lhc machine schedule, coordination & wat k. foraz march 22 nd, 2011 imwg - lhc machine1
TRANSCRIPT
IMWG - LHC machine 1
LHC machineSchedule, coordination & WAT
K. ForazMarch 22nd, 2011
March 22nd, 2011
IMWG - LHC machine 2
WGIM
Initial « constat »
Beginning of last year, situation was:• On the intervenants side:
– Information to the different coordination teams– Edition in the TIOC list– Negotiation to get a date– Safety analysis: VIC, fiche de tache…– Edition of ADI– Edition of AOC, fire permit…– Performance of the task (hopping that nobody is sick..else re-ADI)– Progress report to different coordination teams
March 22nd, 2011
IMWG - LHC machine 3
WGIM
Initial « constat »
• On the coordination sides:– Edition of the information in our own system
• Coming from mails, phone calls, meetings
– Check information with the other system• i.e. with TIOC
– Scheduling– Safety check with safety coordinators– Check in EDH that ADIs were correctly signed by the OP group !!!
• Vocabulary problems• Some work scheduled and approved were rejected• Some work not scheduled were rejected
– LHC operator granted access thanks to the ADI numbers (awful job)
March 22nd, 2011
IMWG - LHC machine 4
WGIM
Initial « constat »
• Discussions were held between OP, EN and GS– We need a tool
• As time was running towards the end of the year, We took the decision to start simple: create and test a tool, which was respecting a simple workflow, not linked to objects, but to activities (as a first stage), allowing us to :– Avoid multiple edition of the same information– Have an accurate control of activities– Ease the access
March 22nd, 2011
IMWG - LHC machine 5
WGIM
General Workflow
March 22nd, 2011
Request
Technical Approval
Scheduling
Safety preparation
Follow-up
Closure
IMWG - LHC machine 6
WGIM
1. Intervenants make a Work Request (1/2)
Same type of work covering different areas in the machine
• What– Title– Type: consolidation, upgrade, inspection, maintenance, repair, test…
– System type: based on the LHC naming convention
– Long description
• Technical Approval from LMC needed
• Who– Work responsible– Max participants per location (needed to estimate the number of keys)
– Number of teams (needed for schedule purposes)
– Participants names
March 22nd, 2011
IMWG - LHC machine 7
WGIM
• When• Date constraints• Intervention date• Intervention period type• Duration per area• Comments
• Locations
• Safety• Activity risks (anoxia, Chemical/industrial hygiene, Compressed air, Cryogenics, Electrical,
Fire/Explosion, Gas, Ionizing radiation, Mechanical. Non Ionizing radiation)• & compensatories measures • Lock-out type: CV, compressed air, cryogenics, DIMR, electrical lock-out level 2, electricily, Fire
permir, Gas, IS37, RP
1. Intervenants make a Work Request (2/2)
March 22nd, 2011
Send
IMWG - LHC machine 8
WGIM
2. Coordination team analyzes the request
• Can add activity risks/ Locations / Participants
• Can specify whether AET is needed or not
• WAT generates automatically tasks with the same characteristics as its Work Request, but for the spectrum of location defined.
March 22nd, 2011
IMWG - LHC machine 9
WGIM
3. Scheduling phase (1/3)
• From all the requests– 1. Constraints schedule
• Identification and schedule of the blocking activities
March 22nd, 2011
IMWG - LHC machine 10
WGIM
3. Scheduling phase (2/3)
– Schedule of the other activities w.r.t.• The constrainsts schedule• Resources available• Minimize co-activities
• First draft in MsProject….. But not all the participants read it…
– Insert correct dates in WAT, thanks to an excel sheet
March 22nd, 2011
IMWG - LHC machine 11
WGIM
3. Scheduling phase (3/3)
• Extraction from WAT in Excel….. Macro…– Schedule under excel readable by all
March 22nd, 2011
IMWG - LHC machine 12
WGIM
4. Safety preparation
• Each Work Request is discussed in preparation meetings with work responsible and safety coordinators
• If an AET is needed, then – Automatic generation of the AET(one week before the start), thanks to
the information already edited in WAT– For the last Xmas break, derogation from HSE to have all the AET send
only for approval…– Else it will have followed the AET-EDH workflow (future presentation
by Serge ?)– If AET is approved, then the task is approved
March 22nd, 2011
IMWG - LHC machine 13
WGIM
5. Access and Progress
March 22nd, 2011
• Providing that today• One has the access right to the machine• A work for a specific location
• Declared• accepted technicaly• Scheduled• approved in matter of safety
• Access will be granted• If access is in restricted, this person will be
delivered a key
• Schedule is updated through the Excel schedule
Request
Technical Approval
Scheduling
Safety preparation
Access & Follow-up
Closure
EDH
Access
IMWG - LHC machine 16
WGIM
WAT Inside: Integration with existing systems
March 22nd, 2011
WATEDH Layout Database
ADAMS
Foundation
Access Control (person/place/time)
LHC Locations
Access Points
Notifications
Signatures
Persons, Organic Units
Excel
Schedule Export, Bulk Update (Upload)
IMWG - LHC machine 17
WGIM
WAT Inside: Integrating the AET (EDH)
March 22nd, 2011
EDH buttons: authorization without leaving WAT (or still from within EDH)
EDH Document status / Info lines
Direct URL to access a task
Adams access control
IMWG - LHC machine 18
WGIM
WAT debriefing after the break
• Powerful Tool
• Very good feed-back form all the actors: users, coordination teams, access control…
• Strong control of activities with flexibility for users (intersite doors opened, addition of intervenient..)
• The operator is no longer a bottleneck with multiple access points in simultaneous access request, and more importantly no more waiting times of several minutes for the users to get the operator attention to get by.
• Very good support form AIS
• Some improvements already done and other in the queue
March 22nd, 2011