lake barton dredging, restoration and riser modification

17
A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Lake Barton Dredging, Restoration and Riser Modification Project July 16, 2019

Upload: others

Post on 12-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Lake Barton Dredging, Restoration and Riser Modification

A Fairfax County, VA, publication

Department of Public Works and Environmental ServicesWorking for You!

Lake Barton Dredging, Restoration and Riser Modification Project

July 16, 2019

Page 2: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Meeting Agenda

Meeting Agenda

• Introduction

• Facility Overview

• Project Need

• Project Objectives

• Work Completed

• Construction

• Next Steps

2

Meeting Agenda

Page 3: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Introduction

Introduction

• Fairfax County Staff

– Aaron George, PE, CFM - DPWES Maintenance and Stormwater

Management Division

– Chris Triolo, PE, CCM – DPWES Utilities Design and Construction Division

• Design Engineering Consultant

– Eric Neast, PE - Gannett Fleming, Inc.

3

Page 4: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Facility Overview

Facility Overview

Lake Barton (9992WP)

• Constructed in 1978 to provide flood control by the Natural Resources Conservation Service (NRCS) with Fairfax County and Northern Virginia Soil and Water Conservation District (NVSWCD) as local sponsors

• One of six NRCS designed flood control dams in the Pohick Watershed

• Drainage Area - 538 acres (0.8 square miles)

• Surface Area - 9.6 acres

• Lake Barton Dam is regulated by the Department of Conservation and Recreation (DCR) with operation and maintenance completed by Fairfax County

• Last dredged in 2011

4

Page 5: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Facility Overview 5

Facility Overview

Page 6: Lake Barton Dredging, Restoration and Riser Modification

Project Need

Lake Barton Dredging, Restoration and Riser Modification Project

Project Need

6

Page 7: Lake Barton Dredging, Restoration and Riser Modification

Project Need

Lake Barton Dredging, Restoration and Riser Modification Project

Project Need

7

Page 8: Lake Barton Dredging, Restoration and Riser Modification

Project Need

Lake Barton Dredging, Restoration and Riser Modification Project

Project Need

8

Page 9: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Project Objectives

• Dredge accumulated sediment

– Currently estimated to remove 15,700 CY

• Facility restoration

– Shoreline rehabilitation

– Riser rehabilitation

• Trash Rack

• Cold Water Intake

• Facility Improvements

– Secondary forebay

– Improvements to existing forebay

– Water quality benefits (forebay volume)

– Mid-level sluice gate

– Fish habitat

9

Project Objectives

Page 10: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Work Completed

• Survey

– Bathymetric

– Topographic

– Utility

– Environmental

• Sediment Sampling

• Environmental Permitting

• Design

– 95% Design Plan

– Specifications

– Permitting

10

Work Completed

Page 11: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Work Completed 11

Work Completed

Page 12: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Work Completed 12

Work Completed

Forebay

Forebay

Berm

Forebay

Berm

Riser

Improvements

Access

Page 13: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Construction

Mechanical Dredge (Dry)

• General Sequence– Initiate drawdown of lake

– Establish access and staging areas

– Establish diversion channels within lake

– Conduct dredging

• Benefits– Higher daily sediment removal rates

– Minimal sediment handling effort at disposal area

– Potentially lower cost

– Constructability of improvements

• Challenges– Very weather dependent

– Higher potential for delays due to weather

– Potential for odor from lake bottom being exposed

– Need to relocate/salvage fish

13

Construction

Page 14: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Construction

Similar Projects

• Huntsman Lake

• Woodglen Lake

• Royal Lake

14

Construction

Page 15: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Construction 15

Construction

Page 16: Lake Barton Dredging, Restoration and Riser Modification

Lake Barton Dredging, Restoration and Riser Modification Project

Next Steps

• Finalize Design / Permitting / Disposal Options

– Plan, specifications, and permits to be acquired for construction

– 3 months

• Bid

– Acquire bids from qualified contractors

– 3-4 months

• Construction

– 12 months

16

Next Steps

Page 17: Lake Barton Dredging, Restoration and Riser Modification

Additional Information

For additional information, please contact

www.fairfaxcounty.gov/dpwes

Lake Barton Dredging, Restoration and Riser Modification Project

17

Aaron George, PE

703-877-2809

[email protected]