Locally Administered Federal Aid Project
Owner: Broome County, NY
NYSDOT Region 9
Engineer: McFarland Johnson
Contractor: Economy Paving
Design 2013 – Construction 2014
Hooper Road Bridge Town of Union, NY
Project Location
Hooper Road Bridge Town of Union, NY
Project Location
Hooper Road Bridge
NYS 17C
Project Location
Existing Bridge 3-span Bridge 150’ (28’-83’-39’)
Constructed in 1964
Condition Rating 4.45, FSR 68.3
Bridge Condition
Leaking Joints = Widespread Deterioration
Bearings Heavily Corroded
Pier Concrete Cracked & Delaminated
Deck Has Areas of Deterioration
Rehabilitation Required
Existing Bridge
Problems:
• Deck Joint Failure
Problems:
• Deteriorated Pedestals
Problems:
• Deteriorating Piers
Bridge Importance
Hooper Road – Urban Arterial
Large Traffic Volumes – ADT 10,000
Vital Link between Residential & Commercial Areas
Previous Construction Projects & Traffic Disruption
Hooper Road Bridge
Detour West
3 miles – Route 17C North Street, Hayes Avenue
Watson Boulevard Detour East
6 miles – Rt 17C Rt 17, Rt 201, Harry L Drive
Watson Boulevard
Hooper Road Detour
1. Conventional Construction
2. Accelerated Bridge Construction (ABC)
Options for Construction
• Bridge Constructed in Halves
• One Lane of Traffic on Hooper Road during Construction
• Hooper Road Southbound Maintained on Bridge
• Hooper Road Northbound – Off Site Detour
• Traffic Impact to Hooper Road = 4-5 Months
• Bridge Closed to Traffic During Construction
• Bridge Constructed with Prefabricated Elements to Accelerate Construction
• Hooper Road NB & SB – Off Site Detour
• Traffic Impact to Hooper Road = Approx. 2-4 Weeks
What is “ABC”?
Components & Benefits of ABC
Prefabricated Bridge Elements & Systems (PBES) Reduces on site Construction Duration Improves Work Zone & Worker Safety
Minimized Traffic Impacts (Reduced Roadway User Costs)
Primary Objectives
1) Restore the bridge condition using cost effective techniques
2) Minimize life cycle cost of maintenance and repair
Secondary Objectives
3) Utilize construction techniques to minimize traffic impacts to Hooper Road
4) Minimize impacts to NYS Route 17C during construction
Project Objectives
Alternatives Considered
Bridge Improvement Alternatives Objectives Satisfied
1 2 3 4
Alternative 1 Deck Replacement
Alternative 2 Superstructure Replacement - Conventional
Alternative 3* Superstructure Replacement - ABC
Alternative 4 Bridge Replacement - ABC
ABC Superstructure Replacement • Full Depth Precast Deck Panels • New Steel Girders • Precast Pier Caps • Precast Approach Slabs
21 day Hooper Road Closure 2 Lanes on NYS Route 17C Liquidated Damages $5,000/day Reduced User Costs Public Strongly Favored Short Term Closure
ABC elements Pre-Closure
Remove / construct abutment pedestals Column repairs
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Pier Caps
ABC elements – Precast Deck Panels
Formwork critical UHPC Connections Watertight
ABC elements – Precast Deck Panels
Delivery
ABC elements – Precast Deck Panels
Setting Panels
ABC elements – Precast Deck Panels
ABC elements – Precast Deck Panels
Mix UHPC Batch on site Ductal Representative on site
ABC elements – Precast Deck Panels
Place UHPC Form high – grind later
ABC elements – Precast Deck Panels
ABC elements – Precast Deck Panels
ABC elements – Precast Deck Panels
Stud Pockets Fill from top
ABC elements – Precast Approach Slabs
Day 2 – Superstructure Demolition Underway
Day 4 – Superstructure Demolition Complete
Day 9 – Precast Pier Caps Installed
Day 11 – New Structural Steel Installed
Day 12 – Installation of Precast Deck Panels Begins
Day 21 – Bridge Open to Traffic
Construction Cost = $1,600,000
EE = $1,900,000
Completed in 21 days without Liquidated Damages
Lesson Learned = Discuss Lead Time with Fabricators
Positive Feedback from Community