Lan xess and Prometheus SAP Scheduling made easy. Bobby Tynes – Lan xess Corp. Randy Linzel – Prometheus Group. Lan xess & Prometheus SAP Solutions. The story of Lanxess The introduction to the Prometheus Group The application and success - PowerPoint PPT PresentationTRANSCRIPT
Produced by:
LanLanxessxess and Prometheus and Prometheus SAP Scheduling made easySAP Scheduling made easy
Bobby Tynes – Lanxess Corp.
Randy Linzel – Prometheus Group
•The story of LanxessThe story of Lanxess•The introduction to the Prometheus Group The introduction to the Prometheus Group •The application and success The application and success •Going Global with Going Global with Unity for Plant MaintenanceUnity for Plant Maintenance•Lessons LearnedLessons Learned•QuestionsQuestions
Lanxess & Prometheus SAP Solutions
Primary tools used by Lanxess Orange Site
• Mass transfer of date/status changes• Mass transfer of data to a spreadsheet
• Mass print function • Manpower leveling—outside of schedule• Scheduling for progress monitoring• Data retention through O2TL and O2B• KPI measurements
Lanxess Spins off from Bayer AG
Products Lines Manufactured
FocusFocus
Subhead (Arial 40 Bold)
• Text (Arial 40 Regular)o Demoted Text (Arial 34 Regular)
Slide 7
BU Performance Butadiene RubbersBU Performance Butadiene RubbersOrange Site FactsOrange Site Facts
Property: 880 acres
Replacement value: $806MM
Staffing:300 LANXESS Employees 175 contractors
Name plate capacity: 303,600 MT/year
Applications: Tires; automotive; plastics
ISO 9001:200 & RC/ISO14001 Certified
HR spend (incl. contractors): $48MM
Utility & Raw Mat spend: >$250MM
Taxes: >$3MM
LANXESS Business Units present at site
Performance Butadiene Rubbers (PBR) CoBR (Clear / Black Masterbatch) LiBR / NdBR
Technical Rubber Products (TRP) LANXESS BUNA LLC (EPR) Therban (HNBR)
• The Key Points to Take Home slide is all about distilling and conveying your experience to conference delegates. Try answering the following questions as you wrap upo Reflecting back on my experience, what have been my greatest insights?o What did I get right?o If I did it all again what would I do differently?o If I was in your shoes and embarking on a similar project, what would I do
or not do?
Global Presence
Welcome to Orange Texas Welcome to Orange Texas Challenge 2005 (Rita)Challenge 2005 (Rita)
Challenge 2007 (Humberto)Challenge 2007 (Humberto)
Challenge 2008 (Ike)Challenge 2008 (Ike)
Slide 13
GWOS/KPI 2008
July 22, 2008 KPI
July 23, 2009 KPI
GWOS/SCH KPI Conversion
GWOS KPI Layout
GWOS KPI Filters
June 9, 2011
Demo Mass Transfer from SAP to KPI Sheet
Confirmation of completed operations
GWOS Shutdown Scheduling
• Many Issues to Overcome
• Changes to Work Centers
• Changes to Critical Paths
• Changes Basic Start/Finish Dates
Changes to Work Centers
• Due to the last minute changes to the way the turnaround was to be billed, we had to replace the planned work centers to reflect the newly
created work center that was to bill at a higher rate.
(Turnaround Rate)
Mass Change saved the day
Planning Board made shifting work orders, to mirror real world activities, much more user
friendly and accurate.
Planning Board used for Manpower Leveling
Monitoring Manpower Needs by Work Centers & Adjust with Mass Change based on
Workload per Work Center
Work could then be re-distributed to balance Work Load
Mass Change was used to update Priority Changes as they occurred, monitoring
Critical Path
Post Turnaround activities means only on thing, Getting ready for the Next One
Enhancement Tab MeansPreparing for the Future, by learning from the
Past
Lessons Learned
• With Prometheus - Overall ease of use
• With Prometheus - There is no longer a need to use multiple systems to perform daily or future planning and scheduling tasks—you can do everything live in SAP
• With Prometheus - When given the task of centralizing maintenance, everyone should follow the same agenda
Primary tools used by Lanxess Orange Site
• Mass transfer of date/status changes• Mass transfer of data to a spreadsheet • Manpower leveling—outside of schedule• Scheduling for progress monitoring • Mass print function• Data retention through O2TL and O2B• KPI measurements
Produced by:
Bobby Tynes Lanxess Corporation
Randy Linzel Prometheus Group