l-01 introduction to erection - 000

Upload: sam

Post on 05-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 L-01 Introduction to Erection - 000

    1/14

    23 May 2012 PMI Revision 00 1

    INTRODUCTIONTO ERECTION

  • 7/31/2019 L-01 Introduction to Erection - 000

    2/14

    23 May 2012 PMI Revision 00 2

    ROLE OF ERECTION DEPARTMENT IN NTPC

    NTPC has been entrusted with the responsibility toengineer the Project from concept to commissioning state intotality and thereafter operate Super Thermal PowerStations.

    Construction management of such large STPS involves amulti-disciplinary approach over a diversified area ofactivities from the state of preconstruction till start up andprecommissioning state.

    Construction management functions involve executing aSTPP during various phases of construction activities i.e.from taking a green site till handing over of erected andtested equipments for commissioning.

  • 7/31/2019 L-01 Introduction to Erection - 000

    3/14

    23 May 2012 PMI Revision 00 3

    Construction line function involves different disciplines :-

    1. Civil construction including structural fabrication. 2. Mechanical equipment erection. 3. Electrical erection. 4. C&I erection.

    As per NTPC Corporate philosophy construction has beenorganized into two major groups :- i) Construction : This includes civil construction and structural fabrication. ii) Equipment Erection : This includes erection of mechanical,

    electrical and C&I equipments. Equipment erection involves erection of all plant and systems such as

    boiler, turbo-generator, auxiliary systems like Coal handling system,Electrical and C&I system.

  • 7/31/2019 L-01 Introduction to Erection - 000

    4/14

    23 May 2012 PMI Revision 00 4

    BROAD FUNCTIONAL RESPONSIBILITIES FOR

    EQUIPMENT ERECTION GROUP :- To ensure proper co-ordination with the contractors for timelyexecution of various equipments erection work, at site as per

    contract agreements / LOIs.

    To allot necessary land and infra-structure facilities to variouscontractors to enable them to mobilize their work-force and

    proceed with the erection work as per schedule.

    To plan, monitor and review the erection work on a regularbasis so that work progresses as per schedule.

  • 7/31/2019 L-01 Introduction to Erection - 000

    5/14

    23 May 2012 PMI Revision 00 5

    To ensure all work-fronts, inputs and resources are

    regularly made available during course of executionof the work and to preempt any foreseen hold-ups

    due to non-availability of any of these.

    -- To exercise judicious control over consumption of bulk material and other consumables.

    -- To ensure that quality of erection work meets the

    company standards and norms. -- To maintain checks and ensure proper work

    measurements.

  • 7/31/2019 L-01 Introduction to Erection - 000

    6/14

    23 May 2012 PMI Revision 00 6

    EQUIPMENT ERECTION :-

    Execution and Supervision system Objective :-

    To ensure that equipment erection works are completed

    within the time schedule of overall construction Network so asto enable the start-ups, trial runs and pre-commissioning

    activities of equipments, system within the frame-work of

    overall project schedule.

  • 7/31/2019 L-01 Introduction to Erection - 000

    7/14

    23 May 2012 PMI Revision 00 7

    Basic responsibilities of erection execution

    supervision group are :- 1. Study of LOI / Bid Documents :- a) Scope of work and terminal points. b) Location, lay outs, technical specification and erection methodology for various equipment.

    c) Quality plan. d) Contractors resource commitment. e) Contractors schedule. f) Scope of supply and erection.

    2. Land allotment and infrastructure services.

    3. Erection planning implementation of detailed construction planning system. 4. Monitoring of equipment despatch, transportation,

    receipts and expediting.

  • 7/31/2019 L-01 Introduction to Erection - 000

    8/14

    23 May 2012 PMI Revision 00 8

    5. Work front release :-

    a) Erection plans are finalized.b) Availability of fabrication and erection drgs.

    c) Availability of erectable equpt. at site.

    d) Availability of bulk materials and erection matl.e) Helping and lifting equipment requirements and

    their detailed deployment plan.

    f) Availability of civil works front.6. Equipment supply and receipt where

    erection and supply are split up.

  • 7/31/2019 L-01 Introduction to Erection - 000

    9/14

    23 May 2012 PMI Revision 00 9

    7. Erection supervision Aims at assisting the

    contractor to work efficiently in terms of quality and

    parameters.

    a) Inspection of works and field quality control.

    b) Measurement of work for decision of making payment.

    c) Taking over of erected equipment for

    commissioning.

    d) Completion reports and contract closure.

  • 7/31/2019 L-01 Introduction to Erection - 000

    10/14

    23 May 2012 PMI Revision 00 10

    ISSUES IN ERECTION

    Responsibilities

    Safety

    Statutory regulationsContract closing

  • 7/31/2019 L-01 Introduction to Erection - 000

    11/14

    23 May 2012 PMI Revision 00 11

    CONSTRUCTION EQUIPMENTS

    TOWER CRANE(50T) / BK-1000(100T) / FMC(350T)

    GANTRY CRANECRAWLER CRANE:- TATA1055(90T)

    TATA955(75T)

    TATA655(36T)

    TATA320(18T)HYDRA CRANE

    BULL DOZER

    TRACTOR/TRAILER

    WELDING SETS

    ROAD ROLLER

    AIR COMPRESSOR

    LOCO SHUNTER

    BFR-WAGONS

  • 7/31/2019 L-01 Introduction to Erection - 000

    12/14

    23 May 2012 PMI Revision 00 12

    ELECTRIC/HAND/PNEUMETIC WINCHES/SLINGS/PULLEY BLOCKS

    DERRICKSWELDING GENERATORS/TRANSFORMER, HEAT TREATMENT EQUIP.

    TIG/ARC WELDING EPUIPMENTS, DRYING OVEN

    JACKS/PIPE BENDING M/C, CHAMFERING M/C

    SMALL T&P---CHISELS, SRAPPERS, SPANNERS,HAMMERFILES, SCREW DRIVERS, WIRE ROPES

    HACK SAWS. DRILLING/GRINDING M/C

    ELECTRICAL TOOL, ULTRSONIC TESTING M/C

    REDIOGRAPHY SOURCE

    MEASURING INSTRUMENTS

    SPACE CLIMBER

  • 7/31/2019 L-01 Introduction to Erection - 000

    13/14

    23 May 2012 PMI Revision 00 13

    CLASSIFICATION OFCHECKS

    CHECKED/WITNESSED BY

    COUNTERCHECK BY ACCEPTINGAUTHORITY

    DISPOSITIONINGAUTHORITY

    CRITICAL / A FQA CQA AS PERNECESSARY

    FQA HEAD / CQA INCONSULTATION WITHENGG

    MAJOR/ B EXECUTING DEPT. FQA HEAD /EXECUTINGDEPT.

    HEAD / FQA INCONSULTATION WITHGM PROJECT

    MINOR / C CONTRACTOR REP. EXECUTING DEPT. EXECUTINGDEPT.

    HEAD / EXECUTINGDEPT.

    a. FOR RECEIPT INSPECTION STORAGE,ASSEMBLY AND ERECTION

    EXECUTING DEPT. MEANS

    CONCERNED ERECTION/CONSTRUCTION ENGINEER

    b. FOR PRE-COMMISSIONING & COMMISSIONING CONCERNED PRE-COMMISSIONING /O&M ENGINEER AND ERECTIONENGINEER

  • 7/31/2019 L-01 Introduction to Erection - 000

    14/14

    23 May 2012 PMI Revision 00 14