• As firms become more global in their operations,
they tend to turn to one or more global logistics
service firms to provide logistics services globally
• Firm and logistics providers form close relationships
through IT integration, co-location of logistics
service providers at the shipping firms, capital and
infrastructure investment
School of Engineering
Logistics Outsourcing (Case Study)
Nokia Factory
BGKI
S&C
Current no. of park members : 16
Total investment: more than 10 billion RMB
Sales volume: 50 billion RMB per year(about 1/3 for export)
Current no of staff: 3,800
Gross area: 500k sqm for each phase (1&2)
Construction area: 400k sqm for each phase (1&2)
Technology Park in Beijing led by Nokia, began operation in 4Q2001. Nokia Xing Wan Industrial Park
School of Engineering
Benefits of Logistics Outsourcing
Improved business focus
• Allows both firm and its contractor to focus on what they do best ─
“core competence”
E.g. Dell (PC assembly) & YCH Logistics (other logistics functions), Nokia and Exel in
Xing Wan Industrial Park, Beijing.
More current logistics technology
• Contract logistics providers generally better able to stay current with
technology than firms that hires them
• Contractors generally quicker to incorporate new software and better
able to upgrade hardware necessary to run it well
Greater technological flexibility
• Contract logistics providers are better positioned to adapt to different
technologies used for the firm’s clients
School of Engineering
Benefits of Logistics Outsourcing
More efficient warehousing for rapid replenishment
•Rapid replenishment requires warehouse close to clients
•Using contract logistics provider’s warehouse is cheaper than
building or acquiring firm’s own warehouse
Improved service to customers
•Contract logistics providers may be able to offer a variety of
services to firm’s customers
More workforces and resources flexibility
•Quicker and simpler to hire a contract specialist for a new
function; than to hire and fire workers to reflect market changes
School of Engineering
Potential Risks & Challenges for
Logistics OutsourcingLoss of control
• Contracting logistics means giving up control over some or all aspects
of that function
• May be difficult to develop a comprehensive logistics strategy for firm
• Becomes problematic if contractor establishes direct connection with
firm’s customers
Potential for inefficiency
• Firm may already be doing a good job for its logistics function; contract
logistics provider may actually perform with reduced efficiency
• Language, time zone and cultural barriers
• Legal & Political differences
High level of trust required
School of Engineering
Today’s Problem• Understand about global logistics issues
• Be familiar with international logistics functions
• Identify the key logistics goals
Define logistics strategy guidelines (For long term, strategic purpose)
Develop short-term tactical logistics strategies
• Select suitable intermediaries including third party logistics
(3PL) or fourth party logistics (4PL)
• Outsource non-core logistics functions, such as
distribution, transportation and export management
• Explore the possibility of outsourcing to Contract
Manufacturer (CM) for lower-end products (longer term
plan)
School of Engineering
Learning Outcomes
• International Logistics Functions
• Global Logistics Issues, Goals &
Strategies
• Types of Logistics Intermediaries
• Outsourcing Logistics Operation
SCHOOL OF ENGINEERING
P02 – Demand Planning
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore
SCHOOL OF
ENGINEERING
Page 2 of 2
Demand Planning
Go-There Pte Ltd is an international company that specializes in selling vehicle Global Positioning System (GPS) devices. Jennifer is the account manager in charge of the sales for both Singapore and Malaysia region. Currently, one of the best-selling GPS model for the company is Navi 3000TM.
Table 1-1 below gives the historical sales data of Navi 3000TM GPS.
Table 1-1: Historical Sales Data of Navi 3000TM GPS
Month-Yr Actual Sales Month-Yr Actual Sales
Apr-09 932 Oct-09 970
May-09 950 Nov-09 915
Jun-09 1020 Dec-09 942
Jul-09 980 Jan-10 933
Aug-09 940 Feb-10 961
Sep-09 950 Mar-10 945
Having been in this trade for more than eight years, Jennifer is fully aware of the expectations of the customers. Once they make the decision to buy a GPS device, they would expect the product to be available for purchase over the counter. If the stores they visit do not have the product they want, they may just look elsewhere for other brands and models. This is a highly competitive industry. It is not practical for the distributor to maintain a large inventory because of high inventory holding cost and obsolescent cost. On the other hand, Jennifer wants to meet the customers’ demand for Navi 3000TM GPS as much as possible, to ensure that most numbers of the devices are sold. How would you help Jennifer in her demand planning so that she can meet the customers’ expectations while not keeping a huge inventory for the subsequent months?
School of Engineering
P02 – Demand Planning
• Sources of Demand Variability
• Qualitative and Quantitative
Forecasting Techniques
• Calculate Seasonality
E222 – Logistics Planning And Control
School of Engineering
Forecasting Forecasting is a necessary part of business planningSome guidelines when deciding how much product likely to sell,
therefore need to produce/import
Affects decisions & activities throughout an organization (E.g. sales,
marketing & logistics)
Examples of forecasting in business organization• Accounting - New product/process cost estimates, profit projections, cash
management
• Finance – Equipment/ equipment replacement needs, timing and amount of
funding/borrowing needs
• Human resources – Hiring activities, including recruitment, interviewing, training,
layoff, counseling
• Marketing – Pricing & promotion, e-business, global competition strategies
• Management of Information System (MIS) - New/ revised information systems
• Operations – Schedules, work assignments & workloads, inventory planning
• Product/ service design – Design of new products or services
School of Engineering
Features of Forecasts
Causal systemForecast techniques generally assume that the same underlying causal system
that existed in the past will continue to exist in the future
Forecast error
Forecasts are rarely perfect; actual results usually differ from predicted values
Group forecastsForecasts for groups of items tend to be more accurate than forecasts for
individual items because forecasting errors among items in a group usually have
a cancelling effect
Accuracy and time
Forecast accuracy decreases as the time period covered by the forecast (i.e. the
time horizon) increases. Generally, short-term forecasts must deal with fewer
uncertainties than long-term forecast
School of Engineering
Considerations of Forecasts
A company must be knowledgeable about numerous
factors that are related to the demand forecast.
Past demand
Lead time of product
Planned advertising or marketing efforts
State of the economy
Planned price discounts
Actions competitors have taken
School of Engineering
Sources of Demand Variability
Competition•The most basic fact of life in a market economyCompetitors’ unpredicted innovations can cut into market share; alternatively,
competitors’ unpredicted problems can suddenly increase demand for your
product
Seasonality•Demand for many products and services varies with the changing
seasons of the yearE.g. demand for clothing undergoes seasonal variations, demand for snow
shovels (winter)
Life cycle trends•Demand fluctuates over life cycle of a productE.g. Demand builds to a peak before product comes into market (popular
books, movies, initial public offerings); or demand build slowly as buyers
become gradually aware of product’s existence or refinement
School of Engineering
Sources of Demand Variability
External factors• Factors external to the product & market (e.g. business cycle) tends
to stimulate and depress demand across many markets in long-
wave terms
Promotions• Special pricing, advertising blitzes, “no-interest” financing and other
promotional scheme can cause upward fluctuation in demand
• Demand planning needs to take promotions into account
Disasters• Disasters may seem unforeseeable and devastating but planning
can mitigate their effectE.g. With proper planning, Procter & Gambler (P&G) was able to recover its
business operation fully (within 45 days) at New Orleans after hurricane
Katrina (Aug, 2005)
School of Engineering
Types of Forecasting Qualitative
•Based on judgment & intuition (human touch)
•Advice from most experienced, market-savvy, objective
person/ group of experts
•A rough estimate of likely demand (difficult or impossible to
quantify)
Quantitative
•Rely on historical data
•Two main types Intrinsic forecasting: Time series models; focus upon data about
demand for the product/service (e.g. past sales data)
Extrinsic forecasting: Associative models; analyze data on conditions
thought to be associative with changes in demand for a particular item/
group of items
School of Engineering
Qualitative Forecasting Methods
Personal insight•Based upon the insight of most experienced, most knowledgeable, or
most senior person available person available
Sales force consensus estimate•Sales & marketing area maintain closest contact with customers, hence
they bring expertise to forecasting
Management estimate•Similar to sales force estimate
•Relies upon a consensus of panel members
•Depends on forecasting techniques like:
Pyramid forecasting – Begins by aggregating item forecasts for a product group to
establish a new group forecast; forecast is then “disaggregated” to generate item forecast
consistent with product group plan
Historical analogy - study patterns of demand for a similar product/ service
School of Engineering
Qualitative Forecasting Methods
Market research• “The systematic gathering, recording, and analyzing of data about
problems relating to the marketing of goods and services” (APICS Dictionary; 11th Edition)
• Involves market analysis (e.g. product potential studies), sales analysis
(e.g. sales data study) and consumer research (e.g. questionnaires,
focus groups)
Delphi method •Relies upon a panel of experts (their experience, wisdom, insight and
intuition acting in concert)
•Questionnaires submitted to individual expert for their anonymous
response in successive rounds
•Useful for technological forecasting
•Frequently used when data are thin or non-existence
School of Engineering
Quantitative
(Time-Series Forecasting)
Also known as Intrinsic forecasting
techniques
Predicting the future from past historical data
Based on a sequence of data collected during
set intervals of time (hours, days, weeks,
months, quarterly etc.)
Causal variables and qualitative factors are
not considered
School of Engineering
Time-series forecasting shows combinations of four types of
variability-Trends: A steady movement up or down
-Seasonality: Changes that correlates or changes related to temporal
phenomenon
-Cycles: Series of data show alternating cyclical movements, each
lasting for years
-Chance: Random variation that can neither be predicted or explained
Time-Series Forecasting
School of Engineering
Time-Series Models Naïve approach Assumes that demand in the next period will be the
same as demand in the last time
Rules out all types of fluctuations; a baseline for use to
evaluate more sophisticated approaches
Moving averages
Weighted moving averages
Exponential smoothing
Inc
rea
sin
g o
rde
r o
f
so
ph
isti
ca
tio
n
School of Engineering
Moving Average
N
FFFF tNtNt
t11 .....
Where Ft is the forecast in period t and N is
the number of most recent periods used in
the forecast.
3
3213
MMMAverageMovingMonth
Example:
School of Engineering
Moving Average Moving average corrects for chance variation,
with longer periods removing more of the
randomness (+)
Moving average are not sensitive to trends (NB:
The averages of previous numbers cannot
predict higher or lower value than period
preceding forecast) (-)
Calculations become complex and have to
collect more data, as more periods are included
in the average (-)
School of Engineering
Weighted Moving Average
N
i
tNNtNtt
W
FWFWFWF
1
1121 .....
where Wi’s are the individual weights.
• Greater weights may be placed on more recent data to
improve the responsiveness of forecast to changes
6
)332211(3
MMMAverageMovingWeightedMonth
Example:
School of Engineering
Exponential Smoothing
Ft = Ft-1 + α (At-1 – Ft-1)
OR
Ft = α At-1 + (1 – α) Ft-1
where:
Ft = new forecast
Ft-1 = previous forecast
α = smoothing constant (0≤α≤1)
At-1 = previous period’s actual demand
School of Engineering
Extrinsic Forecasting Techniques
Also known as causal techniques
Analyze conditions that may cause demand
May include leading, concurrent or lagging
indicators
Examples: Gross National Product (GNP),
steel production, contract awards, automobile
production (worldwide)
School of Engineering
Seasonality Calculation
Variation of sales volume with season is typical of many products
and services. More products are sold during summer or winter
season. Such demand pattern is call seasonality
Seasonality can be represented using the seasonal index
associated with a particular demand stream
The Seasonal index is period average demand divided by the
average demand for all periods
It is best to get more that one year’s worth of data for seasonality
calculations
periods allfor demand average
demand average period IndexSeasonal
School of Engineering
Seasonal Demand of Servers
Annual sales growth = 4% (Based on Annual Sales for 2010 assumption)
The Seasonal Index = Period average demand/average demand
for all periods
School of Engineering
P02 :Suggested Solution
School of Engineering
Time Series Chart
• Use Regression Analysis in Excel to check for linear trend
• Tools> Data Analysis> Regression
• P-value associated with slope is 0.3733 > 0.05 significant level
• No strong evidence to conclude there is significant linear trend in data
• Also not enough data over time horizon to show seasonality and cycles
•Chart shows mainly chance or random variations
School of Engineering
Naive Forecasting
School of Engineering
3-Mth Moving Average Forecasting
School of Engineering
3-Mth Weighted Moving Average
Forecasting
School of Engineering
When α= 0.5
Exponential Smoothing Forecasting•Assumption: The initial forecast used (982) is the forecast value of 3-month
weighted average for July 09. (Note: It may also be from naïve, 3MA methods)
School of Engineering
RecommendationsJennifer should
Take into account the various sources of demand variability when
planning for sales, marketing & logistics activities
Be aware of the merits & limitations of different forecasting
techniques
Use a combination of Qualitative & Quantitative techniques during
forecasting Example:• Use qualitative techniques (e.g. personal insights, management estimate) for
longer range forecast (e.g. 6 months)Qualitative techniques are especially critical in new products without prior historical
sales data
Insights from Market Intelligences and inputs from Business Plan becomes the main
sources in gauging the overall market potential
• Complement longer range forecast with suitable quantitative techniques,
when more actual demand data becomes available
School of Engineering
Learning Outcomes
•Sources of Demand Variability
•Qualitative and Quantitative
Forecasting Techniques
•Calculate Seasonality
SCHOOL OF ENGINEERING
P03 – Managing Forecast Accuracy
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore
SCHOOL OF
ENGINEERING
Page 2 of 3
MANAGING FORECAST ACCURACY Maxtronics (Singapore) Ltd is a contract manufacturing firm that specializes in producing LCD monitors. Maxtronics’ customers include major electronics and computer companies in Asia. Nancy is a senior planner from the Sales and Operation Department. Each month, Nancy and her team would need to determine the number of LCD monitors to produce. Their forecasts are based on a combination of qualitative and quantitative methods. (Note: See Table 1 below for forecast and actual demand of LCD monitors.)
Table 1: Forecast and Actual Demand of LCD monitors (From January 2009 to February
2010)
Inaccurate forecasting
has caused many
problems.
Robert, General Manager
I better do something
to improve the
situation.
Nancy
SCHOOL OF
ENGINEERING
Page 3 of 3
For some of the months, Nancy realizes that the forecasts deviate a lot from the actual demand. This has caused problems to the Procurement Department when they could not order the raw materials and components on time. Moreover, the Production Department also complains that inaccurate forecasts have caused them to produce shortfall or excessive LCD monitors. Robert, the General Manger (GM) of Maxtronics is quite unhappy with the current situation and expects Nancy to do something. The meeting with Robert is next week. However, Nancy is still unsure of how to better measure, monitor and control the forecast accuracy. She is getting worried. Put yourself in Nancy’s shoes. What will be your recommendation for the department?
School of Engineering
P03 – Managing Forecast Accuracy
• Reasons for Forecast Inaccuracy
• How Forecast Accuracy is
Measured
• Why & How Forecast should be
Monitored
E222 – Logistics Planning And Control
School of Engineering
Measure & Monitor Forecast
Why Measure & Monitor?
• Monitoring forecast feedback & measuring
forecast performance are parts of forecasting
process
If we don’t measure, how do we know it is okay?
• Alert the forecaster if processes are out of
control.
Appropriate action then can be taken to regain control
• To hold people accountable for forecast accuracy
School of Engineering
Reasons for Forecast Inaccuracy
• Inappropriate forecasting methodE.g. Selecting a 3-mth moving average method when
there is a clear evidence of seasonal pattern.
• Lack of participationE.g. Forecast done by Production Department without
consulting Sales & Marketing.
• Too difficult to understand If users do not understand, you will have a “garbage in
garbage out” situation.
School of Engineering
• Lack of compatibility Is it compatible with the capabilities of the organization?
Can the users understand the technique?
• Inaccurate/Inappropriate data Dependent demands or parts should not be forecasted
• Lack of monitoring No comparing of actual to forecast results, no way to
assess the current forecast performance and no way for
improvement
Reasons for Forecast Inaccuracy
School of Engineering
Forecast Accuracy Measurement
• Forecast AccuracyForecast Accuracy(%) = 100% - Forecast Error(%)
• Period Forecast ErrorForecast Error = Actual Demand – Forecast Demand
• Absolute Percentage of Error (APE)
• Relative error measure is more
appropriate for comparison purpose
A = Actual demand, F = Forecast demand
%100
A
FAAPE
School of Engineering
Forecast Accuracy Measurement
Example: APE
School of Engineering
• Mean Absolute Percentage of Error (MAPE)A measure of how much the average percentage
forecast values deviated from the actual values.
Relative
Forecast Accuracy Measurement
%1001
1
n
A
FA
nMAPE
School of Engineering
Forecast Accuracy Measurement
Example: MAPE
School of Engineering
• Mean Absolute Deviation (MAD)
The average of the absolute values of the
deviations of the observed values from the
forecasted values
The average amount in which the forecast is in error
Measures the variations of the actual value from
the forecasted value, but does not consider if
the variation is plus (+) or minus (-)
Forecast Accuracy Measurement
School of Engineering
n = Number of periods
Forecast Accuracy Measurement
Example: MAD
n
FAn
MAD1
||1
School of Engineering
• Mean Square Error (MSE)
MAD places equal weight on small and large
deviation
Process of squaring the error will give a much
wider range of numbers
• Greater range gives a more sensitive measure of error
rate
Forecast Accuracy Measurement
2
1
)(1
n
FAn
MSE
School of Engineering
Forecast Accuracy Measurement
Example: MSE
School of Engineering
• Standard Deviation (σ)
Similar as Mean Absolute Deviation (MAD)
Measures the distance of error and does not
consider the direction of error
Forecast Accuracy Measurement
Note: Denominator uses n-1 for a sample population of fewer than 30
data points; and n if 30 data points or more
2
1
1
2
1
)(
.
n
FA
DS
n
School of Engineering
Forecast Accuracy Measurement
Example: Std Deviation
School of Engineering
• BIAS
Bias is the tendency of the forecast to be
either above or below the actual
observation.
Should strive for zero bias
• Indicates that forecaster’s model is good
Forecast Accuracy Measurement
n
FA
Bias
n
1
)(
n
FA1
)(
is also known as Running
Sum of Forecast Errors
(RSFE)
School of Engineering
Effects of Bias
• Continually low forecast (+ Bias) Late shipment
Unhappy customers
Scrambling
Unplanned overtime
• Continually high forecast (- Bias) Surplus inventories
Excess capacity
layoffs
School of Engineering
Demand Filters
• “A standard that is set to monitor sales data for individual
items in forecasting models. It is usually set to be tripped
when the demand for a period differs from the forecast by
more than some numbers of mean absolute deviations
(MAD)”
(APICS Dictionary)
• It is a quantity limit setting
• When order exceeds filter setting, filter is tripped and
the order is flagged and has to be dealt with separately
Demand filter catches data entry errors
Forecast Accuracy Measurement
School of Engineering
Today’s Problem Errors are significant for some of the months E.g. May
2009, Feb 2010
School of Engineering
Today’s Problem
“Tripping” triggers
investigations/
attention
School of Engineering
Today’s Problem Nancy needs to be • Aware of
The importance of measure, monitor and control in forecasting accuracy
Reasons for forecast inaccuracy and to avoid making these “mistakes”
• Uses various types of forecast accuracy measurement
techniques to keep track variability E.g. APE, MAD, MSE, MAPE
• Track Bias (Biasness) If negative, it indicates a routinely “over-forecast”
• Uses appropriate demand filter (“control limit”) and takes
action when “tripped”
• Motivates people (Including making them accountable) for
forecasting.
School of Engineering
Tracking Signals
• Used to measure forecast bias
A trip value or predetermined threshold may be
generated (e.g. 4 in both direction). If this is
exceeded, it triggers an investigation
Tracking signal =RSFE
MAD
Forecast Accuracy Measurement
Going Further….
School of Engineering
Learning Outcome
• Reasons for Forecast Inaccuracy
• How Forecast Accuracy is Measured
• Why & How Forecast should be
Monitored
SCHOOL OF ENGINEERING
P04 – Design with Efficiency
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Design with Efficiency
You are the General Manager (GM) of My-Shirt Pte Ltd. Your company manufactures and distributes T-shirts to major retail outlets around Singapore.
Figure 1a and 1b below show the steps to produce a T-shirt.
Figure 1a: Key Steps to produce a T-shirt
Cutting
Stitching
Complete
Product
SCHOOL OF
ENGINEERING
Figure 1b: T-Shirt Manufacturing Process (Overview)
The T-shirts that My-Shirt Pte Ltd manufactures are gaining popularity among many youngsters in Singapore. My-Shirt Pte Ltd current business strategy is to increase its market share. To do so, the company manufactures a wide variety of design and colours to cater to different customers’ preferences. However, having a wide variety (and colours) would mean higher manufacturing, packaging, shipping and inventory holding cost incurred. It will also be harder for the company to forecast the right number of each type of T-shirts to produce. From a product design and manufacturing process perspective, how can you help your company reduce the manufacturing, packaging, shipping and inventory holding cost, while meeting customer requirement at the same time? Discuss your approach.
School of Engineering
P04 – Designing With Efficiency
• Economic Packaging and
Transportation
• Concurrent & Parallel
Processing
• Standardization
E222 – Logistics Planning And Control
School of Engineering
The Manufacturing Environment
• Rapid Changes
• New products rapidly introduced
• Short, unknown product life cycles
• High Variety of Products
• Long Production Lead Times
• Increasing storage and transportation costs
• Difficult to forecast demand
School of Engineering
Problem Faced…
• Forces for keeping low inventory
• inventory expensive
• low salvage values
• Forces for keeping high inventory
• long lead times
• customer service is important
• demand is hard to predict
• reduction in transportation quantity
School of Engineering
Design for Logistics (DFL).. (Why?)
1. Product trends
• High product
variety
• Short life cycles
2. Challenges to meet product
trends
• Shorter production lead times
• Difficult to forecast demand
• High storage & transportation
cost
3. Design for Logistics to meet the challenges posed by
product trends
• Economic Packaging and Transportation
• Concurrent & Parallel processing
• Standardization
3 Components
for DFL
School of Engineering
Economic Packaging and
Transportation (E.g. IKEA)
School of Engineering
• Products are designed to be packed
compactly for customer to take from store
and then assemble at home
• Economies of scale from transporting high
volume of compact furniture
• Warehouse to store and display all its 10,000
products rather than relying on distributors
Economic Packaging and
Transportation (E.g. IKEA)
School of Engineering
Ocean Shipping Cost = Function (Packing density) +
Materials to Ship
Container cost is fixed
Packing more units per container lowers per unit shipping costs.
HOW ?
1.Optimize use of Container Rectangular volume space • Shipping cartons are box-shaped
• Products are collapsible or foldable
2.Robust product design to allow less external packaging
& cushioning/foam materials.
Economic Packaging and
Transportation
School of Engineering
• Some companies would redesign product rather
than packaging
• Many retailers favor products that takes up less
storage space, stack easily and fit onto their
shelves (revenue per m2 increase)
• Therefore, Tupperware and Rubbermaid
containers/pails are made to stack
Economic Packaging and
Transportation
School of Engineering
• Tetrahedron shape reduces material
use
• Box/Square-shaped products
• Foldable products
Economic Packaging and
Transportation
“Square” water-melon
“Foldable” Colander &
Chopping Board
School of Engineering
Considerations: • Design products so that they can be efficiently packed and stored
e.g. Compact, stackable, flat
• Design products to efficiently utilize retail space by packing more
compactly e.g. bulk, sub-packaging, fit to shelves
• Design packaging so that products can be consolidated at cross
docking points e.g. easily identifiable, less than 25kg
• Less packaging material Prism/tetrahedral shaped packaging
Robust product design
Box-shaped product
Economic Packaging and
Transportation
School of Engineering
Concurrent & Parallel Processing
• Steps that are performed in sequence can
be completed at the same time
Reduce manufacturing lead time
Lower inventory cost due to improved
forecasting
Reduce safety stock requirements
If raw material supply is uncertain for a
particular component, a higher inventory can be
held for the component, rather than product
School of Engineering
Customers (Europe)
Serial Processing
Parallel Processing
Plant 1 (Europe) Plant 2 (US) Plant 3 (Asia)
3 Days 3 Days 3 Days 9 Days
Customers (Europe)Assembly Plant
(Asia)
3 Days 6 Days
Plant 1 (Europe)
Plant 2 (US)
3 Days
Concurrent & Parallel Processing
School of Engineering
Standardization
•Modular product – a product assembled from a variety of modules such that for each modules, there are a number of options.
E.g. Personal computer, Mac-Donald’s burgers, watches, cars etc…
•Modular Process – is a manufacturing process consisting of discrete operations so that inventory can be stored in partially manufactured form between operations
E.g. garment making process
School of Engineering
Standardization
• Standardization to help reduce inventory
level and increase forecast accuracy
through risk pooling from aggregate
planning
• Product modularity and process
modularity are key to choosing the right
standardization strategy
School of Engineering
Selecting the Standardization
Strategy
Part
Standardization
Process
Standardization
Product
Standardization
Procurement
Standardization
ModularNon-Modular
Process
Modular
Non-
Modular
Pro
du
ct
School of Engineering
4 Approaches to Standardization
•Part Standardization
•Process Standardization
•Product Standardization
•Procurement Standardization
School of Engineering
Part Standardization
• Common parts are used across many products
• Reduce inventory through risk pooling
• Reduce part cost due to risk pooling and
economies of scale• E.g. Common circuit board & print-head for different printers
• E.g. Same sesame seed buns, lettuce, tomato slices for different types of
burgers (Mac-Donald’s)
• E.g. Nokia Phone
School of Engineering
Process Standardization
• Standardizing as much of the process
as possible for different products, and
customizing the products as late as
possible (postponement)
School of Engineering
Process Standardization E.g. Benetton Manufacturing Process
Purchase Yarn
Old Sequence
Dye Yarn
Finish Yarn
Knit Garment Parts
Join Parts
Purchase Yarn
Dye Yarn
Finish Yarn
Knit Garment Parts
Join Parts
New Sequence
More
accurate,
Consolidate
d demand
Postpone
dyeing process
School of Engineering
Product Standardization
•When product not kept in stock is ordered,
the order may be filled by a product that
offers a superset of features required by
customers - “Downward substitution”
E.g. Car rental, higher functionality/speed chip,
multiple power supply options for printer
When Not
Available
Economy Class (if not
available) Upgrade to Business
Class
School of Engineering
Procurement Standardization
• Particularly useful when processing
equipment is very expensive
• Same equipment is used to produce each of
the possible end-products
E.g. Hand-phone
chipset
Computer
Motherboard
School of Engineering
Today’s Problem
Safety Stock Reduction of 2132 – 1840 = 292
Cost Saving!
School of Engineering
“Old
Sequence”
“New
Sequence”
Today’s ProblemStyling
Cutting
Assembling
Stitching
Features (e.g. color
& design)
Packaging
Shipping
Styling
Cutting
Assembling
Stitching
Features (e.g. color
& design)
Packaging
Shipping
School of Engineering
• Economic Packaging and Transportation
• Packing T-shirts in compact box for ease of stacking
and handling
• Process Standardization
• Re-sequencing of process features (determine
colors + design) takes place after stitching
After customer order is being placed
• Modular Product and Modular Process
• Process Standardization in the form of
Postponement
• Reduction in safety stock
Today’s Problem
School of Engineering
Learning Outcomes
•Economic Packaging and
Transportation
•Concurrent & Parallel Processing
•Standardization
SCHOOL OF ENGINEERING
P05 – Select Suitable Process
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Select Suitable Process
T-Com Inc. is a manufacturer of computer components including motherboards, graphic cards and sound cards. As part of the company business expansion and vertical integration initiatives, the management decides to set up a plant in Bintan, Indonesia to produce computers.
The following attachment shows a typical manufacturing process of computers in a factory.
Key Processes in Computer Maufacturing.pdf
Matthew has been appointed as the General Manager (GM) for the new business subsidiary, T-Com Computer Limited. During his preparation work before actual production, Matthew engages an external marketing research company to conduct surveys on potential customers so as to understand their needs and requirements. Matthew needs this information to plan for suitable manufacturing processes in his new factory and build computers that suit different types of customers.
Figure 1a gives a summary of the marketing research findings.
Category A B C
Brief description of
the customer
Home users or
individuals who want
their computers to be
reasonably priced
with standard
configuration
(Customization is not
required.) Prompt
delivery is important
Corporate customers
who order anything
from 10-500
computers. Typically,
they require
computers with some
forms of
customization (both
hardware and
“Techies” who need
high quality, highly
reliable computers
with good after-sales
and repair services.
Typically, they want
computers that are
fully customized to
their individual needs.
SCHOOL OF
ENGINEERING
Category A B C
to this group of
customer
software) to suit their
company’s needs
Price sensitivity of
customer
Most price sensitive
customers among all.
Price is not a primary
concern for this group
Least price sensitivity
among all
Figure 1: Summary of Market Research Findings
What types of manufacturing process (or processes) would you recommend to Matthew for the new plant? Justify your choice.
School of Engineering
P05 – Select Suitable Process
• Key Milestones in Manufacturing
History
• Process Selection
• Manufacturing Process Types Job Shop
Batch
Assembly Line
Flow
E222 – Logistics Planning And Control
School of Engineering
Key Milestones in Manufacturing History
• Andrew Carnegie & Scale (1875) Focused on unit cost through integration, efficiency, velocity of
throughput; Used accounting techniques from railroads to
accurately track costs; Set prices high in good times (made killing),
low in bad times (killed competition)
• Henry Ford & Speed (1913) Mass Production: defined new limits for complex assembly
operation; famous moving assembly line in 1913 Highland Park
plant, mass production became virtually synonymous with
assembly lines after this; single model (Model T)
School of Engineering
Key Milestones in Manufacturing History
• Alfred Sloan &Structure (1920) Restructuring of GM: collection of autonomous operating divisions;
coordination through strong central office; divisions targeted at markets;
used ROI to evaluate units; evolved procedures for forecasting, inventory
tracking, market share estimation
• Frederick Taylor &Scientific Management (1911) Time studies; Planning vs. Doing; Task reduction; etc
• Japan’s Experience & Toyota Production System
(1978) The success of American and Japan was based more on the
system than specific technologies or products (American system
with interchangeable parts and vertical integration; Japanese JIT
system)
School of Engineering
Production Process
• Production Process: the conversion of inputs (raw materials) into outputs (finished goods); core of operation management
• Process Structure
• The way the process is organized to make or deliver a product or service
• Determines the way the product flows through different stages of the production process
• Is dictated by business strategy E.g. low cost mass production OR product differentiation/ customization
• Implications? It affects:
• Layout of production facilities
• Capacity planning
E.g. Skills and quantity of labor, flexibility of equipment
School of Engineering
Process Selection
Forecasting
Product &
service
design
Technological
change
Facilities &
Equipment
Layout
Work Design
Capacity
Planning
Process
Selection
Inputs Outputs
School of Engineering
Process Selection Variables
• Also known as Manufacturing Variables
• Product Variety: How much the product changes from customer to customer.
• Equipment Flexibility: Whether equipment provides very specialized function or has the flexibility to provide certain level of product differentiation
• Production Volume: Some products are produced on small volume depending on customer needs, while others are produced in huge quantities in anticipation of customer demand
School of Engineering
Manufacturing Process Types
Product Variety
Equipment
Flexibility
Production
Volume
Flow
Processing
Assembly Line
Batch
Processing
Job Shop
School of Engineering
Job Shop
• For highly specialized product in low volume on
customer-order basis
• Equipment must be flexible enough to change
with each new job
• Jumbled flow – each product is made in a different
sequence of activities
• E.g. Computer Aided Manufacturing (CAM) workshop
which produces wide variety of parts based on
specific customer order (usually low volume)
School of Engineering
Batch Processing
• For higher volume product with standard
product design and a few product ‘types’
• Disconnected production line flow –
produced in small lots or batches
• Uses flexible equipment (adjustable for
multiple tasks) to produce a variety of
products in moderate volume• E.g. Shoes, pharmaceutical products
School of Engineering
Assembly Line• Small variety of highly standardized product to be produced
in large volume
• Originated by Henry Ford for automobile production in 1913
• Uses a connected line for production & moves the product
along the line
E.g. On a conveyor system along a series of work stations
• Structured with each line producing only one type of
product
• Cannot easily switch product, but there are options to offer
some variety on the product being produced
E.g. Car assembly lines, electrical appliances
School of Engineering
Flow Processing
• For very standardized product in very large
volume in the most cost-effective manner
• Like assembly line, flow processing has a fixed
pace and fixed sequence of activities.
• Each piece of equipment performs a specific
function & seldom modified for special needs
• Quantity of product is measured in weight or
volume• Eg. Steel plant, oil refineries
School of Engineering
Manufacturing Process Types
(Summary)
Job Shop BatchAssembly
LineFlow
Description Customized
goods or services
Semi-
standardized
goods or
services
Standardized
goods or
services
Highly
standardized
goods or
services
Merits
Able to handle a
wide variety of
work
Flexibility
Low unit cost,
high volume and
efficient
Very efficient,
very high volume
Limitations
Slow, high cost
per unit, complex
planning and
scheduling
Moderate cost
per unit,
moderate
scheduling
complexity
Low flexibility,
high cost of
downtime
Very rigid, lack of
variety, costly to
change, very
high cost of
downtime
School of Engineering
Job Shop BatchAssembly
LineFlow
Variety Highest High Low Lowest
Equipment
Flexibility Highest High Low Lowest
Volume Lowest Low High Highest
Manufacturing Process Types
(Summary)
School of Engineering
Manufacturing Objectives
• One key manufacturing objective is to achieve the
cost advantage of the Flow Process and the
product variety and/or customization associated
with the Job Shop.
• Most companies operate in between the 4 types of
configuration, to achieve optimal production mode
and better respond to market changes.
E.g. Companies that operate primarily in flow mode will often
have repair shops (job shop) to fix equipment that fails.
School of Engineering
Today’s Problem Standardized computer (Category A product) has high volume of
demand (account 73% of total sales), the set up of an assembly-line
type of process can be justified.
Computers for corporate customers (Category B product) where
orders are anything from 10 to 500 units (account 20% of sales) →
Batch processing may be a more suitable process. The volume is lower than assembly line and the equipment can be shared among the
different varieties
Category C product has very low demands (account 7% of sales)
where product variety and equipment flexibility are highest → Job-
shop is suitable.
To justify the process selection, the fixed and variable costs have to
be determined for different processes. Comparison of the total cost for
each process can then be made against the volume of demand
expected
School of Engineering
Batch-Processing for computers for
corporate customers (Category B )
+Load customized software
(E.g. Packed in batches, customer specific)
Assembly–Line for Standardized Computer (Category A)
Load common software+
Job-Shop (Category C )
Kitting +Custom
Build Area +
Testing Area +
Repair &
Servicing
(E.g. Pack to
customer)
Suggested Solution
Build Area
(customized)
School of Engineering
Learning Outcome
• Key Milestones in Manufacturing
History
• Process Selection
• Manufacturing Process Types Job Shop
Batch
Assembly Line
Flow
SCHOOL OF ENGINEERING
P06 – Planning For Manufacturing
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Planning For Manufacturing
Aaron is the Chief Operating Officer (COO) of Kelter Electronics Ltd- a contract manufacturing company that specializes in manufacturing printed circuit boards (PCBs) for computers, mobile phones and electronic devices. One of the recent initiatives by the upper management is to expand its existing production facilities to manufacture mobile phones with Ketler’s own brand. (Figure 1A shows the key components of a typical mobile phone.)
Figure 1A: Key Component of a Mobile Phone Although Ketler Electronics has been a leader in producing PCBs, manufacturing a complete mobile handset is still a new and unfamiliar area to the company. Mobile phone manufacturing is a lucrative yet highly competitive industry. Aaron understands that careful planning is necessary prior to entering the market. This is not going to be an easy task. How would you advise Aaron in planning for the new business (short, intermediate, long term) from a manufacturing planning and control perspective?
School of Engineering
P06 – Planning For Manufacturing
• Understand about Manufacturing
• Key Goals of Manufacturing
• Manufacturing Planning and
Control (MPC) System Roles of MPC
Principles of MPC
Activities in MPC
E222 – Logistics Planning And Control
School of Engineering
What is Manufacturing?
• Manufacturing : A series of interrelated activities and
operations involving the design, material selection,
planning, production, quality assurance, management,
and marketing of discrete consumer and durable goods.– From APICS Dictionary
• It is a value-adding process. The raw material is
converted by adding cost (or value) progressively until the
final product is created.
Production
System
Inputs
material
labor
capital
product
components
Outputs
School of Engineering
Manufacturing
Other Activities …
Build/ Rent warehouse
Train employees, schedule
shiftsBuild new assembly
line/ plant
Source Suppliers/
Buy components & parts
Find transportation team or
3PL
Get specialized
manpower E.g.
manager, operators
Buy Machinery &
Equipment
Manufacture
Mobile Phones
Preparation Work Involved in Manufacturing
School of Engineering
Key Processes in Mobile Phones Manufacturing
School of Engineering
Manufacturing Goals
The 3 typical goals for a manufacturing plant:
1) Quality: The manufactured product must be equal or better than its competitors
2) Cost : The cost of making the product must be equal or lower than its competitors
3) Time : The product must be delivered to the customer on time, every time
School of Engineering
Cost, Quality and Time
Cost
Time Quality
Note: Trade-off relationship exists among the 3 goals
School of Engineering
Cost, Quality and Time
Cost• Unit product cost
• Unit labor cost
• Unit material cost
• Total manufacturing overhead cost
• Inventory turnover-raw material, WIP, finished
gds
• Capital productivity
• Capacity/machine utilization
• Materials yield
• Direct/Indirect labor productivity
Time• Quoted delivery time
• % of on-time delivery
• Average lateness
• Inventory accuracy
• Master Production schedule performance/stability
Quality• Internal failure cost
• External failure cost
• Quality of incoming materials from
suppliers
• Warranty cost as % of sales
• Rework cost as % of sales
School of Engineering
Manufacturing Planning and Control (MPC)
System
A Manufacturing Planning and Control (MPC)
system is a methodology designed to manage
efficiently the flow of material, the utilization of
people and equipment, and to respond to customer
requirements by utilizing the capacity of our
suppliers, that of our internal facilities, and in some
cases that of our customers to meet customer
demand.(Source: Vollman, Berry, Whybark & Jacobs, “Manufacturing Planning and
Control for Supply Chain Management”, Mc-Graw-Hill Inc, 5th Edition”)
School of Engineering
MPC consists of…
• Sales & Operation Planning (S&OP)
• Master Production Scheduling (MPS)
• Material Requirement Planning (MRP)
• Capacity Planning
• Production Activity Control
• Just-in-Time Manufacturing (JIT)
School of Engineering
Role of MPC in Manufacturing - Center of Activity!
School of Engineering
Role of MPC in Manufacturing - Center of Activity!
Customers
Distribution
MPC SuppliersProcurement
Engineering
Design
Sales
Marketing
Plant Floor
Quality
To all functions
School of Engineering
Factors Affecting MPC
Supplier
Production process
Customer’s needs
Manpower
Resource
Cost
Quality
Timing
School of Engineering 13
Principles of MPC• Manufacturing planning and control systems should support
the strategy and tactics pursued by the firm.
• The MPC system's design will vary, depending on the
distinctive needs of the firm.
• Different manufacturing processes often dictate the need
for different designs of the MPC system.
• The framework for MPC is general, and all three phases
must be performed, but specific applications necessarily
reflect particular company conditions and objectives.
• The system should evolve to meet changing requirements
in the market, technology, products, and manufacturing
processes.
School of Engineering
MPC Activities
• Short Term
• Intermediate Term
• Long Term
School of Engineering
Short Term
There is a need for detailed scheduling of
resources to meet production
requirements.
• Involves time, people, material, equipment
and facilities.
• Involves people working on the right things.
• Involves tracking the use of resources and
execution results.
• Provide problem-solving support.
School of Engineering
Intermediate TermThe fundamental issue is matching supply
and demand in terms of both volume and
product mix.
• Planning for the right logistics.
• Providing customers with information on correct
quantities and location to meet market needs.
• Planning of capacity to determine employment
levels, budgets, overtime and subcontracting
needs, etc.
School of Engineering
Long Term
The system is responsible for providing
information to make decisions on:
• The appropriate amount of capacity
(including supplier capacity) to meet the
market demands of the future.
• Provide the appropriate mix of human
resource capabilities, technology, and
geographic locations (e.g. new plant).
School of Engineering
Today’s ProblemAaron’s objectives would include:
Provide good-quality, low-price mobile phones
and deliver promptly to customers.
Have good MPC system with following activities
• Short term
• Schedule production activities so people and equipment are
working on the correct things.
• Track material, people, customers' orders. equipment and
other resources in the factory.
• Respond when things go wrong and unexpected problems
arise.
School of Engineering
Today’s Problem (continued)
• Intermediate term
• Maintain appropriate inventories of raw materials (e.g.
PCBs), work in process and finished goods (e.g. complete
handset) in the correct locations.
• Plan for materials/components to arrive on time in the right
quantities needed for product production.
• Long term
• Plan capacity requirements and availability to meet market-
place needs.
• Communicate with customers and suppliers on specific
issues and long- term relationships.
School of Engineering
Learning Outcomes
•Understand about Manufacturing
•Key Goals of Manufacturing
•Manufacturing Planning and
Control (MPC) SystemRoles of MPC
Principles of MPC
Activities in MPC
SCHOOL OF ENGINEERING
P07 – How Many To Make
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
How Many To Make
You are the Production Planning Manager of Eco-Eyewear Manufacturing Limited. Your company manufactures environmentally friendly sunglasses from recycled materials. The sunglasses manufactured by Eco-Eyewear come in various sizes, models and specifications but the resources used in production (E.g. raw materials, labour and machinery) are identical. As the Production Planning Manager, one of your tasks is to determine how many sunglasses to produce based on the sales forecast from the Sales and Marketing Department. Table 1A shows the sales forecasts of sunglasses from January 2011 to December 2011.
Table 1A: Sales Forecasts of Sunglasses
Month Sales Forecasts
(Units)
Month Sales Forecasts
(Units)
Jan 2011 5,000 Jul 2011 4,600
Feb 2011 4,000 Aug 2011 9,200
Mar 2011 6,500 Sept 2011 9,000
Apr 2011 9,000 Oct 2011 8,000
May 2011 5,500 Nov 2011 8,800
June 2011 8,600 Dec 2011 6,200
In addition, you have the following information about the cost and production. Cost Information
Regular Worker Rate= $12/hr Inventory Holding Cost= $2 per unit/month Cost of Hiring a Worker = $200 Cost of Firing a Worker = $400 Backorders Charge = $3 per unit/month
Other Information
Number of Working Days per month = 22 Current Workers Strength = 15 8 hour shift /day Average Assembly Rate = 20 units/worker/shift
SCHOOL OF
ENGINEERING
Discuss how would you plan for the production of sunglasses in the coming months, with a view to keep the total production cost as low as possible?
School of Engineering
P07 – How Many To Make
E222 – Logistics Planning And Control
• Production Planning
• Key Aspects of Aggregate
Planning
• Types of Aggregate Production
Plans Zero-Inventory Plan
Level Work-Force Plan
Mixed Aggregate Plan
School of Engineering
Production Planning • Production Plan- Determines how much and when to make a
product
Goal: To match production rate and demand rate so that
products are made when needed
• Factors constituting the complexity of Production Planning
Function:
i. Number of products
ii. Demand pattern & uncertainty
iii. Number of periods in planning horizon
iv. Alternative production processes
v. Subcontracting
vi. Overtime
vii. Inventory
School of Engineering
Production Planning
Long Range Plan
Intermediate Range Plan
Short Term Plan
~2-10 year
period
~6 months-2
year period
1 week-6
months
e.g. Long term capacity, location, layout,
product design, work system design
e.g. General level of work-force, output
subcontracting , overtime
Aggregate
Planning
e.g. Job sequencing, detailed machine loading,
work schedules
Time Period
School of Engineering
Aggregate Production Planning
Business
planning by top
management
Manufacturing
management
and planning
School of Engineering
Aggregate Production Planning
• Intermediate range planning is also referred
to as Aggregate Production Planning
• Focus: Determining volume of product
family („aggregate unit”) to produce, not mix
of individual products
• Aim: To balance demand and supply
(production) at the lowest cost
School of Engineering
Aggregate Production Planning • Three key aspects of Aggregate Production Planning
1. Capacity• How much a production system can make
• To satisfy demand, system capacity should exceed demand , at least over the
long run
2. Aggregate Units• A variety of products is produced over intermediate and long range period. They
are lumped together to form aggregate units
• Different products in aggregate units share the same production capacity
3. Costs• Production costs: E.g. Material, direct labor, overtime and subcontracting costs
• Inventory costs: E.g. Holding and shortage costs
• Capacity change costs: E.g. Hiring and training costs, separation costs
School of Engineering
Types of Aggregate Production Plan
1. Zero-Inventory Plan
• Also known as Lot-for-lot , Chase or Just-in-time plan
• Each month, produces exactly the amount demanded
• No inventory is carried over
• Workers are added when demand increases and layoff when
demand decreases
(+) Advantages
• Low investment in inventory
• Labor utilization is kept high
(-) Disadvantages
• Cost of adjusting output rates and/or workforce levels
• Variability in workforce is an undesirable phenomenon seen by many
Zero-inventory plan
Time
Units
DemandProduction
School of Engineering
2. Level Work-Force Plan
• Also called Level production or Constant work-force plan
• Same number of workers used in each period
• Uses inventory produced in off-peak periods to satisfy demand in
peak periods
(+) Advantages
• Stable output rates and workforce
(-) Disadvantages
• Greater inventory costs
• Increased overtime & idle time
• Resource utilization that vary over time
Level work-force plan
Demand
Production
Units
Time
Types of Aggregate Production Plan
School of Engineering
3. Mixed Aggregate Plan
• Combination of Zero-inventory plan & Level Work-
Force plan
Examples: Inventory level cannot exceed x dollars; no more
than y% of workers can be laid off in a month
• Allows inventory, backorders and changing work-force
levels
• Usually yields better outcome than Zero-Inventory plan
and Level Work-Force plan
• How? →Trial & error ,make changes using spreadsheet
Types of Aggregate Production Plan
School of Engineering
Zero-Inventory Plan
• Each month, produces exactly the amount demanded
• No inventory is carried over
• Workers are added when demand increases and layoff when demand decreases
School of Engineering
Zero-Inventory Plan
Work-Force
Fluctuations
School of Engineering
Level Work-Force Plan
• Same number of workers used in each period
• Uses inventory produced in off-peak periods to satisfy demand in peak periods
Note: Assuming backorder
School of Engineering
Level Work-Force Plan
Inventory
Fluctuations
School of Engineering
Proposed Aggregate Plan: Mixed
• Combination of Zero-inventory plan & Level Work-Force plan
• Allows inventory, backorders and changing work-force levels
School of Engineering
Comparing the Aggregate Production
Plans
“Pure Strategies” (zero-inventory & level workforce plan)are useful
as basis for drafting a realistic aggregate plan
o Instances of high inventory & backorder costs > zero-inventory plan is
favored
o Industries employing highly skilled labor > level workforce plan is prevalent
Mixed Aggregate Plan satisfies demand and yields better
outcome in terms of total cost compared to “pure strategies”
School of Engineering
Learning Outcome
• Production Planning
• Key Aspects of Aggregate Planning
• Types of Aggregate Production Plans
Zero-Inventory Plan
Level Work-Force Plan
Mixed Aggregate Plan
SCHOOL OF ENGINEERING
P08 – SCHEDULING FOR PRODUCTION
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Scheduling For Production
After graduation from Republic Polytechnic, you have been employed to work as a Production Planner at Astro-Optics Corporation, a manufacturer of optical instruments (E.g. Telescopes, binoculars, spectacle lens). You are put in charge on the production planning for the company’s V-Max model of binoculars.
You need to work out the Master Production Schedule (MPS) for V-Max binoculars over the next three months from October to December.
The weekly forecasts of V-Max binoculars by the Sales and Operations Department are shown in Table 1A. In addition, the company has secured two months of committed customers’ orders for October and November (See Table 1B). Committed customers’ orders for December are still pending inputs from the Sales Department.
Table 1A: Weekly Sales Forecast of V-Max Binoculars
Table 1B: Committed Customers’ Order for V-Max Binoculars
SCHOOL OF
ENGINEERING
You check with the warehouse manager and know that there are still 200 units of V-Max binoculars in the warehouse on 30th September. The factory manager updates you that in every production run, the factory floor would produce 500 units of V-Max binoculars.
Based on the information provided, how would you decide on the weekly production quantity for the period? Determine also the level of inventory that is uncommitted and available for new customer orders.
School of Engineering
P08 –Scheduling For Production
E222 – Logistics Planning And Control
• Master Production Schedule
(MPS) Functions
Applications (Inputs & Outputs)
• Available-to-Promise (ATP)
School of Engineering
Types of Operational Problems Faced
by a Manufacturing Company
• Missed customer deliveries
• Mismatched inventory
• Large queues and excessive work-in-
progress
• Unplanned overtime
• Under-used resources
• End-of-month rush to meet financial
closing date
School of Engineering
What is Master Production
Schedule (MPS) ?
A detailed plan that states how many end
items will be produced within specified periods
of time.
a. End items are either finished products or the
highest level assemblies from which shippable
products are built.
b. Time periods are usually measured in weeks,
although they may be measured in hours, days,
or even months.
School of Engineering
Master Production Schedule
(MPS) Process
Figure G.1
No
Yes
Are resources
available?
Authorized
production
plan
Prospective master
production
schedule
Material
requirements
planning
Authorized master
production schedule
School of Engineering
Functions of MPS
• Provide tangibility to production activities
• Manage inventory
• Manage capacity constraints Hedge demand variations
Balance to a constraint
• Control engineering changes
• Plan material requirements
• Optimize production activity sequence
School of Engineering
MPS indicates quantity and timing of planned
production, taking into account desired delivery quantity
and timing, as well as on-hand inventory.
Inputs: 1. Inventory at start
2.Forecast for each scheduling period
3.Committed customer orders
Outputs: 1.Projected inventory
2.Production requirements
3.Uncommitted inventory (available-to-promise)
Master Production Schedule
School of Engineering
Problem Statement Analysis
• The MPS presented indicates a lot size of 500
• Objectives are to avoid missed deliveries, excessive
WIP and mismatched inventories
• Assumptions:
• Customer orders to be filled by end of the week
• Production to start at beginning of week and MPS
quantities will be achieved at end of the week
• No capacity constraint
• Availability of material is not an issue
School of Engineering
• Forecasted demand is given on a weekly basis for the next three months.
• First step is to calculate Net Inventory before MPS quantity. In this example, the specified limit is assumed to be zero. Hence, we will continue until the Net Inventory before MPS is negative.
• Net Inventory before MPS = Previous week inventory -current week requirements
where the current week's requirements is the larger of forecast and customer orders (committed)
Master Production Schedule
School of Engineering
• For the first week, projected on-hand inventory
equals inventory at start minus the larger of
forecast and customer orders. Because forecast
(220) is smaller than the customer orders (230),
the customer order quantity is used. Thus, for the
first week, we obtain:
Production requirement = max(220,230) = 230
Net Inventory before MPS = 200 - 230 = -30
Master Production Schedule
School of Engineering
• When the Net Inventory before MPS
becomes negative, this is a signal that
production will be needed to replenish
inventory Planned production is hence required
• Production will take place according to
the lot size of 500
Master Production Schedule
School of Engineering
• Hence, the negative Net Inventory before MPS
in Wk 1 will require production of one lot size,
which is 500 units of binoculars
This will meet the projected shortfall of 30 units
and leave 470 units for future demand.
• These calculations continue for the entire
schedule. Every time Net Inventory before
MPS becomes negative, another production lot
of 500 units will be triggered in the schedule.
Master Production Schedule
School of Engineering
Available-to-Promise (ATP)
• Available-To-Promise (ATP) inventory is that portion of the on-hand inventory plus scheduled production that is still not committed to the customer orders.
• Using a "look-ahead" procedure: Add the booked customer orders week by week until (but not including) the week in which there is an MPS entry.
• For the first period (Wk 1), the ATP includes the beginning inventory plus any MPS amount in that period, minus the total of booked orders up to the time when the next MPS amount is available.
Thus, ATP (Week 1) = 200 +500 - 230 - 200 - 240 = 30
School of Engineering
Available-to-Promise (ATP)
• In subsequent periods (other than period 1), the ATP inventory consists of the MPS amount in that period, minus the actual customer orders already received for that period and all other periods until the next MPS amount is available.
• E.g. For Week 4, promised amounts are 230 + 180 = 410,
and the ATP is 500 - 410 = 90
•The same method continues for the rest of the weeks.
School of Engineering
Available-to-Promise (ATP)
• As additional orders are booked, these would be entered into the schedule and the ATP (Available-To-Promise) quantity would be updated to reflect these orders
• Astro-Optics Corporation can then use the ATP quantity to provide realistic delivery dates to new customers
School of Engineering
Today’s Problem
School of Engineering
Conclusion
• In October, Astro-Optics Corporation
needs to produce 500 units of V-Max
binoculars in Week 1 & Week 4
• In November & December, the company
needs to produce 500 units of V-Max
binoculars in Week 2 & Week 4 for both
months
School of Engineering
Learning Outcome
• Master Production Schedule (MPS) Functions
Applications (Inputs & Outputs)
• Available-to-Promise (ATP)
SCHOOL OF ENGINEERING
P09 – Manage the Material
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Manage the Material
You are the Materials Planning Executive of Lifestyle Furniture Ltd. Your company manufactures a wide range of furniture (E.g. Sofas, cabinets and coffee-tables) for sale in the local market.
The bill-of-material (BOM) for the company best-selling Coffee-Table is given below. (See Figure 1A)
Figure 1A: Bill-of-Material (BOM) of Coffee-Table
Recently your company has secured an order to supply coffee-tables to a hotel chain. The Master Production Schedule (MPS) for the Coffee-Table is shown below for the next 8 weeks or 2 months.
Table 1B: Master Production Schedule (MPS) of Coffee-Tables
SCHOOL OF
ENGINEERING
Work out the Material Requirements Planning (MRP) record for the Coffee-Table “Legs” (Part No: 203). Assume that it (Coffee-Table “Legs”) has a lead-time of one week and the production lot size is 30 units. There is an on-hand inventory of 200 “Legs” in Week 0 and a scheduled receipt of 30 “Legs” in Week 2. After you have created the MRP records, the Sales and Planning Department announced that there will be addition of customer orders for the Coffee-Tables in Week 6. The new requirement will be 65 units. With the changes, the MRP records for the Coffee-Table “Legs” will need to be updated. How would you update the records? Should you regenerate a new set of MRP or do you simply just update those records that need changing? Give your recommendations?
School of Engineering
P09 – Manage the Material
E222 – Logistics Planning And Control
•Understand Material Requirement
Planning (MRP)
•Bill of Material Structure
•MRP Generation
•MRP Updating ApproachesRegenerative Method
Net Change Method
School of Engineering
Material Requirements Planning (MRP)
• An MRP system generates time-phased
requirements for components or raw materials to be
used for production.
The inputs to a MRP system are
1. Inventory record
2. Master production schedule (MPS)
3. Bill of material (BOM)• BOM is a listing of all sub-assemblies, intermediates, parts and raw
materials that go into making the parent assembly showing the quantities of
each required to make an assembly (APICS Definition)
• MRP output is net requirement, used in generating
purchase and work orders.
School of Engineering
MRP System Overview
School of Engineering
MRP Process Sequence
• Explosion : Use information from MPS and BOM to derive quantity required for every product component and raw material
• Netting : Gross requirements are adjusted (at every level of the BOM & for each time bucket) to account for inventory and receipts
• Offsetting : Timing of order release is determined, to take into account production and supplier lead times
• Lot sizing : Batch size to be purchased or produced is determined
Net requirement = Gross requirement – Scheduled receipts -
Projected inventory balance (preceding week)
School of Engineering
MRP Explosion – illustration
BOM information
School of Engineering
MRP Explosion – illustration
BOM information
School of Engineering
Bill of Material (Multilevel Bill)
• Multilevel bills are formed as logical groupings of parts into
subassemblies based on the way the product is assembled
Coffee- Table
100
Base (1)
200
Legs (4)
203
Leg Bolts (4)
220
Frame (1)
300
Leg Supports (4)
Glue
066
Ends (2)
411
Sides (2)
622
Top (1)
023
Glue
066
Boards (3)
030
School of Engineering
Bill of Material (Multiple Bill)
• A multiple bill is used when companies usually make more than
one product, and the same components are often used in several
products. This is particularly true with families of products
Example of multiple bills
School of Engineering
Bill of Material (Single-Level Bills)
• A single-level bill of materials contain only the parent and its
intermediate components
Example of single-level bills
School of Engineering
Original Material Requirements Planning
1) Referring to BOM, gross requirement for Legs is 4 for each Coffee Table(explosion of
required quantities)
2) Scheduled receipts refer to castors that are to be received due to open work or
purchase order (open work order is assumed here)
3) Lot size is assumed to be 30 (lot sizing) Assume receipt at the beginning of the week
Net requirement (netting) = Gross requirements – Scheduled receipts – On-hand
quantity (previous week)
4) Offsetting process is done in Planned Order Release to cater for the 1-week lead
time
(Note: Net requirement for the week cannot be a negative value)
School of Engineering
Changes that Affect MRP
• Forecasts/ Demand (MPS) changes
• Product structure changes
• Promised deliveries arriving late
• Lead time changes
Note: Whenever there are any changes, it
should be updated accurately and quickly
School of Engineering
MRP Updating Methods
•The two basic methods used to update the MRP records are:
Net Change
Regenerative
•A Regenerative System is updated periodically while a Net-Change system is updated continuously.
School of Engineering
Regenerative Method
The entire material plan is recalculated,
based on the current MPS and exploding
the entire BOM.
Each item record is completely recalculated.
(i.e. all part numbers are reconstructed and
current planning orders are removed.)
All requirements are recalculated, as are the
inventory data and planned orders.
School of Engineering
Net Change Method
Recalculates requirements only for those items
affected by change; i.e. A partial explosion is
performed, only the changes are exploded
through the system, level by level. The entire
plan is not regenerated.
Only additions and deletions from the master
schedule are entered.
Production plan modified to reflect changes as
they occur, e.g. some defective purchased
parts had to be returned to a vendor.
School of Engineering
New MPS
Change in the MPS quantity in week 6
is the input to net change updating
method.
School of Engineering
Updated MRP Record
(Regenerative Method)
• Entire MRP record is regenerated, but changes are only
in the highlighted boxes
• Other files such as BOM, inventory data and rest of the
MRP records are also completely regenerated.
School of Engineering
Updated MRP Record Using Net
Change Method
• Only records that need changing will be updated. The net change in requirements
(+120) is updated in Week 6.
• The blank records in the table above mean no recalculation needed unlike
Regenerative method where all records are recalculated
• In Net Change method, the system will immediately update the net change, i.e. +120
in gross requirements (Week 6) and +120 in planned order release (Week 5)
• MRP records of other components are processed in the same manner
• All inventory data are kept current with the update of ‘On-hand’ quantities
School of Engineering
Regenerative Method
Suitable for fairly stable systems
Disadvantages:
Deterioration of MRP – status and requirements are
not updated constantly.
Long computer time
Advantages:
Less processing costs (frequency of updating is lesser
for this method therefore requiring less computing
power)
School of Engineering
Net Change Method
Suitable for systems that have frequent changes
Disadvantages:
High processing costs due to many small and frequent
updates (require more computing power)
Net change may generate too many action notices
Advantages:
Quick on-the-spot implementation
Requires little computer time
Up-to-date information for planning and control
purposes
School of Engineering
Conclusion
Both Regenerative and Net Change methods are
available and applied in conjunction in most
Enterprise Resource Planning (ERP) software
Regeneration is usually performed once a week or
once a month to clean up all records
Between regenerations, the records can be updated
using the Net Change method
Decision to operate Regeneration or Net Change
method depends on the nature of manufacturing
environment.
School of Engineering
Learning Outcome
•Understand Material
Requirement Planning (MRP)
•Bill of Material Structure
•MRP Generation
•MRP Updating Approaches•Regenerative Method
•Net Change Method
SCHOOL OF ENGINEERING
P10 – Plan and Order
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Plan and Order
Motor Hub Pte Ltd (MH Pte Ltd) specializes in manufacturing standard motorcycle as well as customizing motorcycle for motorcycling enthusiasts. Over the past year, there has been a huge growth in business (over 75%) for the company. In order to perform better resource planning and scheduling, MH Pte Ltd decides to invest in a new manufacturing planning and control (MPC) system. After a few months of research and testing, a MRPII system (SAP) is finally being implemented within the company. Recently, MH Pte Ltd receives an order to customize a new batch of motorcycles. These motorcycles are to be delivered at various dates. In addition, the customer has requested that some parts/components to be customized and the orders are to be delivered at the shortest time possible.
The components used for manufacturing the customized motorcycle are shown below. (See Figure 1A)
Level Item
Description Material Number
Item Type Components of Original Design (Component ID)
Lead Time
(Days) Quantity
Safety Stock
0 Motorcycle A1-
XXXXXX Finished Product
1300-1400 5 1 0
1 Light B1-
XXXXXX Semi-Finished
Product 2300-101 5 4 0
1 Body C1-
XXXXXX Semi-Finished
Product 1300-251 10 1 0
2 Wheels D1-
XXXXXX Raw Material 3300-113 5 2 0
2 Engine E1-
XXXXXX Raw Material 3300-113 5 1 0
Figure 1A: Bill-of-Material of Customized Motorcycle
SCHOOL OF
ENGINEERING
As the company’s operation planner, you have been tasked to generate a schedule to meet this demand using the new SAP system. You are also expected to describe how SAP helps in fulfilling the functions of MRPII, to some new planners who just join your department.
School of Engineering
P10 – Plan and Order
E222 – Logistics Planning And Control
• Describe Manufacturing
Resource Planning II (MRP II)
• Using an ERP tool to perform
some of the MRP II functions• Production Master Data
• BOM
• MPS
• MRP
School of Engineering
What is Manufacturing Resource Planning
(MRP II)
• Second generation of MRP (extension of functionality)
• MRP is the heart of MRP II
• More than scheduling and ordering of materials – it integrates Sales, Engineering, Finance, Quality, etc
• Effective planning of all resources in an organization through integrated system
• Addresses operation planning in units, financial planning in dollars, has simulation capability to answer „what-if‟ questions
• Outputs integrated with financial reports like business plans, purchase commitment report, shipping budget, inventory production in dollars, etc.
• Is essentially a „closed-loop‟ MRP with connections to business and financial planning, reporting facilities and „what-if‟ simulation capabilities
School of Engineering
Manufacturing Push System
• Central planning approach
(work center activities based on MRP schedule)
• Schedule in advance (plan ahead by MRP)
• Forecast (Master Production Schedule – MPS)
• Lot size based on economic consideration
• Local optimization (maximize production throughput)
• Work center “pushes” completed jobs to next center
• Functions best in a high demand, continuous
production environment
School of Engineering
MRP II System (ERP)
MRP IIO
per a
t ion
Pla
nn
ing
MRP
Ex
ecut io
n
Upp
er
Man
ag
em
en
tP
lannin
g
Production
Planning
Master
Production Schedule
MRP
Shop Floor Control
Capacity Planning &
Simulation
Feedback
- Routings
- Inventory Status- BOM- Item Master
Files
Part ID, lead time,
lot size and etc..Material
Plan
Shop
Orders
Purchasing Planning
Purchasing
School of Engineering
• Provides robust and fully integrated financial and sales
management capabilities, the solution gives managers
on-demand access to critical real-time information
• Has customisable packages for large organizations,
small and midsize companies, and industries
• Effective planning of all resources in an organisation
through integrated system
• Addresses operation planning in units, financial planning
in dollars, has simulation capability to answer „what-if‟
questions
• Outputs integrated with financial reports like business
plans, purchase commitment report, shipping budget,
inventory production in dollars, etc.
MRP II Functions Using SAP
School of Engineering
• Systems, Applications, and Products in Data Processing
• Central relational database
• Three-tier Client/Server system
• Collections of logically related transactions within business
functionsPP (“Make”)
MM (“Buy”)
SD (“Sell” and “deliver”)
FI and CO (“Track”)
HR, etc.
• Add-ons: Customer Relationship Management (CRM)
Supply Chain Management (SCM)
Product Lifecycle Management (PLM)
Etc.
Architecture
School of Engineering
Structure Terminology
SAP
School of Engineering
Suggested Solution
School of Engineering
After Logon
School of Engineering
Material Master – Basic Data
Create Item ID
Input Item
Name
Define Unit of
Measure
Material
Group
School of Engineering
Material Master – MRP 1
Purchasing
Group
MRP Type
Lot Sizing
School of Engineering
Material Master – MRP 2
Planned
Delivery Time
School of Engineering
BOM
Parent Item ID
Material used
in producing
the parent part
Item # in
Material BOM
Quantity per
Parent
School of Engineering
View Overall BOM Generated
A1-XXX
B1-XXXC1-XXX
D1-XXX E1-XXX
School of Engineering
Planned Result (A1-XXX)
School of Engineering
Planned Result (B1-XXX)
School of Engineering
Planned Result (C1-XXX)
School of Engineering
Planned Result (D1-XXX)
School of Engineering
Planned Result (E1-XXX)
School of Engineering
Material Master DataContains all data required to define and manage all types of
materials
• Raw materials:
Materials purchased from external suppliers
• Semi-finished goods (Sub-assemblies):
Components that have been assembled from raw materials
• Finished goods:
The final product that is sold to the customer
School of Engineering
Conclusion
With the help of SAP, MH Pte Ltd is able to:
Plan its materials flow from raw materials until
finished product, more efficiently
The company is able to keep track of all the
necessary information regarding the product
including,
Components for each parts
Lead time
Cost
School of Engineering
Learning Outcome
• Describe Manufacturing Resource Planning II
(MRP II)
• Using an ERP tool to perform some of the
MRP II functions• Production Master Data
• BOM
• MPS
• MRP
Page 1 of 3
SCHOOL OF ENGINEERING
P11 – WHEN TO WHERE AND HOW MANY
E222 – LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Page 2 of 3
When to Where And How Many
Tamaya Motor Corporation is a manufacturer of motorbikes. Its manufacturing plant is located in Hokkaido, Japan.
To serve the Southeast Asia market, the company has a Regional Warehouse (RW) located in Singapore. In addition, there are two distribution centers (DC), one located in Bangkok (Thailand) and the other in Jakarta (Indonesia) to serve the customers (retailers) in the region. Motorbikes from the Hokkaido plant would ship to the Regional Warehouse first and then distribute to Jakarta and Bangkok DCs. The two DCs would then distribute the motorbikes to their respective retailers. (See figure below)
In August - September 2010 (for a period of 8 weeks), Tamaya Motor decides to hold a promotion for one of its most popular model of motorbikes – Trailer SX. To ensure that there are sufficient stocks for the retailers, the following requirements are obtained from the Bangkok and Jakarta Distribution Centers (DCs) respectively.
Table 1a: Requirement of Bangkok DC
Week 1 2 3 4 5 6 7 8
Gross requirements 75 85 90 65 85 95 80 85
Table 1b: Requirement of Jakarta DC
Week 1 2 3 4 5 6 7 8
Gross requirements 70 60 70 70 80 80 65 85
SCHOOL OF
ENGINEERING
Page 3 of 3
As the Company’s Logistics Planner, you have been tasked to work out the distribution requirements plan (DRP) for the Regional Warehouse (Singapore). The forecast for the Singapore Regional Warehouse (RW) is also given.
Table 1c: Forecast for Singapore RW
Week 1 2 3 4 5 6 7 8
Forecast 40 40 40 30 30 30 50 50
The following table gives some additional information about the 3 warehouses.
Lot Size (Units)
Lead time (Weeks)
Safety-Stock Required
(Units)
Scheduled Receipts (Units)
Bangkok DC 100 1 10 0
Jakarta DC 100 2 15 0
Singapore Regional
Warehouse 200 2 60 200 (Week 1)
There are on-hand inventory of 100, 90 and 200 motorcycles for Bangkok DC, Jakarta DC and Singapore Regional Warehouse (RW) respectively. Discuss how would you go about planning for the distribution?
School of Engineering
P11 – When To Where And How Many
E222 – Logistics Planning And Control
• Distribution Requirements
Planning (DRP) Linkages with MPC System
• DRP Techniques Basic DRP Record
Linking several warehouse records
Safety stock in DRP
School of Engineering
Distribution Requirement Planning
(DRP)
• The basis for integrating supply chain inventory
information and physical distribution activities with the
Manufacturing Planning and Control (MPC) system.
• Managing the flow of materials between firms,
warehouses, distribution centers. DRP helps to manage these material flows.
Similar to MRP in Manufacturing.
• Relate firms in the supply chain by providing planning
records that carry demand information from receiving
points to supply points and vice versa.
School of Engineering
A Multi-Echelon Inventory System
Example
School of Engineering
What if I Use Traditional Techniques?
• In multi-echelon inventory systems with
decentralized control, lot size / reorder
point logic will:
Create and amplify "lumpy" demand
Lead to the mal-distribution of available stock,
hoarding of stock, and unnecessary stock-outs
Result in large safety stocks, expediting, and
re-distribution.
School of Engineering
Impact of Multi-Echelons
RDC Inventory
Patterns
LDC Inventory
Patterns
Demand for
Retailer
Layers of Inventory Create “Lumpy Demand “
Plant Inventory Patterns
School of Engineering
Purposes of DRP
• DRP enables the firm to capture data, including local
demand conditions, for modifying the forecast and to
report current inventory positions.
• This is specially true when they have vendor managed
inventories (VMI).
• DRP provides data for managing the distribution facility
and the database for consistent communications with
the customers and the rest of the company.
• “DRP is simply the application of the MRP principles
and techniques to distribution inventories”
School of Engineering
DRP, MRP & MPC Relationship
School of Engineering
Basic DRP Record
• Forecast requirements (Gross Requirement)
• In transit (Scheduled Receipts)
• Requirements (Net Requirement)
• Projected available balance (Available)
• Planned shipments (Planned Order Releases)
• Forecast in central supply (if applicable)
School of Engineering
Time Phased Order Point (TPOP)
• MRP-like time planning logic for independent demand
items, where gross requirements come from a
forecast, not via explosion.
• Technique can be used to plan distribution center
inventories as well as to plan for service (repair) parts. Because MRP logic can readily handle items with dependent demand,
independent demand, or a combination of both.
• Time-phased order point is an approach that uses
time periods, thus allowing for lumpy withdrawals
instead of average demand. When used in distribution environments, the planned order releases are
input to the master schedule dependent demands.
School of Engineering
Safety Stock and DRP
• When there is more uncertainty in terms of timing, then it may be better to use safety lead time.
• When the uncertainty is in quantity then safety stock may be better.
• Carry safety stock where there is uncertainty (near the customer) or where there is some element of independent demand
School of Engineering
Potential Management Issues with
DRP
• Data Integrity and Completeness
• Organizational Support
• Stock-Aging
School of Engineering
Data Integrity and Completeness
• A key issue is the use of aggregate forecasts which are later on broken down into detailed forecasts.
Adding up of errors
• Forecast errors should be avoided especially biased errors.
• Management programs should be established to monitor the process.
• Inventory accuracy depends on transaction process routines and discipline.
School of Engineering
Organizational Support
• To better coordinate a chain like this,
information in DRP form as well as organization
form (e.g. material management) is required
DRP
School of Engineering
Monitoring Stock Aging
• Use strict first-in first-out (FIFO) physical
movement.
• Identify those products that may be heading
for a problem before it is too late.
Messages to flag potential shelf life problems.
• If demand is dropping – forecast should be
reduced. Available inventory or in transit
should cover a larger period of time. Maybe
shipped to another warehouse.
School of Engineering
Today’s Problem
Plant (Hokkaido, Japan)
Regional Warehouse
(Singapore)
Bangkok DC Jakarta DC
Retailer A
Retailer B
Retailer C
Retailer X
Retailer Y
Retailer Z
School of Engineering
DRP (Bangkok DC)
• Assumptions:
Lot size of 100 units
Lead time of 1 week
10 units of safety stock are needed
School of Engineering
• Assumptions:
Lot size of 100 units
Lead time of 2 week
15 units of safety stock are needed
DRP (Jakarta DC)
School of Engineering
Regional Warehouse (Singapore)Note: Gross Requirements of Regional Warehouse = Forecast + Planned release
order of DCs (Bangkok & Jakarta)
• Assumptions:Lot size of 200 units
Lead time of 2 week
60 units of safety stock are needed
School of Engineering
• DRP relates current field inventory availability,
forecast & knowledge of demand to develop resupply
plans and bring those to the MPS of the MPC system
• Gross requirement for Regional Warehouse (RW) is
the sum of all planned order release from various
DCs plus forecast
• Stocks at RW needs to be planned 2 weeks in
advance
Lead time for RW is 2 weeks
• Stocks need to be fulfilled once it falls below the
Safety Stock (SS) requirement
Conclusion
School of Engineering
Learning Outcome
• Distribution Requirements Planning
(DRP)
Linkages with MPC System
• DRP Techniques
Basic DRP Record
Linking several warehouse records
Safety stock in DRP
SCHOOL OF ENGINEERING
P12 – REVERSING THE FLOW
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the School of Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Reversing The Flow
You are the Sales Manager of Inno-Com Ltd− a laptop manufacturing company. Selling laptop is a highly competitive business. To keep up with the intense competition, your company has maintained a “seven day return policy” for the customers. Under this policy, unsatisfied customers may return their merchandise to the company’s customers service center ,promising a full refund of the item’s cost within seven days of purchase* (Note: *Terms and conditions apply). For the past few months, sales performance for the company’s laptops has been excellent. As sales volume grows, so are the number of returned products due to defects, warranties and other issues. The returned laptops are piling up in the company’s warehouse wasting valuable storage space. In addition, your customer service staffs are receiving many phone calls from customers enquiring about the status of their returned laptops that they have sent in for repair. You feel that the current return process is too inefficient and generates too much unnecessary costs to the company. What kind of recommendation(s) would you suggest so that your company can manage its returned products more effectively?
School of Engineering
P12 –Reversing The Flow
E222 – Logistics Planning And Control
•Reasons for Reverse Logistics
System
•Reverse Logistics Process
•Overcoming Reverse Logistics
Challenges
School of Engineering
Reverse Logistics
Reverse Logistics
Raw
materials
suppliers
1 2 3 4 5
Manufacturer Distributor Wholesaler Retailer
6
End-User
Obtain Produce Distribute
Typical Materials/Goods Flow
School of Engineering
Reasons For Reverse Logistics
• Return of goods for credit
IT products
• Rental or lease returns
Material handling equipment
• Warranty returns
Printers, MP3 players,
consumer electronic products
• Reusable containers
Milk crates, Pallets
• Consignment agreement returns
Fashion, leather products
• Online purchase returns
Arts and crafts
• Disposal
• Trade-ins
Old PCs
• Take-backs
Old clothes
• Universal product recalls
Contact lens solutions
• Units for inspection or recalibration
Microscope
• Products not meeting guarantees
Lowest price by Carrefour
• Product/Component reuse, recycle
and retrieve residual value
Electronic chips, plastics, batteries,
paper, tin cans
School of Engineering
• Savings In The After-Market
Sometimes there is literally gold in the reverse supply
chain, not to mention platinum, silver, copper and a whole
range of commercial metals
• Competitive Edge
Consumers can be wooed and won with products that
promise good service.
Ease of return, repair & recycling may add to a product’s
value in the consumer’s mind
Motivations For Reverse Logistics
System in Company
School of Engineering
• Consumer & Shareholder Pressure
Shareholder groups may propose various “green”
policies
• Growing Market For Environmentally Safe
Products
Some customers will pay a premium for products
that protect themselves and the earth
• Environmental Awareness & Regulations
Motivations For Reverse Logistics
System in Company
School of Engineering
Key Issues in Reverse Logistics
• Prevention
• Data Tracking
• Customer Service
• Using 3rd Party Logistics Specialist
• Consolidation
• Cost Savings
• Generating Revenue
School of Engineering
Prevention
• “The best way to handle a return is never have
to handle it in the first place”
But if it happens;
• Establish clear procedures to handle returns effectively
• To ensure returns are inherent in product and not due
to usage
• Clear guidance on website/helpline/manuals for
troubleshooting, to segregate faulty product from
product fault caused by usage
School of Engineering
• Companies need to learn more about why their
consumers are returning goods. The data they
collect is a way for them to
Reduce returns & improve product and/or production
and/or operating instructions and/or distribution process
Identify trends (if any)
Eliminate certain type of goods
Quickly redistribute the goods
• Data should be entered uniformly and consistently
for tracking
Data Tracking
School of Engineering
• Short cycle time between customer calling to report,
collection of faulty product and return of repaired/new/
substituted product
• Helpful hotlines, websites and instructions sheets to
report faults and activate technical support/collection
• Bring new product/repaired/substitute product to
exchange as soon as possible
E.g. provide ready-to-mail-back envelopes
• Quick to collect faulty product from customer through
use of couriers or set up collection centers
Customer Service
School of Engineering
Third-Party Logistics Specialist
• A growing number of retailers/e-tailers outsource to a
reverse-logistics specialist.
For fees typically ranging from US $1 to $5 per returned item (plus
shipping), companies such as Newgistics, UPS E-Logistics, and
Genco can take over every aspect of a returns process or just a part
of it
After contracting with Newgistics, one company closed the area of its
warehouse devoted to returns, lowering its handling costs
• Email updates to inform them the status of their return
• Efficient collection, consolidation, sorting, reuse, repair
and return products process
E.g. Intermec products are repaired in UPS warehouse instead of at
designated product service centers
School of Engineering
Consolidation
• Consolidation (Aggregation) allows
returned products to be Sorted
Tested
Data Collected
Transported
Product requirements consolidated and ordered
more economically
School of Engineering
• Cost-savings for reverse logistics are
achieved through:
Data collection
Redistribution of goods
Effective reporting
Remedial actions
Cost Savings
School of Engineering
Generating Revenue
• Minor product faults can be repaired
quickly and sold at reduced prices to
generate revenues rather than disposing it
• Take advantage of actual value that can
be derived versus perceived value from
person discarding the product
School of Engineering
Reverse Logistics ProcessesCustomer returns
Product
Closed loop
Exchange inc
warranties
Sortation/
testing
Can the product
Be resold?
Basic
Processing
Eg repack
Primary market
Stock, vendor,
supplier
Can the product
Be repair/
Refurbished?
Repair/
Refurbished
recondition
Secondary markets
E-auction, outlet
Stores, jobbers, etc
Does the
Product have
residual value?
Value
recovery
Preprocessor,
Recycle
markets
Waste
disposal
Compliance
information
No No No
Yes Yes Yes
spares
Data
Collection
Compliance
information
Consolidation
School of Engineering
Performance Measurement
• Defining metrics to measure the success
of reverse logistics activities is important
• Not too different from forward
logistics/supply chain measurements
Total cost of Reverse Logistics
Reliability
Flexibility
Asset Management
Responsiveness/Cycle Time
School of Engineering
Key Benefits
• Improved control and asset recovery
• Income generation through recycling,
reuse, repackage rather than unsold
inventory
• Efficient route planning – returns
collections matched with outbound
deliveries
• Reduced inventory and obsolescence
School of Engineering
Today’s Problem
• Find out why customers return their laptops (Data
Tracking and Prevention)
Identify trends (if any)
To establish clear procedures to handle returns effectively
• Do away with warehouse and outsource to 3PL
(e.g. SingPost) to handle the returns, consolidations
& repackaging so as to achieve Cost Savings
• Sell returned/repaired products (Laptops &
accessories) at reduced prices rather than
accumulating them (Generate Revenue)
School of Engineering
• Examples of reverse logistics @ SingPost
NLB Books
HP ink cartridges
Canon Printers And Cameras
Epson Printers
Acer Laptops And Desktops
Robinson Shopping Centre And John Little
Apple iPod
SingTel Hand Phones
SingNet Modems ….
Problem Statement
School of Engineering
Problem Statement
Customer Post Office
Branches
Consolidate at
Centralized
Collection Centers
Manufacturing PlantSuppliers
Repackage to resell
For
recycle
and repair
Suggested Reverse Logistics Process for Inno-Com Ltd
School of Engineering
With conservation of the environment in mind, Inno-
Com Ltd can design/manufacture their products for
reverse logistics (Reduce, Reuse, Recycle)• Make products recyclable
• Use recycled materials
• Use less-harmful ingredients
• Use lighter components
• Use less energy
• Use less material
E.g. Singapore Packaging Agreement
http://app.nea.gov.sg/cms/htdocs/article.asp?pid=2905
Environmental Issues are becoming more important!
Going Further…
School of Engineering
Learning Outcome
•Reasons for Reverse Logistics
System
•Reverse Logistics Process
•Overcoming Reverse Logistics
Challenges
SCHOOL OF ENGINEERING
P13 – How Does It Perform
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical,
photocopying, recording or otherwise, without the prior permission of the School of
Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
How Does It Perform
PTC Medical Instrument Ltd, established in July 2008, manufactures and distributes medical instruments to various parts of Asia. Its customers include hospitals, clinics and major pharmacies.
Our Mission: At PTC Medical Instrument, we aim to excel as the best manufacturer in the medical instrument industry with faster turnaround time, reliability, quality and optimum cost to meet our customers’ needs. You have been employed as the Logistics Manager of PTC Medical Instrument. One of the tasks that your General Manager (GM) has assigned you is to set new targets for your department as part of continuous improvement initiative. To do so, you have collected information from past records and then tabulate them as shown.
Table 1:
SCHOOL OF
ENGINEERING
Using the data provided, discuss how would you go about measuring your department’s performance and setting the new targets?
School of Engineering
P13 – How Does It Perform
• Measurement System Objective
• Characteristic of a Good Performance
Measurement
• Logistics Performance AssessmentCost Management
Customer Services
Quality
Productivity
Asset Management
E222 – Logistics Planning And Control
School of Engineering
Objectives of Measurement System
Effective measurement systems are used
for:
• Monitoring the system performance for reporting.
• Controlling performance by the established
standards and decide the possible modification to
the logistics system.
• Directing measures to motivate employee
performance.
School of Engineering
Characteristics of a Good
Measurement System
Quantitative The measure can be expressed as an objective
value
Easy to understand The measure conveys at a glance what it is
measuring, and how it is derived
Encourages
appropriate behavior
The measure is balanced to reward productive
behavior and discourage “game playing”
Visible The effects of the measure are readily apparent
to all involved in the process being measured
Is defined and
mutually understood
The measure has been defined by and/or agreed
to by all key process participants
Encompasses both
outputs and inputs
The measure integrates factors from all aspects
of the process measured
School of Engineering
Measures only what
is important
The measure focuses on a key performance
indicator that is of real value to managing a
process
Is multidimensional The measure is properly balanced between
utilization, productivity, and performance, and
shows trade-off
Uses economy of
effort
The benefits outweigh the costs of collection and
analysis
Facilitates trust The measure validates the participation among
the various parties
Characteristics of a Good
Measurement System
School of Engineering
Challenges in Logistics & Supply Chain
Performance
• The metrics must be consistent with overall corporate
strategy
• The metrics must focus upon customer needs and
expectations
• Prioritize the metrics
• Focus upon processes not functions
• Use a balanced approach in selecting and developing
metrics
• Precise cost measurement is an important aspect for
gauging improvement
• Use technology to enhance efficient performance
measurement
School of Engineering
Typical Performance Metric
Classification
• Cost Management
• Customer Services
• Quality
• Productivity
• Asset Management
School of Engineering
Typical Performance Metrics
(Cost Management)
• Total Cost
• Cost per unit product/order processed
• Cost as a percentage (%) of sales
• Inbound /Outbound freight
• Direct labor Cost
• Actual vs. budgeted Cost
School of Engineering
• Total Cost = Sum of costs of warehousing,
outbound, inbound transportation, order processing
(receiving, storage, picking, etc…)
Customer Service Levels
-Customer service
- Parts & Service Support
- Return goods handlingTransportation Costs
- Traffic & transportation
Warehousing Costs
-Warehousing and
storage
-Plant and warehouse
site selection
Order processing and
information costs
- Order processing
- Logistics communications
- Demand
forecasting/planning
Inventory carrying cost
-Inventory management
-Packaging
-Reverse logistics
Lot quantity costs
- Material handling
-Procurement
Typical Performance Metrics
(Cost Management)
School of Engineering
Total Cost Analysis
• Key to managing the logistics function is total
cost analysis
• Management should minimize total logistics cost,
rather than attempt to minimize cost of individual
activities
• E.g. aggregating all finished goods into one warehouse
may minimize warehousing costs, but it may also lead to
increased transportation expenses
• Thus, cost trade-offs among the various
components of the logistics system are essential
School of Engineering
• Fill rate
• Stock-outs
• Shipping errors
• On-time delivery
• Cycle Time
• Customer Complaints
Typical Performance Metrics
(Customer Service)
School of Engineering
• Item Fill Rate = No. of items ordered by
customers/No. of items delivered to customers
• Line Fill Rate = No. of purchase order lines ordered
by customers/No. of purchase order lines delivered
complete to customers
• Value Fill Rate = Total dollar value of customer
orders/Total dollar value delivered to customers
• Order Fill Rate = Number of customer orders/Number
of orders delivered complete
Typical Performance Metrics
(Customer Service)
School of Engineering
• Damage frequency
• Order entry accuracy
• Packing/shipping accuracy
• Document /invoicing accuracy
• Number of customer returns/ shipment
Typical Performance Metrics
(Quality)
School of Engineering
• Units processed/
received/picked/stored/shipped per staff
• Units per labor dollar ($)/ labor hour
• Comparison between peers &historical
records
Typical Performance Metrics
(Productivity)
School of Engineering
• Inventory turns
• Weeks of Supply
• Obsolete inventory
• Inventory Cycle Counting Accuracy
• Storage Space Utilization
• Scrap rates
• Slow moving/non-moving inventory
Typical Performance Metrics
(Asset Management)
School of Engineering
Typical Performance Metrics
(Asset Management)
Used most of
the time
For products whose price and cost
fluctuates E.g. oil, gold
Used by some
retail
organization
School of Engineering
Typical Performance Metrics
(Asset Management)
School of Engineering
Problem Statement
School of Engineering
• Data for performance indicators can be from ERP, WMS,
invoices, picking list etc…
• Logistics performance indicator to meet Company’s mission
objective
Cost ManagementProductivity
Problem Statement
Asset Management
Quality
Customer Service
School of Engineering
• To set targets based on cost management,
customer service, quality, productivity & asset
management . • Example.
• Reduce cost as percentage of sales to 20% in next Qtr
• Achieve line fill rate of 1 in next Qtr
• Achieve on-time delivery of 99% in next Qtr
• Increase no of outbound/man hr to 12 within next 1
month
• Improve inventory turns to 6 in next Qtr
•Targets to be used as basis for performance
appraisal and rewards
Problem Statement
School of Engineering
Learning Outcome
• Measurement System Objective
• Characteristic of a Good Performance
Measurement
• Logistics Performance AssessmentCost Management
Customer Services
Quality
Productivity
Asset Management
Page 1 of 2
SCHOOL OF ENGINEERING
P14 – WORK STUDY
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the School of Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Page 2 of 2
Work Study
You are the Materials Handling Manager of GTech Limited- a manufacturer of computer parts. As part of an initiative to improve work efficiency in the factory floor, you decide to do time studies for some tasks that your staffs perform and see if improved work productivity can be achieved. You decide to start with a commonly performed task, which is loading to-be- processed parts on a workstation. (Note: Your facilitator will pass you thumb-drives containing the video clip of how loading parts on a workstation is typically carried out.) Based on the work descriptions (from the video clip), record the total time taken for the task. Predetermined Time Standards (PTS) like MODAPTS can also be used to perform a time study. Explore how can PTS be used here? Suggests ways how the task may be performed more efficiently.
School of Engineering
P14 – Work Study
E222 – Logistics Planning And Control
• Carry out time studies to
determine the standard time for a
task.
• Use a Predetermined Time
System (PTS) to derive the
normal time required for a
repetitive task.
• Apply basic MODAPTS codes
School of Engineering
Time Study and Work
Measurement• Time measurement
• Measurement of time taken to complete a cycle of operation.
• Cycle time:
Time taken to complete a cycle of operation
• Tact time:
Time taken to produce a piece of product
• Ways to conduct time study• Stop watch (Direct Time Study)
• Video and stop watch
• Video time measurement (Time Study Software)
School of Engineering
Time Study and Work
Measurement
• Work measurement:
• Capture and analyze the task and motion
required to perform an operation.
• Purpose is to look into ways to simplify,
combine and reduce operation tasks elements
in order to improve the work efficiency.
School of Engineering
• Work Elements
• Define motion elements to each motion
• Purpose is to understand the
repeated/redundant elements for analysis
Time Study and Work Measurement
School of Engineering
Motion Elements
Classification
Serial
No
.
Motion type Definition
Type I
1 Reach(Reach-RE) Move with empty hands
2 Move(Move-M) Move object from one place to another place with hands or certain parts.
3 Grasp(Grasp-G) Control object with hand or palm.
4 Position(Position-P) Place object on certain position.
5 Assemble(Assemble-A) Match two objects.
6 Disassemble(Disassemble-DA) Make object sever from other objects.
7 Use(Use-U) Use tool or equipment for the purpose of operation.
8 Release(Release-RL) Release the object held.
Type II
9 Search(Search-SH) Feel the position of object with eyes or hands.
10 Select(Select-ST) Select one from two or above similar objects.
11 Inspect(Inspect-I) Inspect the object if it complies with standard.
12 Plan(Plan-PN) Consideration for the next step during the operation.
13 Preposition(Preposition-PP) Pre-place the object on the positioned place before positioning.
Type III
14 Hold(Hold-H) Hold the object continually with hands or palm, and keep static.
15Unavoidable
Delay(Unavoidable Delay-UD)Work is interrupted due to the factors uncontrollable.
16 Avoidable Delay(Avoidable Delay-AD) Work is interrupted due to the artificial reason (intentionally or negligently).
17 Rest(Rest-RT) Work stops working due to over-fatigue.
School of Engineering
Ratings
• The speed of the operator during the study
could be varying from the normal speed
due to physiological effect.
• The time recorded is to be adjusted so that
the record could reflect the actual time.
• The percentage of the adjustment is
known as Ratings.
School of Engineering
Predetermined Time Study
• Predetermined time study (without using stopwatch)• To define the time taken to perform a certain standard motion
using international recognized time data.
• Such as:
MODAPTS
MTM/MTM I/MTM II/MTM X
Work factors
MOST
• Steps in performing PTS:• Breaking the motion into element tasks:
• Such as reach, grasp, move, release and others.
• Apply the modification factors
• such as distance, weight, texture of material and others.
• Get time data from the time standard
• Sum them up
School of Engineering
Common Predetermined Time Systems:
Use of common predetermined time systems like :
• MTM – Methods Time Measurement. Analyzes any manual
operation or method into basic motions required to perform it, and
assigns to each motion a predetermined time standard, by the nature
of the motion and the conditions.
• MODAPTS - MODular Arrangement of Predetermined Time
Standards. The accuracy of the system has been found comparable to
most other such systems. It differs from most other systems in that it is
based on human physiology.
• MOST - Maynard Operation Sequence Technique. A simplified and
faster standard establishment system. Establish standards at least 5
times faster than with MTM. Utilizes larger blocks of fundamental
motions than MTM – hence quicker.
School of Engineering
Direct Time Study Vs Predetermined Time Systems
Direct Time Study
Advantages:
a. Can be applied to any operation
b. Data reflects reality, based on actual activities performed
Disadvantages:
a. Requires observer to be patient, sharp and quick
b. Need to handle apprehension/anxiety of operator under timing
Predetermined Time Standards (PTS)
Advantages:
a. Time value can be computed almost immediately
b. Simulation of time impact of various work methods done easily
Disadvantages:
a. Specific classification of work motion using tables not always possible
b. Needs extensive training and practice to achieve proficiency
School of Engineering
MODAPTSOverview
MODular Arrangement of Predetermined Time Standards
Developed by Chris Heyde in 1966
Predetermined time system (like MTM and MOST) where
work is divided into micro elements. These elements are
assigned standard time values
Can be used to validate time studies, calculate production
standards, evaluate plant capacity and identify unnecessary
movements
Relatively simple to use, low cost and widely accepted in
many countries
School of Engineering
Steps (similar for all other predetermined time systems)
- Document (or determine the best method if the operation is
new) the method of operation
- Analyze the operation by projecting the body parts used to
carry out the actions
- Determine the codes and the time values (in units of MOD)
assigned to each work element
- Sum up the times (assuming additivity and independence) and
divide the total by 7.75 to obtain the normal time in seconds
1 MOD = 0.129 sec
1 MOD = 0.00215 min
1 sec = 7.75 MODS
1 min = 465 MODS
MODAPTS
School of Engineering
Contains 21 basic alphanumeric codes
Alpha code depends on the type of activity. The
number attached to the code is the distance moved
or effort required for the move.
For example, M2 is the movement of the palm
which will take 2 MODS (0.258 seconds) to
complete
Major classes of motions are:• Upper limb (shoulder to finger) movement
• Terminal movements: done at the end of upper limb motion
• Auxiliary activities: walking, bending, inspection, deciding, etc
MODAPTS Codes
School of Engineering
Types of Motions
• Movement
• Done by the finger-hand-arm-shoulder trunk system
• Required to position a part of the arm to perform the
Terminal activities
• Terminal Activities (GET and PUT)
• Done at the end of a movement
• In close proximity to the things being worked on
• Auxiliary Activities
• Walking, bending, inspection, deciding, etc.
School of Engineering
Movements
• Movements and terminal activities take place in pairs.
• Movement first then terminal activities• Move to get, move to put
• Examples: M3GO (move to touch)
• Movement activities are classified by:• Distance moved
• Body part required to perform the move
• Light/small objects vs. heavy/large objects• Large objects : 16” x 16” x 16”
• Heavy objects : over 18 lbs.
• Award the lowest category that is possible to successfully complete the activity
School of Engineering
Finger
1 MODHand
2 MODs
Forearm
3 MODs
Arm
4 MODsExtended Arm
5 MODs
1”
2”
6”
12”
18”
Movements
School of Engineering
Moves with Small/Light Objects
Type Movement MODs Distances
Finger (M1) Knuckle 1 1”
Hand (M2) Wrist 2 2”
Forearm (M3) Elbow 3 6”
Whole Arm
(M4)
Shoulder directly forward,
perhaps body assistance
4 12”
Extended Arm
(M5)
Shoulder fully left, right,
or across the body
5 18”
Trunk (M7) Shoulder involving the
body trunk
7 30”
Note: Body assistance means to require the body to bend slightly (simultaneously with Move).
It increases distances not time.
School of Engineering
Problem Statement
Screenshot of Double-E ™ software interface
School of Engineering
Problem Statement – MODAPTS Calculations
Sequence of Work
Activities
Practical Time
(sec)
Code Frequency Mod
1. Walk 4 steps towards table 2.28 W5 4 20
2. Bend & Arise with simple
grasp (1st cycle)
1.72 B17G1 1 18
3. Place computer box on table
(1st cycle)
1.52 M5M5P2 1 12
4. Bend & Arise with simple
grasp (2nd cycle)
2.48 B17G1 1 18
5. Place computer box on table
(2nd cycle)
1.68 M5M5P2 1 12
6. Bend & Arise with simple
grasp (3rd cycle)
2.56 B17G1 1 18
7. Place computer box on table
(3rd cycle)
1.80 M5M5P2 1 12
8. Move arm to computer
keypad
0.80 M5M5G0 1 10
9. Press keypad 0.40 M1P0 1 1
School of Engineering
Problem Statement – MODAPTS Calculations
Summary of Motion Types
Motion Type Practical Time ST (MODAPTS) No. of Datas
1st Type 15.24 15.67 9
2nd Type 0.00 0.00 0
3rd Type 0.00 0.00 0
Other Types 0.00 0.00 0
Motion Name Count Average Median Minimum Maximum VariancePreimprovement Improvement
Walking 1 2.28 2.28 2.28 2.28 0 2.28 2.6
Bend & Arise (w grasp) 3 2.25 2.48 1.72 2.56 0.21 6.76 6.96
Place on table 3 1.67 1.68 1.52 1.8 0.02 5 4.68
Move arm to computer 1 0.8 0.8 0.8 0.8 0 0.8 1.3
Press keypad 1 0.4 0.4 0.4 0.4 0 0.4 0.13
School of Engineering
Problem Statement – MODAPTS Output
Total Normal Time (sec) = 15.67
School of Engineering
Suggested Ways to Improve
Efficiency
• Start walking from closer starting point
• Move trolley closer to work-station
• Raise height of trolley
• Move computer terminal nearer
• Carry two boxes per bend/arise cycle
School of Engineering
Other ScenariosScenario A:
Set allowance to be 10% comprising 4% fatigue
2% standing
4% mental stress
The standard time would be 1.1 x 15.67 or 17.24 seconds
Hence time to perform this manual task should be 17.24 sec
Scenario B:
Apply L1 weight adjustment in the PTS. Applicable when the
weight is more than 2kg. Each increment of 4kg, time
increases by 1 MOD
School of Engineering
Learning Outcome
• Carry out time studies to determine
the standard time for a task.
• Use a Predetermined Time System
(PTS) to derive the normal time
required for a repetitive task.
• Apply basic MODAPTS codes
Page 1 of 2
SCHOOL OF ENGINEERING
P15 – BETTER SECURITY
E222 : LOGISTICS PLANNING AND CONTROL
Copyright © 2010 School of Engineering, Republic Polytechnic, Singapore
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the School of Engineering, Republic Polytechnic, Singapore.
SCHOOL OF
ENGINEERING
Page 2 of 2
Better Security
You are the Logistics and Warehousing Manager of FMD (Asia) Electronics Limited, a manufacturer of circuit boards for super-computers. FMD (Asia) Electronics has a factory in Batam and Senai,Johor respectively as well as a regional warehouse at Tuas, Singapore. Currently the company exports most of the circuit boards manufactured (over 75%) to various parts of Asia and Europe. Mr Potter the General Manager (GM) of FMD (Asia) Electronics became very concerned when he read a newspaper article last week. The article reported that some microchips worth RM500, 000 were hijacked along the way during transportation. (See article below)
To prevent similar things from happening, Mr. Potter would want you to step-up the security of the regional warehouse as well as logistics flow In addition, the company is also planning to enter the US market as part of market expansion. You understand that there are some regulations introduced in United States to make goods going into the country safer after September-11 terrorist attack .The US government views product visibility as an integral part of the country security. As the Logistics and Warehousing Manager of FMD (Asia) Electronics, discuss what would be your recommendation(s) to meet all the requirements?
School of Engineering
P15 – Better Security
E222 – Logistics Planning And Control
• Key aspects of Supply Chain/
Logistics Security
• Major Supply Chain Security
Initiatives
• Enhanced Supply Chain/Logistics
Security with product visibility
School of Engineering
Supply Chain/Logistics Security
Why security along the supply chain?
Helps to prevent:• Nuclear, biological and chemical materials falling
onto wrong hands
• Theft/Pilferage
• Sabotage
• Pirates
• Product contamination
• Environmental hazards
• Counterfeit product introduction
• Contraband goods etc… Sabotage on USS Cole at Yemen on 2002
School of Engineering
Implications (Some facts & figures…)
• Global transit loss estimates- $30 to $50 Billion/year
• Typically 2-8% income reduction for Fortune 500
companies due to poor security
• Estimated, 80% of cargo thefts are “made to order thefts”
• Threat rated “severe” in Brazil, Russia, South Africa,
Indonesia, Nigeria & Malaysia
What would be the cost of an effective terrorist attack
using the supply chain- UNKNOWN ??? But will be impactful
An attack would probably cause major international disruptions and
closure of some businesses in the supply chain
Source of information: LRQA Training materials on ISO280000:2007
School of Engineering
Supply Chain Security
Suppliers Manufacturer Distributor Customer
Physical Material Flow
Information Flow
transportation security
physical facility security
information (including financial) flow security
material flow security
personnel security
Financial Flow
Potential for
security
threats & risks
School of Engineering
Transportation Security
• Regular and emergency communication equipment
• Security training of staff
• Non-intrusive inspection technology
• Focus on petroleum and cargo vessels
• Secure the movement of Inter-modal containers
• Secure air cargo and aircraft
• Reduce vulnerabilities to
Catering/Refueling/Maintenance equipment
School of Engineering
Information Flow Security
• Password protection
• Firewalls
• Compartmentalize information/segregate data
• Encryption
Personnel Security• Conduct personnel background checks
• Obtain security clearances
• Identification and verification
School of Engineering
Material Flow Security
• Apply tracking and tracing technologies to
monitor freight
• Use sensors to detect and report intrusions or
tampering with the shipments while en-route or
at a transshipment node
• Apply tamper resistant electronic seals
• Advance reporting of freight movements to
expedite processing through the transportation
nodes
School of Engineering
Physical Facility Security
• Securing the physical facility
Through the use of fences/physical
barriers/guards/controlled access
Enhanced lighting, video, sensors
• Facility Layout (E.g. warehouse, factory)
• Includes screening passengers, cargo and
physical inspections
School of Engineering
Original Warehouse Layout Plan
1 2
3 4
5 6
7
8
Security Issues
with existing
layout
School of Engineering
Problems Identified 1.Do not put a dumpster or other garbage containers by a door. This
dumpster is in an ideal spot for employees to hide stolen things and
move them to their cars later on.
2.The closeness of this parking area, plus the fact that it is right by a door,
makes it easier for employees to take things from the warehouse and
put them in their cars. The further people park from the warehouse, the
better. If possible, have a fence separating the warehouse from the
parking lot.
3.The receiving dock and the shipping dock are too close together, and
there is no barrier between them. It would be easy to take things from
one truck and put them into another.
4.Staging area may be too close to the loading docks. If no one is around
to keep an eye out, it would be easy to take something and put it in a
truck.
Original Warehouse Layout Plan
School of Engineering
5.Existing warehouse has far too many doors. There should only be one
that is open, and there should be a guard or other employee in charge of
watching this door. If fire regulations require more than one door, use
bars that set off an alarm if the doors are opened.
6.This is a bad spot for the restroom. To reach it, the truckers have to walk
through the warehouse. This puts your goods at risk of being stolen.
Just because people are dropping off or picking up shipments doesn't
mean they are free to wander around. It's best to keep unauthorized
people out of the warehouse.
7.To get to this lounge area, the truckers have to walk all through the
warehouse. It is important to restrict movement in your warehouse. Do
not let people just go wherever they want.
8.These bushes are a good hiding spot for things stolen out of the
warehouse, especially because they are right by the door. So either get
rid of the bushes, or lock the doors
Original Warehouse Layout Plan
School of Engineering
Warehouse Layout Plan (Suggested)
To have a security post at
the entrance/ exit of the
premise
Resolves
physical facility
security
School of Engineering
Major Supply Chain/Logistics Security Initiatives
• ISO 28000:2007- Specification for security
management systems for the supply chain
• Secure Trade Partnership (STP)
• Transported Asset Protection Association (TAPA)
Standards A, B and C
• Customs-Trade Partnership Against Terrorism (C-
TPAT)
• 24 hour Advance Manifest Rule
• Container Security initiative (CSI)
School of Engineering
ISO 28000:2007- Specification for security
management systems for the supply chain
• Specifies requirements for a security management system
critical to security assurance of the supply chain
• Applicable to both small and multinational companies, in any
stage of the production or supply chain that wishes to:
establish, implement, maintain and improve a security management
system;
assure conformance with stated security management policy;
demonstrate such conformance to others;
seek certification/registration of its security management system by an
Accredited third party Certification Body; or
make a self-determination and self-declaration of conformance with
ISO 28000:2007.
School of Engineering
ISO 28000:2007 Contd…
ISO 28000:2007 is NOT about
managing your security
department.
It is all about managing your
security in the supply chain !
School of Engineering
Secure Trade Partnership (STP)
• The Secure Trade Partnership (STP) Guidelines spells out
the requirements which companies in the supply chain
should adopt to enhance the security of their operations
and supply chains
• Under the STP Guidelines, companies are required to:
(a) have security management systems;
(b) conduct risk assessments of their business operations; and
(c) implement the security measures under the STP Guidelines to
secure their supply chains.
• Companies meeting such requirements will be certified as
STP companies by Singapore Customs, and can look
forward to greater ease to bring goods into/out from
Singapore
School of Engineering
• “Transported Asset Protection Association” is an association of
security professionals and related business partners from high
technology companies who have organized for the purpose of
addressing the emerging security threats that are common to the
technology industry
• Develop and utilize common tools (Freight Security Requirements,
contract language, assessment protocol) to: Increase security awareness and communicate best known methods (BKM’s) to
industry and supplier base
Communicate value and attractiveness of high-tech cargo to criminal element,
particularly to violent criminals
Develop performance of existing supplier base, or create a market niche for
entrepreneurs
Establish industry forum to evaluate effectiveness, pursue continuous
improvement, and set future goals
Transported Asset Protection Association
(TAPA)
http://www.tapa-asia.org/
School of Engineering
Sample of TAPA Scoring MatrixAudit Rating Score
Point ValueProcess & Procedures - Description of Measurement
CriteriaStandard
0 Not present or utilized - No plans to adopt or implement Not
Acceptable:
1 Generally present Acceptable:
2 Firmly in place and adopted as best practice Acceptable:
X
AUDIT RESULTS
Facility Classification
Total Score 131.2
Possible Score 138
Percentage 95.07%
Overall Score/Standard Exceeds Requirements
Area of Concern:
1. Perimeter SecurityPreventative Measures
ScoreWarehouse
Classification
X if not
Scored
Total
Score
1.2 CCTV Systems 1.2.1 - CCTV external coverage of shipping and receiving
yard to cover movement of vehicles and people
2 A 2
1.2.2 - 100% CCTV external coverage of all dock doors 2 A 2
1.2.3 - CCTV system able to view all sides of the facility 2 A 2
IMPROVEMENT STATUS
Requirement does not apply
Not Applicable
PREVIOUS AUDIT
School of Engineering
Documentation
• Freight security requirements
Specific required security
elements, with functional
descriptions, measurable
• Contractual language
Performance expectations
and effects of non-
compliance
• Standard assessment protocol
Standardized worksheet
Standardized scoring
Standardized reports
Processes
• Consequences
Corrective actions
$ reimbursement consistent
with value
Termination of contract
• Training
Internal and Supplier
Requirements and assessment
• Investigations
Roles and responsibilities after
loss
Recovery of property and
apprehension of thieves
Freight Security Elements
School of Engineering
Customs-Trade Partnership Against
Terrorism (C-TPAT)
• In November 2001, US Customs initiated C-TPAT to improve
container security as they move through the global supply chain
• Customs officials work in partnership with private industry to
review supply chain security plans and recommending
improvements
• In return, C-TPAT members’ cargo are less likely to be
screened for weapons of mass destruction (WMDs)
• Participants include importers, Carriers, Brokers, Warehouse
operators, manufacturers (including foreign manufacturers)
School of Engineering
C-TPAT Validation Process
Security Guidelines (defined by C-TPAT)
Security Plan (defined
by each member)
C-TPAT Compliance Evaluation.
Validation Process
C-TPAT guideline coverage:
-Personnel Security, Physical Security, Access Control,
Education & Training Awareness, Manifest procedures,
Conveyance Security
School of Engineering
24-Hour Advance Manifest RuleOcean Cargo
• Carriers must submit a cargo declaration to US Customs and Border Protection 24 hours before cargo is laden aboard the vessel at a foreign port
Air Cargo
• At “wheels up” for flights less than four hours
• Four hours prior to arrival for flights over four hours in length.
• No-Load Order or Inspections for Invalid cargo descriptions
No address, incomplete address
Fields left blank
Inconsistent documents
School of Engineering
Container Security Initiative (CSI)
• Government to government initiative
• Deploy Customs and Border Protection staff in foreign
ports
• US “borders” now at foreign ports
• Targeting, screening and inspecting suspect cargo prior
to lading
• Non-intrusive inspections
• Screen against WMD at foreign ports
• Reward “low-risk” shippers through less inspections
School of Engineering
CSI Framework
Foreign Port What do we need here to ensure only legitimate goods are loaded
TransportHow can we be sure nothing “slipped in” ?
US PortHow can we maximize the likelihood of a high-detection hit-rate.
School of Engineering
Supply Chain Security (to US)
Manufacturer
or SupplierIntermediate
Facility
Intermodal
Transfer
US
Distribution
Facility
Port of
ExportPort of Import
Customs
Inspect
manifest in
advance
CSI Inspection
C-TPAT
Validation
Note: TAPA & ISO 28000:2007 applies to entire supply chain
School of Engineering
Suggested Problem Solution
School of Engineering
Security Enhanced by Supply Chain Visibility
3. Port of Loading - Vessel load
• Verify clear for loading status
• Automatically verify security status at quay cranes
2. Port of Loading - Arrival
• Automatically record container arrival
• Automatically verify security status at entry gate
6. Port of Discharge - Departure
• Automatically record departure
• Automatically verify security status at exit gate
1. Manufacturer/Consolidator
• Associate manifest with container and seal ID
• Verify user and electronically secure container
• Automatically record departure time and place
• Transmit data to TSSTransportation Security
System Platform
5. Port of Discharge - Vessel Unload
• Verify clear for unloading status
• Automatically verify security status at quay cranes
• Transmit documentation and updates to Customs
• Provide alerts if container deviates from plan
• Provide reports and other analytics for supply chain and security inefficiencies
• Maintain audit trail of accountability
• Provide web access to users
School of Engineering
Supply Chain Visibility
• Enhance C-TPAT validation and CSI process
• Product visibility enables tracking and tracking for
security breach investigation
When did it happen
Who was in custody of the goods
• Meets multiple security concerns
Theft
Smuggling
Bombs and Weapons of Mass Destruction (WMD)
School of Engineering
Today’s Problem• Improve existing warehouse layout for supply chain security
• Use seals on the packages so that tampering will be obvious
• Check the background of staff involved in transportation, and
information like contents revealed to only a few key staff
• Provide driver/transportation staff with hand-phone to alert
company/civil defense in case of emergency
• GPS tracking of transportation trucks
• Plan for TAPA certification and C-TPAT validation
• Adhere to 24-Hour Advance Manifest Rule
• Regular audits of supplier qualification criteria – To comply to
certain security standards
School of Engineering
SOX (Sarbanes Oxley Act) and its impact on the supply chain
Going Further…
Sarbanes Oxley Act (SOX)
• The purpose of SOX (or SarbOx) is to keep away large
businesses from financial deception and misleading their
investors and shareholders.
• The investors are also prevented from being misguided into
investing in business.
• Sarbanes Oxley impacts the supply chain in terms of Purchasing
Supplier qualification
Inventory control
Inventory Management Systems (ERP, MRP, etc…)
School of Engineering
• Purchasing e.g. SOX audits will evaluate signature policy
Written, electronic records
Levels of authority
Audit of actual documents
• Supplier Qualification e.g. Are all potential suppliers given a fair chance to tender? Clear
supplier selection criteria and performance monitoring capability?
• Inventory Management Systems e.g. Who can enter/change Inventory Management System Data?
Why?
• Inventory Control e.g. Verification of inventory accuracy – How?
SOX (Sarbanes Oxley Act) and its impact on the supply chain
School of Engineering
Learning Outcome
• Key aspects of Supply
Chain/Logistics Security
• Major Supply Chain Security
Initiatives
• Enhanced Supply Chain/Logistics
Security with product visibility