LHC - LS2 2018-2021Coordination meeting #63
1LHC coordination meeting, 18th February 2020
18th February 2020, week 8
Marzia Bernardini, María Baberán, Julie Coupard, Michela Pirozzi, Estrella Vergara
LHC-LS2 Coordination
2
• Piquet’s phone number: 161669
• INDICO: https://indico.cern.ch/category/7200/ (LHC-LS2)
• OSS website (planning, constraints, useful links…):
https://lhc-coordination.web.cern.ch/
• LS2 Plannings (all accelerators)
• LS2 Access constraints
• LS2 Baseline EDMS 1817804
LHC coordination meeting, 18th February 2020
3
EL tests & maintenance(EDMS 2058996) NO ACCESS
400 kV maintenance 22 July – 27 Sept 2019 (W30-39)
4 July – 27 Sept 2019 (W27-39)
4 July- 4 October (W27-40)
Auto-
transfert
No autotransfert from
16th September 2019 to May 2020
Test: 27-29 April 2020
Maintenance NO ACCESS* AUG NO ACCESS*
Point Day Point Day
LHC1 + ATLAS6 -7- 8 -13 January 2020 – NO access (W2)
9 - 10 January 2020 - Limited access (W2)LHC1 + ATLAS 13 January 2020 (W3)
LHC18 + SM18 23-25 April 2019 (W17) LHC18 + SM18
26 April 2019 (W17)
15 April 2020 (TBC)
Under discussion September 2020
(Exact date TBC from EN-EL)
LHC2 + ALICE
11-14 June 2019 (W24) – Access OK
LHC2 + ALICE 27 January 2020 (W5)20-21-22-27 January 2020 – NO access (W4)
23-24 January 2020 - Limited access (W4)
LHC3 + PM32 9-12 March 2020 (W11) LHC3 + PM3230 April 2019 (W18)
13 March 2020 (W11)
LHC417-20 June 2019 (W25) – Access OK
LHC47 Oct. 2019 (W41)
24-28 February 2020 (W9) 2 March 2020 (W10)
LHC5 + CMS 20-24 May 2019 (W21)
LHC5 + CMS 27 May 2019 (W22)
24-27 June 2019 (W26) – Access OK 5 May 2020 (W19)
LHC63-6 June 2019 (W23) TBC – Access OK
LHC6 20 Sept. 2019 (W38)17-19 Sept. 2019 (W38)
LHC7 23-27 Sept. 2019 (W39) LHC7 30 Sept. 2019 (W40)
LHC8
15-19 April 2019 (W16) – Access OK
LHC8 16 Dec. 2019 (W51)9-10 Dec. 2019 – NO access (W50)
11-12-13 Dec. 2019- Limited access (W50)
TEST SECOURS 2020 Mardi 26 Mai 2020 Prevessin4 April 2020 (W14)
under discussion 27 June 2020 (W26)
Meyrin (Administrative)
Meyrin (PS complex)
6 June 2020
16+17 May 2020
NEXT WEEK
4
EL tests & maintenance P4 NO ACCESS
LHC coordination meeting, 14th January 2020
From 24th February to 2nd March 2020
EDMS:
• LHC-L-PRD-0002
LHC coordination meeting, 28th January 2020 5
SM18 informed that the shutdown will be performed on September 2020 and in order to reduce
perturbations on June they request if the CV maintenance and the AUG test at SM18 can be shifted on
September (w36 and forwards).
• AUG test on w36 or 37 EN-EL confirmed that is ok
• CV maintenance from w36-w37
• From CV point of view there is no problem to postponed the maintenance, but instead of 2w they
will need 3 weeks.
• This maintenance affect the cryo in the sector 12 in which the COOL-DOWN is scheduled from
w38.
• TE-CRG if the CV maintenance is finished before week 38, the cryo won’t be affected.
• CV maintenance could start on week 35 to 37.
• ELQA test on w36-37 if in the tunnel the ventilation and the humidity remains normal, the test
can be performed in parallel with the CV maintenance.
SM18 could start the test on week 35 instead of 36 as requested in view of the EN-CV and TE-CRG
constraint.
SM18 Shutdown on September
W35-39 (24th August 28th September)
LHC-LS2 EN-CV Maintenance
6
Point Activity Week Start Start Date End Date Duration Status
LHC5
SF - CV Maintenance W50 10-Dec-18 01-Feb-19 6 wks Completed
SU - AC Maintenance W50 10-Dec-18 14-Dec-18 1 wk Completed
USC55 - CV Maintenance W50 10-Dec-18 08-Mar-19 11 wks Completed
SU - Ventilation Maintenance W10 04-Mar-19 29-Mar-19 4 wks Completed
Ventilation Maintenance in RRW14W15
01-Apr-1908-Apr-19
30-Apr-19 4 wks Completed
SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started
USC55 reduced - CV Maintenance W3 11-Jan-21 29-Jan-21 3 wks Not Started
Point Activity Week Start Start Date End Date Duration Status
LHC6
UW, UA, RE - CV MaintenanceW40W39
30-Sep-1923-Sep-19
25-Oct-19 4 wks Started
SF - CV Maintenance W44 28-Oct-19 10-Jan-20 9 wks Not Started
SU - CV Maintenance W3 13-Jan-20 07-Feb-20 4 wks Not Started
UW reduced - CV Maintenance (TBC) W28 06-Jul-20 24-Jul-20 3 wks Not Started
SF+SU reduced - CV Maintenance (TBC) W46 09-Nov-20 27-Nov-20 3 wks Not Started
Point Activity Week Start Start Date End Date Duration Status
LHC8
SF - CV Maintenance W7 10-Feb-20 08-Apr-20 8.5 wks Not Started
SU - CV Maintenance W16 14-Apr-20 19-May-20 5 wks Not Started
UW, UA , RE - CV Maintenance W21 20-May-20 18-Jun-20 4 wks Not Started
SF+SU reduced - CV MaintenanceW42 12-Oct-20 30-Oct-20 3 wks Not Started
W41 5-Oct-20 23-Oct-20 3wks
UW reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC1
SU1 - Ventilation Maintenance (RR, RE) W51 17-Dec-18 21-Dec-18 1 wk Completed
SU1 - Cooling Maintenance W2 07-Jan-19 01-Feb-19 4 wks Completed
SF - CV Maintenance - Dependant from SPS tests in BA6
W4 21-Jan-19 29-Mar-19 10 wks Completed
USA15 + US15 cooling + ventilation maintenance - Impact on LHC Tunnel
VentilationW6 04-Feb-19 01-Mar-19 4 wks Completed
USA15 EM W10 04-Mar-19 29-Mar-19 4 wks Completed
SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started
USA reduced - CV Maintenance + ventilation RR, RE
W3 11-Jan-21 29-Jan-21 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC2
UW - CV Maintenance -Cooling, UA, RE W40 30-Sep-19 01-Nov-19 5 wks Not Started
SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started
SU - CV Maintenance W16 15-Apr-20 20-May-20 5 wks Not Started
UW reduced - CV Maintenance -EG Only W34 17-Aug-20 14-Sep-20 4 wks Not Started
SF+SU + Ventilation UA- CV reduced Maintenance
W45 02-Nov-20 20-Nov-20 3 wks Not Started
Point ActivityWeek Start
Start Date End Date Duration Status
LHC4
SF - CV Maintenance W4 20-Jan-20 13-Mar-20 8 wks Not Started
SU - CV Maintenance W12 16-Mar-20 14-Apr-20 4 wks Not Started
UW - CV Maintenance - Cooling, UA, RE W21 22-May-20 19-Jun-20 4 wks Not Started
UW reduced - Cooling Maintenance -Ventilation reduced
W37 07-Sep-20 28-Sep-20 3 wks Not Started
SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started
UW25 off
(Transfo replacement)
Week 10
from 02-Mar-20
to 06-Mar-20
UW45 off
(Transfo replacement)
Week 8
from 17 to 21 Febr. 20
UW65 off
(Transfo replacement)
Week 48
from 25-Nov-19
to 29-Nov-19
UW85 off
(Transfo replacement)
Week 51
from 17-Dec-19
to 20-Dec-19
In progress
Next to start
Maintenance tableau Hazemeyer EN/CV dates under definition
LHC coordination meeting, 18th February 2020
LHC-LS2 EN-CV Maintenance
7
Point Activity Week Start Start Date End Date Duration Status
LHC 18
LHC 3.2
LHC3.3
LHC 7
LHC 18- CV Maintenance W35 24-Aug-20 14-Sept-20 3 wks Not Started
LHC 3.2UW PM32
W27W31
30-Jun-2027-July-20
6-July-2031-July-20
1 wk1 wk
Not Started
LHC 3 W26 22-Jun-20 24-July-20 5 wks Not Started
LHC 7 W26 22-Jun-20 24-July-20 5 wks Not Started
In progress
Next to start
LHC coordination meeting, 18th February 2020
8
LS2 cryogenics milestonesCryogenics unlockout surface Date
P18
25-Feb-20
18-Feb-20
P2 25-May-20
P4 (S.3-4) 23-Mar-20
P4 (S.4-5) 20-Apr-20
P6 (S.5-6) 21-Apr-20
P6 (S.6-7) 21-Apr-20
P8 (S.7-8) 06-Apr-20
P8 (S.8-1)
10-Feb-20
06-Jan-20
Cryogenics unlockout
undergroundDate
s. 1-2 06-Apr-20
s. 2-3 16-Apr-20
S.3-4 01-Jun-20
S.4-5 04-May-20
S.5-6 15-Jun-20
S.6-7 29-Jun-20
S.7-8 18-May-20
S.8-1 06-Apr-20
Cryo ok for ELQA@warm
and cool-downDate
S. 1-2 04-Jun-20
S. 2-3 07-Aug-20
S. 3-4 17-Jul-20
S. 4-5 19-Jun-20
S. 5-6 31-Jul-20
S. 6-7 14-Aug-20
S. 7-8 06-Jul-20
S. 8-1 26-May-20
Cryo Unlock Surface and Underground
Cryo Ready for ELQA & Cool Down
LHC coordination meeting, 18th February 2020
NEXT
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 9
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 10
Thursday 16th April 2020
Open Points
LHC coordination meeting, 28th January 2020 11
• BE-BI
• BPMWI @ A5L8.R News? Draft presented at LMC on 5th February
• BGC modifications??? HL-LHC integration
• Major changes with respect to the original ECR on the increased footprint, orientation, volume, blackening coating, reuse of the BGI
system and racks.
• ECR update under preparation
• Ready to install 3rd February 2020 ??? date change
• PM56 Lift Replacement
• New dates Start from 30th March until 17th June (1st April – 6th June)
• Procedure for mitigation measures on going
• BE-ICS Installation of UL16 /UL14 access point
• Check magnet transport
• UL14 2nd - 3rd March
• UL16 4th – 5th March
Open Points
LHC coordination meeting, 28th January 2020 12
• Kicker pulse test (MKBV) TE-VSC News• TE-VSC :
• The MKB in RA63 (vacuum sector BTD62.DR) is ready for TE-ABT test.
• Issue with one ion pump on the MKB located in RA67 (vacuum sector BTD68.DB) Need to be changed (around 2
days of mechanic and between 1 and 2 weeks to recondition the sector)
TB discuss if postponed after the Kicker pulse test
• TE-ABT:
• Preparatory works on generators at UA starting on 17th February
• W10-13 validation test on MKBH & MKBV (Beam1) (LSS6L & UA67)
• W14-18 validation test on MKBH & MKBV (Beam2) (LSS6R & UA63)
Magnet Exchange Campaign
LHC coordination meeting, 18th February 202013
Next
ma
in a
ctivities-
On
go
ing–
Co
mp
leted
• 26/28 removed (takes into account WP11 HL-LHC + C16L2 + Q16L2)
• 30/36 reinstalled (takes into account 3 parts per 11T and cryo assemblies)
Q16L2:
• Disconnection starting from 20/09/2019
• Transport new magnet: 19/11/2019
C16L2:
• Disconnection starting from 24/09/19
• Transport new magnet: 11/11/2019
CC-C11L2:
• Disconnection starting from 26/09/2019
• Installation 2 LEP: 4 and 5/11/2019
• Installation LEN: 8/11/2019
CC-C11R2:
• Disconnection starting from 02/10/2019
• Transport 1st LEP: 29/11/2019
Due to a NC, this LEP has been removed from
the tunnel but already re-installed (03/02/20).
Currently it is being connected
• Transport 2nd LEP: 13/12/19
• Transport LEN: 17/12/19
11T LSS7L:
• Disconnection starting from 19/03/2019 (tbc)
• Transport old magnet starting: 26/03/2019 (tbc)
• Transport 11T & LEN starting: 17/04/2020 (tbc)
11T LSS7R:
• Disconnection starting from mid March (tbc)
• Transport old magnet starting: (tbc)
• Transport 11T & LEN starting: (tbc)
TCLD arc 12 installation
LHC coordination meeting, 18th February 2020 14
TBC if pre-series is going to be installed on 27th February vs series
TDIS crane status vs weight of TDIS
LHC coordination meeting, 28th January 2020 15
New crane will be installed in both point LSS2L and LSS8R
LSS2L EN-HE not before mid-March 2020 W13 Confirmed
Installation date postponed to 6th April 2020
LSS8R EN-HE W14 Confirmed
NO IMPACT on the installation dates (13th July 2020)
16
UPR 13 SAS installation w12 EN-EL will confirn on w9 or
10 if the cable pulling is finished to give the green light to SMB
Opening from w13 to w16
SAS dismantling and Metallic plate installation w17
UPR 53 SAS installation 6th April / Smoke test w14
Opening from w15 to w19
SAS dismantling and Metallic plate installation w 20
HL-LHC UPRs 13 & 53 Request new dates for Opening
LHC coordination meeting, 28th January 2020
LHC coordination meeting, 28th January 2020
LSS5 Realignment Planning consolidated
17
Phase I – Realignment from Q7 to Q5 14th Sep to 10th Oct 2019
Phase II – Realignment between Q5 to Q5 in progress (From January 2020 to May 2020)
• Q5-D1 (6 MBWX, 1 Q4, 1 D2, 1 TAN, 4 pick-ups and 4 Collimators)
• Q1L-Q1R (2 TAS, VAS and 2 BPMWK)
LSS5L
Relative Vertical alignment (3 tours) Q5-D1, Q1L-Q1R W3-4
Radial measurement of the principal (with duct) components Q5-D1, Q1L-Q1R W10-11
Calculations W12-13
Radial alignment principal components (2-3 last days with duct) Q5-D1, Q1L-Q1R W16-17
Alignment secundary components W20-21
LSS5R
Relative Vertical alignment (3 tours) Q5-D1, Q1L-Q1R W5-6-7
Radial measurement of the principal (with duct) components Q5-D1, Q1L-Q1R W8-9
Calculations W12-13
Radial alignment principal components (2-3 last days with duct) Q5-D1, Q1L-Q1R W14-15
Alignment secundary components W18-19
Q1 – DFBX Alignment on the Inner Triplet area project (V Parma)
LSS5L W5
Endoscopy TE-VSC on Wednesday 29 January
X-Ray 4th February
LSS5R w11
Endoscopy TE-VSC on Wednesday 11th March
X-Ray 12th March
TAS (Right side) (F Sanchez Galan) w11 in // with the DFBX LSS5R
EN-STI: Beam Dump ReplacementLink to schedule (in work) / IMPACT 149959
LHC coordination meeting, 18th February 2020 18
Opening of the shielding and storage of the activated
dumps in the UDs week 9 (UD62 and UD68) + scans
Work in UX65 till end of
May 2020 Installation of
the spare dumps from June
Collimators installation dates
LHC coordination meeting, 28th January 2020 19
Asset number Collimator LocationDelivery date at CERN
(On 20/09/2019)Delivery date at CERN
(On 14/02/2020)Ready to install(Baseline 2.2)
Ready to Install(Foreseen dates)
Removal old collimator
Installation date (Baseline 2.2)
Installation date (Foreseen dates)
HCTCPPM001-CZ000001 TCPP #1 TCP.C6R7.B2 10/2019 28/12/2019 20/12/2019 20/01/2020 06/02/2020 17/01/2020 12/02/2020 +4wks
HCTCPPM001-CZ000002 TCPP #2 TCP.D6L7.B1 11/2019 28/12/2019 20/12/2019 20/01/2020 30/09/2020 10/02/2020 05/10/2020 +33wks
HCTCPPM001-CZ000003 TCPP #3 TCPP.C6L7.B1 11/2019 ???? 03/02/2020 ?????? - 14/02/2020 - -
HCTCPPM001-CZ000004 TCPP #4 TCP.D6R7.B2 10/2019 19/12/2019 03/02/2020 04/02/2020 06/02/2020 17/01/2020 12/02/2020 +4wks
HCTCLDA001-CZ000001/2 TCLD #2 TCLD.A11L2.B2 12/2019 19/02/2020 05/02/2020 27/03/2020 - 21/02/202027/02/2020 (pre-series)
03/04/2020 (series)+1wk (pre-series)
+6wks (series)
HCTCLDA001-CZ000002/3 TCLD #3 TCLD.A11R2.B1 12/2019 19/02/2020 05/02/2020 27/03/2020 - 30/03/2020 06/05/2020 +5wks
HCTCLDA001-CZ000003/4 TCLD #4 TCLD.A9L7.B2 01/2020 11/03/2020 05/03/2020 20/04/2020 - 27/07/2020 TBC -
HCTCLDA001-CZ000004/5 TCLD #5 TCLD.A9R7.B1 01/2020 11/03/2020 05/03/2020 20/04/2020 - 11/06/2020 TBC -
HCTCSPM001-CZ000001 TCSPM #1 TCSPM.B4L7.B1 02/2020 15/04/2020 28/02/2020 25/05/2020 - 05/06/2020 26/05/2020 -2wks
HCTCSPM001-CZ000002 TCSPM #2 TCSPM.B4R7.B2 02/2020 15/04/2020 28/02/2020 25/05/2020 - 13/03/2020 27/05/2020 +10wks
HCTCSPM001-CZ000003 TCSPM #3 TCGS.D4R7.B2
(TCSPM)03/2020 12/05/2020 04/05/2020 20/06/2020 17/06/2020 10/03/2020 22/06/2020 +10wks
HCTCSPM001-CZ000004 TCSPM #4 TCSPM.6R7.B1 03/2020 12/05/2020 04/05/2020 20/06/2020 - 15/05/2020 23/06/2020 +5wks
HCTCSPM001-CZ000005 TCSPM #5 TCSPM.E5L7.B2 04/2020 09/06/2020 02/06/2020 17/07/2020 - 16/07/2020 20/07/2020 +1wks
HCTCSPM001-CZ000006 TCSPM #6 TCSPM.E5R7.B1 04/2020 09/06/2020 02/06/2020 17/07/2020 - 11/05/2020 21/07/2020 +10wks
HCTCSPM001-CZ000007 TCSPM #7 TCSPM.6L7.B2 05/2020 07/07/2020 01/07/2020 20/08/2020 - 08/07/2020 24/08/2020 +6wks
HCTCSPM001-CZ000008 TCSPM #8 TCGS.D4L7.B1
(TCSPM)05/2020 07/07/2020 01/07/2020 20/08/2020 12/08/2020 09/06/2020 25/08/2020 +11wks
TCAPM #1 TCAPM.A5L7.B1 - - 29/06/2020 02/03/2020 - 15/07/2020 19/03/2020 -16wks
TCAPM #2 TCAPM.A5R7.B2 - - 27/04/2020 02/03/2020 - 15/05/2020 25/03/2020 -7wksTCPP #5 TCPP.C6L7.B1 07/2020 04/08/2020 03/02/2020 15/09/2020 30/09/2020 - 06/10/2020 -
20
Collimators
LS2 Baseline 2.2
Collimators
LS2 Foreseen dates
NEG activation after Cool-Down
Sector 67:
- W40/41 Survey measurement at cold
- W43/45 Survey V and R smoothing at cold
Sector 78:
- W37/38 Survey measurement at cold
- W41/43 Survey V and R smoothing at cold
Updated Collimators schedule after new reception dates
21LHC coordination meeting, 18th February 2020
LHC P7 RR73 / RR77
11T installation in Sector 78
22
New dates presented in the LMC on the 20th of November are obsoleted:
• 9R7 removal postponed to March 2020
LHC coordination meeting, 18th February 2020
Reminder
LHC coordination meeting, 18th February 2020 23
LHC Access Constraint overview
W8-W9, 2020
24LHC coordination meeting, 18th February 2020
25
Week 8/9 2020 - P1 + Sector 1-2 + P2 + Sector 2-3
LHC coordination meeting, 18th February 2020
26
Week 8/9 2020 - P3 + Sector 3-4 + P4 + Sector 4-5
LHC coordination meeting, 18th February 2020
27
Week 8/9 2020 - P5 + Sector 5-6 + P6 + Sector 6-7
LHC coordination meeting, 18th February 2020
28
Week 8/9 2020 - P7 + Sector 7-8 + P8 + Sector 8-1
LHC coordination meeting, 18th February 2020
Next meetings
29
W9: 25th February LS2 coordination meeting #64
W11: 10th March LS2 coordination meeting #65
https://indico.cern.ch/category/7200/
LHC coordination meeting, 18th February 2020
Back-up Slides
30LHC coordination meeting, 18th February 2020
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 31
Friday 8th May 2020
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 32
Friday 26th
June 2020
(tbc with CMS)
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 33
Monday 3rd August 2020
BE-ICS: Access System Commissioning
LHC coordination meeting, 18th February 2020 34
Friday 21st August 2020
35LHC coordination meeting, 18th February 2020
LHC General
36LHC coordination meeting, 18th February 2020
LHC P1
37LHC coordination meeting, 18th February 2020
LHC P1.8
No Access
38LHC coordination meeting, 18th February 2020
LSS1L/R
39LHC coordination meeting, 18th February 2020
LHC P1 RR13 / RR17
40
LHC P1 RR13 / RR17
LHC coordination meeting, 18th February 2020
LHC coordination meeting, 18th February 2020 41
Arc
1-2
: D
ISM
AC
42
Arc 1-2: 16L2 & CC-C11L2
LHC coordination meeting, 18th February 2020
43LHC coordination meeting, 18th February 2020
TI2
44LHC coordination meeting, 18th February 2020
LHC P2
45LHC coordination meeting, 18th February 2020
LHC P2 UA23
46LHC coordination meeting, 18th February 2020
LHC P2 UA27
No
Acce
ss
47LHC coordination meeting, 18th February 2020
LSS2L/R
LHC coordination meeting, 18th February 2020 48
Arc
2-3
: D
ISM
AC
LHC coordination meeting, 10th December 2019
49
Arc 2-3: CC-C11R2
LHC coordination meeting, 18th February 2020
50LHC coordination meeting, 18th February 2020
LHC P3.2 + P3.3
No
Acce
ss
No
Acce
ss
LHC-L-PRD-0002https://edms.cern.ch/document/2138732/
51LHC coordination meeting, 18th February 2020
LSS3L/R
EN
-EL
Main
tenance P
4
LHC coordination meeting, 18th February 2020 52
Arc
3-4
: D
ISM
AC
53LHC coordination meeting, 18th February 2020
LSS4L/R
EN
-EL M
Ain
ten
an
ce
54LHC coordination meeting, 18th February 2020
LHC P4
No
Acce
ss
LHC-L-PRD-0002https://edms.cern.ch/document/2138732/
55LHC coordination meeting, 18th February 2020
LHC P4
No
Acce
ss
No
Acce
ss
LHC coordination meeting, 18th February 2020 56
Arc
4-5
: D
ISM
AC
57
LHC P5
LHC coordination meeting, 18th February 2020
58LHC coordination meeting, 18th February 2020
LHC P5 RR53 / RR57
LHC coordination meeting, 18th February 2020 59
LSS5L/R
EN
-EL M
ain
ten
ance P
4
LHC coordination meeting, 18th February 2020 60
Arc 5-6: DISMAC
61
LHC P6
LHC coordination meeting, 18th February 2020
62
LHC P6 UA63 UA67
LHC coordination meeting, 18th February 2020
LHC coordination meeting, 18th February 2020 63
LSS6L/R
TE-VSC vacuum control section will be finished week 8 (left side)
LHC coordination meeting, 18th February 2020 64
Arc 6-7: DISMAC
65
LHC P7
LHC coordination meeting, 18th February 2020
66LHC coordination meeting, 18th February 2020
LSS7L/R
67LHC coordination meeting, 18th February 2020
LHC P7 RR73 / RR77
LHC coordination meeting, 18th February 2020 68
Arc 7-8: DISMAC
LHC coordination meeting, 18th February 2020 69
Arc
7-8
: 11
T &
SIT
70LHC coordination meeting, 18th February 2020
LSS8L/R
LHC coordination meeting, 18th February 2020 71
LHC P8
LHC coordination meeting, 18th February 2020 72
LHC P8 UA83 UA87
73LHC coordination meeting, 18th February 2020
Ti8
Under definition
LHC coordination meeting, 18th February 2020 74
Arc 8-1
LHC LSS1 Co-Activities in March 2020
W10W14, 2020
75LHC coordination meeting, 18th February 2020
RL
P1 Week 10 (from 2 to 6 March)
LHC coordination meeting, 18th February 2020 76
Pulling cable campaign
From US15 to 6R including ITs
Scaffolding needed (DFBX MBXW.4R1)
Pulling cable campaign
From US15 to 6L including ITs
Scaffolding needed (DFBX MBXW.4L1)
RL
P1 Week 11 (from 9 to 13 March)
LHC coordination meeting, 18th February 2020 77
Optical Fibre Campaign
US15cell 14L1
9-12 Mar
EN-SMM alignment
Q8R1Q1R1
9 - 13 March
Connection&Test cable campaign
From US15 to 6L including ITs
Scaffolding needed (DFBX MBXW.4L1)
Connection&Test cable campaign
From US15 to 6R including ITs
Scaffolding needed (DFBX MBXW.4R1)
Canalis reinstallation
RR13
10-16 March
RL
P1 Week 12 (from 16 to 20 March)
LHC coordination meeting, 18th February 2020 78
Optical Fibre Campaign
US15cell 14R1
16-17 Mar
EN-SMM alignment
Q8L1Q1L1
16- 20 March
Connection&Test cable campaign
From US15 to 6L including ITs
Scaffolding needed (DFBX MBXW.4L1)
Scaffolding removal:19 March
Connection&Test cable campaign
From US15 to 6R including ITs
Scaffolding needed (DFBX MBXW.4R1)
Scaffolding removal:19 March
RL
P1 Week 13-14 (from 23 to 27 March)
LHC coordination meeting, 18th February 2020 79
EN-SMM alignment
Q8L-Q8R
Until 27 March
LHC LS2 OSS Organisation
80LHC coordination meeting, 18th February 2020
General Information
LHC coordination meeting, 18th February 2020 81
LHC-LS2 Coordination
82LHC coordination meeting, 18th February 2020
LIU-TCDIL in Ti2&Ti8F.X.-Nuiry
Connexion cryostat full assembly in LSS2
D. Schoerling
11T Dipole Full Assembly in LHC P7
D. Schoerling
DISMAC (Dipole diodes consolidation
& Magnets replacement)
J.-Ph. Tock
Water cooled cablesreplacementB. Gutierrez
Facility Coordinators
Frame & ArcsMarzia Bernardini
EROS
LHC 4 & 5Emmanuel Paulat
Integration
Frederic Galleazzi
Jean Pierre Corso
Configuration / Layout DB
Anne-Laure PerrotCollimators
(TCLIA in LSS2, TCSPM in LSS7)
I. Lamas
Installation of generalservices in the UPR
L. Tavian
Consolidation of the LHC access system
T. Hakulinen
New TANB in LSS8F. Sanchez
LSSsMichela Pirozzi
Maria Barberàn
Support for projects:
- DISMACEstrella Vergara
- HL-LHC UPRMarta Alcaide
New TDIS in L2 and R8A. Perillo
Activity Technical
Coordinator
TDE consolidationD. Grenier
Service areasJulie Coupard
LHC 2 & 3 & 6Michel Bonnet
LHC 1John Etheridge
LHC 7 & 8Cyrille Bedel
LHC Piquet phone 161669
INDICO LHC-LS2 Coordination
LHC LS2 coordination website
83
LHC-LS2: cryogenics FULL lock out completed
LHC coordination meeting, 18th February 2020
LHC-LS2 MsProject Planning Breakdown Structure
84
LHC MASTER Schedule
• LHC_LS2_GENERAL
• LHC LS2 Main Frame
• Service Areas + RRs planning
• Arcs planning
• LHC_LS2_LSS
• LHC LSS planning
• WCC Project detailed planning
• Collimators
• Cabling campaign
• HL-LHC
• LHC_LS2_TI2-TI8
• LHC TI2-TI8 planning
• LIU-LHC: TCDIL installation planning
• LHC_LS2_DISMAC
• DISMAC detailed planning
• Magnet exchange campaing detailed planning
• HL-LHC: WP11 11T
LHC_LS2_GENERAL
LHC_LS2_LSS LHC_LS2_TI2-TI8 LHC_LS2_DISMAC
• Main Constraints
• Main activities summary tasks
LHC MASTER SCHEDULE
_EDMS1817804
_EDMS2000365
_EDMS2030625
_EDMS2020179
Planning Baseline in EDMS on week 48 (end November 2018) LHC coordination meeting, 18th February 2020
LHC-LS2 Linear & Constraint Planning
85LHC coordination meeting, 18th February 2020
LHC_LS2_GENERAL LHC_LS2_DISMACLHC_LS2_LSS LHC_LS2_TI2-TI8