Year 2013 ‑ Level 1 EUROCONTROL Local Single Sky ImPlementation (LSSIP) AZERBAIJAN

Upload: phungphuc

Post on 16-May-2018

223 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

Year 2013 ‑ Level 1

EUROCONTROL

Local Single Sky ImPlementation (LSSIP) AZERBAIJAN

Page 2: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 3: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 4: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 5: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan Released Issue

DOCUMENT IDENTIFICATION SHEET

LSSIP for Azerbaijan

Infocentre Reference: 14/01/07-04

Document Identifier Edition: Year 2013

LSSIP Year 2013 AZERBAIJAN Edition Date: 22/04/14

LSSIP Focal Point – Farhan GULIYEV E-mail: [email protected] Head of Development

LSSIP Contact Person – Predrag Vranjkovic

E-mail: [email protected]

Unit DSS/EIPR

Status Intended for

Working Draft General Public

Draft Agency Stakeholders

Proposed Issue Restricted Audience

Released Issue

Accessible via: Internet (www.eurocontrol.int)

Path: X:\03 LSSIP\1. LSSIP States\Azerbaijan (AZ)\Year 2013\Azerbaijan\Released\LSSIP_AZ_2013_Released.doc

LINKS TO REFERENCE DOCUMENTS

1. LSSIP Guidance Material: http://www.eurocontrol.int/articles/guidance-material 2. ESSIP Plan Edition 2013: www.eurocontrol.int/pepr 3. ESSIP Report 2012: www.eurocontrol.int/pepr 4. STATFOR Forecasts: www.eurocontrol.int/statfor 5. Acronyms and abbreviations: http://www.eurocontrol.int/articles/glossaries 6. European ATM Master Plan: https://www.atmmasterplan.eu/ 7. LSSIP Documents: http://www.eurocontrol.int/articles/lssip

Page 6: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 7: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 8: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 9: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan Released Issue

TABLE OF CONTENTS

Executive Summary ................................................................................................................................. 1 

Introduction .............................................................................................................................................. 3 

Chapter 1 - National ATM Environment ................................................................................................... 4 1.1  Geographical Scope ................................................................................................................ 4 

1.1.1  International Membership ......................................................................................................... 4 1.1.2  Geographical description of the FIR(s) ..................................................................................... 4 1.1.3  Airspace Classification and Organisation ................................................................................. 5 1.2  National Stakeholders .............................................................................................................. 6 

1.2.1  Civil Regulator(s) ...................................................................................................................... 7 1.2.2  Airports .................................................................................................................................... 10 1.2.3  Military Authorities ................................................................................................................... 10 1.2.4  Accident/incident Investigation Body ...................................................................................... 13 

Chapter 2 - En-route Traffic and Capacity ............................................................................................. 14 2.1  Evolution of traffic in Azerbaijan ............................................................................................ 14 2.2  BAKU ACC ............................................................................................................................. 15 

2.2.1  Summer 2013 performance .................................................................................................... 15 2.2.2  Planning Period 2014-2018/19 - Summer .............................................................................. 15 

Chapter 3 - ESSIP Report recommendations ........................................................................................ 17 

Chapter 4 - National Projects ................................................................................................................. 18 

Chapter 5 - Regional Co-ordination ....................................................................................................... 19 Regional coordination projects ........................................................................................................... 19 

Chapter 6 - ESSIP Objective Implementation ....................................................................................... 20 

ANNEXES

Page 10: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 11: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 1 Released Issue

Executive Summary

State Context

Azerbaijan is the farthest ECAC Member State to the east of Europe bordering with Kazakhstan, Turkmenistan and Russia to the North and East, Islamic Republic of Iran to the South and Georgia, Armenia and Turkey to the West.

Azerbaijan is among the former USSR countries with the highest economic development characteristics in the area. Azerbaijan’s economy is dynamically evolving and supporting a liberalised political, economic and social system.

Oil and gas production, the chemical industry, agriculture and tourism have become the backbone for this swift advance.

Azerbaijan’s Airspace was located at the interface zone between ECAC/non-ECAC States and Azerbaijan was responsible for transitional tasks (RVSM and non – RVSM, metric system of flight level systems within adjacent FIRs. From November 17th, 2011 buffer zones with Russian Federation, Kazakhstan and Turkmenistan were eliminated due to the RVSM transition in these countries.

Azerbaijan is playing a proactive role in the regional and international co-operation in ATM. In addition to ICAO and ECAC membership, Azerbaijan has joined CANSO. Azerbaijan’s membership to EUROCONTROL is under State consideration.

ESSIP Objective Implementation

Implementation of ESSIP objectives is progressing in Azerbaijan, albeit with some delay. The prime cause of delay is the lack of human resources in the CAA and lack of human resources and delayed implementation of new ATM systems in the ANSP.

As Azerbaijan is not a EUROCONTROL or EU member State there has also been a perceived lack of urgency to implement some objectives, e.g. the ones based on EU legislation. Azerbaijan is working on EUROCONTROL membership, which will accelerate the implementation of ESSIP objectives.

LSSIP 2013 - Azerbaijan * FOC Date █ Planned implementation date (see legend at the bottom of the table)

State-related ESSIP Objectives

<=

2007

20

08

2009

20

10

2011

20

12

2013

20

14

2015

20

16

2017

20

18

2019

20

20

AOM13.1 Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling

[IDP] [E] *

AOM19 Implement Advanced Airspace Management [IDP] [E] *

AOM20 Implement ATS Route Network (ARN) - Version 7 [E] * AOM21 Implementation of Free Route Airspace [IDP]

[E] *AOP03 Improve runway safety by preventing runway incursions * ATC02.2 Implement ground based safety nets - Short Term Conflict

Alert (STCA) - level 2 [E] *

ATC02.5 Implement ground based safety nets - Area Proximity Warning - level 2 [E] *

ATC02.6 Implement ground based safety nets - Minimum Safe Altitude Warning - level 2 [E] *

ATC02.7 Implement ground based safety nets - Approach Path Monitor - level 2 [E] *

ATC07.1 Implement arrival management tools [E] * ATC12 Implement automated support for conflict detection and

conformance monitoring [E] *

ATC15 Implement, in En-Route operations, information exchange mechanisms, tools and procedures in support of Basic AMAN operations

[IDP] [E] *

ATC16 Implement ACAS II compliant with TCAS II change 7.1 * ATC17 Electronic Dialogue as Automated Assistance to Controller

during Coordination and Transfer [IDP]

[E] *

Page 12: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 2 Released Issue

LSSIP 2013 - Azerbaijan * FOC Date █ Planned implementation date (see legend at the bottom of the table)

COM09 Migrate ground international or regional X.25 data networks or services to the Internet Protocol (IP)

[IDP] * COM10 Migrate from AFTN to AMHS * COM11 Implementation of Voice over Internet Protocol (VoIP) in

ATM *FCM01 Implement enhanced tactical flow management services [E] * FCM03 Implement collaborative flight planning [IDP]

[E] *

FCM04 Implementation of Short Term ATFCM Measures - phase 1 [IDP] [E] *

FCM05 Implementation of interactive rolling NOP [IDP] [E] *

INF04 Implement integrated briefing * ITY-ADQ Ensure quality of aeronautical data and aeronautical

information [E] *

ITY-AGDL Initial ATC air-ground data link services above FL-285 [IDP] [E] *

ITY-AGVCS2 Implement air-ground voice channel spacing requirements below FL195 *

ITY-COTR Implementation of ground-ground automated co-ordination processes [E] *

ITY-FMTP Apply a common flight message transfer protocol (FMTP) [IDP] * ITY-SPI Surveillance performance and interoperability *NAV03 Implementation of P-RNAV [E] * NAV10 Implement APV procedures [IDP]

[E] *

SAF10 Implement measures to reduce the risk to aircraft operations caused by airspace infringements *

SAF11 Improve runway safety by preventing runway excursions *SRC-CHNG Implementation of Safety Oversight of Changes to ATM by

National Supervisory Authorities (NSA) *

SRC-RLMK Implement the EUROCONTROL Safety Regulatory Requirements (ESARRs) *

SRC-SLRD Safety Levels and Resolution of Deficiencies *

Airport-related ESSIP Objectives

<=

2007

20

08

2009

20

10

2011

20

12

2013

20

14

2015

20

16

2017

20

18

2019

20

20

UBBB-Baku AOP01.2

Implement airside capacity enhancement method and best practices based on Eurocontrol capacity and efficiency implementation manual

*

AOP04.1 Implement Advanced Surface Movement Guidance and Control System (A-SMGCS) Level1

[E] * AOP04.2 Implement Advanced Surface Movement Guidance and

Control System (A-SMGCS) Level 2 *AOP05 Implement Airport Collaborative Decision Making (CDM) [IDP]

[E] *ENV01 Implement Continuous Descent Operations (CDO)

techniques for environmental improvements [IDP] *

ENV02 Implement Collaborative Environmental Management (CEM) at Airports *

Understanding the Table

Objective Completed No Plan

Objective Partly Completed Missing Data

Objective Planned Not Applicable ( AZ does not participate in this obj.)

Late

NOTE: The year where the coloured box is placed indicates the ‘Implementation Completion Date’ as stated in the ESSIP for each objective. The colour-code indicates the Local progress with respect to this date.

Page 13: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 3 Released Issue

Introduction

The Local Single Sky ImPlementation documents (LSSIPs), as an integral part of the ESSIP/LSSIP mechanism, constitute a five-year plan containing ECAC States’ actions to achieve the Implementation Objectives as set out by the ESSIP and to improve the performance of their national ATM System. The LSSIP document – Year 2013 describes the situation in the State at the end of December 2013.

The LSSIP documents are structured into 6 chapters to better differentiate the Stakeholder(s) accountable for the information contained in each of them:

Chapters 1 to 5 present the key players in the State, and sets the institutional and geographical scenes to help the reader understand the specifics of the State and interpret the rest of the document correctly. It also presents a short description of the main national and regional projects in which the national Stakeholders are involved.

Chapter 6 contains high-level information on progress and plans of each ESSIP Objective. The information for each ESSIP Objective is presented in boxes giving a summary of the progress and plans of implementation for each Stakeholder. The conventions used are presented at the beginning of the section.

Note: Chapter 6 is completed with a separate document called LSSIP Level 2. This document consists of a set of tables organised in line with the list of ESSIP Objectives. Each table contains all the actions planned by the four national stakeholders to achieve their respective Stakeholder Lines of Action (SLoAs) as established in the ESSIP.

Page 14: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 15: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 4 Released Issue

Chapter 1 - National ATM Environment

1.1 Geographical Scope

1.1.1 International Membership

Azerbaijan is a Member of the following international organisations in the field of ATM:

Organisation Since

ECAC 2002

EUROCONTROL -

European Union -

European Common Aviation Area -

EASA -

ICAO 1992

NATO ATM/CNS Committee

1.1.2 Geographical description of the FIR(s)

The geographical scope of this document addresses the single Baku FIR. The FIR boundaries approximate the state border of Azerbaijan Republic. The region is strategically located at the conjunction of Europe, Central Asia, and the Middle East. This area has served as a crossroads for centuries, a critical junction in the Silk Road connecting Europe and Asia.

The following map shows the geographical location of Azerbaijan Republic (indicating the location of main Airports):

Map of Azerbaijan FIR is shown on the picture below.

Page 16: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 5 Released Issue

Baku FIR borders the following FIRs/UIRs:

ECAC States:

- West: Yerevan FIR/UIR (Armenia) In March, 2006 - Armenia became a member of EUROCONTROL.

- North-West: Tbilisi FIR/UIR (Georgia).

Non-ECAC States:

- North: Rostov FIR/UIR (Russia);

- North-East: Aktau FIR/UIR (Kazakhstan);

- East: Turkmenbashi FIR/UIR (Turkmenistan);

- South: Tehran FIR/UIR (Iran).

1.1.3 Airspace Classification and Organisation

All airspace is divided into Upper Airspace and Lower Airspace. The boundary between them is FL195. The graphical presentation is below.

The re-organisation of the Baku FIR airspace to ensure a uniform and simplified application of ICAO Air Traffic Service classes Flight Level 195 and below within ECAC airspace has been achieved.

Page 17: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 6 Released Issue

1.2 National Stakeholders

The main National Stakeholders involved in ATM in Azerbaijan are the following:

- Government (Cabinet of the Ministry);

- State Civil Aviation Administration (SCAA);

- “Azerbaijan Hava Yollari” Closed Joint Stock Company;

- AZANS – Azerbaijan Air Navigation Services.

Their activities are detailed in the following subchapters and their relationships are shown in the diagram below.

GovernmentThe cabinet

CAA Ministry of Defense

“Azerbaijan Hava Yollari”CJSC

Commander of Air ForceAnd Air Defense

Air DefenseAir Force

Aviation SafetyInspection and

Certification Office

Air NavigationServices

Airports National Airlines

Civil Aviation Authority is the responsible body for all civil aviation regulatory matters and safety oversights and reports directly to the government.

Issues related to military aviation matters are dealt with through the Ministry of Defence.

Azerbaijan became a member of the International Civil Aviation Organisation (ICAO), the Interstate Aviation Committee (IAC) in 1992 and a member of ECAC since 2002. All Azerbaijan Airlines flights are in compliance with international laws and regulations.

Page 18: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 7 Released Issue

The CAA is directed in its operation by Air Codex, by decrees and orders of the President of Azerbaijan, by decrees and orders of the Government of Azerbaijan, by the SARPs adopted by ICAO, and by other legislative acts. The authority and responsibilities of the CAA are assigned in its Order, affirmed by the Government of Azerbaijan. Acting within its authority, the CAA produces legal documents and oversees other ministries, departments, enterprises, organisations and personnel which regulate the operation of civil aviation in Azerbaijan. The Director of the CAA and his deputies are assigned by decree of the President of Azerbaijan.

Air navigation services, airports authorities, aviation security and national airline are managed by “Azerbaijan Hava Yollari” which is a Closed Joint Stock Company.

Contained within “Azerbaijan Hava Yollari” is “Azeraeronavigation” (AZANS) which is responsible for the provision of air traffic services. AZANS is also responsible for provision of the meteorological and Aeronautical Information Service.

1.2.1 Civil Regulator(s)

1.2.1.1 General information

Civil Aviation in Azerbaijan is the responsibility of the Civil Aviation Authority. The different national entities having regulatory responsibilities in ATM are summarised in the table below.

Activity in ATM: Organisation responsible Legal Basis

Rule-making CAA / AHY CJSC Aviation Law

Safety Oversight CAA State Safety Programme

Establishment of Tolerable Safety Levels

National Minima not yet established State Safety Programme

Safety Performance Monitoring Procedures not yet established State Safety Programme

Enforcement actions in case of non-compliance with safety regulatory requirements

Formal procedures for enforcement have yet to be established

Airspace CAA

Economic Azerbaijan Hava Yollari CJSC

Environment CAA

Security CAA/ Azerbaijan Hava Yollari CJSC

The creation of a National Supervisory Authority as per the SES Service Provision Regulation has not been implemented in Azerbaijan. The CAA fulfils the role of the NSA.

1.2.1.2 General information

Civil Aviation in Azerbaijan is the responsibility of the Civil Aviation Authority. The different national entities having regulatory responsibilities in ATM are summarised in the table below.

Activity in ATM: Organisation responsible Legal Basis

Rule-making CAA / AHY CJSC Aviation Law

Safety Oversight CAA State Safety Programme

Establishment of Tolerable Safety Levels

National Minima not yet established State Safety Programme

Safety Performance Monitoring Procedures not yet established State Safety Programme

Enforcement actions in case of non-compliance with safety regulatory requirements

Formal procedures for enforcement have yet to be established

State Safety Programme

Airspace CAA Rules use of airspace Azerbaijan Republic

Economic Azerbaijan Hava Yollari CJSC Degree of the Cabinet of the Ministers

Environment CAA State law

Security CAA/ Azerbaijan Hava Yollari CJSC

State Law, Degree of the President

Page 19: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 8 Released Issue

The creation of a National Supervisory Authority as per the SES Service Provision Regulation has not been implemented in Azerbaijan. The CAA fulfils the role of the NSA.

1.2.1.3 CAA

The Civil Aviation Authority is responsible for:

- Supervision of utilisation of the airspace of Azerbaijan Republic;

- Certification of airports, aircraft and equipment;

- Supervision of the aviation safety;

- Licensing;

- Investigation of incidents.

The organisational chart of the CAA is shown in the Annex B of this document.

Annual Report published: N CAA is not yet producing the Annual Report.

www.caa.gov.az

1.2.1.4 AZANS

Azeraeronavigation (AZANS) is the only ANS provider within Azerbaijan Republic.

AZANS has one FIR for the whole upper airspace of Azerbaijan Republic, five TMA’s at Baku, Ganja, Nakhchivan, Lankaran, Zagatala, Gabala aerodromes and a CTR at Zabrat heliport. There are also other aerodromes which are not permanently manned by AZANS staff due to lack of traffic.

AZANS is responsible for:

- provision of air traffic services;

- development of air traffic management system;

- maintenance of ATC technical facilities;

- modernisation of ATC technical facilities;

- provision of aeronautical information service;

- provision of meteorological service.

Name of the ANSP: Azerbaijan Air Navigation Services (AZANS)

Governance: Subdivision of CJSC Ownership: CJSC “Azerbaijan Hava Yollari”

Services provided Y/N Comment

ATC en-route Y Baku ACC (East and West) Nakhichevan ACC (South)

ATC approach Y Baku APP, Nakhichevan APP/TWR, Ganja APP/TWR, Lankaran APP/TWR , Gabala APP/TWR

ATC Airport(s) Y Baku TWR , Nakhichevan APP/TWR, Ganja APP/TWR, Lankaran APP/TWR, Zabrat TWR, Zagatala TWR, Gabala TWR

AIS Y AIP, NOTAMs, AIC, PIB

CNS Y All type of services for all International airports in Azerbaijan

MET Y All type of services for all International airports in Azerbaijan

ATCO training Y National Aviation Academy/AZANS

Provision of services in other State(s):

N

Remark: APP/TWR means combined unit.

Page 20: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 9 Released Issue

Number of air traffic controllers 171

Supervisors 25

ACC 38

APP 32

TWR 95 (including 29 ATCO of heliport)

Annual Report published:

N/A

The organisational chart of AZANS is shown in the Annex B of this document..

1.2.1.5 ATC system in use

Specify the manufacturer of the ATC system currently in use: Air Traffic Control System (RDPS&FDPS) : Eurocut 1000 RADAR systems: Thales MSSR/PSR Communication systems: VHF Rohder - Schwartz Navigation aids: ILS/DME Thales, DVOR/DME Thales Meterorological radars: Vaisala

Major upgrade1 of the ATC system is performed or planned? Air Traffic Control System (RDPS&FDPS) : Indra AIRCON 2100 (2014) RADAR systems: Indra MSSR (2014) Communication systems: VHF Jotron (2014) CPDLC: INDRA (2014) A-SMGCS – ERA/ HITT (2014)

1.2.1.6 ATC units

The ATC units in the Azerbaijan’s airspace, which are of concern to this LSSIP are the following:

ATC Unit Number of sectors Associated FIR(s) Remarks

En-route TMA

Baku 2 1 Azerbaijan ACC Baku (West, East)

Ganja 1 Azerbaijan

Nakhichevan 1 1 Azerbaijan ACC Nakhichevan (South)

Zagatala 1 Azerbaijan

Lenkoran 1 Azerbaijan

Gabala 1 Azerbaijan

Buffer zones with Russia, Kazakhstan and Turkmenistan were eliminated due to RVSM transition in these countries.

1 Upgrade is defined as any modification that changes the operational characteristics of the system (SES Framework Regulation 549/2004, Article 2 (40))

Page 21: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 10 Released Issue

1.2.2 Airports

1.2.2.1 General information

“Azerbaijan Hava Yollari” CJSC regulates operation of: Heydar Aliyev (Baku), Ganja, Nakhchivan, Yevlakh, Zagatala, Naftalan, Lankaran, Sheki airports and Zabrat heliport. This is shown in the picture below. Yevlakh, Naftalan, Sheki are not operational due to lack of traffic. Heydar Aliyev (Baku), Ganja, Nakhchivan, Lenkaran and Zagatala airports are International.

 “Azerbaijan Hava Yollari” CJSC  

Baku   

Ganja  Nakhchivan  Zabrat  

AZANS   

    

AZAL Oil   

  

Aviation 

Security  

  

      

Azerbaijan 

 Airlines 

AZAL Cargo 

  Aviation 

Academy 

Airport     

Airport    Airport  

AZANS    AZANS    AZANS 

   AZAL

Helicopter  

Airport 

AZANS 

Airport   

Technical 

Maintenance  

Airport   

AZANS   

Airport 

AZANS 

Lenkoran Zagatala  Regional a/p

1.2.2.1 Airport(s) covered by the LSSIP

This edition of the LSSIP contains information regarding the main national airport, Baku Heydar Aliyev.

1.2.3 Military Authorities

The Military Authorities in Azerbaijan are comprised of:

- Ministry of Defence;

- Commander of Air Forces and Air Defence;

They report to the Cabinet.

The Commander of Air Forces and Air Defence is the responsible body for military aviation matters in the Azerbaijan Republic. Military authorities provide air traffic services at military aerodromes and designated zones for military training flights and exercises.

There is a military co-ordination unit established in OPS room of Baku ACC responsible for operational co-ordination. Although Flexible Use of Airspace (FUA) is not formally defined most of the principles of FUA are in place and the co-ordination procedures are at very good level.

Information on Civil-Military airspace coordination is presented in Chapter 6 ‘Airspace Organisation and Management’.

Page 22: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 11 Released Issue

Ministry of Defence

Commander of Air Forcesand Air Defence

Co-ordination unitBaku ACC

Military aerodromes

Inspection

1.2.3.1 Regulatory role

Regulatory framework and rule-making

Oversight

OAT GAT

OAT and provision of service for OAT governed by national legal provisions?

Y Provision of service for GAT by the Military governed by national legal provisions?

N

Level of such legal provision: Ministry of Defence – Air Law for Air Defence ,

Level of such legal provision :

Authority signing such legal provision: Minister of Defence

Authority signing such legal provision: Cabinet of the Ministry

These provisions cover: These provisions cover:

Rules of the Air for OAT Y

Organisation of military ATS for OAT Y Organisation of military ATS for GAT N

OAT/GAT Coordination Y OAT/GAT Coordination Y

ATCO Training N ATCO Training N

ATCO Licensing N ATCO Licensing N

ANSP Certification N ANSP Certification N

ANSP Supervision N ANSP Supervision N

Aircrew Training N ESARR applicability N

Aircrew Licensing N

Means used to inform airspace users (other than military) about these provisions:

Means used to inform airspace users (other than military) about these provisions:

National AIP N National AIP Y

National Military AIP N National Military AIP N

EUROCONTROL eAIP N EUROCONTROL eAIP N

Other: * Other: National Regulatory Documents Y

OAT GAT

National oversight body for OAT: Ministry of Defence No military oversight role

Page 23: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 12 Released Issue

1.2.3.1 Service Provision role

Military ANSP providing GAT services SES certified?

N If YES, since: Duration of the Certificate:

Certificate issued by: N If NO, is this fact reported to the EC in accordance with SES regulations?

1.2.3.2 User role

1.2.3.3 Flexible Use of Airspace (FUA)

OAT GAT

Services Provided: MIL Services Provided: None

En-Route N En-Route N

Approach/TMA N Approach/TMA N

Airfield/TWR/GND Y Airfield/TWR/GND Y

AIS N AIS N

MET N MET N

SAR N SAR N

TSA/TRA monitoring N FIS N

Other: Other:

Additional Information: Additional Information:

IFR inside controlled airspace, Military aircraft can fly?

X GAT only

If Military fly OAT-IFR inside controlled airspace, specify the available options:

Free Routing Y Within specific corridors only X

Within the regular (GAT) national route network Y Under radar control Y

Within a special OAT route system Y Under radar advisory service N

If Military fly GAT-IFR inside controlled airspace, specify existing special arrangements:

No special arrangements N Exemption from Route Charges X

Exemption from flow and capacity (ATFCM) measures N Provision of ATC in UHF N

CNS exemptions: RVSM N 8.33 N Mode S N ACAS N

Others: * If there is request from the military, and radar control is not possible, ATC close the route until the military aircraft has passed through it.

Military in Azerbaijan applies FUA requirements as specified in the Regulation No 2150/2005: N

FUA Level 1 implemented: N

FUA Level 2 implemented: N

FUA Level 3 implemented: N

Page 24: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 13 Released Issue

1.2.4 Accident/incident Investigation Body

1.2.4.1 Technical investigations

Azerbaijan is a non-EU Member. The CAA in Azerbaijan carries out technical investigations following accidents and/or incidents. A special investigation commission is created for each accident/serious incident.

The CAA conducts investigations for civil aviation (GAT) aircraft accidents.

Interstate Aviation Committee in Moscow (IAC) is involved in investigation process.

The CAA and EASA in December 2006 signed an agreement on the collection and exchange of information on the safety of airlines using community airports and airports of the Republic of Azerbaijan.

1.2.4.2 Collection, Evaluation & Processing of Data

Azerbaijan has not developed, and does not use, any special tools/software for data processing. However, there is an occurrence reporting culture developed in AZANS and this procedure is implemented.

1.2.4.3 Civil-Military Accidents/Incidents

There is a state rule on accident and incident investigation procedures approved by the Prime Minister.

Commander of Air Forces and Air Defence is the responsible body for military aviation matters in Azerbaijan Republic. Military authorities provide air traffic services within military aerodromes’ CTR and designated zones for military training flights and exercises.

There is a military co-ordination unit established in OPS room of Baku ACC, responsible for operational co-ordination. Although, Flexible Use of Airspace is not approved, most of the principles of FUA are in place and the co-ordination procedures are at very good level.

Special coordination body established between Ministry of Defence and CAA.

Page 25: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 14 Released Issue

Chapter 2 - En-route Traffic and Capacity

2.1 Evolution of traffic in Azerbaijan

Azerbaijan - Annual IFR Movements

0

50000

100000

150000

200000

250000

2009 A 2010 A 2011 A 2012 A 2013 F 2014 F 2015 F 2016 F 2017 F 2018 F 2019 F

IFR

flig

hts

IFR movements - Actuals

IFR movements - Baseline forecast

IFR movements - High forecast

IFR movements - Low forecast

Azerbaijan - Distribution (Ref. year 2012)

International Dep/Arr

32%

Domestic flights 4%

Overflights 64%

A = ActualF = Forecast

2010 A 2011 A 2012 A 2013 F 2014 F 2015 F 2016 F 2017 F 2018 F 2019 FH -0,6% 6,8% 9,0% 8,6% 8,1% 8,4% 8,2%B 10,9% 2,8% 5,4% -1,0% 4,9% 6,9% 7,0% 6,4% 6,7% 6,7%L -1,5% 3,1% 4,9% 5,4% 4,8% 5,0% 5,0%

ESRA B 0,8% 3,1% -2,4% -0,9% 1,4% 2,6% 2,7% 2,2% 2,5% 2,5%

STATFOR Medium-Term Forecast (September 2013)IFR flights yearly growth

Azerbaijan

2013 Traffic in Azerbaijan increased by 1.5% in 2013, when compared to 2012.

2014-2018/19

The STATFOR medium-term forecast (MTF) predicts an average annual traffic growth between 4.7% and 8.2%, with an average baseline growth of 6.4% throughout the planning cycle.

Page 26: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 15 Released Issue

2.2 BAKU ACC

2.2.1 Summer 2013 performance

Traffic Evolution 2013 Capacity Baseline

En-route Delay (min/flight) Capacity

gap Optimum All reasons Without weather

-1.8 % 40 (0%) 0.1 0.0 0.0 No

Capacity Plan - Sufficient to meet demand Achieved Comments

ATS route network optimisation - an on-going process in co-operation with neighboring States.

Yes

Building of new Baku ATC Center. Installation of new ATC system - Trialing phase

Yes

Resectorisation of airspace structure : Training phase Yes

Maximum configuration: 4 + 3 APP sectors Yes

Summer 2013 performance assessment

It is assessed that the capacity offered was enough to meet demand. During the measured period, the average peak 3 was 19 and the average peak 1 was 33.

2.2.2 Planning Period 2014-2018/19 - Summer

The planning focuses on the Summer season to reflect the most demanding period of the year from a capacity perspective. This approach ensures consistency with the previous planning cycles.

The 2014-2018/19 summer capacity profile and delay breakdown has been derived according to the following parameters:

2014: capacity requirement profiles based on the delay breakdown per ACC as provided in January

2011

2015-2018/19: Reference value based on the breakdown of a yearly European delay target of 0.5

min/flight

2014 2015 2016 2017 2018 20190.23 0.01 0.01 0.01 0.01 0.010.21 0.01 0.01 0.01 0.01 0.01

En-route ATFM delay breakdown - Reference ValuesUBBACTA

AnnualSummer

H 40 0% 40 0% 40 0% 43 8% 45 5% 48 7%Ref. 40 0% 40 0% 40 0% 42 5% 44 5% 45 2%

L 40 0% 40 0% 40 0% 40 0% 41 2% 42 2%C/R 40 0% 40 0% 41 2% 42 2% 44 5% 45 2%

2017 20182015 20162014

UBBA 40

ACC2013

baseline 2019Profiles (hourly movements and % increase over previous year)

Capacity Profiles

Page 27: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 16 Released Issue

Capacity Plan

Year 2014 2015 2016 2017 2018 2019

Measures planned

ATS route network optimisation - an on-going process in co-operation with neighboring States

Building of new Baku ATC

Center. Installation of

new ATC system

Final Phase

Resectorisation of airspace structure

Implementation

Max sectors 5 + 3APP 5 + 3APP 5 + 3 APP 5 + 3 APP 5 + 3 APP 5 + 3 APP

Capacity increase

Sufficient capacity to meet demand

Reference profile

0% 0% 0% 5% 5% 2%

Additional information

AZANS has experience of installation of new ATC system (THALES Eurocat 1000 was installed in 2000). Transition plan is developed and approved. Cut over in March 2014. Sector capacities during transition period will not be reduced.

UBBACTA - Reference capacity profile and alternative scenarios

0

10

20

30

40

50

60

Cap

acit

y p

rofi

le (

mo

vem

ents

per

ho

ur)

2014-2019 Reference Capacity Profile 40 40 40 42 44 45

Capacity Profile - Current Routes 40 40 41 42 44 45

Capacity Profile - High 40 40 42 43 45 48

Capacity Profile - Low 40 40 40 40 41 42

Capacity Baseline 40 40

2014 - 2019 Plan 40 40 42 43 45 48

2012 2013 2014 2015 2016 2017 2018 2019

2014-2018/19 Planning Period Outlook

No problems are foreseen for Azerbaijan during the current planning cycle.

Page 28: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 17 Released Issue

Chapter 3 - ESSIP Report recommendations

Recommendations issued from the ESSIP Report for 2012 applicable to Azerbaijan for all items that require corrective actions and improvements ahead of the 2013 reporting exercise.

Number Recommendation Ownership

REC-2012-03 To ensure that all Stakeholders report the expected completion dates as defined in their National business plans.

All States

Response: Dates provided are according to national planning.

Number Recommendation Ownership

REC-2012-05 To ensure correct application of LSSIP guidance material and to implement the results of mandatory LSSIP in-cycle check.

All States

Response: LSSIP guidance applied to maximal possible extend in cooperation with CP.

Number Recommendation Ownership

REC-2012-10 To ensure actions for overcoming present delays in the implementation of basic ATSMHS capability (ESSIP objective COM10).

AL, AM, AZ, CY, CZ, DK, EE, FI, FR, GR, HR, HU, IT, LU, MAS, MD, MT, NO, SE,

SI, UA

Response: COM10 is partly completed. AMHS is implemented in the new ATC centre in Baku. For full implementation, it is necessary to extend the functionality to other regions of AZ.

Number Recommendation Ownership

REC-2012-22 States are encouraged to speed up the AFP implementation and to schedule AFP testing with Network Manager.

All States

Response: AZ is not EUROCONTROL Member State. Therefore, there are no timescales in relation to connection with the Network Manager.

Number Recommendation Ownership

REC-2012-40 ANSPs are encouraged to publish more APV routes.

All ECAC ANSPs

Response: All international airports in Azerbaijan are equipped with ILS. In the framework of implementation RNAV procedures, the application of APV will be discussed by the end of 2016.

Page 29: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 18 Released Issue

Chapter 4 - National Projects

The main projects currently ongoing in Azerbaijan are depicted in the table below.

Name Schedule Description – Scope Status Link with European Master Plan

Expected Contribution to the Key Performance Areas2

A-SMGS Level II March 2014 Implementation of the A-SMGCS Level II system comprising new ground radar at Heydar Aliyev Airport Baku.

Ongoing, on schedule. AOP04.1 and AOP04.2

Increasing capacity, enhancing safety of operations.

Gabala Airport (Greenfield)

2011 New Greenfield investment. Completed in 5 months. First flight at the airport conducted in October 2011 (B767).

Completed - Capacity

ADS-B \WAM implementation

2012 Implementation of ADS-B station and WAM around Azerbaijan and Caspian Sea where required.

Completed SUR05 Enhancing Safety, increasing cost-efficiency.

Baku Airport Mid 2012 Construction of new runway, apron and terminal at Heydar Aliyev Airport Baku.

Completed - Increasing capacity.

New ATC system 2013 New state of the art ATC system, Mode –S capable, AMHS .

Completed ATC, COM objectives.

Enhancing safety, increasing the capacity, improving cost-efficiency.

New ATC centre Baku

April 2013 New building for ACC, also TWR for Heydar Aliyev Airport Baku.

Completed - Capacity, safety

2 Capacity, safety, cost-efficiency and environment – as defined in Recital 2 of Regulation (EU) No 691/2010.

Page 30: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 19 Released Issue

Chapter 5 - Regional Co-ordination

Regional coordination projects

Performance of the local ATM system will be enhanced by the implementation of the following national projects:

- Expansion of EUROCONTROL Black Sea/Caucasus VSAT network;

- Integration into CFMU/IFPS area;

- Participation in EUROCONTROL Working Arrangements and implementation of EUROCONTROL requirements;

- Implementation of the interchange of radar data to obtain overall radar coverage through the region;

- Improved civil/military coordination;

- Development of AIS services and cartography (e – maps);

- Implementation and maintaining ISO;

- Implementation E – TOD.

Page 31: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 20 Released Issue

Chapter 6 - ESSIP Objective Implementation

Conventions

Two colour codes are used for each ESSIP Objective ‘box’:

o one colour code is used to show the Objective Scope in the Objective ID cell, and

o another colour code is used to show the Objective Progress in the State and for each national stakeholder.

Obj. ID (*) Obj. Title (By mm/yyyy of overall objective, inc non-State SloAs) Obj. Progress (**) 

State’s high level progress statement  State Impl. Date

REG (By:mm-yyyy) REG high level progress statement 

APO. Progress (**) 

APO Impl. Date

ASP (By:mm-yyyy) ASP high level progress statement 

ASP. Progress (**) 

ASP Impl. Date

MIL (By:mm-yyyy) MIL high level progress statement 

MIL. Progress (**) 

MIL Impl. Date

APO (By:mm-yyyy) APO high level progress statement 

APO. Progress (**) 

APO Impl. Date

(*) Objective Scope Code: (**) Objective/Stakeholder Progress Code:

ECAC Completed No Plan

EU+ Partly Completed Not Applicable

Multi-N Planned Missing Data

APT Late

Page 32: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 21 Released Issue

AOM13.1 Harmonise Operational Air Traffic (OAT) and General Air Traffic (GAT) handling (By:12/2018)

[IDP] [Essential]

Partly Completed

  OI Step(s): AOM‐0202 [E], AOM‐0301 New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules were developed in accordance with ICAO and EUROCONTROL requirements. CIV/MIL group spesifies some certain points of the activity.

04/2014

REG (By:12-2018)

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry.  Rules developed in accordance with ICAO and EUROCONTROL requirements. CIV/MIL group spesifies some certain points of the activity.

Completed

  12/2013 

ASP (By:12-2018) 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules developed in accordance with ICAO and EUROCONTROL requirements. CIV/MIL group spesifies some certain points of the activity. 

Partly Completed

  04/2014 

MIL (By:12-2018) 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules developed in accordance with ICAO and EUROCONTROL requirements. CIV/MIL group spesifies some certain points of the activity. 

Partly Completed

  04/2014 

 

AOM19  Implement Advanced Airspace Management (By:12/2016) [IDP] 

[Essential]  No Plan 

  

OI Step(s): AOM‐0201, AOM‐0202 [E], AOM‐0205 [E], AOM‐0401 [E], DCB‐0203 [E] 

Azerbaijan is currently not in a position to establish collaborative civil‐military airspace planning at the European Network level. 

‐ 

ASP (By:12-2015) 

Azerbaijan is currently not in a position to establish collaborative civil‐military airspace planning at the European Network level. 

No Plan

  ‐ 

MIL (By:12-2015) 

Azerbaijan is currently not in a position to establish collaborative civil‐military airspace planning at the European Network level. 

No Plan

  ‐ 

 

AOM20 Implement ATS Route Network (ARN) - Version 7 (By:10/2013) 

 

[Essential]  

Partly Completed 

 

OI Step(s): AOM‐0205 [E], AOM‐0401 [E], AOM‐0402, AOM‐0504 [E], AOM‐0801 [E], AOM‐0802 [E] 

New Airspace structure started to implement in a new ATC centre. CIV/MIL ccordination group specifies  some certain points of the activity. 

04/2014 

ASP (By:10-2013) 

New SIDs and STARs on the basis of area navigation (RNAV) procedures using the European Civil Aviation Conference (ECAC) Criteria.  The next step to analyse the entire airspace of Azerbaijan in relation to the strengths and weaknesses of the current and future airspace structure, including a revised SIDs/STARs structure developed by DFS in cooperation with AZANS. New Airspace structure started to implement in a new ATC centre.. CIV/MIL ccordination group specifies  some certain points of the activity. 

Partly Completed

  04/2014 

MIL (By:10-2013) 

New Air Rule on use of the airspace has been modified and approved by Cabinet of Ministry. Rules developed in accordance with ICAO and EUROCONTROL requirements. This rules will actively involve Mil in Aisppace Management. CIV/MIL ccordination group specifies  some certain points of the activity. 

Partly Completed

  04/2014 

 

AOM21  Implementation of Free Route Airspace (By:12/2017) (Outside Applicability Area) 

[IDP] [Essential]  

Not Applicable   

OI Step(s): AOM‐0401 [E], AOM‐0402 

Azerbaijan is not in the applicability area of this objective.  ‐ REG (By:12-2017)  ‐ 

Not Applicable

  ‐

ASP (By:12-2017)  ‐ 

Not Applicable

  ‐

MIL (By:12-2017)  ‐ 

Not Applicable

  ‐

 

Page 33: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 22 Released Issue

 

AOP01.2 Implement airside capacity enhancement method and best practices based on Eurocontrol capacity and efficiency implementation manual (By:12/2013) 

   

Not Applicable   

OI Step(s): AO‐0305, AUO‐0701 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airport related objective.   ‐ 

ASP (By:12-2011) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:12-2011) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

AOP03 Improve runway safety by preventing runway incursions (By:12/2013) 

   

Completed   

OI Step(s): AO‐0101 

The aerodrome service unit is responsible for runway safety issues. The activities of this unit are closely coordinated with other services. A Special team is organised for runway incursion and all objectives have been met.  Training and awareness are, of course, ongoing.  Procedures for RWY incursions are continuously updated.  Further updates were approved in 2010. 

12/2008 

REG (By:12-2013) 

The Regulator has audited and approved all existing operational procedures, documents and training programmes. Procedures for RWY incursions are continuously updated. Further updates were approved in 2010. 

Completed

  12/2008 

ASP (By:12-2013) 

AZANS works with all airport stakeholders to maintain awareness and improve runway safety. 

Completed

  12/2008 

MIL (By:12-2013)  No plan to implement this objective.  No civil ATS role. 

Not Applicable

  ‐

APO (By:12-2013) 

Each international aerodrome has established a Local Runway Safety Team and all procedures, documents and training programmes have been audited by the CAA. 

Completed

  12/2008 

 

AOP04.1 Implement Advanced Surface Movement Guidance and Control System (A-SMGCS) Level1 (By:12/2011) 

 

[Essential]  Not Applicable 

  

OI Step(s): AO‐0201 [E] 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airport related objective.   ‐ 

REG (By:12-2010) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

ASP (By:12-2011) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

MIL (By:12-2010) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:12-2010) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

AOP04.2 Implement Advanced Surface Movement Guidance and Control System (A-SMGCS) Level 2 (By:12/2017) 

   

Not Applicable   

OI Step(s): AO‐0102 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airpot related objective.   ‐ 

REG (By:12-2017) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

ASP (By:12-2017) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:12-2017) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

Page 34: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 23 Released Issue

 

AOP05 Implement Airport Collaborative Decision Making (CDM) (By:01/2016) 

[IDP] [Essential]  

Not Applicable   

OI Step(s): AO‐0501 [E], AO‐0601 [E], AO‐0602 [E], AO‐0603 [E], DCB‐0301 [E], DCB‐0302 [E] 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airport relatedobjective.   ‐ 

ASP (By:01-2016) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

MIL (By:01-2016) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:01-2016) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

ATC02.2 Implement ground based safety nets - Short Term Conflict Alert (STCA) - level 2 (By:01/2013) 

 

[Essential]  

Partly Completed 

 

OI Step(s): CM‐0801 [E] 

STCA functions exist and are optimised to the local environment.  Existing system has STCA functions. Review of  new EUROCONTROL specifications was done during 2010.  NEW ATC Centre has been  built and ATC Tower and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. New system has worked in test mode. ATCOs have passed training at new equipment. 

04/2014 

REG (By:01-2013) 

STCA functions exist and are optimised to the local environment.  Existing system has STCA functions. Review of  new EUROCONTROL specifications was done during 2010.  NEW ATC Centre has been  built and ATC Tower and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. New system has worked in test mode. ATCOs have passed training at new equipment. 

Partly Completed

  04/2014 

ASP (By:01-2013) 

STCA functions exist and are optimised to the local environment.  Existing system has STCA functions. Review of  new EUROCONTROL specifications was done during 2010.  NEW ATC Centre has been  built and ATC Tower and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. New system has worked in test mode. ATCOs have passed training at new equipment. 

Partly Completed

  04/2014 

MIL (By:01-2013)  Military ATCOs are joint users of the civil system. 

Not Applicable

  ‐

 

ATC02.5 Implement ground based safety nets - Area Proximity Warning - level 2 (By:12/2016) 

 

[Essential]  

Partly Completed 

 

OI Step(s): CM‐0801 [E] 

APW functions exist and are optimised to the local environment.  Requiremenst for the new ATC System which  is  implemented in 2013 consist EUROCONTROL specifications.  

04/2014 

ASP (By:12-2016) 

 APW functions exist and are optimised to the local environment.  Requiremenst for the new ATC System which  is implemented in 2013 consist EUROCONTROL specifications. Some fine tuning issues still remain. 

Partly Completed

  04/2014 

MIL (By:12-2016)  Military ATCOs are joint users of the civil system. 

Not Applicable

  ‐

 

Page 35: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 24 Released Issue

 

ATC02.6 Implement ground based safety nets - Minimum Safe Altitude Warning - level 2 (By:12/2016) 

 

[Essential]  

Partly Completed 

 

OI Step(s): CM‐0801 [E] 

MSAW functions exist and are optimised to the local environment.   NEW ATC Centre has been  built and ATC Tower and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. New system has worked in test mode. ATCOs have passed training at new equipment. 

04/2014 

ASP (By:12-2016) 

MSAW functions exist and are optimised to the local environment.  It is planned to review the EUROCONTROL specifications at a later date.MSAW functions exist and are optimised to the local environment.  NEW ATC Centre has been  built and ATC Tower and new Modern ATC equipment were installed. Specification has done according to the later EUROCONTROL Requirements. New system has worked in test mode. ATCOs have passed training at new equipment.  

Partly Completed

  04/2014 

MIL (By:12-2016)  MIL has no civil ATS role. 

Not Applicable

  ‐

 

ATC02.7 Implement ground based safety nets - Approach Path Monitor - level 2 (By:12/2016) 

 

[Essential]  Planned 

  

OI Step(s): CM‐0801 [E] 

AZANS will implement an Approach Path Monitor system in the future but only at those airports where terrain or other obstacles pose a hazard.  New systems will be in place next year and corresponde to  EUROCONTROL requirements . 

12/2014 

ASP (By:12-2016) 

AZANS will implement an Approach Path Monitor system in the future but only at those airports where terrain or other obstacles pose a hazard.  New systems will be in place next year and corresponde to  EUROCONTROL requirements . 

Planned

  12/2014 

MIL (By:12-2016)  MIL has no civil ATS role. 

Not Applicable

  ‐

 

ATC07.1  Implement arrival management tools (By:12/2015) (Outside Applicability Area) 

 

[Essential]  Not Applicable 

 

OI Step(s): TS‐0102 [E] 

Azerbaijan is not within the area of applicability of this multi‐national objective.  Moreover, there is no OPS need. However implemnattion of AMAN system is discussed in the frame of existing modernization programme.  

‐ 

ASP (By:12-2015)  No OPS needs, the investment can not be justified 

Not Applicable

  ‐

 

ATC12 Implement automated support for conflict detection and conformance monitoring (By:12/2016) 

 

[Essential]  Planned 

  

OI Step(s): CM‐0202 [E], CM‐0203 [E] 

FASTI specification will be implemented in new ATC centre. Starting implementation after full system installatiion.  

12/2014 

REG (By:12-2016) 

FASTI specification will be considered in new ATC centre.  Starting implementation after full system installatiion. 

Planned

  12/2014 

ASP (By:12-2016) 

FASTI specification and tools will be considered in new ATC centre.. Starting implementation after full system installatiion.  

Planned

  12/2014 

 

Page 36: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 25 Released Issue

 

ATC15 

Implement, in En-Route operations, information exchange mechanisms, tools and procedures in support of Basic AMAN operations (By:12/2017) (Outside Applicability Area) 

[IDP] [Essential]  

Not Applicable   

OI Step(s): TS‐0305 [E] 

There is no operational need for this tool in Azerbaijan. Azerbaijan is not in the applicability area of this objective. 

‐ 

REG (By:12-2017)  ‐ 

Not Applicable

  ‐

ASP (By:12-2017)  ‐ 

Not Applicable

  ‐

 

ATC16 Implement ACAS II compliant with TCAS II change 7.1 (By:12/2015) 

   

Planned   

Enabler(s): CTE‐S11a 

Approval programme for equipping aircraft with ACAS II version 7.1. Implementation process will start in 2014   

12/2014 

REG (By:12-2015) 

Approval programme for equipping aircraft with ACAS II version 7.1. Implementation process will start in 2014 

Planned

  12/2014 

ASP (By:03-2012) 

Acquisition information about TCAS II version 7.1and develop training plan to train ATCO in ACAS II (TCAS II version 7.1) Approval training plan. 

Planned

  12/2014 

MIL (By:12-2015)  MIL has no ATS role. 

Not Applicable

  ‐

 

ATC17 Electronic Dialogue as Automated Assistance to Controller during Coordination and Transfer (By:12/2018) 

[IDP] [Essential]  

Planned   

OI Step(s): CM‐0201 [E] 

OLDI started to implement into the new ATC system. System will be capable by 06/2014.    06/2014 REG (By:12-2018)  OLDI started to implement into new ATC system. 

Planned

  06/2014

ASP (By:12-2018)  OLDI started to implement into the new ATC system 

Planned

  06/2014

 

COM09 Migrate ground international or regional X.25 data networks or services to the Internet Protocol (IP) (By:12/2014) 

[IDP]   

Planned   

Enabler(s): CTE‐C11a, CTE‐C11b 

Azerbaijan does not have OLDI connections with adjacent States at present moment.  Internal IP network started to implement.  IP network and OLDI with adjacent States is planned for completion in 2014. 

12/2014 

REG (By:12-2010) 

The regulator will mandate IPv6 in 2014. REG actions not applicable to AZ as they are result of EU legislation. 

Not Applicable

  06/2014 

ASP (By:12-2014) 

Azerbaijan does not have OLDI connections with adjacent States at present moment.  Internal IP network started to implement.  IP network and OLDI with adjacent States is planned for completion in 2014. 

Planned

  12/2014 

MIL (By:12-2014) 

Mil systems are not interconnected with Civil ATC. One position of Baku ATC system is dedicated for  Mil sector at Baku ACC.  

Not Applicable

  ‐ 

 

COM10  Migrate from AFTN to AMHS (By:12/2014)    

Partly Completed 

 

Enabler(s): CTE‐C10 

Azerbaijan started to implement AMHS.  System is working into the new Centre. For full imlementation the system needed to involve all regions of Azerbaijan. 

12/2014 

ASP (By:12-2014) 

AZANS sterted to implement of AMHS system.  Complete implementation of AMHS is planned for the during of this year.  

Partly Completed

  12/2014 

MIL (By:12-2014)  Not applicable for MIL.MIL has no civil ATS role. 

Not Applicable

  ‐

 

Page 37: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 26 Released Issue

 

COM11 Implementation of Voice over Internet Protocol (VoIP) in ATM (By:12/2020) 

   

Planned   

Enabler(s): CTE‐C8 

AZANS has not yet relible infrustructure for VoIP. WAN system implemenation project under development.  

12/2016 

REG (By:12-2018) 

AZANS has not yet relible infrustructure for VoIP . WAN system implemenation project under development.  

Planned

  12/2016 

ASP (By:12-2020) 

AZANS has not yet relible infrustructure for VoIP.  WAN system implemenation project under development.  

Planned

  12/2016 

MIL (By:12-2020)  MIL does not provide service to GAT. 

Not Applicable

  ‐

 

ENV01 Implement Continuous Descent Operations (CDO) techniques for environmental improvements (By:12/2013) 

[IDP]   

Not Applicable   

OI Step(s): AOM‐0701 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airport related ESSIP objective.   ‐ 

ASP (By:12-2013) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:12-2013) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

ENV02 Implement Collaborative Environmental Management (CEM) at Airports (By:12/2016) 

   

Not Applicable   

OI Step(s): AO‐0703, AO‐0705, AO‐0706 

UBBB - Baku(Outside Applicability Area)

Azerbaijan is not within the area of applicability of this airport related objective.   ‐ 

ASP (By:12-2016) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

MIL (By:12-2015) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

APO (By:12-2016) 

Azerbaijan is not within the area of applicability of this multi‐national objective.  

Not Applicable

  ‐ 

 

FCM01 Implement enhanced tactical flow management services (By:12/2006) 

 

[Essential]  Not Applicable 

  

OI Step(s): IS‐0102 [E] 

Azerbaijan is currently outside the geographical scope of the CFMU.  This objective is therefore not applicable. This scope will be considered after the EUROCONTROL membership. 

‐ 

ASP (By:12-2006)  Azerbaijan is currently outside the geographical scope of the CFMU.  

Not Applicable

  ‐

MIL (By:12-2001)  Not applicable. 

Not Applicable

  ‐

 

FCM03  Implement collaborative flight planning (By:12/2015) [IDP] 

[Essential]  Not Applicable 

  

OI Step(s): DCB‐0302 [E], IS‐0101 [E], IS‐0102 [E] 

Azerbaijan is currently outside the geographical scope of the CFMU.  This objective is therefore not applicable. 

‐ 

ASP (By:12-2015)  Azerbaijan is currently outside the geographical scope of the CFMU.   

Not Applicable

  ‐

MIL (By:12-2015)  Not applicable. 

Not Applicable

  ‐

 

Page 38: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 27 Released Issue

 

FCM04 Implementation of Short Term ATFCM Measures - phase 1 (By:12/2015) (Outside Applicability Area) 

[IDP] [Essential]  

Not Applicable   

OI Step(s): DCB‐0205 [E] 

Azerbaijan is not in the applicability area of this objective.  ‐ REG (By:12-2015)  ‐ 

Not Applicable

  ‐

ASP (By:12-2015)  ‐ 

Not Applicable

  ‐

 

FCM05  Implementation of interactive rolling NOP (By:12/2016) [IDP] 

[Essential]  Not Applicable 

  

OI Step(s): AOM‐0205 [E], DCB‐0102 [E] 

Azerbaijan is currently outside the geographical scope of the CFMU.  This objective is therefore not applicable. This scope will be considered after the EUROCONTROL membership. 

‐ 

REG (By:12-2016)  ‐ 

Not Applicable

  ‐

ASP (By:12-2016)  ‐ 

Not Applicable

  ‐

MIL (By:12-2016)  ‐ 

Not Applicable

  ‐

APO (By:12-2016)  ‐ 

Not Applicable

  ‐

 

INF04  Implement integrated briefing (By:12/2012)    

Completed  

OI Step(s): IS‐0201 

Integrated briefing is implemented at Baku Heydar Aliyev Airport. AZANS currently implementing self briefing automated system at Baku Heydar Aliyev Airport.  

01/2012 

ASP (By:12-2012) 

Integrated briefing is implemented at Baku Heydar Aliyev airport. AZANS currently implementing self briefing automated system at Baku Heydar Aliyev airport.  

Completed

  01/2012 

MIL (By:12-2012)  Not applicable. 

Not Applicable

  ‐

 

ITY-ADQ 

Ensure quality of aeronautical data and aeronautical information (By:07/2017) (Outside Applicability Area) 

 

[Essential]  Not Applicable 

  

OI Step(s): IS‐0202, IS‐0204 [E] 

 

This objective is not applicable to AZ. AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done. Development plan is forseen according  

12/2014 

REG (By:07-2017) 

AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done. Development plan is forseen according  

Planned

  12/2015 

ASP (By:07-2017) 

AZANS AIS is ISO 9001/2008 Certified by DQS. Gap analyses for ITY‐ADQ requirements implementation is done. Development plan is forseen according  

Planned

  12/2014 

MIL (By:07-2017)  ‐ 

Not Applicable

  ‐

APO (By:07-2017)  AZANS AIS is responsible for APO  

Planned

  12/2014

 

Page 39: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 28 Released Issue

 

ITY-AGDL 

Initial ATC air-ground data link services above FL-285 (By:02/2015) (Outside Applicability Area) 

[IDP] [Essential]  

Not Applicable   

OI Step(s): AUO‐0301 [E] 

Azerbaijan is not within the area of applicability of this EU+ objective. In New ATC Centre Air Ground Data Link Services is exist, but implementation does not commence yet.  

12/2014 

REG (By:02-2015) 

Azerbaijan is not within the area of applicability of this EU+ objective.In New ATC Centre Air Ground Data Link Services is exist, but implementation does not commence yet.   

Planned

  12/2014 

ASP (By:02-2015) 

Azerbaijan is not within the area of applicability of this EU+ objective.  In New ATC Centre Air Ground Data Link Services is exist, but implementation does not commence yet.  

Planned

  12/2014 

MIL (By:-) 

Azerbaijan is not within the area of applicability of this multi‐national objective. 

Not Applicable

  ‐ 

 

ITY-AGVCS2 

Implement air-ground voice channel spacing requirements below FL195 (By:12/2020) (Outside Applicability Area) 

   

Not Applicable   

Enabler(s): CTE‐C5 

Azerbaijan is not in the applicability area of this objective.  ‐ REG (By:12-2018)  ‐ 

Not Applicable

  ‐

ASP (By:12-2018)  ‐ 

Not Applicable

  ‐

MIL (By:12-2020)  ‐ 

Not Applicable

  ‐

APO (By:12-2018)  ‐ 

Not Applicable

  ‐

 

ITY-COTR 

Implementation of ground-ground automated co-ordination processes (By:02/2015) (Outside Applicability Area) 

 

[Essential]  Not Applicable 

  

OI Step(s): CM‐0201 [E] 

Azerbaijan is not within the area of applicability of this EU+ objective. OLDI system will be implemented with adjusent ACCs with implementation of new ATC Centre.  

12/2014 

REG (By:12-2012) 

Azerbaijan is not within the area of applicability of this EU+ objective.OLDI system will be implemented with adjusent ACCs with implementation of new ATC Centre. 

Planned

  12/2014 

ASP (By:02-2015) 

Azerbaijan is not within the area of applicability of this EU+ objective.OLDI system will be implemented with adjusent ACCs with implementation of new ATC Centre. 

Planned

  12/2014 

MIL (By:12-2012)  Azerbaijan is not within the area of applicability of this EU+ objective. 

Not Applicable

  ‐

 

ITY-FMTP Apply a common flight message transfer protocol (FMTP) (By:12/2014) 

[IDP]   

Planned   

Enabler(s): CTE‐C11b 

Azerbaijan does not have OLDI connections with adjacent States.  Internal IP network exists at present.  IP network and OLDI with adjacent States is planned for completion in 2014 with complete implementation of new ATC centre. 

12/2014 

REG (By:12-2014)  CAA will conduct the certification of new ATC Centre  

Planned

  09/2014

ASP (By:12-2014) 

Azerbaijan does not have OLDI connections with adjacent States.  Internal IP network exists at present.  IP network and OLDI with adjacent States is planned for completion in 2014 with comlete implementation of new ATC centre. 

Planned

  12/2014 

MIL (By:12-2014) 

Mil systems are not interconnected with Civil ATC. One position of Baku ATC system is dedicated for  Mil sector at Baku ACC.  

Not Applicable

  ‐ 

 

Page 40: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 29 Released Issue

 

ITY-SPI Surveillance performance and interoperability (By:12/2019) (Outside Applicability Area) 

   

Not Applicable   

AZ is not within the applicability area of this EU+ objective. ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE requirements.  Airborn equipment or modification is subject to EASA certification.  

‐ 

REG (By:12-2013) 

ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE. Airborn equipment or modification is subject to EASA certification.  

Not Applicable

  ‐ 

ASP (By:02-2015) 

ATC systems is procured from EUROPEAN famous suppliers and correspond to EUROCAE. Airborn equipment or modification is subject to EASA certification.  

Not Applicable

  ‐ 

MIL (By:12-2019)  MIL has no civil ATS role. 

Not Applicable

  ‐

 

NAV03  Implementation of P-RNAV (By:12/2012)  

[Essential]  Late 

 

OI Step(s): AOM‐0601 [E] 

AZANS  developed P‐RNAV procedures with the support of DFS.  The new procedures were tested in a Baku terminal area simulation in 2010. In 2012 new RWY was put in operation. Therefore new procedures are developing. PBN Plan is developed and run in cooperation with ICAO. National Legislation Documents were  approved by Cabinet of Ministry. CIV/MIL coordination group  spesifies some certain points of the activity. 

06/2014 

REG (By:01-2005) 

 National Legislation Documents  were approved by Cabinet of Ministry. CIV/MIL coordination group  spesifies some certain points of the activity. 

Late

  06/2014 

ASP (By:12-2012) 

 The P‐RNAV procedures were tested in a Baku terminal area simulation in 2010. In 2012 new RWY was put in operation. Therefore new P‐RNAV procedures are developing. PBN Plan is developed and run in cooperation with ICAO.  

Late

  06/2014 

MIL (By:12-2012)  MIL has no civil ATS role. 

Not Applicable

  ‐

 

NAV10  Implement APV procedures (By:12/2016) [IDP] 

[Essential]  Planned 

  

OI Step(s): AOM‐0602‐A [E], AOM‐0602‐B [E] 

 International airports of the Republic are equipped with ILS. In the framework of implementation RNAV procedures  the application of APV will be discussed later. 

12/2016 

REG (By:04-2016) 

 International airports of  Republic are equipped with ILS. In the framework of implementation RNAV procedures  the application  of APV will be discussed later. 

Late

  12/2016 

ASP (By:12-2016) 

 International airports of  Republic are equipped with ILS. In the framework of implementation RNAV procedures  the application  of APV will be discussed later. 

Planned

  12/2016 

MIL (By:12-2016)  Not applicable as MIL users are not significant. 

Not Applicable

  ‐

 

SAF10 Implement measures to reduce the risk to aircraft operations caused by airspace infringements (By:12/2011) 

   

Late   

Airspace infringements do occur in Azerbaijan.  Civil radar data is shared with the military to increase situational awareness.  However, it has not been possible to implement the European Action Plan to date. Procedures and regulations are in place to avoid airspace infringements. After coming into the force the New Rules of using airspace procedures will be renewed. 

09/2014 

REG (By:12-2011) 

Airspace use is regulated by Ari law of Azerbaijan Republic and corresponding ATS procedures are developed.   The European Action Plan has not been developed to date.  Procedures and regulations are in place to avoid airspace infringements. After coming into the force the New Rules of using airspace procedures will be renewed. 

Late

  09/2014 

ASP (By:12-2011) 

Civil radar data is shared with the military to increase situational awareness.  Procedures and regulations are in place to avoid airspace infringements. The European Action Plan will be implemented over the next two years.  

Late

  06/2014 

MIL (By:12-2011)  MIL has no ATS role. 

Not Applicable

  ‐

 

Page 41: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 30 Released Issue

SAF11 Improve runway safety by preventing runway excursions (By:01/2018) 

   

Missing Data   

‐  ‐ REG (By:01-2018)  ‐ 

  ‐

ASP (By:12-2014)  ‐ 

  ‐

MIL (By:01-2018)  ‐ 

  ‐

APO (By:12-2014)  ‐ 

  ‐

 

SRC-CHNG Implementation of Safety Oversight of Changes to ATM by National Supervisory Authorities (NSA) (By:12/2010) 

   

Late   

Any safety related changes to ATM systems are notified by the ANSP to the CAA including documentary evidence of any testing (FAT, SAT) together with any new documented procedures etc.   

12/2014 

REG (By:12-2010) 

The CAA must formally approve the implementation of any new safety related equipment and/or procedures.  Neither AZANS nor the CAA have the personnel to properly produce and analyse a safety argument/case. 

Late

  12/2014 

MIL (By:12-2010) 

Not applicable. The military have no civil ATS role. MIL systems are not utilised in the provision of ANS to GAT  

Not Applicable

  ‐ 

 

SRC-RLMK Implement the EUROCONTROL Safety Regulatory Requirements (ESARRs) (By:12/2010) 

   

Late   

The CAA of the Azerbaijan Republic has established rules and procedures in ATM Safety regulation based on the principles of ICAO and ESARRs.  National regulations are equal to ESARRs in terms of requirements.  As Azerbaijan is not an EU or EUROCONTROL member State there has been no State requirement to subsume ESSARs into State law.  However, Azerbaijan recognises that compliance with ESARRs will be required as a EUROCONTROL member State. 

12/2014 

REG (By:12-2010) 

The CAA of the Azerbaijan Republic has established rules and procedures in ATM Safety regulation based on the principles of ICAO and ESARRs.  National regulations are equal to ESARRs in terms of requirements.  As Azerbaijan is not an EU or EUROCONTROL member State there has been no requirement to subsume ESSARs into State law. The new legislation should soon coming into force. CAA will develop new regulatory provisions. 

Late

  12/2014 

MIL (By:12-2010) 

Not applicable.  The military have no civil ATS role. MIL systems are not utilised in the provision of ANS to GAT (i.e. IOP issue) 

Not Applicable

  ‐ 

 

SRC-SLRD  Safety Levels and Resolution of Deficiencies (By:12/2010)    

Late  

The CAA was established in 2007.  Since that time the CAA has developed safety oversight and regulations for ATM.  Due to the lack of resources at the CAA level the process to establish safety levels is in developing 

09/2014 

REG (By:12-2010) 

The CAA was established in 2007.  Since that time the CAA has developed safety oversight and regulations for ATM.  Due to the lack of resources at the CAA level the process to establish safety levels is in developing 

Late

  09/2014 

MIL (By:12-2010) 

Not applicable.  The military have no civil ATS role. MIL systems are not utilized in the provision of ANS to GAT  

Not Applicable

  ‐ 

Page 42: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses
Page 43: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 31 Released Issue

Annexes

Annex A – Specialists involved in the LSSIP Process LSSIP Co-ordination

LSSIP Focal Point for Azerbaijan AZANS Farhan Guliyev

LSSIP Contact Person for Azerbaijan

EUROCONTROL Predrag vranjkovic

ESSIP Objective Implementation

ESSIP Objective

EUROCONTROL Objective Owners EUROCONTROL EIPR Objective Coordinator

National Stakeholder Specialist(s)

AOM13.1 R. BUCUROIU, O. MROWICKI, E. REUBER

A. DYBOWSKA Bala Mirzoyev

AOM19 G. ACAMPORA, O. MROWICKI A. DYBOWSKA Bala Mirzoyev

AOM20 R. BUCUROIU A. DYBOWSKA Bala Mirzoyev

AOM21 R. BUCUROIU A. DYBOWSKA Bala Mirzoyev

AOP01.2 P. ADAMSON P. VRANJKOVIC Farhan Guliyev

AOP03 T. LICU P. VRANJKOVIC Farhan Guliyev

AOP04.1 P. ADAMSON P. VRANJKOVIC Farhan Guliyev

AOP04.2 P. ADAMSON P. VRANJKOVIC Farhan Guliyev

AOP05 P. ADAMSON P. VRANJKOVIC Farhan Guliyev

ATC02.2 B. BAKKER, S. DROZDOWSKI I. FEIJT Farhan Guliyev

ATC02.5 B. BAKKER, S. DROZDOWSKI I. FEIJT Farhan Guliyev

ATC02.6 B. BAKKER, S. DROZDOWSKI I. FEIJT Farhan Guliyev

ATC02.7 B. BAKKER, S. DROZDOWSKI I. FEIJT Farhan Guliyev

ATC07.1 N. GAUTIER L. DELL’ORTO Farhan Guliyev

ATC12 N. GAUTIER L. DELL’ORTO Farhan Guliyev

ATC15 N. GAUTIER L. DELL’ORTO Farhan Guliyev

ATC16 S. DROZDOWSKI L. DELL’ORTO Farhan Guliyev

ATC17 N. GAUTIER L. DELL’ORTO Farhan Guliyev

COM09 B. GASZTYCH, J. POUZET O. ALFARO Elman Muzaffarov

COM10 B. GASZTYCH, J. POUZET A. KOKONA Elman Muzaffarov

COM11 B. GASZTYCH, J. POUZET A. KOKONA Elman Muzaffarov

ENV01 P. ADAMSON B. HILL Naila Aliyeva

ENV02 S. MAHONY, A. WATT B. HILL Naila Aliyeva

FCM01 H. KOOLEN O. CIOARA Bala Mirzoyev

FCM03 S. SMIDT O. CIOARA Bala Mirzoyev

FCM04 M. RICHARD O. CIOARA Bala Mirzoyev

FCM05 N. AGACDIKEN O. CIOARA Bala Mirzoyev

INF04 P. MATERN A-P. FRANGOLHO Farkhan Guliyev

ITY-ADQ M. UNTERREINER A-P. FRANGOLHO Farkhan Guliyev

ITY-AGDL E. CERASI, S. DISSING A. KOKONA Farkhan Guliyev

ITY-AGVCS2 J. ROCA O. ALFARO Farkhan Guliyev

ITY-COTR N. GAUTIER L. DELL’ORTO Farkhan Guliyev

ITY-FMTP B. GASZTYCH, J. POUZET O. ALFARO Elman Muzaffarov

Page 44: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 32 Released Issue

ESSIP Objective

EUROCONTROL Objective Owners EUROCONTROL EIPR Objective Coordinator

National Stakeholder Specialist(s)

ITY-SPI M. BORELY, R. STEWART A-P. FRANGOLHO Farkhan Guliyev

NAV03 F. PAVLICEVIC A. KOKONA Bala Mirzoyev

NAV10 R. FARNWORTH, F. PAVLICEVIC A. KOKONA Bala Mirzoyev

SAF10 T. LICU I. FEIJT Alexander Telegin

SAF11 S. LAWRENCE I. FEIJT Alexander Telegin

SRC-CHNG M. DEBOECK A. DYBOWSKA Alexander Telegin

SRC-RLMK M. DEBOECK A. DYBOWSKA Alexander Telegin

SRC-SLRD M. DEBOECK A. DYBOWSKA Alexander Telegin

Page 45: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 33 Released Issue

Annex B – National Stakeholders Organisation Charts

1. SCAA organisational chart

2.

2. AZANS

Page 46: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 34 Released Issue

Chief of MET CentreChief of CNS Centre 

SUR 

NAV 

COM 

Zabrat  MET

Lankaran  MET

Zagatala  MET

President of AZAL

Director  of AZANS

Head of DEVELOPMENT First Deputy DirectorDeputy Director  HRHead of SMS 

Chief of ATS Centre  Chief of AIS Centre 

Baku ACC 

Baku APP/TWR 

Ganja APP/TWR 

Nakhchivan 

APP/TWR

Zabrat TWR 

Lankaran APP/TWR 

ATC AS 

Baku  MET

Ganja  MET

Nakhichevan  MET

AIS 

Baku Briefing  

Zagatala APP/TWR 

PWR 

ISO process implemented 

Page 47: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 35 Released Issue

Annex C – Glossary of Abbreviations

ACAS Airborne Collision Avoidance System

ACC Area Control Centre

AIS Aeronautical Information Services

AMC Acceptable means of Compliance

ANS Air Navigation Services

ANSP ANS Provider

AOP Airports Operations (Domain)

APV Approach with Vertical Guidance

ARN ATS Route Network

ATC Air Traffic Control

ATCO Air Traffic Controller

ATFM Air Traffic Flow Management

ATM Air Traffic Management

ATS Air Traffic Services

CAD Civil Aviation Department

CDM Collaborative Decision Making

CFMU Central Flow Management Unit

CNS Communications, Navigation and Surveillance

COM Communications

CTR Control Zone

DFL Division Flight Level

EAD European AIS Database

eAIP European Aeronautical Information Publication

EATM European Air Traffic Management

ECAC European Civil Aviation Conference

ESARR EUROCONTROL Safety Regulation Requirement

ESP European Safety Programme

FDP Flight Data Processing

FIR Flight Information Region

Page 48: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 36 Released Issue

FL Flight Level

FSQA Flight Safety and Quality Assurance

FUA Flexible Use of Airspace

GBAS Ground Based Augmentation System

GNSS Global Navigation Satellite System

HRS Human Resources

HUM Human (Domain)

ICAO International Civil Aviation Organisation

IFPS Initial Flight-plan Processing System

IFR Instrument Flight Rules

ISO International Standards Organisation

JAA Joint Aviation Authorities

kHz Kilohertz

LoA Letters of Agreement

MIL Military

NAV Navigation

NM Nautical Mile

NOTAM Notice To Airmen

OLDI On Line Data Interchange

OPS Operations

PSR Primary Surveillance Radar

QMS Quality Management System

REG Regulatory Authorities

RNP Required Navigation Performance

RVSM Reduced Vertical Separation Minimum

SAN Sakaeronavigatsia Ltd (ATM of Georgia)

SBAS Satellite-Based augmentation systems (SBAS)

SLOA Stakeholder Line of Action

SMQS Safety Management and Quality System

SMS Safety Management System

SRC Safety Regulation Commission

Page 49: Local Single Sky ImPlementation (LSSIP) AZERBAIJAN · (LSSIP) AZERBAIJAN. ... Islamic Republic of Iran to the South and Georgia, ... The geographical scope of this document addresses

LSSIP Year 2013 Azerbaijan 37 Released Issue

SSR Secondary Surveillance Radar

STCA Short Term Conflict Alert

SUR Surveillance (Domain)

TMA Terminal Manoeuvring Area; Terminal Control Area