large lng storage tank construction – commenced

14
Large LNG Storage Tank Construction Update EPC Tank Contractor Selected: Preload Cryogenics Contract signed December 22, begin work December 28,2017 Tank Excavation Completed in February Flat-Loop Evaporators placed in March Backfilling and instrumentation placed in March Rat Slab for tank poured in Mid-March, Tank Slab Forms, Rebar and instrumentation placement began Mid-March First Panel of outer tank poured at Anchorage Sand & Gravel March 30 Tank Slab poured April 12 Flat Loop Evaporators are operating (22 degrees) 1

Upload: others

Post on 04-May-2022

23 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Large LNG Storage Tank Construction – Commenced

Large LNG Storage Tank Construction Update• EPC Tank Contractor Selected: Preload Cryogenics

• Contract signed December 22, begin work December 28,2017

• Tank Excavation Completed in February

• Flat-Loop Evaporators placed in March

• Backfilling and instrumentation placed in March

• Rat Slab for tank poured in Mid-March,

• Tank Slab Forms, Rebar and instrumentation placement began Mid-March

• First Panel of outer tank poured at Anchorage Sand & Gravel March 30

• Tank Slab poured April 12

• Flat Loop Evaporators are operating (22 degrees)

1

Page 2: Large LNG Storage Tank Construction – Commenced

Large LNG Storage Tank Construction UpdateFairbanks Tank Foundation Pour

• 1800 CY of concrete, 90 Tons of steel in the foundation

• Approximately 50 personnel on site

• Local subcontractor, Rady Concrete of North Pole responsible for this work

• Three pumper trucks and a spar

• All three Concrete plants produced concrete for the pour, 26 different delivery trucks

• Work completed in one day

2

Page 3: Large LNG Storage Tank Construction – Commenced
Page 4: Large LNG Storage Tank Construction – Commenced
Page 5: Large LNG Storage Tank Construction – Commenced
Page 6: Large LNG Storage Tank Construction – Commenced
Page 7: Large LNG Storage Tank Construction – Commenced
Page 8: Large LNG Storage Tank Construction – Commenced
Page 9: Large LNG Storage Tank Construction – Commenced

Large LNG Storage Tank Construction Update

Anchorage Precast Panels: • Anchorage Sand & Gravel responsible for the precast panels

• Approximately 88’ long, 8’ wide

• Each panel has 36, 5/8” cables prestressed to over 40,000 LBS.

• Each Panel has over 3100 studs attached

• Anchorage Fabricators Superior Welding and Machine, Greer, Alaska Steel and Weona Corporation preparing the panels

• Currently producing one panel / day

• Shipping anticipated after road restriction are lifted about June 1

Page 10: Large LNG Storage Tank Construction – Commenced
Page 11: Large LNG Storage Tank Construction – Commenced
Page 12: Large LNG Storage Tank Construction – Commenced
Page 13: Large LNG Storage Tank Construction – Commenced
Page 14: Large LNG Storage Tank Construction – Commenced

Large LNG Storage Tank Construction Update

• Next Steps for April / May• Prepare to Backfill for remainder of pad

• Fabricate outer walls (Anchorage Sand and Gravel)

• Fabricate inner walls and ship to site

• Order long lead items for Balance of Plant, vaporizers, compressors, valves

• Prepare tank roof submittal to the Alaska State Fire Marshall

• Complete tank dome roof design and ship materials to site