lhcf arm2 – status of hardware upgrade in firenze lorenzo bonechi 20 december 2013
TRANSCRIPT
![Page 1: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/1.jpg)
LHCf Arm2 – status of hardware upgrade in Firenze
Lorenzo Bonechi20 December 2013
![Page 2: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/2.jpg)
2
Main points for the work in Firenze• Assembling of new silicon -strip detectors
– New silicon wire bonding scheme to reduce the saturation effect in the front-end electronics for high energy releases with respect to the original scheme
– 8 sensors are available (8 needed)• One recovered from a test plane
• Testing the new hybrid boards– 2 types (Left and Right)– Not enough electronics components for the complete replacement of
the old hybrids– 7+7 under test (8+8 needed)– Some faults found
• Modification of the manipulators– We must increase the speed to decrease the time that is necessary to
go from the GARAGE position to the RUNNING position and vice versa
![Page 3: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/3.jpg)
3
The idea for the new silicon planes
Readout
ReadoutFloating
80 mm implant pitch160 mm readout pitch
Silicon sensor
In the original scheme one strip over two was connected to the front-end electronics and theother strips were floating.
Silicon sensor
Readout
ReadoutGND
OLD
OLD
Loosing some part of the released energy
![Page 4: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/4.jpg)
4
Assembling of new silicon planesGluing of NEW type hybrid circuits to old type kapton fanout
Gluing of silicon layers to the NEW kapton fanout (with GND pads for charge loss)
-strip fanout
Bias pad(to be connected to the silicon back-plane)
![Page 5: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/5.jpg)
5
Glue deposition on the new kapton fanout cable
Y-side
Thin layer of siliconic glue(not hard)
Electrically-conductive(Ag) glue deposited on a bent strip of golden kapton film for sensor biasing
Thin layer of kaptontape for insulation
GND large pad
Plane with vacuum system
![Page 6: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/6.jpg)
6
![Page 7: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/7.jpg)
7
![Page 8: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/8.jpg)
8
![Page 9: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/9.jpg)
9
X-side
![Page 10: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/10.jpg)
10
Gluing X-side silicon+kapton fanout to the thin (0.5 mm) aluminum layer
ARALDITE 2011Epoxy glue
![Page 11: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/11.jpg)
11
![Page 12: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/12.jpg)
12
Wire bonding at the Delvotec machine
![Page 13: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/13.jpg)
13
Wire bonding at the Delvotec machine
![Page 14: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/14.jpg)
14
Wire bonding at the Delvotec machine
Mirko BrianziINFN-Fi technician
![Page 15: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/15.jpg)
15
• Wire bonding on the first layer has been completed yesterday afternoon
• I will continue the assembling after testing the first layer– We can test for pedestals and noise– Do we test also with laser?
![Page 16: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/16.jpg)
16
Test of the new hybrid circuits
• 7 (Left) + 7 (Right) boards have been mounted by an external company– not enough electronics devices to produce 8+8
• Successful testing for 10 boards– 1 board has a problem on one PACE3 chip– 3 boards have shorted power lines
• The 4 faulty boards have been delivered to the company for a x-ray check– There should be some news within today…
![Page 17: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/17.jpg)
17
Pedestals and noise on a good boardAD
Cs
Strip number Strip number
ADCs
PEDESTALS SIGMAS
![Page 18: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/18.jpg)
18
1 PACE3 chip with some problems?AD
Cs
Strip number Strip number
ADCs
PEDESTALS SIGMAS
![Page 19: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/19.jpg)
19
Modification of the manipulatorsOnly one manipulator has been modified and tested (two days ago).The modification was necessary because the beam dumping procedure in 2013 went faster than in 2010. It lasted about 5 min. So the target of this modification was 5 min for 12 cm movement (from the operation position to the garage position it took about 12min before the modification) (email by Menjo)
Replacement of the gear box(decreased the gear ratiofrom 30 to 12.5)
Test with 20.7 kg weightwas successfull.
Final vertical speed: 12 cm / 4 min
Power consumption is well below the limits of the engine
![Page 20: LHCf Arm2 – status of hardware upgrade in Firenze Lorenzo Bonechi 20 December 2013](https://reader035.vdocuments.mx/reader035/viewer/2022070409/56649ea15503460f94ba4874/html5/thumbnails/20.jpg)
20
Conclusions
MERRY CHRISTMAS !!!