lecture cash flow evaluation1

47
Engineering Economics - EIT Revi Cash Flow Evaluation Hugh Miller Colorado School of Mines Mining Engineering Department Fall 2007

Upload: nur-natasha-kamal

Post on 28-Oct-2014

42 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Lecture Cash Flow Evaluation1

Engineering Economics - EIT Review

Cash Flow Evaluation

Hugh MillerColorado School of MinesMining Engineering DepartmentFall 2007

Page 2: Lecture Cash Flow Evaluation1

Introduction

As we have addressed the fundamental concepts associated with engineering economics and cash flows, is now time to convert these estimates into measures of desirability as a tool for investment decisions.

We will use the following criteria:

Present & Future Value Annual Value Benefit / Cost Ratio Payback period Internal Rate of Return Variations of IRR

Page 3: Lecture Cash Flow Evaluation1

Present Value

The Present value or present worth method of evaluating projects is a widely used technique. The Present Value represents an amount of money at time zero representing the discounted cash flows for the project.

T = 0 +/- Cash Flows

PV

Page 4: Lecture Cash Flow Evaluation1

Net Present Value (NPV)The Net Present Value of an investment it is simply the difference between cash outflows and cash inflows on a present value basis.

In this context, the discount rate equals the minimum rate of return for the investment

Where:

NPV = ∑ Present Value (Cash Benefits) - ∑ Present Value (Cash Costs)

Page 5: Lecture Cash Flow Evaluation1

Initial Investment: $100,000 Project Life: 10 years Salvage Value: $ 20,000 Annual Receipts: $ 40,000 Annual Disbursements: $ 22,000 Annual Discount Rate: 12%

What is the net present value for this project?

Is the project an acceptable investment?

Present Value Example

Page 6: Lecture Cash Flow Evaluation1

Present Value Example Solution

Annual Receipts $40,000(P/A, 12%, 10) $ 226,000

Salvage Value $20,000(P/F, 12%, 10) $ 6,440

Annual Disbursements $22,000(P/A, 12%, 10) -$124,000

Initial Investment (t=0) -$100,000

Net Present Value $ 8,140 Greater than zero, therefore acceptable project

Page 7: Lecture Cash Flow Evaluation1

Future Value

The future value method evaluates a project based upon the basis of how much money will be accumulated at some future point in time. This is just the reverse of the present value concept.

T = 0 +/- Cash Flows

FV

Page 8: Lecture Cash Flow Evaluation1

Initial Investment: $100,000 Project Life: 10 years Salvage Value: $ 20,000 Annual Receipts: $ 40,000 Annual Disbursements: $ 22,000 Annual Discount Rate: 12%

What is the net future value for this project?

Is the project an acceptable investment?

Future Value Example

Page 9: Lecture Cash Flow Evaluation1

Future Value Example Solution

Annual Receipts $40,000(F/A, 12%, 10) $ 701,960

Salvage Value $20,000(year 10) $ 20,000

Annual Disbursements $22,000(F/A, 12%, 10) -$386,078

Initial Investment $100,000(F/P, 12%, 10) -$310,600

Net Future Value $ 25,280 Positive value, therefore acceptable project Can be used to compare with future value of other projects

Page 10: Lecture Cash Flow Evaluation1

PV/FV Example

No theoretical difference if project is evaluated in present or future value

PV of $ 25,282

$25,282(P/F, 12%, 10) $ 8,140

FV of $8,140

$8,140(F/P, 12%, 10) $ 25,280

Page 11: Lecture Cash Flow Evaluation1

Annual Value

Sometimes it is more convenient to evaluate a project in terms of its annual value or cost. For example it may be easier to evaluate specific components of an investment or individual pieces of equipment based upon their annual costs as the data may be more readily available for analysis.

Page 12: Lecture Cash Flow Evaluation1

Annual Analysis Example

A new piece of equipment is being evaluated for purchase which will generate annual benefits in the amount of $10,000 for a 10 year period, with annual costs of $5,000. The initial cost of the machine is $40,000 and the expected salvage is $2,000 at the end of 10 years. What is the net annual worth if interest on invested capital is 10%?

Page 13: Lecture Cash Flow Evaluation1

Annual Example Solution

Benefits: $10,000 per year $10,000

Salvage $2,000(P/F, 10%, 10)(A/P, 10%,10) $ 125

Costs: $5,000 per year -$ 5,000

Investment: $40,000(A/P, 10%, 10) -$ 6,508

Net Annual Value -$1,383

Since this is less than zero, the project is expected to earn less than the acceptable rate of 10%, therefore the project should be rejected.

Page 14: Lecture Cash Flow Evaluation1

Benefit/Cost Ratio

The benefit/cost ratio is also called the profitability index and is defined as the ratio of the sum of the present value of future benefits to the sum of the present value of the future capital expenditures and costs.

Page 15: Lecture Cash Flow Evaluation1

B/C Ratio Example

Present value cash inflows Project A Project B

$500,000 $100,000 Present value cash outflows

$300,000 $ 50,000 Net Present Value

$200,000 $ 50,000 Benefit/Cost Ratio

1.67 2.0

Page 16: Lecture Cash Flow Evaluation1

Payback Period

This is one of the most common evaluation criteria used by engineering and resource companies.

The Payback Period is simply the number of years required for the cash income from a project to return the initial cash investment in the project.

The investment decision criteria for this technique suggests that if the calculated payback is less than some maximum value acceptable to the company, the proposal is accepted.

The following example illustrates five investment proposals having identical capital investment requirements but differing expected annual cash flows and lives.

Page 17: Lecture Cash Flow Evaluation1

Payback Period

Page 18: Lecture Cash Flow Evaluation1

ExampleCalculation of the payback period for a given investment proposal.

a) Prepare End of Year Cumulative Net Cash Flowsb) Find the First Non-Negative Yearc) Calculate How Much of that year is required to cover the previous period

negative balanced) Add up Previous Negative Cash Flow Years

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(45,000) 10,500 11,500 12,500 13,500 13,500 13,500 13,500 13,500 13,500 13,500

End of Year Cummulative Net Cash Flow(45,000) (34,500) (23,000) (10,500) 3,000 16,500 30,000 43,500 57,000 70,500 84,000

Pay Back PeriodFraction of First Positive Year 0.78Pay Back Period 3.78

a

b

c) 0.78 = 10,500/13,500

d) 3 + 0.78

Page 19: Lecture Cash Flow Evaluation1

Example: Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(120) 10 10 50 50 50 50 50 50 50 50

End of Year Cummulative Net Cash Flow(120) (110) (100) (50) 0 50 100 150 200 250 300

Pay Back PeriodFraction of First Positive Year 1.00Pay Back Period 4.00

Page 20: Lecture Cash Flow Evaluation1

Example:

Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(120) 10 10 50 50 50 50 50 50 50 50

End of Year Cummulative Net Cash Flow(120) (110) (100) (50) 0 50 100 150 200 250 300

Pay Back PeriodFraction of First Positive Year 1.00Pay Back Period 4.00

Page 21: Lecture Cash Flow Evaluation1

Example:

Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(120) 10 10 50 50 50 50 50 50 50 50

End of Year Cummulative Net Cash Flow(120) (110) (100) (50) 0 50 100 150 200 250 300

Pay Back PeriodFraction of First Positive Year 1.00Pay Back Period 4.00

Page 22: Lecture Cash Flow Evaluation1

Example:

Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(250) 86 50 77 52 41 70 127 24 6 40

End of Year Cummulative Net Cash Flow(250) (164) (115) (38) 14 55 124 252 276 282 322

Pay Back PeriodFraction of First Positive Year 0.73Pay Back Period 3.73

Page 23: Lecture Cash Flow Evaluation1

Example:

Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(250) 86 50 77 52 41 70 127 24 6 40

End of Year Cummulative Net Cash Flow(250) (164) (115) (38) 14 55 124 252 276 282 322

Pay Back PeriodFraction of First Positive Year 0.73Pay Back Period 3.73

Page 24: Lecture Cash Flow Evaluation1

Example:

Calculate the payback period for the following investment proposal

Initial Annual Net Cash FlowsInvestment 1 2 3 4 5 6 7 8 9 10

Alternative A(250) 86 50 77 52 41 70 127 24 6 40

End of Year Cummulative Net Cash Flow(250) (164) (115) (38) 14 55 124 252 276 282 322

Pay Back PeriodFraction of First Positive Year 0.73Pay Back Period 3.73

Page 25: Lecture Cash Flow Evaluation1

Effect of Pre-production Period

When calculating the payback period for a new project we typically have several years of negative cash flows (investment) prior to positive cash flows.

Two Approaches: Total Payback and Payback After 1st Production

Page 26: Lecture Cash Flow Evaluation1

Effect of Pre-production PeriodThe total payback period is calculated from the start of the project and represents the commitment of the investor throughout the pre-production period, particularly the opportunity cost associated with the investment during this period.

Disadvantages:

A) This criterion fails to consider cash flows after the payback period, therefore, it can’t be regarded as a suitable measure of profitability.

B) It doesn’t consider the magnitude or timing of the of cash flows during the payback interval.

Page 27: Lecture Cash Flow Evaluation1

Advantages

1. Simple and easy to calculate, providing a simple number which can be

used as an index of proposal profitability.

2. Prevents management from exposure to excessive risk

The shorter the payback the less risk associated with the investment

3. Measure of lost opportunity risk

Projects with short payback will minimize opportunity risk since early

cash flows will be returned to the firm within a short span of time. (Liquidity)

4. Payback period represents a break even point.

Projects with life greater than the payback period will contribute profit to

the firm

Page 28: Lecture Cash Flow Evaluation1

Engineering Economics

EIT ReviewIRR & Discount Rates

Page 29: Lecture Cash Flow Evaluation1

Investment Rate of Return

In mineral evaluation, any reference to rate of return normally refers to the discounted cash flow return on investment (DCF-ROI) or the discounted cash flow rate of return (DCF-ROR)

These terms are special versions of the more generic term, Internal Rate of Return (IRR) or sometimes called marginal efficiency of capital

Besides NPV, is probably the most common evaluation technique used in the minerals industry

Page 30: Lecture Cash Flow Evaluation1

Internal Rate of Return

Internal Rate of Return refers to the interest rate that the investor will receive on the investment principal

IRR is defined as that interest rate (r) which equates the sum of the present value of cash inflows with the sum of the present value of cash outflows for a project. This is the same as defining the IRR as that rate which satisfies each of the following expressions:

∑ PV cash inflows - ∑ PV cash outflows = 0

NPV = 0 for r

∑ PV cash inflows = ∑ PV cash outflows

In general, the calculation procedure involves a trial-and-error solution unless the annual cash flows subsequent to the investment take the form of an annuity. The following examples illustrate the calculation procedures for determining the internal rate of return.

Page 31: Lecture Cash Flow Evaluation1

Example

Given an investment project having the following annual cash flows; find the IRR.

Solution:

Step 1. Pick an interest rate and solve for the NPV. Try r =15%

NPV = -30(1.0) -1(P/F,1,15%) + 5(P/F,2,15) + 5.5(P/F,3,15) + 4(P/F,4,15)

+ 17(P/F,5,15) + 20(P/F,6,15) + 20(P/F,7,15) - 2(P/F,8,15) + 10(P/F,9,15)

= + $5.62

Since the NPV>0, 15% is not the IRR. It now becomes necessary to select a higher interest rate in order to reduce the NPV value.

Step 2. If r =20% is used, the NPV = - $ 1.66 and therefore this rate is too high.

Step 3. By interpolation the correct value for the IRR is determined to be r =18.7%

Year 0 1 2 3 4 5 6 7 8 9

Cash Flow (30.0) (1.0) 5.0 5.5 4.0 17.0 20.0 20.0 (2.0) 10.0

Page 32: Lecture Cash Flow Evaluation1

IRR using Excel

Using Excel you should insert the following function in the targeted cell C6:

Page 33: Lecture Cash Flow Evaluation1

Analysis

The acceptance or rejection of a project based on the IRR criterion is made by comparing the calculated rate with the required rate of return, or cutoff rate established by the firm. If the IRR exceeds the required rate the project should be accepted; if not, it should be rejected.

If the required rate of return is the return investors expect the organization to earn on new projects, then accepting a project with an IRR greater than the required rate should result in an increase of the firms value.

Page 34: Lecture Cash Flow Evaluation1

Analysis

There are several reasons for the widespread popularity of the IRR as an evaluation criterion:

Perhaps the primary advantage offered by the technique is that it provides a single figure which can be used as a measure of project value.

Furthermore, IRR is expressed as a percentage value. Most managers and engineers prefer to think of economic decisions in terms of percentages as compared with absolute values provided by present, future, and annual value calculations.

Page 35: Lecture Cash Flow Evaluation1

AnalysisAnother advantage offered by the IRR method is related to the calculation procedure itself:

As its name suggests, the IRR is determined internally for each project and is a function of the magnitude and timing of the cash flows.

Some evaluators find this superior to selecting a rate prior to calculation of the criterion, such as in the profitability index and the present, future, and annual value determinations. In other words, the IRR eliminates the need to have an external interest rate supplied for calculation purposes.

Page 36: Lecture Cash Flow Evaluation1

Multiple Roots Case One of the disconcerting aspects associated with the internal rate of return is that more than one interest rate may satisfy the calculation. The solution procedure for IRR is essentially the solution for an nth degree polynomial of the form:

NPV = 0 = A0 + A1X + A2X2 + A3X3 + .... + AnXn

where X = 1/(1 + r)

For a polynomial of this type there may be n different real roots, or values of r, which satisfy the equation. Multiple positive rates of return may occur when the annual cash flows have more than one change in sign.

Page 37: Lecture Cash Flow Evaluation1

Multiple Roots Case

The following example illustrates the possibility of multiple rates which satisfy the definition of IRR:

Suppose a mining operation has a remaining life of eight years, but an investment is considered to increase the production rate. This will result in depleting the deposit in six years. Assuming the following cash flows, is the investment justified?

Because there are two sign reversals in the cash flows, Descartes‘ Rule of Signs indicates there are a maximum of two real roots to the IRR polynomial.

Solving for these roots by trial and error yields the following:

Year 0 1 2 3 4 5 6 7 8

Existing 10.0 10.0 10.0 10.0 10.0 10.0 10.0 10.0

Proposed (15.0) 16.0 16.0 16.0 16.0 15.0 15.0 - -

Difference (15.0) 6.0 6.0 6.0 6.0 5.0 5.0 (10.0) (10.0)

Page 38: Lecture Cash Flow Evaluation1

Multiple Roots CaseGraphically this appears as shown in the following figure:

The rates at which NPV = 0 are, by definition, the internal rates of return. By interpolation, the two solving rates of return for this example are approximately 4.5 and 12.3%

Rate 0% 4% 5% 10% 12% 15%

NPV (1.00) (0.07) 0.06 0.05 0.03 (0.25)

Page 39: Lecture Cash Flow Evaluation1

Multiple Roots Case

Should the firm invest in the project or not?

If both rates were above the firm's required rate of return there would be no problem and the firm would accept the project.

However, what if the required rate of return is 10%? Which of the calculated IRR values is correct? The answers to these questions are that they are both mathematically correct, but they are meaningless from an economic standpoint.

Neither of these rates can be considered an adequate measure of the project's rate of return because a project can not earn more than one rate of return over its life. Therefore, the calculation of an IRR value(s) does not always enable the decision-maker to make accept/reject decisions on investment proposals.

Page 40: Lecture Cash Flow Evaluation1

Multiple Roots Case

How often this problem of multiple rates actually occurs?

The possibility of multiple-rate occurrences is perhaps more prevalent in the case of new mining ventures than in most other industries. The negative cash flows are typically the result of anticipated periods of reduced market prices, major capital expenditures for equipment replacement, expansion programs, and/or major environmental expenditures, particularly at the end of project life.

Because of the possibility of multiple rates and the reinvestment assumption when using-the IRR to rank projects, the evaluator must carefully consider the exclusive use of this technique for decision-making.

Page 41: Lecture Cash Flow Evaluation1

Selecting a Discount Rate

“There is nothing so disastrous as a rational investment policy in an irrational world” John Maynard Keynes

We have discussed the time value of money and illustrated several examples of its use. In all cases an interest rate or “discount rate” is used to bring the future cash flows to the present (NPV - Net Present Value)

The selection of the appropriate discount rate has been the source of considerable debate and much disagreement. In most companies, the selection of the discount rate is determined by the accounting department or the board of directors and the engineer just uses the number provided to him, but short of just being provided with a rate, what is the correct or appropriate rate to use?

Page 42: Lecture Cash Flow Evaluation1

ExampleWhat is the impact of the discount rate on the investment?

Cash Flow Yr 0

Cash Flow Yr 1

Cash Flow Yr 2

Cash Flow Yr 3

Cash Flow Yr 4

Cash Flow Yr 5

-500 -500 +750 +600 +800 +1000

ROR NPV

2% 1,941

6% 1,581

10% 1,283

15% 981

20% 739

IRR 47.82% 0

Page 43: Lecture Cash Flow Evaluation1

What is in the Discount Rate?

According to our text book and several authors, the discount rate has to cover the following items: Opportunity Costs Transaction Costs Compensate for Risk Cover anticipated Inflation

Some of these items can be accounted for in other financial analysis methods and do not have to be address in the discount rate itself.

Page 44: Lecture Cash Flow Evaluation1

Financial Cost of Capital

The financial cost of capital is based on the assumption that financing is unlimited and the company can always pay off loans or buy stock back, so the financial cost of capital rate of return is the average cost of debt after tax (remember interest is tax deductible) and the cost of equity (what the share holders desired return is using the capital asset pricing model CAPM)

Page 45: Lecture Cash Flow Evaluation1

Marginal Weighted Average Cost of Capital

The cost of capital is the minimum rate of return that a firm needs to earn on new investments to maintain the existing value of it’s shares of common stock. To determine the cost of capital a weighted average of all sources of capital must be evaluated. The weighted average should include a mix of debt and equity on an after tax basis.

Page 46: Lecture Cash Flow Evaluation1

Hurdle Rate

The hurdle rate is a common term used by companies as an expression of their rate of return used for financial analysis.

This is generally a higher number than the FCC rate as they add an imposed “economic hurdle” for the project to overcome. This helps companies express that a project that just achieves a FCC rate of return does not add real value to the company.

Page 47: Lecture Cash Flow Evaluation1

Opportunity Cost of Capital

The opportunity cost of capital is the most common method of establishing the investor’s minimum rate of return.

This is based upon the expected returns that the company will generate in the next 1 to 15 years. It is the average return that investors expect to make over the next few years expressed as a compound interest.