23 May 2012 PMI Revision 00 1
INTRODUCTIONTO ERECTION
-
7/31/2019 L-01 Introduction to Erection - 000
2/14
23 May 2012 PMI Revision 00 2
ROLE OF ERECTION DEPARTMENT IN NTPC
NTPC has been entrusted with the responsibility toengineer the Project from concept to commissioning state intotality and thereafter operate Super Thermal PowerStations.
Construction management of such large STPS involves amulti-disciplinary approach over a diversified area ofactivities from the state of preconstruction till start up andprecommissioning state.
Construction management functions involve executing aSTPP during various phases of construction activities i.e.from taking a green site till handing over of erected andtested equipments for commissioning.
-
7/31/2019 L-01 Introduction to Erection - 000
3/14
23 May 2012 PMI Revision 00 3
Construction line function involves different disciplines :-
1. Civil construction including structural fabrication. 2. Mechanical equipment erection. 3. Electrical erection. 4. C&I erection.
As per NTPC Corporate philosophy construction has beenorganized into two major groups :- i) Construction : This includes civil construction and structural fabrication. ii) Equipment Erection : This includes erection of mechanical,
electrical and C&I equipments. Equipment erection involves erection of all plant and systems such as
boiler, turbo-generator, auxiliary systems like Coal handling system,Electrical and C&I system.
-
7/31/2019 L-01 Introduction to Erection - 000
4/14
23 May 2012 PMI Revision 00 4
BROAD FUNCTIONAL RESPONSIBILITIES FOR
EQUIPMENT ERECTION GROUP :- To ensure proper co-ordination with the contractors for timelyexecution of various equipments erection work, at site as per
contract agreements / LOIs.
To allot necessary land and infra-structure facilities to variouscontractors to enable them to mobilize their work-force and
proceed with the erection work as per schedule.
To plan, monitor and review the erection work on a regularbasis so that work progresses as per schedule.
-
7/31/2019 L-01 Introduction to Erection - 000
5/14
23 May 2012 PMI Revision 00 5
To ensure all work-fronts, inputs and resources are
regularly made available during course of executionof the work and to preempt any foreseen hold-ups
due to non-availability of any of these.
-- To exercise judicious control over consumption of bulk material and other consumables.
-- To ensure that quality of erection work meets the
company standards and norms. -- To maintain checks and ensure proper work
measurements.
-
7/31/2019 L-01 Introduction to Erection - 000
6/14
23 May 2012 PMI Revision 00 6
EQUIPMENT ERECTION :-
Execution and Supervision system Objective :-
To ensure that equipment erection works are completed
within the time schedule of overall construction Network so asto enable the start-ups, trial runs and pre-commissioning
activities of equipments, system within the frame-work of
overall project schedule.
-
7/31/2019 L-01 Introduction to Erection - 000
7/14
23 May 2012 PMI Revision 00 7
Basic responsibilities of erection execution
supervision group are :- 1. Study of LOI / Bid Documents :- a) Scope of work and terminal points. b) Location, lay outs, technical specification and erection methodology for various equipment.
c) Quality plan. d) Contractors resource commitment. e) Contractors schedule. f) Scope of supply and erection.
2. Land allotment and infrastructure services.
3. Erection planning implementation of detailed construction planning system. 4. Monitoring of equipment despatch, transportation,
receipts and expediting.
-
7/31/2019 L-01 Introduction to Erection - 000
8/14
23 May 2012 PMI Revision 00 8
5. Work front release :-
a) Erection plans are finalized.b) Availability of fabrication and erection drgs.
c) Availability of erectable equpt. at site.
d) Availability of bulk materials and erection matl.e) Helping and lifting equipment requirements and
their detailed deployment plan.
f) Availability of civil works front.6. Equipment supply and receipt where
erection and supply are split up.
-
7/31/2019 L-01 Introduction to Erection - 000
9/14
23 May 2012 PMI Revision 00 9
7. Erection supervision Aims at assisting the
contractor to work efficiently in terms of quality and
parameters.
a) Inspection of works and field quality control.
b) Measurement of work for decision of making payment.
c) Taking over of erected equipment for
commissioning.
d) Completion reports and contract closure.
-
7/31/2019 L-01 Introduction to Erection - 000
10/14
23 May 2012 PMI Revision 00 10
ISSUES IN ERECTION
Responsibilities
Safety
Statutory regulationsContract closing
-
7/31/2019 L-01 Introduction to Erection - 000
11/14
23 May 2012 PMI Revision 00 11
CONSTRUCTION EQUIPMENTS
TOWER CRANE(50T) / BK-1000(100T) / FMC(350T)
GANTRY CRANECRAWLER CRANE:- TATA1055(90T)
TATA955(75T)
TATA655(36T)
TATA320(18T)HYDRA CRANE
BULL DOZER
TRACTOR/TRAILER
WELDING SETS
ROAD ROLLER
AIR COMPRESSOR
LOCO SHUNTER
BFR-WAGONS
-
7/31/2019 L-01 Introduction to Erection - 000
12/14
23 May 2012 PMI Revision 00 12
ELECTRIC/HAND/PNEUMETIC WINCHES/SLINGS/PULLEY BLOCKS
DERRICKSWELDING GENERATORS/TRANSFORMER, HEAT TREATMENT EQUIP.
TIG/ARC WELDING EPUIPMENTS, DRYING OVEN
JACKS/PIPE BENDING M/C, CHAMFERING M/C
SMALL T&P---CHISELS, SRAPPERS, SPANNERS,HAMMERFILES, SCREW DRIVERS, WIRE ROPES
HACK SAWS. DRILLING/GRINDING M/C
ELECTRICAL TOOL, ULTRSONIC TESTING M/C
REDIOGRAPHY SOURCE
MEASURING INSTRUMENTS
SPACE CLIMBER
-
7/31/2019 L-01 Introduction to Erection - 000
13/14
23 May 2012 PMI Revision 00 13
CLASSIFICATION OFCHECKS
CHECKED/WITNESSED BY
COUNTERCHECK BY ACCEPTINGAUTHORITY
DISPOSITIONINGAUTHORITY
CRITICAL / A FQA CQA AS PERNECESSARY
FQA HEAD / CQA INCONSULTATION WITHENGG
MAJOR/ B EXECUTING DEPT. FQA HEAD /EXECUTINGDEPT.
HEAD / FQA INCONSULTATION WITHGM PROJECT
MINOR / C CONTRACTOR REP. EXECUTING DEPT. EXECUTINGDEPT.
HEAD / EXECUTINGDEPT.
a. FOR RECEIPT INSPECTION STORAGE,ASSEMBLY AND ERECTION
EXECUTING DEPT. MEANS
CONCERNED ERECTION/CONSTRUCTION ENGINEER
b. FOR PRE-COMMISSIONING & COMMISSIONING CONCERNED PRE-COMMISSIONING /O&M ENGINEER AND ERECTIONENGINEER
-