:: TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED:: From: To: The Divisional Engineer, 1. The Senior Divisional Electrical Engineer TL & SS, APTRANSCO, Traction division , AT/ PO- Jatni Garividi. Khurda-Dist. Viziangaram-Dist. 2.The Senior Divisional Electrical Engineer Traction division / DRM office Visakhapatnam Lr.No.DE / TL & SS/ Garividi / F. / D.No. /13, Dt: 08.05.13 Sir, Sub: APTRANSCO– EHT /TL & SS/Garividi–220kv Tekkali s.s – 132kv Tekkali – Naupada RT feeder - Programmed Shutdown on 15 -05- 2013 – Alternate supply from 132kv Baruva RTSS or 132kv Ponduru RTSS – Line clear –Requested. * * * It is proposed to replace the damaged 132kv B phase Bus conductor of 132kv Tekkali - Narasannapeta feeder at loc. 4 to 5 by availing shutdown on132kv Tekkali - Naupada RT feeder due to line crossing from 08.00 hrs. to 16:00 hrs. on 16.04.2012. During this line clear period alternative supply to 132kv Naupada RTSS will have to be availed from 132kv Baruva RTSS or 132kv Ponduru RTSS as per your connivance. The APEPDCL Authorities have conveyed their willingness to ignore the overshoot in M.D during the above L.C period. The approval for ignoring the overshoot in M.D is communicated herewith.

Upload: sbrshb38

Post on 11-Dec-2015

215 views

Category:

Documents


2 download

DESCRIPTION

LC Proposal of 132kv Naupada RT Feeder 15.05.2013

TRANSCRIPT

Page 1: LC Proposal of 132kv Naupada RT Feeder 15.05.2013

:: TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED::

From: To:The Divisional Engineer, 1. The Senior Divisional Electrical Engineer TL & SS, APTRANSCO, Traction division , AT/ PO-JatniGarividi. Khurda-Dist.Viziangaram-Dist.

2.The Senior Divisional Electrical Engineer Traction division / DRM office

Visakhapatnam

Lr.No.DE / TL & SS/ Garividi / F. / D.No. /13, Dt: 08.05.13Sir,

Sub: APTRANSCO– EHT /TL & SS/Garividi–220kv Tekkali s.s – 132kv Tekkali – Naupada RT feeder - Programmed Shutdown on 15 -05- 2013 – Alternate supply from 132kv Baruva RTSS or 132kv Ponduru RTSS – Line clear –Requested.

* * * It is proposed to replace the damaged 132kv B phase Bus conductor of 132kv

Tekkali - Narasannapeta feeder at loc. 4 to 5 by availing shutdown on132kv Tekkali -

Naupada RT feeder due to line crossing from 08.00 hrs. to 16:00 hrs. on 16.04.2012. During

this line clear period alternative supply to 132kv Naupada RTSS will have to be availed from

132kv Baruva RTSS or 132kv Ponduru RTSS as per your connivance. The APEPDCL

Authorities have conveyed their willingness to ignore the overshoot in M.D during the above

L.C period. The approval for ignoring the overshoot in M.D is communicated herewith.

Hence it is requested to approve the above Line clear and arrange to

communicate the same.

Thanking you Sir, Yours faithfully

Divisional Engineer TL&SS, APTRANSCO

GARIVIDI. VIZIANAGARAM- DT.

Copy submitted to Copy submitted to the Chief Engineer / Vizag zone / Visakhapatnam.Copy submitted to the Superintending Engineer/ TL & SS / VisakhapatnamCopy submitted to the Superintending Engineer/ TLC / VisakhapatnamCopy to submitted to Superintending Engineer / Operation / APEPDCL/Srikakulam. Copy communicated to the Executive Engineer/ TL C / SrikakulamCopy communicated to the Divisional Engineer / Load Dispatch / V.S / HyderabadCopy communicated to the Divisional Engineer /Operation/APEPDCL /Tekkali.Copy to Assistant Divisional Engineer / Maintenance / 220kv Tekkali s.s.Copy to Assistant Divisional Engineer / Shift / 220kv Tekkali s.s.Copy to Assistant Divisional Engineer / MRT / Tekkali s.s.

Page 2: LC Proposal of 132kv Naupada RT Feeder 15.05.2013

:: TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED::

From: To:The Divisional Engineer, The Superinteding Engineer,TL & SS, APTRANSCO, Operation,APEPDCL,Garividi. Srikakulam. Viziangaram-Dist.

Lr.No.DE / TL & SS/ Garividi / F. / D.No. /13, Dt: 08 .05.13Sir,Sub: APTRANSCO – EHT / TL & SS /Garividi – 220kv Tekkali s.s – 132kv Tekkali – Naupada RT feeder - Programmed Shutdown on 15 -05- 2013 – Alternate supply from 132kv Baruva RTSS or 132kv Ponduru RTSS – Line clear –Requested.

* * *

It is proposed to replace the damaged 132kv B phase Bus conductor of 132kv

Tekkali - Naupada Traction feeder at 220kv Tekkali substation on 15.05.2013 from 08.00

Hrs. to 12.00 Hrs.

In this connection it is to submit that the railway traction supply will have to

be fed from either Baruva RTSS or Ponduru RTSS during the above period to maintain

uninterrupted supply to railway traction which understandably leads to over shoot of MD at

the alternative source. It is requested to kindly arrange to ignore the over shoot in MD to

facilitate availing the above proposed line clear.

Thanking you sir,

Yours faithfully

Divisional Engineer TL&SS, APTRANSCO

GARIVIDI. VIZIANAGARAM- DT.

Copy submitted to the Chief Engineer / Vizag zone / Visakhapatnam.Copy submitted to Superintending Engineer/ TL & SS / Visakhapatnam.

Page 3: LC Proposal of 132kv Naupada RT Feeder 15.05.2013

Copy submitted to Divisional Engineer/ Operation/APEPDCL/ SrikakulamCopy submitted to Divisional Engineer/ Operation/APEPDCL/ TekkaliCopy to Senior Divisional Electrical Engineer/Traction division/ DRM office / VisakhapatnamCopy to Senior Divisional Electrical Engineer/ Traction division/ AT/ PO-Jatni / Khurda -Dist.