3 Informations generales LHC machine Schedule for YETS, EDMS , INDICO W51 – du 14 au 18 Decembre Blindages ouverts exceptionnelment Machine en restreint automatique Jeudi 17 Machine en mode restreint Tous les blindages fermes IMPACTS interrompus (Excepté les interventions du vendredi et celles prevues pendant le Xstmas break) Pendant les 2wks de Noel : TI garde la machine Access en surface et souterrain en mode restreint (accès avec clé et depuis la CCC) À partir du 4 Janvier : Machine en mode générale (surface et souterrain) Patrouille à refaire pendant la W8 pour le test DSO Test DSO le 26 Février Machine rendue à OP le 4 Mars Consignations pendant la W51 circuits demandes via IMPACT Déconsignation W9 (du 29 Février au 4 Mars)TRANSCRIPT
LHC-YETS Coordination meeting #9
24th November, 2015
LHC machine Schedule for LHC TS3 EDMS 1556530 2
Information generales
• Toutes les demandes de consignation via Impact
• LHC- YETS: de Lundi 14 Decembre @ 6am, au Vendredi 4 Mars
• LHC sera sous le control BE-OP a partir du 4 Mars
• IMPACT: intervention period YETS-LHC-2015/16:• Les IMPACTs doivent etre soumis avant le 1er Decembre
• Téléphone piquet: 161669 – du Lundi 14 Decembre jusqu’à mi-Mars
• Planning de detail: https://espace.cern.ch/en-dep-mef-lpc/YETS2015-2016/Global%20Schedules/Forms/AllItems.aspx
• INDICO : https://indico.cern.ch/category/7197/
3
Informations generales
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
• W51 – du 14 au 18 Decembre• Blindages ouverts exceptionnelment• Machine en restreint automatique
• Jeudi 17 Dec @17h00:• Machine en mode restreint• Tous les blindages fermes• IMPACTS interrompus (Excepté les interventions du vendredi et celles prevues
pendant le Xstmas break)• Pendant les 2wks de Noel :
• TI garde la machine• Access en surface et souterrain en mode restreint
(accès avec clé et depuis la CCC)• À partir du 4 Janvier :
• Machine en mode générale (surface et souterrain)• Patrouille à refaire pendant la W8 pour le test DSO• Test DSO le 26 Février• Machine rendue à OP le 4 Mars
• Consignations pendant la W51 circuits demandes via IMPACT• Déconsignation W9 (du 29 Février au 4 Mars)
4
Actions
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
PIQUET• Quelles activités ont besoin d’un service de piquet pendant le Xmas Break?
CONSIGNATION 60A qui en a besoin?
Points ouverts CV&CRG- Maintenance CV au P18- Cryo start du secteur 12- No CV backup @ P2
5
YETS schedule overview – as 17th Nov.
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
• LHC back to OP on 4th March• Powering tests from 5th to 16th March • Experiments closed on 16th March• Machine check out 17th and 18th March
OBSOLETE
6
YETS schedule overview- main changes
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
CRG• CRG Sectors 78 and 81 will be emptied of Liquid Helium• Cryo back on the whole LHC machine on 4th March –
Sectors 34 and 45 some days before
BE-BI & VSC• BSRT replacement in LSS4 during W51• BWS change (ferrite) is not a baseline – could be done according to the evolution of the YETS
MSC• No intervention on ULO and No magnet exchange (sector 81)
EN-EL• Systematic inspection of Bus Bars to be realised – To be added in the schedule
ELQA• Investigations on the RCS is sector 78 can be realised in January, and the decision to realise ELQA before
the restart will be taken in Chamonix• If ELQA will be realised during HWC
Powering tests• Extension allocated - from 5th March to 16th March.
Some UPS tests included in this period.
Experiments• Readiness' of Atlas and CMS will be confirmed in Chamonix
7LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
• LHC back to OP on 4th March• Powering tests from 5th to 16th March • Experiments closed on 16th March• Machine check out from 17th to 20th March
YETS schedule overview – as 24th Nov.
LHC machine Schedule for YETS, EDMS 1552100 8
EDMS: 1544142
Test Secours (10min)All points on 17th December (7am)
Works on the Automatism & Circuit Breaker
LHC5 + CMS 21st – 24th December
No Access in the Surface & Underground Areas
LHC1 + ATLAS 25th January (ATLAS ok)LHC2 + ALICE 9th FebruaryLHC3 5th FebruaryLHC4 6th JanuaryLHC5 + CMS 5th JanuaryLHC6 14th JanuaryLHC7 15th JanuaryLHC8 + LHCb 7th JanuaryPM18 12th FebruaryPrevessin 13th February (Saturday)Meyrin + Adm. 2nd or 3rd JanuaryMeyrin W. + ISR 23rd January
BA80 23rd February
BA81 24th FebruaryBA82 + 85 25th FebruaryPS + B 9th & 10th JanuaryBA1 19th JanuaryBA2 20th JanuaryBA3 21st JanuaryBA4 + CNGS 13th JanuaryBA5 10th FebruaryBA6 11th FebruaryBA7 4th February
AUG Test
Auto Transfer TestPrevious & final works from 28th January
until 1st February (access possible)No access LHC1 + ATLAS + LHC18 + SPS6 + SPS7
on 30th January (Saturday)
Activités Électriques
9
Secteur 12
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Collimator 5th axis- TDI replacement
- Swap bake-out of TDI8 with TDI2?- AFP control cabling?- WCC in RR17
10
Secteur 23
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- PX24 confirmation?- Cleaning UJ32 confirm w1 & w2?- PM32 consolidation 2nd Phase from
15th January?- LSS3 opened from 4th January
11
Secteur 34
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- LSS3 opened from 4th January- LSS4 closed from 22nd February
12
Secteur 45
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Collimator 5th axis- LSS4 closed from 22nd February
13
Secteur 56
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Collimator 5th axis- TOTEM cabling?
14
Secteur 67
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Access LSS7 from 2nd February
15
Secteur 78
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Collimator TCLA.D6R7.B1 replacement (TBC)- Access LSS7 from 2nd February
16
Secteur 81
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
- Major players:- Collimator 5th axis- TDI
- Swap bake-out of TDI8 with TDI2?- WCC in RR13
17
Touts les points
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
18
LSS1L
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
19
Point 1
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
20
LSS1R
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
21
PM18 & Arc12
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
22
LSS2L
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
23
Point 2
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
24
LSS2R & Arc23
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
25
LSS3L & Point 3
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
26
PM32 & LSS3R & Arc34
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
27
LSS4L
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
28
Point 4
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
29
LSS4R & Arc45
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
30
LSS5L
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
31
LSS5R & Arc56
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
32
LSS6L
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
33
Point 6
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
34
LSS6R & Arc67
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
35
LSS7L & Point 7
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
36
LSS7R & Arc78
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
37
LSS8L & Point 8
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
38
LSS8R & Arc81
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333
39
Coming events
Next meeting Tuesday 1st December, Room 30-7-010
From 8h30 to 10h00
LHC machine Schedule for YETS, EDMS 1560875, INDICO 463333