CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5 CHAPTER 6 CHAPTER 7 CHAPTER 8 CHAPTER 9 CHAPTER 10 Design of Pile Caps 10.1 Introduction A pile cap is defined as a concrete block cast on the head of a group of piles, to transmit the load from the structure to the group of piles. Generally, pile cap transfers the load form the structures to a pile group, then the load further transfers to firm soil. External pressures on a pile are likely to be greatest near the ground surface. Ground stability increases with depth and pressure. The top of the pile therefore, is more vulnerable to movement and stress than the base of the pile. Pile caps are thus incorporated in order to tie the pile heads together so that individual pile movement and settlement is greatly reduced. Thus stability of the pile group is greatly increased. The functions of a pile cap are: 1. To distribute a single load equally over the pile group and thus over a greater area of bearing potential, 2. To laterally stabilise individual piles thus increasing overall stability of the group. And 3. To provide the necessary combined resistance to stresses set up by the superstructure and/or ground movement.

Upload: nelsonsainz

Post on 11-Dec-2015

246 views

Category:

Documents


1 download

DESCRIPTION

Chapter-1

TRANSCRIPT

Page 1: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 1/16

CHAPTER 1

CHAPTER 2

CHAPTER 3

CHAPTER 4

CHAPTER 5 CHAPTER 6

CHAPTER 7

CHAPTER 8

CHAPTER 9

CHAPTER 10

Design of Pile Caps

10.1 Introduction

A pile cap is defined as a concrete block cast on the head of a group of piles, totransmit the load from the structure to the group of piles. Generally, pile captransfers the load form the structures to a pile group, then the load furthertransfers to firm soil.

External pressures on a pile are likely to be greatest near the ground surface.Ground stability increases with depth and pressure. The top of the piletherefore, is more vulnerable to movement and stress than the base of the pile.Pile caps are thus incorporated in order to tie the pile heads together so thatindividual pile movement and settlement is greatly reduced. Thus stability of thepile group is greatly increased.

The functions of a pile cap are:

1. To distribute a single load equally over the pile group and thus over agreater area of bearing potential,

2. To laterally stabilise individual piles thus increasing overall stability ofthe group. And

3. To provide the necessary combined resistance to stresses set up by thesuperstructure and/or ground movement.

Page 2: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 2/16

Pile caps are thick slabs used to tie

a group of piles together to support

and transmit column loads to the piles.

10.2 Pile Cap Arrangement

Spacing of the piles in the pile group

The following should be considered when determining the spacing of the piles:

1. Overall cost of the foundation

2. Nature of the ground

3. Pile behaviour in the group

4. Resulting possible heave or compaction of ground causing damage toadjacent structures

5. Cost of pile cap

6. Size and effective length of ground beam

7. Type and size of pile

Page 3: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 3/16

Piles should be placed in a suitable arrangement so that the spacingbetween piles ranges from (2­3) D (pile diameter) in case of isolated pilecaps and (2­6) D in case of rafts supported on piles.

The C.G. of piles should be placed as far as possible in the C.G. of loadstransmitted from the structure to the group of piles.

In the case of presence of neighbors, piles should be away from theproperty line by a distance not less than D or as the pile installationmethod requires.

The projection of the pile cap should be 10­15 cm.

Initial Layout:The simplest pile layout is one without batter piles. Such a layout should be usedif the magnitude of lateral forces is small. Since all piles do not carry an equalportion of the load, axial pile capacity can be reduced to 70 percent of thecomputed value to provide a good starting point to determine an initial layout.In this case, the designer begins by dividing the largest vertical load on thestructure by the reduced pile capacity to obtain the approximate number of pile.If there are large applied lateral forces, then batter piles are usually required.Piles with flat batters 2.5 (V) to 1 (H), provide greater resistance to lateral loadsand the less resistance to vertical loads. Piles with steep batters 5 (V) to 1 (H)provide greater vertical resistance and less lateral resistance.

Final Layout:

After the preliminary layout was developed remaining load cases should beinvestigated and the layout revised to provide an efficient layout. The goalshould be to produce a pile layout in which most piles are loaded as near tocapacity as practical for the critical loading cases with tips located at the sameelevation for the various pile groups within a given monolith. Adjustments to theinitial layout by the addition deletion, or relocation of piles within the layout gridsystem may be required. Generally, revisions to the pile batters will not berequired because they were optimized during the initial pile layout. The designeris cautioned that the founding of piles at various elevations or in different stratamay result in monolith instability and differential settlement.

Typical Arrangement of Piles

Page 4: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 4/16

Page 5: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 5/16

• Requirements for Pile Caps

Same as spread footings with the following additions:

1. Design must satisfy the punching shear in the vicinity of the individualpiles or shafts

2. The effective depth d must be at least 30 cm. This implies a minimumthickness T of 40 cm.

3. The bearing force between the individual piles or shafts and the caps mustnot exceed the capacity of either element.

• Pile Cap Reinforcement

The amount of pile cap reinforcement is governed by:

1. The loading on the pile cap,

2. The spacing of the piles, and

3. The depth of the pile cap.

Page 6: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 6/16

10.3 Load Distribution

To a great extent the design and calculation (load analysis) of pile foundations iscarried out using computer software. For some special cases, calculations can becarried out using the following methods

For a simple understanding of the method, let us assume that the followingconditions are satisfied:

1. The pile is rigid

2. The pile is pinned at the top and at the bottom

3. Each pile receives the load only vertically (i.e. axially applied );

4. The force P acting on the pile is proportional to the displacement U due tocompression.

x ,y العزوم حول المحورين Mx , My حيث

x , y المسافة بين المحور y والمحور x الى أى خازوق فى المجموعة

x2 , y2 عزوم القصور للمجموعة محسوبة كما فى المعادلة التالية :

Ix = Io + A . X2

بإهمال Io لصغر قيمته٬ وحذف الحد A (حيث (A) مساحة مقطع الخازوق ) من المعادلة ٬ نجد أن حمولةالخازوق الناتجة عن العزوم المطبقة على القيمة هى المبينة فى المعادلة :

Eccentricity of load

( Single )

Page 7: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 7/16

Eccentricity of load

( Double)

Graphical Method

Installation error:

Until now we have been calculating theoretical force distribution on piles.However during installation of piles slight changes in position do occur and pilesmay miss their designed locations.

So the designer must compare theoretical and the actual load distribution as aresult of misalignment after pile installation.

Deviation of the piles

Page 8: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 8/16

Most piling specifications permit a deviation in pile position of not exceeding 75mm in any direction from the intended position. Additional deviations of 1:75from the vertical piles and 1:25 from the designed rake for raking piles are alsopermitted.

Thus, the pile cap should be large enough to accommodate those piles whichhave deviated from the intended position. The pile cap should extend for adistance of 100 to 150 mm outside the outer face of the piles in the group.

Location and Alignment Tolerance:

The pile head at cutoff elevation shall be within 50 mm of plan locations for bentcaps supported by piles, and shall be within 150mm of plan locations for all pilescapped below final grade. The as – driven centroid of load of any pile group atcutoff elevation shall be within 5% of the plan location of the designed centroidof load.

No pile shall be nearer than 100mm from any edge of the cap. Any increase insize of cap to meet this edge distance requirement shall be at the Contractor’sexpense.

Piles shall be installed so that the axial alignment of the top 3m of the pile iswithin 2% of the specified alignment. For piles that cannot be inspectedinternally after installation, an alignment check shall be made before installingthe last 1.5m of pile, or after installation is completed provided the exposedportion of the pile is not less than 1.5m in length. The Engineer may require thatdriving be stopped in order to check the pile alignment. Aligned section on amisaligned section shall not be permitted.

If the location and/ or alignment tolerances specified in the precedingparagraphs are exceeded, the extent of overloading shall be evaluated by theEngineer. If in the judgment of the Engineer, corrective measures are necessary,suitable measures shall be designed and constructed by the Contractor. TheContractor shall bear all costs, including delays, associated with the correctiveaction.

10.4 Design of Pile Cap

• If the pile group is analyzed with a flexible base, then the forces required todesign the base are obtained directly from the structure model.

• If the pile group is analyzed with a rigid base, then a separate analysis isneeded to determine the stresses in the pile cap.

• An appropriate finite element model (frame, plate and plane stress or planestrain) should be used and should include all external loads (water, concrete,soil, etc. ) and pile reactions.

• There are many methods for designing pile caps from which we couldmention the following:

1­ Circulage Method2­ Beam Method

Page 9: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 9/16

3­ FEM methods

10.4.1 Circulage Method

• Circulage method can only be used when the column is loaded with an axialforce and piles are arranged on the circumference of a circle. Piles are notallowed to carry horizontal forces in this case.

• As it is shown in the following figure, the force T’ for which thereinforcement is calculated is calculated using the shown force diagram.

Force Transmission in Circulage Method

Strut­and­tie model

The strut­and­tie model should be considered for the design of deep footings andpile caps or other situations in which the distance between the centres of appliedload and the supporting reactions is less than about twice the member thickness.

Page 10: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 10/16

Struts and ties in a pile cap

The main reinforcement (As) can then be calculated from the following relation:

10.4.2 Beam Method

• The Beam Method is the most widely used method as it suitable for any typeof loading and any shape of the pile cap.

Design Procedure:

A­ Required Data:

Pile Data: 1­ Pile diameter and length,

2­ Pile allowable bearing capacity

Column Data: 1­ Column load (N + M + H),

2­ Column dimensions

B­ Design Steps:

Page 11: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 11/16

1­ Determine required number of piles:

Notes:

In case of (N) only multiply by 1.1

In case of (M+N) multiply by 1.2

Number of piles used is rounded to the upper integer

2­ Pile Cap Arrangement and Plane Dimension:

Piles should be placed in a suitable arrangement so that the spacingbetween piles ranges from (2­3) D in case of isolated pile caps and (2­6) Din case of rafts supported on piles, where D is the pile diameter.

The C.G. of piles should be placed as far as possible in the C.G. of loads.

In the case of presence of neighbors, piles should be away from theproperty line by a distance not less than D or as the pile installationmethod requires.

The projection of the pile cap should be about 10­15 cm.

3­ Pile Cap Preliminary Depth:

The depth of the pile cap could be preliminary estimated assuming an allowablepunching stress of 10 kg/cm2 on the column face.

4­ Check Forces in Piles:

Page 12: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 12/16

5­ Check for punching shear:

6­ Check for shear:

7­ Design for moment:

Page 13: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 13/16

The critical section for moment is taken at the column face.

8­ Check for Bond:

• The reinforcement used in resisting flexural moment should be checked forbond stress acting on it.

• Shear at the same section of the bending moment is calculated.

9­ Details of reinforcement:

Plane

Page 14: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 14/16

10.4.3 FEM Method

Grid used for FLAC 3D analysis of pile groups (After Poulos, 2001)

Page 15: Leer-chapter 1   Chapter 2   Chapter 3   Chapter 4   Chapter 5

25/6/2015 CHAPTER 1 CHAPTER 2 CHAPTER 3 CHAPTER 4 CHAPTER 5

http://osp.mans.edu.eg/deepfoundation/ch10.htm 15/16

10.5 Grade Beams

• Deep foundations are sometimes connected with grade beams.

• Grade beams are required for all deep foundations subject to seismic loads.For seismic design, they must resist a horizontal load equal to 10% of thecolumn vertical load.

• Grade beams must be designed without the support of the underlying soil.

• In the British Standard Code of Practice BS 8004, a ground beam is defined asa beam in a substructure transmitting load(s) to a pile, pad or otherfoundation. The ground beam connects the two pile caps.

• Ground beams should not be confused with capping beams. Capping beamsperform the same function as pile caps. However, the function of a groundbeam is to connect adjacent pile caps to ensure stability of the foundation andto ensure stability against lateral forces.

• Ground beams are designed to connect a group of pile caps in a continuousmanner.

• The top and bottom reinforcement of a ground beam are usually made equal toovercome lateral forces or settlement of one pile cap relative to the adjacentone.

• Ground beams may also require shear reinforcement in the form of binders.

• The depth of the ground beam is usually more than 1/15 of the span. The widthof the beam depends on design requirements.

Ground beams can also be designed to transmit loads from walls to pile caps.