Lake Murray Dam flows and striped bass spawning in Congaree River
Objective
• Consider Congaree River striped bass flow needs in Lake Murray dam license
– Importance
– Biological needs
– Affect of Flow and Temperature
• i.e. it is ‘under the influence’ of the dam
– DNR recommendation
– Questions/Discussion
LakeMurray
LakeWateree
LowerSaluda
River LakeMarion
LakeMoultrie
Importance of Striped Bass
• State Fish of SC
• Initial inland population
• Aquaculture developed
• Economic, recreational -$260 million
• Representative migratory species
• Well-studied
• Santee-Cooper population collapse
84 86 88 90 92 94 96 98 00 02 04 06
Year
Ab
un
dan
ce
> 2 years old
Total catch
Striped Bass Abundance
18” 5/day
21”
5/acre 15/acre
4/1/06 8/1/06 12/1/06 4/1/07 8/1/07
Syste
m K
M
-50
0
50
100
150
200
250Fish 3508
Date
Syste
m K
M
-50
0
50
100
150
200
250Fish 3517
Cong-Wat Confluence
Sal-Broad Confluence
Pinopolis Dam
Diversion Canal
Cong-Wat Confluence
Sal-Broad Confluence
Pinopolis Dam
Diversion Canal
Watere River
Cooper River
Santee River
Broad River
Saluda River
Congaree River
Lake Marion
Lake Moultrie
• > 80% of spawning in Congaree River
• Most spawning from CNP to I-77
•Peak spawning in April through mid-May
0
5
10
15
20
25
0 10 20 30 40 50 60 70 80 90 100
Ave
rage
dai
ly T
em
pe
ratu
re
Date - where '1' is March 1 and '92' is May 31.
Broad
Sal Cola
Sal Dam
0
50
100
150
200
250
300
0 5,000 10,000 15,000 20,000 25,000 30,000
Rec
ruit
men
t o
f ag
e-2
str
iped
bas
s
Average April discharge (cfs)
Average LSR contribution
• LSR @ Cola, 1926-2007
– Mean annual flow = 2,749 cfs
• Congaree R. @ Cola, 1956-2007
– Mean annual flow = 8,872 cfs
• By subtraction, mean flow in Broad = 6,123 cfs
• LSR supplies, on average, 31% of Congaree River flow
• LSR mean flow is 45% of Broad’s mean flow
DNR recommendation
• Period of concern is April 1 through May 10
• Assume base minimum flow is 1,300 cfs
• No flow augmentation when Broad > 7,700
• On a continuous basis each ‘day’, release into LSR– 45% of previous days flow within Broad, OR
– the release needed to reach 9,000 cfs in Congaree (whichever is lower)
• No augmentation needed when Broad < 2,700
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0 10 20 30 40 50 60
Flow, cfs
Broad R. flow
Lower Saluda flow
Congaree R. flow