liu-ions linac3 meeting liu project – planning and installation julie coupard en/mef-oss
TRANSCRIPT
LIU-IONS Linac3 meetingLIU Project – Planning and Installation
Julie CoupardEN/MEF-OSS
LIU - Planning & Installation Coordination Team
1st July 2015 LIU-IONS Linac3 meeting - J.Coupard 2
Wor
k Pa
ckag
es
LIU- IonsS. Gilardoni
D. Manglunki
LIU-IonsCoordination
Meeting
LIU Planning & Installation
Coordination Meeting
IntegrationY. Muttoni
Layout Database & Config.
ManagementS. Chemli
Organization, Scheduling and
SafetyJ. Coupard
+ safety coord.
LIU- PSBK. Hanke
B. Mikulec
J-M. Lacroix
T. Birtwistle
SchedulingD. Hay
Safety Coord.C. Bedel
LIU- PSS. GilardoniH. Damerau
J-M. Lacroix
T. Birtwistle
SchedulingS. Mataguez
Safety Coord.Y. Beraud
LIU- SPSB. Goddard
E. Chapochnikova
LIU-SPSCoordination
Meeting
F. GalleazziA. Kosmicki
S. Bartolome
SchedulingD. McFarlaneSafety Coord.
E. Paulat
J-M. Lacroix
Linac3 LEIR
S. Maridor
T. Birtwistle T. Birtwistle
SchedulingD. Kuchler
Safety Coord.Y. Beraud
SchedulingJ. Axensalva
Safety Coord.Y. Beraud
WBS
1.5
WBS
1.7
WBS
1.8
J-P. Corso
Linac4
Linac4Coordination
Meeting
S. Bartolome
SchedulingJ. Coupard
Safety Coord.E. Paulat
J-M. Lacroix
Linac2
T. Birtwistle
SchedulingC. Mastrostefano
Safety Coord.Y. Beraud
LIU-PSCoordination
Meeting
LIU-PSBCoordination
Meeting
Surface build.
A. Kosmicki
EDMS 1427184
LIU- PLIJ. Coupard
S. Mataguez
LIU-IONS Linac3 meeting - J.Coupard 3
LIU - Planning & Installation Coordination MeetingLIU-PLI
1st July 2015
EDMS 1450798
LIU-IonsCoordination
Meeting
LIU Planning & Installation
Coordination Meeting
LIU-SPSCoordination
Meeting
Linac4Coordination
Meeting
LIU-PSCoordination
Meeting
LIU-PSBCoordination
Meeting
Studies and decisions on design/workwith a preliminary schedule
Draft Engineering Change Request (ECR)in Engineering Check
Integration studiesand validation
Circulation of the ECR to all groups involvedFollow-up on the ECR process and comments
Presentation to IEFCApproval of the ECR
IntegrationMeeting (ICL)
Scheduling Identification of co-activities between machineIdentification of shared resources
LIU Project Team
Meeting
Facilities Coordination
MeetingFacilities
CoordinationMeeting
Facilities Coordination
Meeting
presentation
Report from the Technical coordinator
Check of the integration in case of modification
Report from the superintendents
Linac3Coordination
Meeting
Linac2Coordination
Meeting
LEIRCoordination
Meeting
Consolidations
Design Office
Technical Specifications (Spec., Note etc…)
LIU-IONS Linac3 meeting - J.Coupard 4
LIU - Planning & Installation Coordination MeetingSpace Reservation & Engineering Change Request - Guideline
1st July 2015
All changes (beam line or services) which might impact other equipment or space volume (survey, transport…) have to be declared in an ECR
The integration studies have to be done before the ECRs (at least preliminary studies)
The ECRs have to be presented in the LIU-PLI coordination meeting before circulating EDMS
The ECRs have to be RELEASED before the execution of the work (the sooner the better)
Objective 2015 : All upgrade works for LIU have to be declared in a Space Reservation if the ECR cannot be yet submitted during the course of 2015
Contacts: T.Birtwistle for PS-Complex & S.Bartolome for SPS
EDMS 1465008
• Templates: https://quality.web.cern.ch/templates • Space Reservation Request (SRR)• Engineering Change Request (ECR)
• MS Word older than 2013: MS Word New My Template PS Complex or SPS
• MS Word 2013: MS Word New Shared template PS Complex or SPS
• Templates and Guidelines for Engineering Change Requests : https://edms.cern.ch/document/1271880
DOP meeting - J.Coupard 5
Configuration management (EN-MEF-DC)
Quality Assurance (EN-MEF-QOP)
30 June 2015
All documents of the hardware baseline (functional spec., engineering spec., Note, ECR etc…) are managed by EN-MEF-DC.
As well as equipment code, drawings code. Thomas Birtwistle for the PS Complex
Configuration site : https://espace.cern.ch/configuration/default.aspx
LIU Project EDMS : https://edms.cern.ch/project/CERN-0000090106
LIU-IONS Linac3 meeting - J.Coupard 6
List of activities
1st July 2015
Action Description Details Contact Approved? SRR needed(yes or no)
ECR needed(yes or no)
Presentation of the SRR/ECR to the LIU-PLI
meetingStatus of the
SRR/ECRMechanical
Design OfficeDEC
(yes or no)DIC
(yes or no)
Linac3 - 10 Hz Modification of Linac3 and transfer lines to allow injection into LEIR every 100 ms (instead of 200)
Quadrupoles Power Convertors Jean-Marc Cravero no no no
Linac3 - 10 Hz Modification of Linac3 and transfer lines to allow injection into LEIR every 100 ms (instead of 200)
Magnet Interlocks Markus Zerlauth no no no
Linac3 - LBS New spectrometer line after connection of Linac4 to PSB Magnets
Pierre Alexandre ThonetDominique Bodart
no yes
Linac3 - LBS New spectrometer line after connection of Linac4 to PSB Power convertors Jean-Marc Cravero no yes
Linac3 -ITL (LEBT) Rematched optics in Low Energy Beam Transport, between source & RFQ Einzel-lens installation Giulia Bellodi
Detlef Kuchler no yes
Linac3 -Beam Instrumentation Faraday Cup
Federico RoncaroloSergei Sadovich
no yes
Linac3 -Beam Instrumentation SEMGrids
Federico RoncaroloSergei Sadovich
no yes
Linac3 -Beam Instrumentation PepperPot
Federico RoncaroloSergei Sadovich
no yes
Linac3 -Oven Test stand
Additional lead oven to study the dynamics of the existing one no no no
Linac3 -Source test stand
Alternate source for machine experiments, independent of operational one; can be used as spare in case of emergency
no no no
Consolidation Cooling and Ventilation
the renovation must be designed with sufficient margin for operation at this maximum power load, in particular during the summer months. The budget for this work is requested to the consolidation project
LIU-IONS Linac3 meeting - J.Coupard 7
Scheduling (EN-MEF-OSS)
4 periods of installation:
• Year-End Technical Stop (YETS) 2015-2016
• Extended Year-End Technical Stop (EYETS) 2016-2017
• Year-End Technical Stop (YETS) 2017-2018
• Long Shutdown 2 (LS2) 2018-2019 2019-2020 (not yet official)
Length of YETS 2015-2016 / EYETS 2016-2017: EDMS 1470895
Detailed schedules:
David Hay for the PSB
Simon Mataguez for the PS ring and TT2
David Mcfarlane for the SPS
Cristiano Mastrostefano for Linac3
Jerome Axensalva for the LEIR
Julie Coupard for Linac4
1st July 2015
Start of the Study InstallationProduction
Assembling
Tests
THANK YOU FOR YOUR ATTENTION!
LIU-IONS Linac3 meeting - J.Coupard
1st July 2015
8