leslie barns & connection track - ttc...as of december 2, 2014 . construction liaison group #14...

24
LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #14 December 4, 2014 1 Construction Liaison Group #14 – Dec 4 2014

Upload: others

Post on 29-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

LESLIE BARNS & CONNECTION TRACK

Construction Liaison Group Meeting #14 December 4, 2014

1Construction Liaison Group #14 – Dec 4 2014

Page 2: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

OVERVIEW

2 Construction Liaison Group #14 – Dec 4 2014

• Introduction • Works to Date • Action Items – Follow Up • Community Feedback • Construction Phasing Update

Page 3: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

3 Construction Liaison Group #14 – Dec 4 2014

CLG CODE OF CONDUCT All those attending CLG meetings will be required to adhere to a Code of Conduct.

• Participants should be courteous, listen to others and respect the opinions of others

• Participants should not request that items outside of the mandate of the CLG be discussed at meetings.

• Participants should participate fully in discussions but not dominate the discussion

• Participants should speak one at a time and not interrupt other participants while they are speaking

• To ensure equal participation, participants wishing to make comments should do so through the facilitator . Participants should remain focused on the set agenda topics; participants wishing to hold private discussions shall move outside of the meeting room while the meeting is in progress

• Participants shall not use foul language

• Participants shall not make derogatory comments based on gender, race, ethnicity, religion, sexual orientation or disability

• Personal insults toward other CLG reps and/or to the third party facilitator and TTC staff will not be tolerated

Page 4: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

4 Construction Liaison Group #14 – Dec 4 2014

WORKS TO DATE

Page 5: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

WORKS TO DATE – LESLIE STREET

5 Construction Liaison Group #14 – Dec 4 2014

New pole installation at Queen and Leslie

Page 6: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

WORKS TO DATE – LESLIE STREET

6 Construction Liaison Group #14 – Dec 4 2014

Concreting the road base on Leslie Street at Mosley.

As early as December 6, Leslie Street will be open to vehicular traffic from Eastern Avenue to the Plaza accesses.

Page 7: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #12

7 Construction Liaison Group #14 – Dec 4 2014

Page 8: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #13

ACTION ITEM NO. 1: Provide reports to Marigold Gardens of vibration date from monitors at 77 Leslie RESPONSE: Reports from the vibration monitor located at 77 Leslie* were provided to the Marigold. *This monitor has been relocated to 73 Leslie due to space and safety constraints

ACTION ITEM NO. 2: Provide vibration report from previous complaint with explanation/summary for 30 Leslie RESPONSE: Report sent to resident

8 Construction Liaison Group #14 – Dec 4 2014

Page 9: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #13

ACTION ITEM NO. 3: Investigate duct cleaning for homes on Leslie Street RESPONSE: Homes that front the construction on Leslie Street will be offered reimbursement for one-time duct cleaning as requested.

ACTION ITEM NO. 4: Clarify with Project Team when garage cleaning at Marigold Gardens will take place (to clean debris left over from flooding) RESPONSE: Project team has approved reimbursement to Marigold Gardens for garage cleaning required (as result of underground garage flooding from temporary watermain).

9 Construction Liaison Group #14 – Dec 4 2014

Page 10: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #13

ACTION ITEM NO. 5: Watering/sweeping of streets at Leslie/Lake Shore, Eastern/Leslie and Queen/Leslie RESPONSE: Watering of the streets has been done following CLG and will continue on an as-needed basis and at request of CLOs and residents

ACTION ITEM NO. 6: Send notice to residents on Leslie, Mosley on project update, expected completion dates for Mosley to Lake Shore. RESPONSE: Notice sent to residents south of Eastern in late November. Notice for residents north of Eastern will be provided once work details are confirmed.

10 Construction Liaison Group #14 – Dec 4 2014

Page 11: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #13

ACTION ITEM NO. 7:Pomerleau to request their sub-contractors to observe 2 minute of silence for Remembrance Day RESPONSE: TTC and Pomerleau staff, as well as majority of sub-contractors observed 2 minutes of silence on Remembrance Day

ACTION ITEM NO. 8: Provide a sequencing plan of lane occupations for streetscaping activities in 2015 RESPONSE: The contractor will not block both sidewalks at the same time, as per their contractual agreement. Their sequencing plan is not confirmed yet and will be shared as soon as available (Action Item carried forward)

11 Construction Liaison Group #14 – Dec 4 2014

Page 12: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

ACTION ITEMS – FROM CLG #13

ACTION ITEM NO. 9: Investigate plan of curb height at Commissioners (at North Service Road) RESPONSE: The design shows a depressed curb for the full width of the cross walk and bike crossing at North Service Road (the east leg of Commissioners/Leslie intersection).

12 Construction Liaison Group #14 – Dec 4 2014

Page 13: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

Construction Liaison Group #14 – Dec 4 2014 13

COMMUNITY FEEDBACK LOG (FROM OCT 30 TO DEC 4)

TOPIC CONCERN ACTION

Dust/Noise/ Vibration

Noise from overnight work heard at 4 a.m. TTC track team completed work on the tracks at Mosley and Leslie Street. Track work is done overnight to prevent warping of the track.

Vibrations felt from interior units of the Marigold Gardens

CLOs offered to have inspectors visit these units. Concern speaks to need to recognize more fullsome effects of construction to adjacent buildings and lessons learned. (e.g. study phase did not recognize all units of Marigold being effected, definition needs revisiting, also given impacts to Marigold parking garage which effects full buildng)

Blue mesh dust mitigation was removed from the the gate directly adjacent to Marigold Gardens Leslie Street main gate and from the homes across the street on the West side of Leslie

Mesh was removed due to high winds (mesh can create a sail that can cause the fencing to become unstable causing a safety hazard). The contractor was requested to re-install ASAP after winds no longer an issue. It was reinstalled on Dec 3.

Page 14: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

Construction Liaison Group #14 – Dec 4 2014 14

COMMUNITY FEEDBACK LOG (FROM OCT 30 TO DEC 4)

TOPIC CONCERN ACTION Communications Notices provided to the Marigold regarding a

storm sewer connection to their building included instructions to residents on access points within the condo’s property lines.

The CLOs provided notice to the residents regarding this work as soon as it was received and provided instructions on which entry points were accessible in effort to be helpful. In future, notices will only detail what accesses are closed as a result of construction activities due to liability issues. Approval must be given by Condo Board reps in future. Lesson learned!

Other Water shut to Brick Court unexpectedly during a scheduled shutoff for other streets.

A planned water shut was communicated to residents of Leslie (between Sears and Memory Lane) however the shut impacted residents on Brick court. Water bottles were delivered ASAP and water was restored by 2 p.m.

Bag covering a one-way sign at Laing and Queen is being removed (not by contractor) despite the street being two-way from Queen to Memory Lane. Complaint from businesses and residents.

The City granted permission to the contractor to have the entire sign removed to resolve. The sign will be reinstalled once access from Leslie Street to the laneways is restored.

Page 15: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

Construction Liaison Group #14 – Dec 4 2014 15

COMMUNITY FEEDBACK LOG (FROM OCT 30 TO DEC 4)

TOPIC CONCERN ACTION Leslie Barns Noise Wall

Is the grey wall around the Leslie Barns permanent or is there more to complete? It looks daunting as is.

The final wall will have colourful decorative panels designed by Brown and Storey Architects, with viewing panels. The entire area will be landscaped around it. The wall is a sound barrier and a Ministry of Environment requirement to ensure the facility meets noise limits.

Page 16: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

CONSTRUCTION PHASING

16 Construction Liaison Group #14 – Dec 4 2014

Page 17: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

17

PLANNED CONSTRUCTION PHASING As of DECEMBER 2, 2014

Construction Liaison Group #14 – Dec 4 2014

Two-way traffic from Commissioners to Lake Shore reopened

Leslie between Lake Shore and plazas closed for track installation to early December

Road reconstruction and concrete pouring of Leslie from Mosley to Eastern

Closure from north of Eastern to Queen – access to Marigold Condo parking garage from Eastern and The Duke parking lot from Queen

Pole installation – single curb lane closures

Page 18: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

18 Construction Liaison Group #14 – Dec 4 2014

PLANNED CONSTRUCTION PHASING DECEMBER 6, 2014

Track, road and OCS installation

Lanes on Leslie from south of the plaza driveways to Eastern Avenue restored. Intermittent lane closure expected for OCS pole work.

Utility Work (sewer chamber) and service connections

Page 19: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

PLANNED CONSTRUCTION PHASING

19

BY DECEMBER 17, 2014*

Two lanes of Leslie from Lake Shore Blvd to Plaza driveway opened

*due to weather, two lanes will be restored by Dec. 17

Intermittent lane closure for OCS pole work.

Construction Liaison Group #14 – Dec 4 2014

Track work and roadwork for Marigold parking access

Page 20: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

PLANNED CONSTRUCTION PHASING

20

BY DECEMBER 23 2014

Intermittent lane closure for OCS pole work.

Construction Liaison Group #14 – Dec 4 2014

Four lanes of Leslie from Lake Shore Blvd to Plaza driveway opened Intermittent lane closure for OCS pole work.

Two-Four lanes from Eastern to Marigold parking driveway

Temporary sidewalk on east side available

North pedestrian crossing reinstated

Page 21: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

PLANNED CONSTRUCTION PHASING

21

JANUARY to FEBRUARY 2015

Construction Liaison Group #14 –Dec 4 2014

Track work and road work. Utility work on West side

Intermittent lane closure for OCS pole work.

Page 22: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

PLANNED CONSTRUCTION PHASING

22

MARCH to APRIL 2015 Track, road and OCS installation

Lanes on Leslie Street north of Lake Shore Blvd restored to full capacity except for intermittent lane closure

Streetscaping and sidewalk work on Leslie Street – in various locations

Construction Liaison Group #14 –Dec 4 2014

Track installation south of Lake Shore and service connections

Track and road work at intersection

Utility work on west side. Two lanes and accesses maintained

Page 23: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

23

Final streetscaping– various locations

Centre medians on Lake Shore reconstructed

Construction Liaison Group #14 – Dec 4 2014

Final road paving

MAY 2015

PLANNED CONSTRUCTION PHASING

Page 24: LESLIE BARNS & CONNECTION TRACK - TTC...As of DECEMBER 2, 2014 . Construction Liaison Group #14 – Dec 4 2014 Twoay traffic from -w Commissioners to Lake Shore reopened . Leslie between

END

24 Construction Liaison Group #14 – Dec 4 2014