let's go camping lesley johnson walden university · work breakdown structure: general...
TRANSCRIPT
Let's Go Camping
Lesley Johnson
Walden University
Dr. Deanna Romano
EDUC 6145: Project Management in Education & Training
December 22, 2013
Table of Contents
• Statement of Work
o Worksheet: The Project Charter
• Rationale Statement
• Work Breakdown Structure
o Work Breakdown Structure: General Overview
o Work Breakdown Structure: Workload breakdown by teams
o Work Breakdown Structure: Mind map breakdown by teams
• Cost Estimation
• Resource Allocation
• Gantt Chart
• Responsibility/Accountability Matrix
• Monitoring the Project
• Communication
o Communication Plan
o Communication Calendar
o Monitoring Communication
• Approval & Sign-off Matrix
• Project Checklists
o Project Manager's "Let's Go Camping" Checklist
o Writing Team's "Let's Go Camping" Checklist
o Design Team's "Let's Go Camping" Checklist
o Panel of SMEs' "Let's Go Camping" Checklist
o Client's "Let's Go Camping" Checklist
WK8ProjJohnsonL 1
Back to Table of Contents
Worksheet: The Project Charter Project Name: Our Nation and Society: Let's Go Camping! Date: _November 17, 2013_______
Project Manager: _Gordon Anderson _________________________________________
Project Tracking Number: _CS1P12 ________________ ___________________________
Project Justification:
As the winners of the of a tender for SchoolsOnline, our team is thrilled to begin the project with the learning object, "Let's Go Camping!", an online resource for primary schools through SchoolsOnline. This particular learning object will be created for K-2 learners, but it will be adaptable for grades 3-6 as well. "Let's Go Camping!" will address the differences between needs and wants by having students go on a camping trip with their family, a camping trip that will be done wholly online. Students will choose what items to pack for their camping trip and as they pack, they will journal about their choices so that instructors may ask follow-up questions that further guide the learner. The learning object will provide feedback through the family members who are camping with them. Both forms of feedback will employ the constructivist theories SchoolsOnline strives to use. As requested by SchoolsOnline, Flash™ will be used to create the learning object; however, it is recommended HTML5 be used so that it will be compatible on all mobile devices. This project will be the first of 15 learning objects our team will complete for SchoolsOnline. There is a writing team, design team, and panel of subject and education experts who will be working together with Gordon Anderson, the project manager, who will oversee the project. Each team is responsible for their own portion of the project (see "Primary Stakeholders & Roles" below for more details) but all parts will collaborate to create a finished product that meets SchoolsOnline's expectations and standards.
Overview of Deliverables:
• Students will bring their virtual family camping with them. They will have to pack everything they need for the weekend. They will have to choose between their needs and their wants−tent, bedding, food, candy, chips, soda pop, water, flashlights, firewood, portable devices, swimming suit, towel, etc.
• Students will have a certain amount of space in their bags and in the car so they will need to choose wisely.
• Students will journal about their choices so that the instructor can see the students' thought processes. This journal may be done on paper or it may be done in a Word Document so that it can be uploaded to the CMS (course management system) which would help keep the SchoolsOnline learning object smaller in file size. If the user has no CMS, e-mail would be an acceptable alternative.
• The family members will help provide feedback by asking for the essential things the student should have packed. For example, before the evening, the tent needs to be set up and someone will ask for it.
• If students are ill-prepared, they can go home early but they will get to hear their family members' reactions (i.e., they were hungry all night, they were cold, they got a stomach ache from eating too much candy, etc.).
WK8ProjJohnsonL 2
Back to Table of Contents
• Students can choose to go camping again to see if they make better choices.
o animation: all of the objects (tent, bedding, etc.), bedroom, kitchen, shed, packing bag, camping location, setting up camp, playing camp scene.
o text: Title Page−Let's Go Camping! Content: You are going camping with your family! How many people are in your family? (Student chooses) You must prepare for a camping trip with __ people. Choose what you want to bring with you. Let's start in your bedroom. What are you going to bring with you? (Student selects items.) Great! Let's go to the kitchen. What are you going to bring with you? (Student selects items.) Great! Now let's go outside to the shed. What are you going to bring with you? (Student selects items.) Are you ready? Let's go camping! [Create feedback from various characters−mother, father, brother, sister.]
o audio: Goes along with text. Use different voices for the mother, father, brother, and sister.
Specific Project Objectives & Success Criteria:
Learning Objectives: • Students will know the difference between a want and a need. • Students will select the appropriate supplies to take camping. • Students will review and discuss their choices.
Project Objectives: • Create a learning object that meets the learning objectives. Benchmarks will be created
using the learning objectives so there is a measurable result that shows the student has learned.
• Build a learning object that will be adaptable for older learners. • Generate a learning object that utilizes constructivist theories. • Construct a learning object that will function on multiple devices. • Design a learning object that can be used in a number of contexts to help learners explore
the difference between wants and needs.
Timeline: This is the first of 15 learning objects that will be completed over the next three months. Therefore, we hope to complete this project in two weeks' time. • Day 1−Analyze the learners and w rite project goals. • Day 2−Write learning objectives; list all deliverables; set deadlines for deliverables; and
create master schedule. • Day 3−Approve project goals and learning objectives; list expenses; create budget; and
develop the storyboard. • Day 4−Approve storyboard; write narration script; and design the learning object setting
and packable items. • Day 5−Design the learning object family members; compile setting, items, and family
members to create learning object; approve narration script; and write journal prompts. • Day 6− Create the website to host the learning object; approve journal prompts; and write
feedback.
WK8ProjJohnsonL 3
Back to Table of Contents
• Day 7−Add in narration and journal prompts to learning object; approve feedback. • Day 8−Add feedback; edit learning object. • Day 9−Approve the learning object; create facilitator guide. • Day 10−Approve facilitator guide; publish the learning object.
Cost: • Will be finalized by Gordon Anderson after he has spoken to each team (writing team,
designing team, and panel of subject matter and educational experts). The estimated cost is $15,000 for labor and software.
Constraints:
• Time will be our largest constraint. Completing a learning object in two weeks is a lofty goal, but we will do our best.
• Flash™ will limit the users of the learning object because many people own devices that are not compatible with Flash™.
• Technical difficulties may slow the project. • Communication issues may slow the project.
Primary Stakeholders & Roles:
• Gordon Anderson will oversee the entire project and facilitate communication between the project teams and SchoolsOnline. Mr. Anderson will also give the final approval of each stage of the project and for the final product.
• The writing team (Chris Smith, Jo Jones, and Fran Johnson) will write the storyboard and script of the learning object.
• The design team (Scott Allen, Jeff Parker, Penny Johnson, and Tracey Ward) will use Flash™/HTML5 to design the learning object using the storyboard and script provided by the writing team.
• The panel of subject matter and educational experts will be available to the writing and design team through e-mail, conference calls, and video chat (i.e. Skype). They may be contacted earlier in the development process so that the writers or designers may address issues before getting too far in the design process. The panel will also be responsible for the revision of the learning object and noticing content-or learning-specific issues.
• SchoolsOnline is responsible for running a to-scale pilot test and giving the teams enough time to complete any necessary revisions before the learning object is provided to a larger audience.
Key Assumptions:
• This is a project for Australian learners and instructors. • Designers can use HTML5 instead of Flash™ because it is more applicable for today's
digital world. • If Flash ™ is used, however, the design team will not be held responsible for unhappy
customers who try to use the learning object on a device that is not Flash™ compatible. • If the sponsor is unhappy with the quality of the first learning object, the timeline will be
revisited so that the 15 learning objects can be completed to the sponsor's liking.
WK8ProjJohnsonL 4
Back to Table of Contents
• The first users will be the full-scale pilot test. After the first use of the learning object by a school, the learning object will undergo further revision before becoming available to more users.
• The sponsor will be in constant communication with Gordon Anderson. • The sponsor will be responsible for delivering the learning object to users. • More time will be given to the design team to adapt the learning objects for older
learners.
Signatures—The following people agree that the above information is accurate:
Project team members: Gordon Anderson (manager), the design team: Scott Allen, Jeff Parker, Penny Johnson, and Tracey Ward, and the writing team: Chris Smith, Jo Jones, and Fran Johnson.
Project sponsor and/or authorizing manager(s): SchoolsOnline
Rationale Statement:
I chose "Case Study 1: Scott Allen - Designing Learning Objects for Primary Learners" for my project. I did make up the names of the writing team. I also invented the budget for this project using PayScale's website and personal experience, but I tried to use the text to avoid making assumptions. Nevertheless, I did have to make one assumption and that was that the team will continue with their camping trip idea since the learning object will then be more realistic and easily adapted for older learners. I also made the assumption that the Design Team and the Development Team are one and the same. I am lacking knowledge in this area so I can't grasp what the Development Team would do that the Design Team isn't; therefore, they have become one group. Everything else I have taken from the text after multiple readings and used my own personal experiences with instructional design via Walden courses and working as a school teacher.
WK8ProjJohnsonL 5
Back to Table of Contents
References
Ertmer, P., & Quinn, J. (Eds). (2007). The ID casebook: Case studies in instructional design (3rd
ed.). Upper Saddle River, NJ: Pearson Education, Inc.
Greer, M. (2010). The project management minimalist: Just enough PM to rock your projects!
(Laureate custom ed.). Baltimore: Laureate Education, Inc.
Program Project Manager Average Salary. (2013). In PayScale. Retrieved from
http://www.payscale.com/research/US/Job=Program_Project_Manager/Salary
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project
management: Planning, scheduling, and controlling projects. Hoboken, NJ: John Wiley & Sons,
Inc.
Russell, L. (2000). Project management for trainers. Alexandria, VA: ASTD Press.
WK8ProjJohnsonL 6
Back to Table of Contents
Work Breakdown Structure: General Overview Our Nation and Society: Let's Go Camping!
Planning 1. Analyze the learners 2. Write project goals 3. Write learning objectives 4. Approve goals and objectives 5. List all deliverables 6. Set deadlines for deliverables 7. Create Master Schedule 8. List expenses 9. Create Budget
Mockups 1. Develop storyboard 2. Approve storyboard 3. Design learning object settings 4. Design learning object items 5. Design learning object family
members 6. Compile settings, items, and family
members to create learning object 7. Create the website to host the
learning object
Final Product 1. Write narration script 2. Approve narration script 3. Approve learning object 4. Add in narration 5. Write journal prompts 6. Approve journal prompts 7. Add journal prompts 8. Write feedback 9. Approve feedback 10. Add feedback 11. Edit learning object 12. Create facilitator guide 13. Approve facilitator guide 14. Publish learning object
WK8ProjJohnsonL 7
Back to Table of Contents
Work Breakdown Structure: Workload breakdown by teams Our Nation and Society: Let's Go Camping!
Project Manager Writing Team Design Team Panel of Subject Matter and Educational Experts
Planning 1. Analyze the learners 2. Write project goals 3. Write learning objectives 4. Approve goals and objectives 5. List all deliverables 6. Set deadlines for deliverables 7. Create Master Schedule 8. List expenses 9. Create Budget
Mockups 1. Develop storyboard 2. Approve storyboard 3. Design learning object settings 4. Design learning object items 5. Design learning object family
members 6. Compile settings, items, and family
members to create learning object 7. Create the website to host the
learning object
Final Product 1. Write narration script 2. Approve narration script 3. Add in narration 4. Write journal prompts 5. Approve journal prompts 6. Add journal prompts 7. Write feedback 8. Approve feedback 9. Add feedback 10. Edit learning object 11. Approve the learning object 12. Create facilitator guide 13. Approve the facilitator guide 14. Publish learning object
WK8ProjJohnsonL 8
Back to Table of Contents
Work Breakdown Structure: Workload breakdown by teams Our Nation and Society: Let's Go Camping!
Project Manager Responsibilities
1. Write project goals 2. List all deliverables 3. Set deadlines for all
deliverables 4. Create master schedule 5. List expenses 6. Create Budget 7. Final approval
a. Goals b. Learning Objectives c. Learning Object d. Facilitator guide
8. Monitoring team progress
Writing Team Responsibilities
1. Write learning
objectives 2. Develop storyboard 3. Write journal
prompts 4. Write narration
script 5. Write feedback 6. Write facilitator
guide
Design Team Responsibilities
1. Design learning object
settings 2. Design learning object
items 3. Design learning object
family members 4. Compile settings, items,
and family members to create learning object
5. Add narration to learning object
6. Add journal prompts to learning object
7. Create the website to host the learning object
Panel of Subject Matter and Educational Experts
Responsibilities 1. Analyze the learners 2. Final approval
a. Goals b. Learning Objectives c. Storyboard d. Narration Script e. Journal Prompts f. Feedback g. Learning Object h. Facilitator guide
3. Suggestions
WK8ProjJohnsonL 9
Back to Table of Contents
Work Breakdown Structure: Mind map breakdown by teams Our Nation and Society: Let's Go Camping!
WK8ProjJohnsonL 10
Back to Table of Contents
Task Duration
Resource Name: Project
Manager Rate: $40.00/hr
Resource Name:
Writing Team Rate: 3 people
at $20/hr = $60/hr
Resource Name:
Design Team Rate: 4 people
at $30/hr = $120/hr
Resource Name: Panel
of SMEs Rate: 3 people
at $35/hr = $105/hr Misc. Cost TOTAL
Analyze the learners 8 hours $840.00 $840.00Write project goals 2 hours $80.00 $80.00Write learning objectives 3 hours $180.00 $180.00Approve project goals and learning objectives
2 hours
$80.00 $210.00 $290.00List all deliverables 3 hours $120.00 $120.00Set deadlines for deliverables 2 hours $80.00 $80.00Create master schedule 1 hour $40.00 $40.00List expenses 2 hours $80.00 $80.00Create budget 2 hours $80.00 $80.00Adobe Creative Cloud Monthly Plan
N/A$49.99 $49.99
Develop a story board 5 hours $300.00 $300.00
WK8ProjJohnsonL 11
Back to Table of Contents
Task Duration
Resource Name: Project
Manager Rate: $40.00/hr
Resource Name:
Writing Team Rate: 3 people
at $20/hr = $60/hr
Resource Name:
Design Team Rate: 4 people
at $30/hr = $120/hr
Resource Name: Panel
of SMEs Rate: 3 people
at $35/hr = $105/hr Misc. Cost TOTAL
Approve story board 2 hours $210.00 $210.00Design learning object settings 4 hours $480.00 $480.00Design learning object items 4 hours $480.00 $480.00Design learning object family members
4 hours$480.00 $480.00
Compile settings, items, and family members to create learning object
4 hours
$480.00 $480.00Create the website to host the learning object
8 hours
$960.00 $960.00Write narration script 3 hours $180.00 $180.00Approve narration script 1 hour $105.00 $105.00
WK8ProjJohnsonL 12
Back to Table of Contents
Task Duration
Resource Name: Project
Manager Rate: $40.00/hr
Resource Name:
Writing Team Rate: 3 people
at $20/hr = $60/hr
Resource Name:
Design Team Rate: 4 people
at $30/hr = $120/hr
Resource Name: Panel
of SMEs Rate: 3 people
at $35/hr = $105/hr Misc. Cost TOTAL
Add in narration 2 hours $240.00 $240.00Write journal prompts 2 hours $120.00 $120.00Approve journal prompts 1 hour $105.00 $105.00Add journal prompts 1 hour $120.00 $120.00Write feedback 4 hours $240.00 $240.00Approve feedback 2 hours $210.00 $210.00Add feedback 2 hours $240.00 $240.00Edit learning object 8 hours $960.00 $960.00Approve the learning object 4 hours $160.00 $420.00 $580.00Create facilitator guide 3 hours $180.00 $180.00Approve the facilitator guide 1 hour $40.00 $105.00 $145.00Publish learning object 8 hours $960.00 $960.00
GRAND TOTAL $9,614.99
WK8ProjJohnsonL 13
Back to Table of Contents
Activity Project Manager
Design Team Writing Team Panel of SMEs Client Duration (in hours)
Analyze the learners 8 8Write project goals 2 2Write learning objectives
3 3
Approve project goals and learning objectives
2 2 1 2
List all deliverables 3 3Set deadlines for deliverables
2 2
Create master schedule
1 1
List expenses 2 2Create budget 2 2Develop a story 5 5Approve story board 2 2Design learning object settings
4 4
Design learning object items
4 4
Design learning object family members
4 4
Compile settings, items, and family members to create learning object
4 4
Create the website to host the learning object
8 8
Write narration script
3 3
Approve narration script
1 1
Add in narration 2 2
WK8ProjJohnsonL 14
Back to Table of Contents
Activity Project Manager
Design Team Writing Team Panel of SMEs Client Duration (in hours)
Write journal prompts
2 2
Approve journal prompts
1 1
Add journal prompts 1 1Write feedback 4 4Approve feedback 2 2Add feedback 2 2Edit learning object 8 8Approve the learning object
4 4 4 4
Create facilitator guide
3 3
Approve the facilitator guide
1 1 1 1
Publish learning object
8 8
TOTALS (in hours)
19 45 20 21 6 98
WK8ProjJohnsonL 15
Back to Table of Contents
Task Team/Person Responsible
Estimated Duration Start Finish 12/2/13 12/3/13 12/4/13 12/5/13 12/6/13 12/9/13 12/10/13 12/11/13 12/12/13 12/13/13
Analyze the learners
Panel of SMEs
8 hours 12/2/13 12/2/13
Write project goals
Project Manager
2 hours 12/2/13 12/2/13
Write learning objectives Writing Team
3 hours 12/3/13 12/3/13
Approve project goals and learning objectives
Panel of SMEs & Client
2 hours 12/4/13 12/4/13
List all deliverables
Project Manager
3 hours 12/3/13 12/3/13
Set deadlines for deliverables
Project Manager
2 hours 12/3/13 12/3/13
Create master schedule
Project Manager
1 hour 12/3/13 12/3/13
List expenses
Project Manager
2 hours 12/4/13 12/4/13
Create budget
Project Manager
2 hours 12/4/13 12/4/13
Develop a story board Writing Team
5 hours 12/4/13 12/4/13
Approve story board
Panel of SMEs
2 hours 12/5/13 12/5/13
WK8ProjJohnsonL 16
Back to Table of Contents
Task Team/Person Responsible
Estimated Duration Start Finish 12/2/13 12/3/13 12/4/13 12/5/13 12/6/13 12/9/13 12/10/13 12/11/13 12/12/13 12/13/13
Design learning object Design Team
4 hours 12/5/13 12/5/13
Design learning object Design Team
4 hours 12/5/13 12/5/13
Design learning object
Design Team
4 hours 12/6/13 12/6/13
Compile settings, items, and family members Design Team
4 hours 12/6/13 12/6/13
Create the website to host the learning object Design Team
8 hours 12/9/13 12/9/13
Write narration script Writing Team
3 hours 12/5/13 12/5/13
Approve narration script
Panel of SMEs
1 hour 12/6/13 12/6/13
Add in narration Design Team
2 hours 12/10/13 12/10/13
Write journal prompts Writing Team
2 hours 12/6/13 12/6/13
Approve journal prompts
Panel of SMEs
1 hour 12/9/13 12/9/13
Add journal prompts Design Team
1 hour 12/10/13 12/10/13
WK8ProjJohnsonL 17
Back to Table of Contents
Task Team/Person Responsible
Estimated Duration Start Finish 12/2/13 12/3/13 12/4/13 12/5/13 12/6/13 12/9/13 12/10/13 12/11/13 12/12/13 12/13/13
Write feedback Writing Team
4 hours 12/9/13 12/9/13
Approve feedback
Panel of SMEs
2 hours 12/10/13 12/10/13
Add feedback Design Team
2 hours 12/11/13 12/11/13
Edit learning object Design Team
6 hours 12/11/13 12/11/13
Approve the learning object
Project Manager, Panel of SMEs, &
8 hours 12/12/13 12/12/13
Create facilitator guide Writing Team
3 hours 12/12/13 12/12/13
Approve the facilitator guide
Project Manager, Panel of SMEs, &
1 hour 12/13/13 12/13/13
Publish learning object Design Team
8 hours 12/13/13 12/13/13
WK8ProjJohnsonL 18
Back to Table of Contents
Responsibility/Accountability Matrix Task Project Manager Design Team Writing Team Panel of SMEs Client
Analyze the learners R P, A I, S Write project goals P, A I, S Write learning objectives
R P, A R I, S
Approve project goals and learning objectives
P, A, S P, I P, I, S
List all deliverables P, A R Set deadlines for deliverables
P, A
Create master schedule
P, A
List expenses P, A R, S Create budget P, A R, S Develop a story board P, A Approve story board A, R, S P, I Design learning object settings
P, A
Design learning object items
P, A
Design learning object family members
P, A
Compile settings, items, and family members to create learning object
P, A
Create the website to host the learning object
P, A
Write narration script P, A
WK8ProjJohnsonL 19
Back to Table of Contents
Activity Project Manager Design Team Writing Team Panel of SMEs Client Approve narration script
A, R, S P, I
Add in narration P, A Write journal prompts P, A Approve journal prompts
A, R, S P, I
Add journal prompts P, A Write feedback P, A Approve feedback P, I Add feedback P, A Edit learning object R P, A Approve the learning object
P, A, R, S P, I I, R, S
Create facilitator guide
P, A
Approve the facilitator guide
P, A, R, S P, I I, S
Publish learning object
A, R, S P, A I I, R, S
WK8ProjJohnsonL 20
Back to Table of Contents
Activity Baseline Start
Actual Start
Baseline Finish
Actual Finish
Baseline Duration
Actual Duration
Remaining Variance
Baseline Budget
Actual Cost Difference
Analyze the learners
12/2/13 12/2/13 12/2/13 12/2/13 8 hours 12 hours (4) hours $840.00 $1,260.00 ($420.00)
Write project goals 12/2/13 12/2/13 12/2/13 12/2/13 2 hours 3 hours (1) hour $80.00 $120.00 ($40.00)
Write learning objectives
12/3/13 12/3/13 12/3/13 12/3/13 3 hours 3 hours 0 $180.00 $180.00 $0.00
Approve project goals and learning objectives
12/4/13 12/4/13 12/4/13 12/4/13 2 hours 1 hour 1 hour $290.00 $145.00 $145.00
List all deliverables
12/3/13 12/3/13 12/3/13 12/3/13 3 hours 4 hours (1) hour $120.00 $160.00 ($40.00)
Set deadlines for deliverables
12/3/13 12/3/13 12/3/13 12/3/13 2 hours 1 hour 1 hour $80.00 $40.00 $40.00
Create master schedule
12/3/13 12/3/13 12/3/13 12/3/13 1 hour 1 hour 0 $40.00 $40.00 $0.00
List expenses 12/4/13 12/4/13 12/4/13 12/4/13 2 hours 3 hours (1) hour $80.00 $120.00 ($40.00)
Create budget
12/4/13 12/4/13 12/4/13 12/4/13 2 hours 1 hour 1 hour $80.00 $40.00 $40.00
Develop a story board
12/4/13 12/4/13 12/4/13 12/4/13 5 hours 6 hours (1) hour $300.00 $360.00 ($60.00)
Approve story board
12/5/13 12/5/13 12/5/13 12/5/13 2 hours 1 hour 1 hour $210.00 $105.00 $105.00
Design learning object settings
12/5/13 12/5/13 12/5/13 12/5/13 4 hours 6 hours (2) hours $480.00 $720.00 ($240.00)
Design learning object items
12/5/13 12/5/13 12/5/13 12/5/13 4 hours 3 hours 1 hour $480.00 $360.00 $120.00
WK8ProjJohnsonL 21
Back to Table of Contents
Activity Baseline Start
Actual Start
Baseline Finish
Actual Finish
Baseline Duration
Actual Duration
Remaining Variance
Baseline Budget
Actual Cost Difference
Design learning object family members
12/6/13 12/6/13 12/6/13 12/6/13 4 hours 3 hours 1 hour $480.00 $360.00 $120.00
Compile settings, items, and family members to create learning object
12/6/13 12/6/13 12/6/13 12/6/13 4 hours 4 hours 0 $480.00 $480.00 $0.00
Create the website to host the learning object
12/9/13 12/9/13 8 hours $960.00 $960.00
Write narration script
12/5/13 12/5/13 3 hours $180.00 $180.00
Approve narration script
12/6/13 12/6/13 1 hour $105.00 $105.00
Add in narration
12/10/13 12/10/13 2 hours $240.00 $240.00
Write journal prompts 12/6/13 12/6/13 2 hours $120.00 $120.00
Approve journal prompts
12/9/13 12/9/13 1 hour $105.00 $105.00
Add journal prompts
12/10/13 12/10/13 1 hour $120.00 $120.00
Write feedback
12/9/13 12/9/13 4 hours $240.00 $240.00
Approve feedback
12/10/13 12/10/13 2 hours $210.00 $210.00
WK8ProjJohnsonL 22
Back to Table of Contents
Activity Baseline Start
Actual Start
Baseline Finish
Actual Finish
Baseline Duration
Actual Duration
Remaining Variance
Baseline Budget
Actual Cost Difference
Add feedback
12/11/13 12/11/13 2 hours $240.00 $240.00
Edit learning object 12/11/13 12/11/13 6 hours $720.00 $720.00
Approve the learning object
12/12/13 12/12/13 8 hours $580.00 $580.00
Create facilitator guide
12/12/13 12/12/13 3 hours $180.00 $180.00
Approve the facilitator guide
12/13/13 12/13/13 1 hour $145.00 $145.00
Publish learning object
12/13/13 12/13/13 8 hours $960.00 $960.00
TOTAL $9,115.00 $4,385.00 $4,730.00
WK8ProjJohnsonL 23
Back to Table of Contents
Who Creates & Publishes Receiver What Information When (How Often) How (Form/Medium)
Panel of SMEs Project Manager, Writing Team, Design Team Learner analysis Once (morning of Tues., Dec.
3)
Face-to-face presentation. A visual aid must be created to show and share as a reference throughout the project. Upload to a shared Google Drive folder. If a face-to-face conference isn't a possibility, we will video conference with all teams.
Project Manager Panel of SMEs, Writing Team, Design Team Project Goals Once (morning of Tues., Dec.
3)
Face-to-face presentation. A visual aid must be created to show and share as a reference throughout the project. Upload to a shared Google Drive folder. If a face-to-face conference isn't a possibility, we will video conference with all teams.
Writing Team Project Manager, Panel of SMEs, Client Learning Objectives Once (morning of Wed., Dec.
4)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Design Team, Client
Approval of project goals and learning objectives Once (Wed., Dec. 4)
E-mail with finalized goals and learning objectives. Also, create a document will be stored in shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Design Team, Client
List of all deliverables and deadlines
Once (morning of Wed., Dec. 4)
Face-to-face presentation with the list created in the shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Design Team Project's master schedule Once (morning of Wed., Dec.
4)
Face-to-face presentation with the schedule created in the shared Google Drive folder.
WK8ProjJohnsonL 24
Back to Table of Contents
Who Creates & Publishes Receiver What Information When (How Often) How (Form/Medium)
Project Manager Client Estimated project budget Once (morning of Thurs., Dec. 5)
Face-to-face meeting. Must show Excel file of projected budget and have rationalizations prepared. (Note: Do not store this file in the shared Google Dirve folder.)
Writing Team Project Manager, Panel of SMEs, Design Team Project story board Once (morning of Thurs., Dec.
5)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Design Team
Approval of project story board Once (Thurs., Dec. 5) E-mail confirmation of approval.
Design Team Project Manager Summary of learning object settings & items design Once (morning of Fri., Dec. 6) E-mail summarizing progress.
Project Manager Panel of SMEs, Writing Team, Design Team, Client Weekly Progress Report Every Monday
E-mail bulleted point report of progress. Highlight good things in green and areas to remain cautious in yellow. Upload report to the shared Google Drive folder for future reference.
Design Team Project Manager
Summary of the compiling of the settings, items, and family members to create the learning object
Once (Mon., Dec. 9) E-mail summarizing progress.
Design Team Project ManagerSummary of the website created to host the learning object
Once (Tues., Dec. 10) E-mail website link with any necessary instructions or questions.
Writing Team Project Manager, Panel of SMEs Narration script Once (Thurs., Dec. 5)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
WK8ProjJohnsonL 25
Back to Table of Contents
Who Creates & Publishes Receiver What Information When (How Often) How (Form/Medium)
Project Manager Panel of SMEs, Writing Team, Design Team Approval of narration script Once (Fri., Dec. 6) E-mail confirmation of approval.
Writing Team Project Manager, Panel of SMEs Journal prompts Once (Fri., Dec. 6)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Design Team Approval of journal prompts Once (Mon., Dec. 9) E-mail confirmation of approval.
Design Team Project Manager Addition of narration and journal prompts Once (Tues., Dec. 10) E-mail summarizing progress.
Writing Team Project Manager, Panel of SMEs Learning object feedback Once (Mon., Dec. 9)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager Writing Team, Design Team Approval of learning object feedback Once (Tues., Dec. 10) E-mail confirmation of approval.
Design Team Project ManagerSummary of final learning object with added feedback and editing
Once (Wed., Dec. 11) E-mail summarizing progress.
Project Manager Panel of SMEs, Writing Team, Design Team
Approval of the learning object Once (Thurs., Dec. 12) E-mail confirmation of approval.
Writing Team Project Manager, Panel of SMEs Facilitator guide Once (Thurs., Dec. 12)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager Panel of SMEs, Writing Team, Client
Approval of the facilitator guide Once (Fri., Dec. 13) E-mail confirmation of approval.
Design Team Project Manager, Writing Team, Client
Notification of the publication of the finalized learning object Once (Fri., Dec. 13) Face-to-face meeting. Must
deliver learning object.
WK8ProjJohnsonL 26
Back to Table of Contents
2 3 4 5 6
Learner analysis Learning Objectives Estimated project budgetSummary of learning object settings & items design
Project Goals Approval of project goals and learning objectives Project story board Approval of narration
script
List of all deliverables and deadlines
Approval of project story board Journal prompts
Project's master schedule Narration script
9 10 11 12 13
Weekly Progress ReportSummary of the website created to host the learning object
Summary of final learning object with added feedback and editing
Approval of the learning object
Approval of the facilitator guide
Summary of the compiling of the settings, items, and family members to create the learning object
Addition of narration and journal prompts Facilitator guide
Notification of the publication of the finalized learning object
Approval of journal prompts
Approval of learning object feedback
Learning object feedback
Calendar Key: Project ManagerWriting TeamDesign Team
Panel of SMEs
December
WK8ProjJohnsonL 27
Back to Table of Contents
Who Creates & Publishes Receiver
What Information
When (How Often) How (Form/Medium) Completed Notes
Panel of SMEs
Project Manager, Writing Team, Design Team
Learner analysis
Once (morning of Tues., Dec. 3)
Face-to-face presentation. A visual aid must be created to show and share as a reference throughout the project. Upload to a shared Google Drive folder. If a face-to-face conference isn't a possibility, we will video conference with all teams.
Yes
Meeting held Tuesday at 10:00 a.m. All present. 45 min. long. PPT saved as "Learner Analysis" in Google Drive.
Project Manager
Panel of SMEs, Writing Team, Design Team
Project GoalsOnce (morning of Tues., Dec. 3)
Face-to-face presentation. A visual aid must be created to show and share as a reference throughout the project. Upload to a shared Google Drive folder. If a face-to-face conference isn't a possibility, we will video conference with all teams.
Yes
Meeting held as part of learner analysis meeting. 15 min. long. Document saved as "Project Goals" in Google Drive.
Writing Team
Project Manager, Panel of SMEs, Client
Learning Objectives
Once (morning of Wed., Dec. 4)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
YesReceived Wed., Dec. 4. Subject: "Learning Objectives" (Document has the same title.)
Project Manager
Panel of SMEs, Writing Team, Design Team, Client
Approval of project goals and learning objectives
Once (Wed., Dec. 4)
E-mail with finalized goals and learning objectives. Also, create a document will be stored in shared Google Drive folder.
Yes
Done Wed., Dec. 4 at 12:00 p.m. Subject: "Project Goals & Learning Objectives" (Document has the same title.)
Project Manager
Panel of SMEs, Writing Team, Design Team, Client
List of all deliverables and deadlines
Once (morning of Wed., Dec. 4)
Face-to-face presentation with the list created in the shared Google Drive folder.
Yes
Meeting held Wed. morning at 10:00 a.m. Gave everyone a handout of "Let's Go Camping Deliverables" and saved the document with same name in Google Drive. 15 min. long
WK8ProjJohnsonL 28
Back to Table of Contents
Project Manager
Panel of SMEs, Writing Team, Design Team
Project's master schedule
Once (morning of Wed., Dec. 4)
Face-to-face presentation with the schedule created in the shared Google Drive folder.
Yes
Included in above meeting. Gave everyone a handout of "Let's Go Camping Schedule" and saved the document with same name in Google Drive. 15 min. long.
Project Manager Client Estimated
project budget
Once (morning of Thurs., Dec. 5)
Face-to-face meeting. Must show Excel file of projected budget and have rationalizations prepared. (Note: Do not store this file in the shared Google Dirve folder.)
Yes
Met Thurs. at 9:00 a.m. All elements approved. Saved as "Let's Go Camping Budget" on my (Gordon) laptop.
Writing Team
Project Manager, Panel of SMEs, Design Team
Project story board
Once (morning of Thurs., Dec. 5)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Yes
Received Thurs. at 9:00 a.m. Subject: "Let's Go Camping Story Board" (Document has same title.)
Project Manager
Panel of SMEs, Writing Team, Design Team
Approval of project story board
Once (Thurs., Dec. 5) E-mail confirmation of approval. Yes Team e-mailed at 2:00 p.m.
Design Team Project Manager
Summary of learning object settings & items design
Once (morning of Fri., Dec. 6) E-mail summarizing progress. Yes
Received Fri. at 9:30 a.m. Subject: "Learning Object Design Team Progress"
Project Manager
Panel of SMEs, Writing Team, Design Team, Client
Weekly Progress Report
Every Monday
E-mail bulleted point report of progress. Highlight good things in green and areas to remain cautious in yellow. Upload report to the shared Google Drive folder for future reference.
WK8ProjJohnsonL 29
Back to Table of Contents
Design Team Project Manager
Summary of the compiling of the settings, items, and family members to create the learning object
Once (Mon., Dec. 9) E-mail summarizing progress.
Design Team Project Manager
Summary of the website created to host the learning object
Once (Tues., Dec. 10)
E-mail website link with any necessary instructions or questions.
Writing TeamProject Manager, Panel of SMEs
Narration script Once (Thurs., Dec. 5)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager
Panel of SMEs, Writing Team, Design Team
Approval of narration script
Once (Fri., Dec. 6) E-mail confirmation of approval.
Writing TeamProject Manager, Panel of SMEs
Journal prompts
Once (Fri., Dec. 6)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager
Panel of SMEs, Writing Team, Design Team
Approval of journal prompts
Once (Mon., Dec. 9) E-mail confirmation of approval.
WK8ProjJohnsonL 30
Back to Table of Contents
Design Team Project Manager
Addition of narration and journal prompts
Once (Tues., Dec. 10) E-mail summarizing progress.
Writing TeamProject Manager, Panel of SMEs
Learning object feedback
Once (Mon., Dec. 9)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager
Writing Team, Design Team
Approval of learning object feedback
Once (Tues., Dec. 10) E-mail confirmation of approval.
Design Team Project Manager
Summary of final learning object with added feedback and editing
Once (Wed., Dec. 11) E-mail summarizing progress.
Project Manager
Panel of SMEs, Writing Team, Design Team
Approval of the learning object
Once (Thurs., Dec. 12) E-mail confirmation of approval.
Writing TeamProject Manager, Panel of SMEs
Facilitator guide
Once (Thurs., Dec. 12)
E-mail a link of a Google Document that was created in the shared Google Drive folder.
Project Manager
Panel of SMEs, Writing Team, Client
Approval of the facilitator guide
Once (Fri., Dec. 13) E-mail confirmation of approval.
Design Team
Project Manager, Writing Team, Client
Notification of the publication of the finalized learning object
Once (Fri., Dec. 13)
Face-to-face meeting. Must deliver learning object.
WK8ProjJohnsonL 31
Back to Table of Contents
Task Team/Person Responsible
Estimated Duration
Actual Duration
Estimated Start
Estimated Finish
Actual Start
Actual Finish
Approval Needed From
Date of Approval
Sign-off Needed From
Date of Sign-off
Analyze the learners Panel of SMEs
8 hours 12/2/13 12/2/13 Project Manager, Client Client
Write project goalsProject Manager
2 hours 12/2/13 12/2/13Client Client
Write learning objectivesWriting Team
3 hours 12/3/13 12/3/13 Project Manager, Client Client
List all deliverablesProject Manager
3 hours 12/3/13 12/3/13Client Client
Set deadlines for deliverables Project Manager
2 hours 12/3/13 12/3/13Client Client
Create master scheduleProject Manager
1 hour 12/3/13 12/3/13Client Client
List expensesProject Manager
2 hours 12/4/13 12/4/13Client Client
Create budgetProject Manager
2 hours 12/4/13 12/4/13Client Client
Develop a story boardWriting Team
5 hours 12/4/13 12/4/13Panel of SMEs
Project Manager
Design learning object settings Design Team
4 hours 12/5/13 12/5/13Project Manager
Project Manager
Design learning object items Design Team
4 hours 12/5/13 12/5/13Project Manager
Project Manager
Design learning object family members Design Team
4 hours 12/6/13 12/6/13Project Manager
Project Manager
Compile settings, items, and family members to create learning object Design Team
4 hours 12/6/13 12/6/13
Project ManagerProject Manager
Create the website to host the learning object Design Team
8 hours 12/9/13 12/9/13Project Manager
Project Manager
Write narration scriptWriting Team
3 hours 12/5/13 12/5/13Panel of SMEs
Project Manager
Add in narrationDesign Team
2 hours 12/10/13 12/10/13Project Manager
Project Manager
Write journal promptsWriting Team
2 hours 12/6/13 12/6/13Panel of SMEs
Project Manager
Add journal promptsDesign Team
1 hour 12/10/13 12/10/13Project Manager
Project Manager
WK8ProjJohnsonL 32
Back to Table of Contents
Task Team/Person Responsible
Estimated Duration
Actual Duration
Estimated Start
Estimated Finish
Actual Start
Actual Finish
Approval Needed From
Date of Approval
Sign-off Needed From
Date of Sign-off
Write feedbackWriting Team
4 hours 12/9/13 12/9/13Panel of SMEs
Project Manager
Add feedbackDesign Team
2 hours 12/11/13 12/11/13Project Manager
Project Manager
Edit learning object
Design Team
6 hours 12/11/13 12/11/13 Project Manager, Panel of SMEs, Client Client
Create facilitator guide
Writing Team
3 hours 12/12/13 12/12/13 Project Manager, Panel of SMEs, Client Client
Publish learning objectDesign Team
8 hours 12/13/13 12/13/13Project Manager Client
WK8ProjJohnsonL 33
Back to Table of Contents
Project Manager's "Let's Go Camping" Checklist:
Tasks to do:
Task Start Date Due Date Approval From: Sign-off From: Write project goals
12/2/13 12/2/13 Client Client
List all deliverables
12/3/13 12/3/13 Client Client
Set deadlines for deliverables
12/3/13 12/3/13 Client Client
Create master schedule
12/3/13 12/3/13 Client Client
Approve project goals and learning objectives
12/4/13 12/4/13 Client Client
List expenses 12/4/13 12/4/13 Client Client Create budget 12/4/13 12/4/13 Client Client Approve the learning object
12/12/13 12/12/13 Client Client
Approve the facilitator guide
12/13/13 12/13/13 Client Client
Items to approve: Items to sign-off:
Items you must Approve
Date of Approval
Items you must Sign-off on
Date of Sign-off Notes
Learner analysis Story board Learning objectives
Learning object setting
Learning object setting
Learning object camping items
Learning object camping items
Learning object family members
Learning object family members
Compilation of learning object
Compilation of learning object
Website for learning object
Website for learning object
Narration script
Addition of narration in the
Addition of narration in the
WK8ProjJohnsonL 34
Back to Table of Contents
learning object learning object Addition of journaling prompts in learning object
Journal prompts
Addition of feedback in learning object
Addition of journaling prompts in learning object
Editing of learning object
Feedback
Facilitator Guide Addition of feedback in learning object
Publishing the final learning object
WK8ProjJohnsonL 35
Back to Table of Contents
Writing Team's "Let's Go Camping" Checklist:
Tasks to do:
Task Start Date Due Date Approval From: Sign-off From: Write learning objectives
12/3/13 12/3/13 Project Manager, Client
Client
Develop a story board
12/4/13 12/4/13 Panel of SMEs Project Manager
Write narration script
12/5/13 12/5/13 Panel of SMEs Project Manager
Write journal prompts
12/6/13 12/6/13 Panel of SMEs Project Manager
Write feedback 12/9/13 12/9/13 Panel of SMEs Project Manager Create facilitator guide
12/12/13 12/12/13 Project Manager, Panel of SMEs, Client
Client
WK8ProjJohnsonL 36
Back to Table of Contents
Design Team's "Let's Go Camping" Checklist:
Tasks to do:
Task Start Date Due Date Approval From: Sign-off From: Design learning object settings
12/5/13 12/5/13 Project Manager Project Manager
Design learning object items
12/5/13 12/5/13 Project Manager Project Manager
Design learning object family members
12/6/13 12/6/13 Project Manager Project Manager
Compile settings, items, and family members to create learning object
12/6/13 12/6/13 Project Manager Project Manager
Create the website to host the learning object
12/9/13 12/9/13 Project Manager Project Manager
Add in narration 12/10/13 12/10/13 Project Manager Project Manager Add journal prompts
12/10/13 12/10/13 Project Manager Project Manager
Add feedback 12/11/13 12/11/13 Project Manager Project Manager Edit learning object
12/11/13 12/11/13 Project Manager, Panel of SMEs, Client
Client
Publish learning object
12/13/13 12/13/13 Project Manager Client
WK8ProjJohnsonL 37
Back to Table of Contents
Panel of SMEs' "Let's Go Camping" Checklist:
Tasks to do:
Task Start Date Due Date Approval From: Sign-off From: Analyze the learners
12/2/13 12/2/13 Project Manager, Client
Client
Approve project goals and learning objectives
12/4/13 12/4/13 N/A Client
Approve story board
12/5/13 12/5/13 N/A Project Manager
Approve narration script
12/6/13 12/6/13 N/A Project Manager
Approve feedback
12/10/13 12/10/13 N/A Project Manager
Approve the learning object
12/12/13 12/12/13 N/A Client
Approve the facilitator guide
12/13/13 12/13/13 N/A Client
WK7ProjJohnsonL 36
Back to Table of Contents
Client's "Let's Go Camping" Checklist:
Tasks to do:
Task Description Due Date Notes Approval & Sign-off Learner analysis 12/2/13 Approval & Sign-off Project goals and
learning objectives 12/2/13
Approval & Sign-off List of deliverables 12/3/13 Approval & Sign-off Project schedule 12/3/13 Approval & Sign-off Expense list 12/4/13 Approval & Sign-off Project budget 12/4/13 Approval & Sign-off Approve the
learning object 12/11/13
Approval & Sign-off Approve the facilitator guide
12/12/13
Approval & Sign-off Final learning object 12/13/13
WK8ProjJohnsonL 39
Back to Table of Contents